You are on page 1of 22

ARTICLE IN PRESS

International Journal of Rock Mechanics & Mining Sciences 44 (2007) 174195


www.elsevier.com/locate/ijrmms

Updated owcharts for rock mechanics modelling and


rock engineering design
J.A Hudsona,, X.T. Fengb
a
Imperial College and Rock Engineering Consultants, 7 The Quadrangle, Welwyn Garden City, Herts AL8 6SG, UK
b
Institute of Rock and Soil Mechanics, Chinese Academy of Sciences, Wuhan 430071, China
Accepted 10 June 2006
Available online 28 August 2006

Abstract

In an earlier paper, the ways ahead for rock engineering design methodologies were discussed. In this paper, following an overview of
earlier approaches, we present two updated owcharts: one for rock mechanics modelling in which the modelling options are outlined;
and one for rock engineering design in which the three phases of overall assessment, initial design and nal design are incorporated. We
outline the steps necessary and the principles involved in utilising the owcharts, especially the appropriateness of the modelling methods
for different circumstances together with the integration of methods. Particular emphasis is placed on the cycling through feedback and
nal design. We demonstrate the procedure with three illustrative case study examples representing the range of complexity: a
conventional tunnel, the design and construction of the underground powerhouse for the Shuibuya hydro-electric project in Hubei
Province, China, and designing a radioactive waste repository. The rst and third case examples are presented briey: the rst because of
its relative simplicity; the third because of its relative complexity. The second case of the powerhouse design and construction is presented
at greater length because it clearly illustrates the application of the owcharts.
r 2006 Elsevier Ltd. All rights reserved.

Keywords: Rock engineering; Design; Flowchart; Modelling; Back analysis; Case example

1. Introduction and earlier work [5,6], Hudson [7] and more recently through the work of Li
[8] and Goricki [9]. These owcharts are reproduced here in
In a previous paper [1] we discussed the ways ahead for Figs. 17. Our intention here in the introduction is to
rock engineering design methodologies. In this follow-on present examples of previous owcharts, not to attempt to
paper, we rstly present a rock mechanics modelling include all such earlier design owcharts.
owchart which includes the main modelling methods In the owchart in Fig. 1, the work starts with collection
and then we present an updated owchart for the steps in of geological data and then there is the division between
the rock engineering design process. It is intended that types of instabilityleading to the four columns in the
these owcharts and the associated descriptions and owchart considering instability due to adverse structural
illustrative examples should cover the principles, an outline geology, excessively high rock stress, weathering and/or
of the procedures, plus recent developments in intelligent swelling rock and excessive groundwater pressure or ow.
rock mechanics.1 This then leads to decisions on the support and the
There have been many earlier presentations on this applicability of the site.
subject: e.g. the owcharts developed by Hoek and Brown The owchart in Fig. 2 covers the steps of conceptualis-
[2], Pahl and Beitz [3], Brady and Brown [4] Bieniawski ing the problem, preparing preliminary layouts, establish-
ing the denitive layout and documenting the nal details.
Corresponding author. Tel.: +44 1707 322819; fax: +44 1707 375912. This is more of an administrative guidance, rather than
E-mail address: jah@rockeng.co.uk (J.A. Hudson). dealing with rock mechanics issues specically.
1
The term intelligent rock mechanics refers to the use of articial The owchart in Fig. 3 provides an outline for mine
intelligence methods in rock mechanics analyses. design which has multiple feedback modesindicating the

1365-1609/$ - see front matter r 2006 Elsevier Ltd. All rights reserved.
doi:10.1016/j.ijrmms.2006.06.001
ARTICLE IN PRESS
J.A. Hudson, X.T. Feng / International Journal of Rock Mechanics & Mining Sciences 44 (2007) 174195 175

Fig. 1. Flowchart for the design of underground excavations in rock (from Hoek and Brown [2]).

need to assess the mine response in terms of the site are not explicitly covered and so the precise data required
characterisation, model formulation and design analysis, so are not specied. Although the general principles are
that mine operations can be optimised through a continu- appropriate, modern numerical methods require specic
ing feedback and hence improvement process. input parameters.
Bieniawskis owchart in Fig. 4 covers the collection of The 10 steps in Fig. 5 provide a more expanded
the necessary data leading to processing of the data and explanation of the design process from the statement of
then the design studies. However, the methods of analysis the problem in Stage 1 to implementation in Stage 10,
ARTICLE IN PRESS
176 J.A. Hudson, X.T. Feng / International Journal of Rock Mechanics & Mining Sciences 44 (2007) 174195

Fig. 2. Flowchart for design steps according to Pahl and Beitz [3].

representing evolution of the design by continuously The owchart in Fig. 7 [8] concentrates on the three
improving the design in Stages 68, although the exact components of data from previous projects, rock mass
methods are left to the engineer. classication and numerical analysis. Li et al. explain that
The diagram in Fig. 6 [7] illustrates the con- Precedent Type Analysis is a semi-analytic method that
ceptual nature of the rock engineering design process applies the geological conditions of a so-called typical
as a three-tier process. The outer border represents the project to an analysed tunnelling project for its stability
entry to the problem; the middle border represents analysis. A completed tunnelling project can be used as a
the inter-relations between the various factors; and the typical or reference project for others if it satises three
inner border represents the analysis of individual subjects. criteria: (1) monitoring through construction periods has
The overall design process involves entering the diagram been carried out and all the data obtained are reliable;
with an objective, establishing the content of the three (2) an in situ rock mass characterisation has been carried
borders, and then exiting with a progressively developed out for the project and a relevant complete set of data
design. obtained; and (3) the project should be recognised as
ARTICLE IN PRESS
J.A. Hudson, X.T. Feng / International Journal of Rock Mechanics & Mining Sciences 44 (2007) 174195 177

Fig. 3. Outline owchart for mine design with multiple feedback modes,
Brady and Brown [4].

Fig. 5. Flowchart for the design of underground excavations in rock, from


Bieniawski [6].

having a common feature for the tunnels driven in similar


rock mass classes. Hence, precedent type analysis is based
on the same principles as rock mass classication but
formalises the process for design.
In Fig. 8, Gorickis owchart [9] illustrates a sequential
procedure for characterising the rock mass, using a
hierachical procedure for identication of rock mass
behaviour and potential failure modes, and then integrat-
ing techniques for support determination.
As mentioned earlier, we have not attempted to include
all such rock engineering design owcharts but to illustrate
the variety of types that have already been developed. The
owchart in Fig. 1 includes specic guidance on the rock
mechanics approaches to follow. The owcharts in
Figs. 26, although helpful, do not highlight either the
rock mechanics mechanisms nor the actual analysis
procedures. The owchart in Fig. 7 follows a somewhat
different approach in that, after establishing the rock mass
types and their characteristics, together with those of the
excavation, the behavioural types are identied from a
library of behaviour types and from this the excavation and
support are determined. The owchart in Fig. 8 considers
Fig. 4. Flowchart for the design of rock engineering structures with behaviour types based on the rock conditions and type of
emphasis on the detailed site characterisation, from Bieniawski, [5]. excavation.
ARTICLE IN PRESS
178 J.A. Hudson, X.T. Feng / International Journal of Rock Mechanics & Mining Sciences 44 (2007) 174195

Fig. 6. Diagram illustrating the three tiers of the rock engineering design problem, from Hudson [7].

Fig. 7. Precedent type analysis and the inter-relations between the three components, from Li et al. [8].

Because of the signicant developments in numerical also takes advantage of all the recent developments in
modelling and site investigation techniques, it is topical theory, numerical modelling and construction experience.
now to consider an updated approach to both the rock Thus, based on the previous work and in line with
mechanics modelling and the rock engineering design providing more complete guidance for rock engineering
procedure which builds on the previous owcharts but design, in this paper we present two updated owcharts.
ARTICLE IN PRESS
J.A. Hudson, X.T. Feng / International Journal of Rock Mechanics & Mining Sciences 44 (2007) 174195 179

to the right, simple to complicated. The rst three types


of methods, Categories AC, are widely used in rock
engineering design. The fourth method in the top row of
Category D, extended coupled modelling, is currently being
developed on an international basis, e.g. in the DECOVA-
LEX research program and associated papers on coupled
modelling can be found in the proceedings of the GeoProc
conferences [10,11]. The fourth method in the bottom row
of Category D, integrated systems and Internet-based
approaches, has not yet been developed.
The two rows of boxes with the eight modelling methods
in the large box represent the two main ways in which the
mechanisms are mapped in the modelling. In the top row,
Level 1, 1:1 mapping, there is an explicit attempt in the
modelling to represent the geometry and operating
mechanisms on a 1:1 basis. For example, if there is a
major fracture in the vicinity of a tunnel, this can be
incorporated explicitly in a numerical model. However, in
the lower row, Level 2, not-1:1 mapping, the modelling
techniques are not designed to include the geometry and
mechanisms directly. For example, in the neural network
technique, there are nodes in the neural network used but a
specic node cannot be directly associated with either a
location or a physical variable, as in the nite element
approach.
Nowadays we need an integrated approach, incorporat-
ing the parallel and sequential use of the analysis methods
harmonising the rock engineering design with the host rock
character. The integrated modelling should be a process of
cognition-calibration and modication-re-cognition to
capture the rock-engineering system behaviour. The term
adaptive is appropriate because it refers to the process of
problem solving enabling adaption to changes of geological
conditions, thinking modes, mechanical parameters and
models, and analysis methods. Thus, an adaptive capability
is a key requirement in order to be able to circle through
Fig. 8. Flowchart for the basic procedure of excavation and support
the feedback loop illustrated in Fig. 9of modelling,
design for underground structures, from Goricki et al. [9]. design, construction, further site investigation data to
modelling. Moreover, the system modelling and the
problem solving process is a pattern, so the modelling
The rst is a rock mechanics modelling owchart which should be arranged to facilitate recognition of the pattern,
covers all the rock mechanics modelling approaches and especially the relation between the system input and output
how these can be used separately or in combination. The and the recognition of the inuence of changing or new
second is a rock engineering design owchart which factors.
highlights the design process in a series of seven main steps It should be noted that some of the approaches in
and utilises the modelling owchart. the right-hand part of the owchart, Method D, are
currently on the limit of precedent practice but develop-
2. The modelling owchart ments are anticipated in this column in the near future.
The extended numerical models involve fully coupled
We start by reproducing here in Fig. 9 the modelling thermo-hydro-mechanical-chemical (T-H-M-C) processes
owchart presented earlier in [1]. This concentrates on the and work in this subject area is proceeding in many
analysis approaches. countries. The non-1: 1 approaches, integrated systems
The purpose of this modelling owchart is to include the approaches, possibly internet-based, are being developed
eight basic categories of modelling within the framework of especially in China.
the project objective, site investigation, design and con- The eight rock mechanics modelling methods highlighted
struction. The four columns in the large box in Fig. 9, in Fig. 9 can be used singly, or any number can be used in
Categories AD, are four levels of complexity from the left combination, or as a sequential permutation, depending on
ARTICLE IN PRESS
180 J.A. Hudson, X.T. Feng / International Journal of Rock Mechanics & Mining Sciences 44 (2007) 174195

The rock mechanics modelling flowchart

Objective

Method A Method B Method C Method D

Extended
Use of Basic numerical
Analytical numerical Level 1
pre-existing methods, FEM,
methods, methods,
standard BEM, DEM, 1:1 mapping
stress-based fully-coupled
methods hybrid
models
Site
Invest-
igation
Database
Integrated
Precedent type Rock mass expert
systems Level 2
analyses and classification, systems, &
approaches, Not 1:1 mapping
modifications RMR, Q, GSI other systems
internet-based
approaches

Design based on forward analysis Design based on back analysis

Construction

Fig. 9. Flowchart of rock mechanics modelling techniques.

the modelling requirements. We explain how this can be The project purpose naturally affects the design because of
done later in the paper. the different criteria associated with the purpose. In the
case of a high-pressure water tunnel, the main design
3. The rock engineering design process parameter could be the minimum in situ principal stress
value. For an underground train tunnel, the main design
3.1. Updated rock engineering flowchart issue is maintaining the long-term displacements within
acceptable values. Thus, there can be no xed standard
We will use two owcharts for the rock engineering design or site investigation because both depend on the
design process. The rst is the summary of analysis project purpose and the constraints involved. This is why
procedures already presented in Fig. 9 in the previous we have placed the project purpose and constraints at the
section. This is to be used in conjunction with the updated beginning of the owchart.
rock engineering owchart in Fig. 10, which is similar in
concept to Bieniawskis 1993 owchart (Fig. 5) but
concentrates on the analysis methods and the initial-nal 3.4. Establishing the design approach strategy via the
design work. modelling options

3.2. Steps in the rock engineering design process In order to design a rock engineering structure, it is
necessary to be able to evaluate the consequences of
The individual steps in Fig. 10 are outlined in Table 1. different design options, i.e. to be able to predict what will
happen if a structure with a certain design is constructed in
3.3. Project purpose, constraints and key features of the site, a given rock mass. In order to do this, some form of
rock mass and project predictive capability is requiredthrough modelling. Thus,
in the overall assessment and establishment of the design
In Fig. 10 we outlined the rock engineering design approach strategy, the type of modelling has to be chosen
process. It is of crucial importance to have a clear from a combination of the eight individual methods
understanding of the purpose of the project, plus any outlined in Fig. 9.
constraints on the design. For example, the design The choice will depend on the nature of the project and
considerations and the site investigation parameters the risk involved, i.e. to what extent any failure can be
required for a short-term mining rock slope and for a tolerated. As an example, consider the design of a simple
long-term radioactive waste repository will be different. cavern in sedimentary rock with a design life of 120 years.
ARTICLE IN PRESS
J.A. Hudson, X.T. Feng / International Journal of Rock Mechanics & Mining Sciences 44 (2007) 174195 181

The rock engineering design flowchart

DESIGN STEP CONTENTS OF THE DESIGN STEP

1. Project purpose Establish the objective and sub-objectives of the project

2. Key features of the


Identify the features and constraints of the site,
site, rock mass and
rock mass and project
project
OVERALL
ASSESSMENT
3. Design approach Develop the overall design approach strategy based on
strategy the options in the Methods A to D in the Fig. 9 flowchart

4. Choose modelling Utilize the principles Utilize the principles


method and appropriate of modelling, of code implementation,
code(s) choose method(s) choose code(s)
INITIAL
DESIGN

5. Establish Establish initial design, conduct hazard assessment, and


initial design initiate construction, with monitoring

Consider feedback inform-


6. Integrated Consider the integration
ation from construction,
modelling and feedback of the modelling
as in Fig. 9, leading to
information methods in Fig. 9
closed-loop design
FINAL
DESIGN
7. Final design
Establish final design and verify by monitoring
and verification

Fig. 10. Updated owchart for the rock engineering design process.

Table 1
Notes on the steps in the rock engineering design process

1. Project purpose: There can be many engineering objectives and sub-objectives which need to be rmly established at the top of the owchart. Different
project objects imply that different rock properties and analyses are required for the different purposes. Unless this is rmly established before the
design work commences, the work cannot be optimally conducted.
2. Key features of the site, rock mass and project: Different sites, rock masses and projects mean that there will be different emphases in the design,
indicating that it will be rarely that two projects are essentially identical. Thus, each rock engineering design is likely to be a one-off occurrence. This is
why the application of the principles is so important.
3. Design approach strategy: Given the identication of the features in Step 2, a modelling design approach strategy is now provisionally established by
the choice of modelling methods in Fig. 9. There are many aspects to be considered, such as the resources available for the work, the consequences of
design failure, spatial variations in the rock mass properties, whether there is any need to consider time dependent effects, etc.
4. Choose modelling method and appropriate code(s): In this step, the overall approach is now made specic through the exact choice of methods and
codes. It is wise to go through the principles outlined later in this paper in order to ensure that correct choices are made.
5. Establish initial design: This step crystallises the initial design so that construction can begin. We are anticipating that this may not be the nal design
but it is the best that can be achieved before monitoring results and back analysis are possible.
6. Integrated modelling and feedback information: In this step, we change from a forward analysis to a back analysis (see Fig. 9) by directly using the
monitoring results to improve the design through enhanced integration of the rock property information, modelling methods, monitoring information
and back analysis. In other words, the initial construction is a full-scale experiment enabling the nal design to be established.
7. Final design and verification: Finally, the monitoring is continued, so that the criteria associated with the engineering objective are conrmed to be
satised.

There will be many variations on the seven step theme described here, but it is extremely useful to bear the structure of this upgraded owchart in mind
throughout the design and construction project. For example, if a tunnel is passing through a cyclothem of sandstone, limestone and mudstone, the
owchart can be considered to apply to each of the geological domains.
ARTICLE IN PRESS
182 J.A. Hudson, X.T. Feng / International Journal of Rock Mechanics & Mining Sciences 44 (2007) 174195

Design of a simple cavern


in sedimentary rock

Method A Method B Method C Method D


Use of analytical Not required
methods, stress- Use of standard
Consideration of Extended
based for numerical
pre-existing numerical
Level 1
guidance on methods, to
standard methods, 1:1 mapping
stress concen- account for 3-D,
methods fully-coupled
trations and shape, fractures
Site displacements models
Invest-
igation Not required Not required
Consideration of
Use of rock mass
guidance from Database expert Integrated Level 2
classification,
precedent type systems, & other systems
RMR, Q, GSI Not 1:1 mapping
analysis system approaches,
approaches internet-based

Design based on forward analysis Design based on back analysis

Construction

Fig. 11. Example of the modelling methods used in the design of a simple cavern in sedimentary rock.

If there are no complicating features, a design strategy can long-term displacements are a key issue, then an elastic
be based on (see the shaded boxes in Fig. 11): analysis is inappropriate, by denition.
Ideally, there should be a protocol established to ensure
 consideration of pre-existing standard designs; that the modelling is appropriate (e.g. [12]). In Table 2, we
 via precedent type analysis, consideration of the type of outline nine principles for good modelling practice. These
standard design best suited to the conditions; are expressed fairly strictly and, for various reasons, it may
 use of analytical methods for rst pass study of stress not be possible to ensure that they are all followed. However
concentrations, potential for block fallout and displace- and conversely, the modelling could be adversely ineffective
ments; if, for example, a key variable is missing in the modelling.
 use of rock mass classications, RMR, Q, GSI to It is all too easy to use an off-the-shelf computer
indicate required support; and program and hope that it is sufcient for the purpose. In
 use of standard numerical methods, e.g. Examine, fact, an effort should be made, going back to the code
FLAC, UDEC, 3DEC, to provide more detailed study. distributor if necessary, to ensure that it is t for the
modelling purpose. In Table 3, we provide a further seven
Rather than jump directly the last bullet point, it is better principles, in this case for code implementation.
to utilise the methods in this order, to check that the This then leads to Step 5 in Fig. 10 in which the initial
different approaches are indicating similar designs. This design is established and construction can begin. It is
provides the overall assessment as indicated in Fig. 10. anticipated that later there will be feedback from monitor-
In the more complex case for radioactive waste disposal, ing information enabling Steps 6 and 7 in Fig. 10 to be
it is necessary to ensure, not only the practicality of completed. If this is not anticipated, then naturally the
construction and the long-term stability of openings, but initial design will then be the nal design and care must be
also the over-arching project purpose: that an unacceptable taken to ensure that it has been sufciently well established.
quantity of radionuclides should not escape to the bio-
sphere. In this case, much more complex modelling is 3.6. Establishing and verifying the design
required, as highlighted in Fig. 12.
Steps 6 and 7 in Fig. 10 represent the modied design in
3.5. Utilising the principles of modelling and code which the monitoring information has been utilised,
implementation together with an improved integration of the modelling
methods. We provide a specic example of how this is done
To lead into the initial design in Fig. 10 having decided in the Shuibuya case example following. Also, given the
on a modelling strategy, it is important to consider whether closed-loop operation between Steps 6 and 7, there could
the modelling can indeed capture the relevant character- be several iterations depending on the complexity and
istics of the site, rock mass and project. For example, if variability of the project and rock mass.
ARTICLE IN PRESS
J.A. Hudson, X.T. Feng / International Journal of Rock Mechanics & Mining Sciences 44 (2007) 174195 183

Design of a radioactive
waste repository

Method A Method B Method C Method D


Not possible
Inadequate Basic Extended
numerical numerical
Use of
methods,
Level 1
Analytical methods, FEM,
pre-existing 1:1 mapping
methods, stress- BEM, DEM, fully-coupled
standard
based hybrid models
methods
Site
Invest-
igation
Not possible Database
Integrated
Rock mass expert
Precedent type classification, systems, &
systems Level 2
approaches, Not 1:1 mapping
analysis and RMR, Q, GSI other systems
internet-based
modifications approaches

Design based on forward analysis Design partly based on back analysis

Construction

Fig. 12. Example of the modelling methods used in the design of a radioactive waste repository.

Table 2 Table 3
Suggested modelling principles to ensure that the modelling does indeed Principles of numerical code implementation
represent the rock reality
Principles of code implementation
Principles for modelling
1. The engineering objective, i.e. reasons for requiring the modelling,
1. All relevant processes (e.g. gradients and mechanisms) should be should be clearly dened, together with the required output
incorporated in the analysis. information.
2. All relevant properties, including any variability, should be 2. All relevant properties should be available for inclusion.
incorporated in the analysis. 3. Only realistic values of properties should be utilised.
3. The necessary spatial dimensionality of the analysis should be captured 4. The modelling domain should be of appropriate size and resolution to
in the modelling. provide sufciently accurate results.
4. Temporal effects should be captured in the modelling. 5. Recognising that it might not be possible for all the other principles to
5. Any computer code used should be checked for correctness. be fully satised, an assessment should be made of the errors
6. Any code considered should be able to incorporate the processes and introduced by any deviations and assumptions made.
properties in the context of the geometry and time frame being 6. A criterion should be established for determining when the modelling
modelled. has satised the modelling objective.
7. The algorithms incorporated in the code should be appropriate in 7. If required, a modelling protocol should be established by producing a
content and execution. reasoned narrative regarding each of the code selection and code
8. The output should be commensurate with the engineering objective. implementation principles.
9. The code should not use properties that are ill dened or signicantly
subjective.

4. Use of the procedure with three illustrative case examples 3. the design of a radioactive waste repository in a
crystalline rock mass.
We now illustrate how the updated rock engineering
design owchart in Fig. 10 (supported by the rock The rst and third case examples are presented
mechanics owchart in Fig. 9) is utilised by presenting briey: the rst because of its relative simplicity;
three case examples: the third because of its relative complexity. The
second case of the powerhouse cavern design and
1. the design of a conventional tunnel in China; construction is presented at greater length because it
2. the design of the powerhouse cavern for the Shuibuya clearly illustrates the application of the owcharts. In the
project, Hubei Province, China, where there are alter- presentation of these illustrative case examples, we have
nating weak and strong sedimentary strata; and highlighted the key issues related to the design approach.
ARTICLE IN PRESS
184 J.A. Hudson, X.T. Feng / International Journal of Rock Mechanics & Mining Sciences 44 (2007) 174195

We have not been able to include all the details of the Step 2: Features. No overburden problem, no water
projects. problem, sandstone with weak layers.
Step 3: Design approach strategy. Use conventional
4.1. Illustrative example 1: The design of a conventional design adapted to the local circumstances.
tunnel: design of Qiaotou tunnel for the Yuanmo expressway, Step 4: Modelling methods. Rock mass classication and
China nite element simulation with feedback from monitored
displacements.
4.1.1. Overview of the project Step 5: Initial design. Established via the rock mass
The Qiaotou tunnel forms part of the Yuanmo Express- classication approach (the Precedent Type Analysis, [8]).
way, China. It has a length of 280 m, is a double span and Step 6: Integration and feedback. The initial design was
has a united arch architecture with a central wall [13]. The considered in the light of the nite element analysis of the
tunnel has single spans of 10.53 m, a net height of 7.2 m and specic ground conditions, and the monitored displace-
the side wall is curved. The central wall is rectangular with ments.
thickness 2 m. The tunnel has an overall width of 23.05 m Step 7: Final design and verification. The nal design was
and excavation span of 24.65 m (Fig. 13). The surrounding conrmed on the basis of Step 6 study.
rock is Classes III and IV in the Chinese rock quality
system with a maximum overburden of 74 m. It belongs to 4.1.3. Example 1: summary
the geological sub-segment of the Xiatongjingxing group of The Qiaotou double highway tunnel was chosen as a
the Baier series (K1J1). The lithology is ash, sandstone with conventional tunnel. There were no outstanding design
inter-layered claystone. The maximum thickness of the difculties and the design could be established using the
strongly weathered strata is 17.9 m. The weakly weathered PTA approach through a knowledge of the ground
strata are relatively intact with some large blocks. The conditions and conrming the design by nite element
support system was designed using WID25 rockbolts with analyses supported by monitored displacements. Thus the
a length of 3 m and spacing of 1  1 m, C25 shotcrete with a design pathway is as illustrated in Fig. 11 but note that the
thickness of 200 mm, reinforcing net 200  200 mm, and the design elements form a pathway through the analysis
secondary support is armoured concrete, 500 m thick. options.
The construction sequence involved excavation of the
upper and lower benches for the left and right tunnel. 4.2. Illustrative example 2: The design of the powerhouse
When the upper part of the tunnel wad excavated and has cavern for the Shuibuya project, Hubei Province, China
the secondary support installed and was 30 m distance from
the working face of the other tunnel, the working face Following the case of the conventional tunnel in
excavation was continued. Finite element simulation Illustrative Example 1, we now present a case example of
analysis and monitoring of eld displacements during and intermediate difculty. The Shuibuya powerhouse cavern is
after the construction enabled verication of the design. part of a hydroelectric project which has a 233 m high
concrete faced rockll dam, interesting Carboniferous
4.1.2. Steps in the Fig. 10 design flowchart geology with hard and soft strata, and the use of intelligent
The modelling procedure used to support the design of rock mechanics analyses with back analysis, and associated
this tunnel was as illustrated in Fig. 11 for the design of a design modication. Because of the more detailed ap-
simple cavern in sedimentary rock. The steps in Fig. 10 proach we are presenting, the descriptive text for this case
design owchart were straightforward and as follows: example is more extensive.
Step 1: Objective. To design the conventional double
highway tunnel mainly in the weak sandstone rock. 4.2.1. Overview of the project and geological conditions
The Shuibuya underground hydropower house is located
near the Shuibuya village in Badong county, Hubei
province in the middle reaches of Qingjiang river, China,
see Fig. 14a.
The Shuibuya power plant is located in the mountainous
rocks of the right bank of the Qingjiang river. The
elevation of the crest of the bank is 540550 m, and the
strike and dip of the strata are 245+8151. The angle
between the main plant axis and the strata strike is 391, the
powerhouse has dimensions 141  23  68 m, and the main
powerhouse axis trends at 2961. The elevation of the main
powerhouse roof is 233 m and that of the oor 165 m. The
minimum distance between the north-west end of the
Fig. 13. Section of the Qiaotou double highway tunnel, part of the powerhouse to the right bank of the Qingjiang river is
Yuanmo Expressway, China. about 80 m. The rock strata from the top downwards
ARTICLE IN PRESS
J.A. Hudson, X.T. Feng / International Journal of Rock Mechanics & Mining Sciences 44 (2007) 174195 185

Harbin

Urumqi

Shenyang
Hohhot
Beijing

r
Riv e
w
lo

Yel

er
v
Ri
Lanzhou Yel l ow
Ya
ng
zt Xi'an Nanjing
e
Shanghai

R
iv
Chengdu Wuhan
er
Lhasa
er Chengqing
Riv

te
z

g
Ya n
Taiwan
Kunming
Shuibuya Guangzhou

Nanning

Haikou
(a)

(b)

Fig. 14. (a) Location of the Shuibuya hydroelectric project in China. (b) The Qingjiang river gorge location of the Shuibuya hydroelectric project. The
powerhouse location is inside the left-hand rock mass (which is the right-hand bank of the river).

consist of the Maokou group (P1m), Qixia group (115 The exposed strata in the powerhouse from the top
sections of P1q) and Maan group of the Permian system downwards consist of the Qixia group P41q , P31q , P21q , P11q as
and the Huanglongqun group of the Carboniferous system, well as the Maan group P1ma and Huanglong group. The
as well as the Xiejingshi group (D3x), Huangjiadeng group strata strike is almost orthogonal to the river direction. The
and Yuntaiguan group of the Devonian system (Fig. 15). strata dips slightly towards the left bank at 8201. The rock
ARTICLE IN PRESS
186 J.A. Hudson, X.T. Feng / International Journal of Rock Mechanics & Mining Sciences 44 (2007) 174195

Fig. 15. Geological map and section of the Shuibuya powerhouse. P21m upper layer of the Maokou group, thick layer limestone; P11m lower layer of the
Maokou group, thick layer limestone; P15 14 13 124 123 122 121 11 10 9 8 7 6 5 4 3 2 1
1q , P1q , P1q , P1q , P1q , P1q , P1q , P1q , P1q , P1q , P1q , P1q , P1q , P1q , P1q , P1q , P1q , P1q as the different segments
of the Xixia group limestone; P1ma Maan group quartz sandstone and powdery sandstone, Permian system; C2hlimestone and quartz sandstone of the
Huanglong group, Carboniferous system.

strata consist of alternating soft and hard layers with the shearing zones weakens the rock continuity, decreases the
Qixia group mainly consisting of weak rock, such as rock mass stiffness, and has an inuence on the stability of
carboniferous biogenic detrital limestone, lime mud, the crown.
clayish limestone, chalky clay, etc. Their cumulative A crane beam was installed on the two side walls of the
thickness is 18% of the total thickness. powerhouse cavern. The rail elevation is 220 m and the
The main faults are F2 and F3. The distance between F2 elevation of the concrete base is 216.8 m. Part of the crane
and F3 at elevation 165 m is 330 m. The shortest distance beam reaches the lower part of the P41q rock and the other
from the east end of the main powerhouse to F2 is 160 m, part is in the P31q rock mass. The cumulative thickness of
while that from the west end to F3 is 25 m. The layout of the weak rock here is 3.75 m, which consists of 56% of the
the powerhouse avoids the inuence of the larger faults F2 6.7 m rock mass in the P31q upper part of the main plant
and F3 with its long axis being almost perpendicular to the There are also four shear zones in this location. Two of
main fault orientations. them have a thickness of about 1 m, while the total
The hard intact rock in the crown of the main power- thickness of the four shear zones is 2.9 m. Therefore, it can
house consists of limestone of the 4th section (P41 ), Qixia be seen that the weak rock proportion in the P31q upper
group. The mean uniaxial saturated compressive strength rock mass is signicant. There are many shear zones with a
of rock specimens was 6065 MPa and the deformation large thickness. In addition, due to the faults and fractures
modulus 1520 GPa. The rock belongs to Class II type of in the rock mass, its overall strength is very low. The safety
surrounding rocks, i.e. strong so the crown rock of the of the crane beam crane could be affected in the
main powerhouse is stable in general. The strata in section operational period by plastic deformation and creep
P41q of the main powerhouse are interspersed with weak deformation due to secondary stresses and the crane beam
layers such as thin and extra-thin chalky clays, carbonifer- loading.
ous chalky clay, etc. There are altogether 21 weak layers in The height of the sidewalls of the powerhouse is 46.5 m.
the powerhouse sidewall of thicknesses generally The strata seen from the top down are P41q , P31q , P21q , P11q ,
20120 mm; however, the thinnest is only 5 mm and the P1ma , etc. Among them, P21q and P41q belong to Class II
thickest reaches 180 mm. The weak layers are embedded category of strong surrounding rocks. These represent
between harder limestones and can be weathered and 63.3% of the sidewall area. P31q , P11q and P1ma mainly
damaged easily. There exist eight prominent shear zones belong to Class IV to IV category of surrounding rocks.
between the layers. There are 15 embedded weak layers in The proportion of their sidewall area is 36.7%.
the P41q stratum above the crown of the main powerhouse, Problems arose because of the following set of circum-
among them seven layers have experienced prominent stances. The rock hosting the four outlets in the upper
shearing. The existence of such embedded weak layers and stream sidewall of the powerhouse consists of P11q , P21q ,
ARTICLE IN PRESS
J.A. Hudson, X.T. Feng / International Journal of Rock Mechanics & Mining Sciences 44 (2007) 174195 187

whilst the rock hosting the four inlets in the lower stream
sidewall consists of P21q , P31q , and the arch rock mainly consists
of P31q . The rock hosting the inlet of the water-out tunnel in
the machine niche consists of P11q , P1ma and C2h, and that of
the arch consists of P11q and P1ma. The surrounding rock at the
intersection is mainly of Class IV category of surrounding A-A
rock. The stress state at the intersection is complex but there
are high stress concentrations. The strata have potential free
faces along the dip direction. The rock mass mainly belongs to y
Class IV category of host rock which has developed shear
zones. At the inlet mouth, there is a developed shear zone,
while at the mouth of the inlet tunnel there are four shear x
zones. At the inlet mouth of the water-out tunnel there are z
B-B
three shear zones. In addition, the faults and cracks further (a)
exacerbate the situation making the construction of cavern at
the intersection difcult due to caving and sidewall sliding Right-upper P1q4
Left-upper
during excavation. P1q3
The bottom of the side wall of the main powerhouse P1q2
consists of P11q and P1ma rock mass, which belongs to Class Main power
Generatrix cavern
IV or V category of host rock. The proportion of soft rock P1q1
Water-in tunnel house
in the rock mass is also higher. There are two shear zones in P1ma
this soft rock at larger scale and with worse properties. The C2h
stress concentration at the side wall bottom is higher.
Water-out tunnel
Therefore, this is a region where plastic deformation can Left-bottom
occur and problems such as sliding between layers and Replacement area with 3 m width
(b)
creep deformation may also occur. Reinforcement mea-
sures must be utilised in the design.
The surrounding rock at the machine niche of the main
plant mainly consists of strata P11q , P1ma and C2h, which
mainly belong to Classes IVV category of host rock. Main
powerhouse Main
There are low shear strength shear zones in the surround- powerhouse
ing rock with c values of 0.0050.01 MPa and low friction
angles. Usually, the Huanglong shear zone is thicker in this
location and exhibits fractured rock and weak cohesion.
The overall strength of the rock mass is low. About one Possible passages set inside
half of the strata in the excavation face of the machine (c) Replacement area with 3 m width
niche shows a free face along the dip direction. In addition, Fig. 16. (a) Main powerhouse system. (b) A section: depth of replacement
the faults and cracks will further deteriorate the rock mass for soft strata P31q , P11q , P1ma : shown in vertical section A-A of main power
causing unstable blocks or free faces along the dip house. (c) Possible passages set inside cavern in horizontal section B-B of
direction. The surrounding rock of the machine niche has main power house.
comparably high secondary stress concentration and this,
together with the loading of the machines and other
auxiliary equipments, will result in the surrounding rock at sequence of the cavern peripheral rock was rstly the left
the machine niche being less stable. lower and right lower and then the left upper and right
As a consequence of the conditions described and in order upper areas. The replacement height of the three strata P31q ,
to ensure the safety of the arch and side walls of the main P11q and P1ma was the whole height with a replacement
powerhouse as well as the wall crane beam and machine niche, width of one gallery. The replacement depths were 3, 6 and
it was necessary to replace the upper part the soft rock of the 6 m, respectively, see Fig. 16 [14,15].
Qixia 3rd section (P31q ) and the lower part of the soft rock of
the Qixia 1st section and Maan group (P1ma) by concrete. 4.2.3. Determination of in situ stress
Before the design, the in situ stress was established by
4.2.2. Optimal design of the soft rock replacement scheme at using the hydraulic fracturing method as s1 5:6 MPa
the design stage using intelligent and FEM methods with trend SW 2531 and plunge 591; s2 3:0 MPa with
The optimal soft rock replacement scheme was estab- trend SE1081 and plunge 261; s3 2:1 MPa with trend
lished by using a genetic algorithm, neural network and NE101 and plunge 151. However, the stress state was also
nite element method. The result was the alteration of the estimated by the overcoring method as kx 1:021:4, kz
depth of the water-out tunnel by 1 m, and the replacement 0:821:0 (for hard rock) and kx 0:720:9, kz 0:520:7
ARTICLE IN PRESS
188 J.A. Hudson, X.T. Feng / International Journal of Rock Mechanics & Mining Sciences 44 (2007) 174195

Fig. 17. Cross-section of the Shuibuya underground powerhouse excavation.

3.0 Calculated using non self-gravity in situ stress is reasonable to assume that the in situ stress eld at the
2.5 Calculated using self-gravity in situ stress Shuibuya underground powerhouse is mainly caused by
The convergent displacement (mm)

Monitored
the overburden.
2.0 In fact, this conclusion is compatible with the tectoni-
1.5 cally de-stressed stress state at the underground power-
1.0 housewhich is located at the east wing of the wide and
slightly dipping Sanyouping syncline and between exten-
0.5
sion faults F2 and F3. The strata are slightly dipping and
0.0 there are soft layers, such as shear zones among the layers;
1 2 3 4 moreover, the deep gorge face is adjacent to the project.
-0.5
-1.0
4.2.4. Intelligent back analysis of rock mass parameters
Monitoring section nos.
-1.5 The monitored displacements of the sections 508A-508B,
Fig. 18. Comparison of the computed and monitored displacements at the 509A-509B, s2-1, s3-1 and s2-3 after nishing the excavation
shoulder of the underground powerhouse after nishing the rst of the 1st to 6th steps were used to estimate Youngs
construction layer shown in Fig. 17. modulus of the strata, such as P11q , P1ma , P21q , P31q and P41q
(see Figs. 1822). The back analysis method is based on a
genetic algorithm, support vector machine and FLAC3D
(for soft rock), in which x is the axis of the powerhouse and [15]. The calculated displacements using the Youngs
z is perpendicular to the axis of the powerhouse (see modulus values listed in Table 4 for these ve strata are in
Fig. 16a for the orientations of the axes). Unfortunately, good agreement with the monitored values shown in Fig. 20.
the results from the two methods were quite different.
Feedback analysis based on the monitored displacements 4.2.5. Design of the optimal support system for the
was carried out. The computed displacement eld at the underground powerhouse
shoulder of the underground powerhouse after nishing Based on experience and numerical calculation, the
the rst construction step (Fig. 17) using a gravitational in designer drew up the initial design for the underground
situ stress eld has the same vectorial directions and values powerhouse. The design was then to be veried and
in line with the monitored displacements (Fig. 18). The modied according to the monitored displacement and re-
direction of the displacement was an expansion of the determined in situ stress eld
powerhouse which is contrary to the convergence displace-
ments which would be associated with a major principal  Design of the optimal support system for the 1st
stress acting perpendicular to the powerhouse. Therefore, it excavation step of the underground powerhouse
ARTICLE IN PRESS
J.A. Hudson, X.T. Feng / International Journal of Rock Mechanics & Mining Sciences 44 (2007) 174195 189

According to analysis of the monitored displacements,


conclusions were drawn as follows: (1) The entire
underground powerhouse is stable; therefore the density
of the cable anchor system can be reduced. (2) Some
local areas of the underground powerhouse should be
reinforced by rock bolts; the engineering geologist
suggested that no. 1-1 block and no. 2-1 blocks are
potentially unstable but no. 3 block is stable. (3) The key
to the support is monitoring the displacement velocity
development.
 Design of the optimal support system for the 2nd to 3rd
excavation steps of the underground powerhouse
Because the rock bolted crane beam is located in the
region of the 2nd to 3rd excavation steps and the soft
strata are also replaced by concrete, there is no need for
modication of the support system design. However, the
cumulative vertical displacements at the crown and
Fig. 19. Geological cross-section and the positions of the monitored shoulder of underground powerhouse after the comple-
displacements.
tion of excavation of the 1st to 3rd steps were calculated
using FLAC3D with input of the recommended rock

23m

166.5m

f545
f671
f580

Bus tunel
y
65.47m

z x Replacement of soft rock 3#Set


(a)
(b) Tailrace 1# Set

Fig. 20. (a) The model mesh for the calculation region and (b) the underground powerhouse cavern group.

Fig. 21. Sketch of the layout of the displacement monitoring lines used in the feedback analysis of rock mass parameters.
ARTICLE IN PRESS
190 J.A. Hudson, X.T. Feng / International Journal of Rock Mechanics & Mining Sciences 44 (2007) 174195

mass mechanical parameters. The results were compared support vector machine and FLAC3D. The algorithm is
with the monitored values (Tables 5 and 6). described by Feng et al. [14,15]. Key values, such as the
The difference arises from the fact that the suggested mean settlement at the crown, the mean convergence of
mechanical parameters are higher than the actual ones. the side wall, the volume of the yielding regions and the
Therefore, back analysis of the mechanical parameters volume of the tensile zone of the surrounding rock mass,
based on the monitored displacement is required. the locations of the side wall where displacements are
 Design of the optimal support system for the 4th to 8th larger than 10 mm, plus the support expense, are used to
excavation steps of the underground powerhouse judge the applicability of the support system.
The support system for the 4th to 8th excavation steps
of the underground powerhouse was modied by a Accordingly, the optimal support designs retain the
study based on a combination of genetic algorithm, thickness of concrete as in the initial design as 150 mm. The
three rows of pre-stressed cable anchor for the upper
12
stream and down stream side walls in the original design
Monitored
can be reduced to 2 rows, because two rows of the cable
Calculated using the recognized parameters
10 anchors in the upper area can be united as one, and the
inter-cavern cable anchor in the lowest row can be kept.
Displacement (mm)

8 Meanwhile, the spacing of the cable anchors can be


increased from the original design of 4.57 m. The spacing
6 and row distance of the rock bolt system can be increased
to 3  3 m, and the length of the primary and secondary
4 rock bolts can be changed to 6 and 8 m, respectively.
Using the optimal support system as an input to
2 FLAC3D, the calculated results show that the maximal
displacement at the crown is 4.3 mm. The maximal
0 convergence displacement at the side wall is 12.0 mm, with
1 2 3 4 5 a mean value of 8.8 mm and mean settlement of 3.4 mm.
The monitoring line nos.
The volume of the tensile area is 110 m3 and the plastic
Fig. 22. Comparison between the calculated displacements (using the zone 10368 m3. The tensile stress around the powerhouse is
back-analysed mechanical parameters) with the monitored values. less than the tensile strength. Therefore, the underground
powerhouse is entirely stable. These results were veried by
the eld monitored displacements, indicating that the
Table 4 assumed optimal support system is adequate (Figs. 23
The recognised Youngs moduli values for different strata using the
monitored displacements after nishing the excavation from the 1st to 6th
and 24).
steps, in GPa
4.2.6. Design of the excavation procedure for the generator
P11q P1ma P21q P31q P41q foundation
8.1 1.4 19.3 5.1 20.3
The generator foundation socket was excavated starting
from the 7th step. The issues were that the surrounding

Table 5
Comparison of the calculated cumulative vertical displacement at the crown of the underground powerhouse (after nishing excavation of the 1st to 3rd
steps) with the monitored values (negative values refer to downward displacement)

Cross section no. (XCF)0+140.00 (XCF)0+120.00 (XCF)0+086.00 (XCF)0+055.00

The monitored settlement at the crown (mm) 2.0 2.2 2.9 4.5
The calculated settlement at the crown (mm) 2.4 2.6 2.8 3.6

Table 6
Comparison of the calculated convergence at the shoulder of the underground powerhouse after the completion of excavation of the 1st to 3rd steps with
the monitored values (negative values refer to inward displacement)

Cross section no. (XCF)0+140.00 (XCF)0+120.00 (XCF)0+086.00 (XCF)0+055.00

The monitored convergence at the shoulder (mm) 3.0 2.1 3.0 4.1
The calculated convergence at the shoulder (mm) 1.3 1.9 1.9 5.2
ARTICLE IN PRESS
J.A. Hudson, X.T. Feng / International Journal of Rock Mechanics & Mining Sciences 44 (2007) 174195 191

Fig. 23. Initial support system design provided by the designer (Rook boltRock bolt).

rock mass is weak and there is a secondary stress


concentration. Therefore, an optimal excavation procedure
and support system needed to be developed including
enhancing the stability of the peripheral rock mass. With
1 2 3 4 the recognised mechanical parameters listed in Table 3, the
excavation procedure and support system of the generator-
socket design were optimised using a combination of
genetic algorithm, support vector machine and FLAC3D.
The following ve options were considered:
Fig. 24. Sketch of the key points in the model for calculating the Scheme 1: When full sectional powerhouse excavation is
displacements (Table 7). carried out to the level 179 m, the rock mass below the
ARTICLE IN PRESS
192 J.A. Hudson, X.T. Feng / International Journal of Rock Mechanics & Mining Sciences 44 (2007) 174195

bench should be reinforced using a rock bolt and bolt-pile Step 3: Design approach strategy. The approach strategy
system and then the rock mass bench at level 179 m should included rock mass classication experience in this type of
be reinforced by using armoured concrete of 20 mm rock mass plus FEM analyses leading to an initial design
thickness and concrete grouting. The side wall of the rock which was to be adapted according to calculations and
mass bench is then reinforced by using pre-stressed cable monitored observations.
anchors and system rock bolts during the excavation Step 4: Modelling methods. The modelling methods are
process of the water-out tunnel. The Maanxi group coal shown in Figs. 25 and 26.
and the exposed rock mass is replaced with concrete. Step 5: Initial design. The method for establishing the
Scheme 2: When full sectional excavation is carried out initial design is illustrated in Fig. 25, which is the basic
to the level 169 m (i.e. the base of the powerhouse), the modelling owchart of Fig. 9 but with shaded boxes to
Maanxi group coal and the exposed rock mass is replaced show the methods used. Note that the methods used in the
with concrete to form a generator foundation. initial design were Method A Levels 1 and 2, Method B
Scheme 3: There is no rock bolt-pile; otherwise the Level 2 and Method C Level 1as forward analysis.
design is the same as Scheme 1. Step 6: Integration and feedback. This design was used
Scheme 4: The Maanxi group coal and rock mass for construction. Displacements were monitored and back
exposed is replaced with concrete, and the remaining design analysis conducted to estimate the rock stress and rock
is the same as Scheme 1. mechanics parameters.
Scheme 5: When full sectional excavation is carried out Step 7: Final design and verification. Given the construc-
to the level 179 m, the generator socket foundation is not tion experience and the back analysis of the rock stress and
supported. mechanical parameters, it was possible to re-analyse the
It can be seen from Tables 7 and 8 that Scheme 1 was the powerhouse circumstances by enhancing the modelling
most reasonable for the stability of the generator-socket methods, as shown in Fig. 26. Note that now, and as a
foundation. comparison with Fig. 25, the modelling methods used were
Method C Levels 1 and 2 and Method D Level 2as
linked to back analysis.
4.2.7. Example 2 summary This Shuibuya example demonstrates the way in which
With reference to our design owchart in Fig. 10, the an initial design is converted into a nal design using
design steps are as follows: monitored data during construction for further modelling
Step 1: Objective. To provide a suitable design for the based on back analysis. So, although the circumstances
Shuibuya powerhouse under the conditions known and could have appeared daunting initially, the systematic use
with particular reference to the soft rocks present. of a procedure as in Fig. 10 backed up by the modelling
Step 2: Features. The main feature to be taken into methods as structured in Fig. 9 enabled the nal design to
account was the presence of the weak strata inter-bedded be established and the powerhouse to be safely built in this
with the harder strata in the sedimentary formation, plus sedimentary rock mass with difcult soft and weak layers.
the fact that the host rock in the region was likely to be The initial and nal analysis steps are highlighted in Figs.
destressed because of the proximate faults and gorge walls. 25 and 26.

Table 7
The calculated sidewall displacements (mm) for Schemes 1 and 2

The monitoring lines in Fig. 19 Central section of Central section of Central section of Central section of
Generator 1 Generator 2 Generator 3 Generator 4

Scheme 1 10.0 11.2 9.5 9.0


L5 Scheme 2 11.8 16.2 14.8 10.9
Scheme 1 12.6 11.3 9.5 5.2
L6 Scheme 2 16.3 17.5 14.7 9.0

Table 8
The calculated displacements and yielding regions of the different foundation excavation schemes

Scheme no. Key point 1 in Fig. 24 Key point 2 in Fig. 24 Key point 3 in Fig. 24 Key point 4 in Fig. 24 Volume of yielding region
(mm) (mm) (mm) (mm) (m3)

1 18.4 21.8 12.9 6.5 7427


3 20.2 24.0 14.8 7.9 7496
4 21.3 24.1 15.3 8.3 7478
5 22.6 26.5 16.9 10.2 7564
ARTICLE IN PRESS
J.A. Hudson, X.T. Feng / International Journal of Rock Mechanics & Mining Sciences 44 (2007) 174195 193

Shuibuya Powerhouse

Method A Method B Method C Method D

Extended
Use of Basic numerical
Analytical numerical Level 1
pre-existing methods, FEM,
methods, methods,
standard BEM, DEM, 1:1 mapping
stress-based fully-coupled
methods hybrid
models
Site
Invest-
igation
Database
Integrated
Precedent type Rock mass expert
systems Level 2
analyses and classification, systems, &
approaches, Not 1:1 mapping
modifications RMR, Q, GSI other systems
internet-based
approaches

Design based on forward analysis Design based on back analysis

Construction

Fig. 25. Modelling methods used to support the initial design for the Shuibuya powerhouse.

Shuibuya Powerhouse

Method A Method B Method C Method D

Extended
Use of Basic numerical
Analytical numerical Level 1
pre-existing methods, FEM,
methods, methods,
standard BEM, DEM, 1:1 mapping
stress-based fully-coupled
methods hybrid
models
Site
Invest-
igation
Database
Precedent type Rock mass expert Integrated
analyses and classification, systems, & systems Level 2
modifications RMR, Q, GSI other systems approaches Not 1:1 mapping
approaches

Design based on forward analysis Design based on back analysis

Construction

Fig. 26. Modelling methods used to support the nal design of the Shuibuya powerhouse.

4.3. Illustrative example 3: The design of an underground There are three primary aspects inuencing the design of
radioactive waste repository in crystalline rock a repository for the disposal of radioactive waste.

The disposal of radioactive waste is a design problem 1. From the technical point of view and apart from
unprecedented in rock engineering and involves many political considerations, there is a wide choice for the
issues, both technical and political. Here we simply location of such a repositoryas compared to a
summarise the general principles of the modelling civil engineering tunnel which must run from Point A
and design based on the structured approach provided by to Point B or a mine which must be located at the
Figs. 9 and 10. orebody.
ARTICLE IN PRESS
194 J.A. Hudson, X.T. Feng / International Journal of Rock Mechanics & Mining Sciences 44 (2007) 174195

2. The design life of the repository is much longer than that Step 1: Objective. To design an underground repository
of a civil or mining underground structure. The life of a for the disposal of radioactive waste such that unacceptable
mine excavation can be anything from a few days to a quantities of radionuclides do not escape to the biosphere.
hundred years. Civil engineering structures are usually Step 2: Features. The three main features listed at the
designed for a life of about 120 years. However, a beginning of this third case example, plus the many FEPs
radioactive waste repository must be designed for (features, events and processes) identied during elicitation
thousands, hundreds of thousands, or millions of workshops.
yearsdepending on a particular countrys policy. Step 3: Design approach strategy. The design approach is
3. The function of the repository is that the waste should based on a hazard avoidance strategy, i.e. on nding a
be contained so that unacceptable radionuclide migra- location where the rock stresses are not too high, brittle
tion to the biosphere does not occur. So, the repository deformation zones are not too close, water ow through
is totally successful if nothing happenswhich is proximate fractures is acceptable, chemical effects are not
effectively non-functional compared to a civil and safety-critical issues, etc.
mining engineering facility. Step 4: Modelling methods. With reference to Fig. 9, we
cannot use Method A techniques because there is no
Despite this extraordinary combination of factors, the adequate precedent experience. Also, Method B Level 1
design procedure still follows the outline in Fig. 10 and is techniques are too simple. All other methods can then
supported by the modelling techniques highligfhted in Fig. be used, especially to provide cross-checking of the
9 and specically shown in Fig. 12. However, the rock results, Fig. 27. Moreover, the use of an extensive site
engineering design cannot be conducted in isolation investigation and Underground Research Laboratory
because there are other relevant subject disciplines, such provides the in situ ability to measure the rock parameters
as geology, hydrogeology, hydrogeochemistry and envir- directly and to use both forward and backward analyses. A
onmental issues. The interactions between all the dis- variety of full-scale experiments can be conducted, includ-
ciplines have to be taken into account [12]. ing a prototype repository construction, to provide
Because of the importance and complexity of a monitored values.
repository for radioactive waste, the initial design can be Step 5: Initial design. The initial design is then based on
additionally supported by the use of an Underground the hazard avoidance strategy backed up by the modelling
Research Laboratory, as has been done in several and in situ eld work.
countries. Step 6: Integration and feedback. There is considerable
The steps in the rock engineering design owchart in feedback through Steps 57 in Fig. 10. Additionally, there
Fig. 10 are as follows for this third case example. has to be inter-disciplinary interaction and feedback to

Radioactive waste repository

Method A Method B Method C Method D

Extended
Use of Basic numerical
Analytical numerical Level 1
pre-existing methods, FEM,
methods, methods,
standard BEM, DEM, 1:1 mapping
stress-based fully-coupled
methods hybrid
models
Site
Invest-
igation
Database
Precedent type Rock mass expert Integrated
analyses and classification, systems, & systems Level 2
modifications RMR, Q, GSI other systems approaches Not 1:1 mapping
approaches

Design based on forward analysis Design based on back analysis

Construction

Fig. 27. Modelling techniques used for the nal design and further in situ data provided through the use of an underground research laboratory plus the
repository construction itself.
ARTICLE IN PRESS
J.A. Hudson, X.T. Feng / International Journal of Rock Mechanics & Mining Sciences 44 (2007) 174195 195

ensure that the repository design is harmonious with all Mr. Ying Hu and Mr. Feng Zhang for their help with the
aspects. stability analysis of Shuibuya underground powerhouse
Step 7: Final design and verification. The nal design and to thank Shuibuya Construction Ltd. Co. and the
cannot be validated (in the sense that validation means full Changjiang Institute of Survey Planning Design and
conrmation that the design is adequate) because the Research, Yangtze Water Conservancy Committee, for
repository function cannot be tested for hundreds of the use of the eld and laboratory data relating to the
thousands of years, but it can be veried through Shuibuya underground powerhouse. Dr John Harrison of
monitoring of key parameter values. Imperial College, London, is also thanked for his
contribution to the modelling and code implementation
4.3.1. Example 3 summary principles presented in Section 3.5.
Although the design of a radioactive waste repository is
the most complex rock engineering design task, the
modelling and design principles still follow the owchart References
outlines in Figs. 9 and 10.
[1] Feng XT, Hudson JA. The ways ahead for rock engineering design
methodologies. Int J Rock Mech Min Sci 2004;41:25573.
5. Conclusions [2] Hoek E, Brown ET. Underground excavations in rock. Amsterdam:
Institution of Mining and Metallurgy, Elsevier Applied Science; 1977.
We have reviewed earlier rock mechanics modelling and 527pp.
[3] Pahl G, Beitz W. Engineering design. Berlin: Springer; 1984.
rock engineering design owcharts and concluded that
[4] Brady BHG, Brown ET. Rock mechanics for underground mining.
there is a need for updates to be provided. These have been London: George Allen & Unwin; 1985. 527pp.
provided via the two owcharts in Figs. 9 and 10. [5] Bieniawski ZT. Rock mechanics design in mining and tunneling.
The use of the two owcharts has been demonstrated by Rotterdam: A.A. Balkema; 1989.
three illustrative case examples covering a conventional [6] Bieniawski ZT. Classication of rock masses for engineering: the
highway tunnel, an underground powerhouse in sedimen- RMR system and future trends. In: Hudson JA, editor. Comprehen-
sive rock engineering, vol. 3. Oxford: Pergamon; 1993. p. 55373.
tary rock with weak layers, and a repository for radioactive [7] Hudson JA. Rock properties, testing methods and site characteriza-
waste. Despite the wide range of engineering functions, tion. In: Comprehensive rock engineering, vol. 3. Oxford: Elsevier;
scales and design lives, the new owcharts provide the 1993. p. 140 [Chapter 1].
necessary systematic framework for approaching the [8] Li S, Wu X, Ma F. Application of Precedent Type Analysis (PTA) in
modelling and design. the construction of Ertan Hydro-electric Station, China. Int J Rock
Mech Min Sci 1998;35(6):78795.
The rst and third case examples have been presented [9] Goricki A. Classication of rock mass behaviour based on a
briey: the rst because of its relative simplicity; the third hierarchical rock mass characterization for the design of underground
because of its relative complexity. The second case of the structures. PhD thesis. Austria: Graz University of Technology; 2003.
Chinese Shuibuya powerhouse design and construction has 98pp.
[10] Stephansson O, Hudson JA, Jing L, editors. Coupled thermo-hydro-
been presented at greater length because it illustrates the
mechanical-chemical processes. In: Geo-systems. Proceedings of the
owchart application so clearly. We described the Shui- GeoProc conference held in Stockholm October 2003, Geo-Engineer-
buya project, the geology, rock mechanics setting and ing Book Series. Oxford: Elsevier; 2005.
special features, the initial design of the underground [11] Xu W, Tan X, Yang S, editors. Advances in coupled thermo-hydro-
powerhouse, the monitoring and design feedback, the mechanical-chemical processes in geosystems and engineering.
modied design and design verication. Proceedings of the GeoProc conference held in Nanjing, China,
May 2006. China Science Press; 2006 (in press).
Thus, the owcharts in Figs. 9 and 10 can be used for the [12] Hudson JA, Stephansson O, Andersson J. Guidance on numerical
full spectrum of rock engineering designfrom the modelling of thermo-hydro-mechanical coupled processes for perfor-
simplest conventional type of tunnel right through to the mance assessment of radioactive waste repositories. Int J Rock Mech
more comprehensive analyses required for increasingly Min Sci 2005;42(56):85070.
[13] Zhou Y, Zhao Y, Cheng C, Zhi Q. The monitoring and analysis of
complex projects.
construction of Qiaotou tunnel at Yuanmo Express. Underground
Space 2002;22(2):1159.
Acknowledgements [14] Xia-Ting Feng, Honggang An. Hybrid intelligent methods optimiza-
tion of soft rock replacement scheme for large cavern excavated in
Financial support from the National Nature Science strata alternated with soft and hard rocks. Int J Rock Mech Min Sci
Foundation of China under Grant No. 50325414 and the 2004;41(4):65567.
[15] Xia-Ting Feng, Hongbo Zhao, Shaojun Li. A new displacement back
Special Funds for Major State Basic Research Project analysis to identify mechanical geo-material parameters using
under Grant No. 2002CB412708 are gratefully acknowl- integrated intelligent methodology. Int J Numer Anal Method
edged. The authors would like to thank Mr. Qigui Yang, Geomech 2004;28:114165.

You might also like