You are on page 1of 163

THIRD EDITION

Guide to

CONCRETE
OVERLAYS
Sustainable Solutions for Resurfacing and Rehabilitating Existing Pavements

May 2014

ACPA publication TB021.03P


On the Cover

source: Todd Hanson, Iowa DOT source: Jim Cable, Iowa State University source: Randell Riley, Illinois chapter, ACPA

source: Kevin Merryman, Iowa DOT source: The Transtec Group source: Todd Hanson, Iowa DOT
Technical Report Documentation Page

1. Report No. 2. Government Accession No. 3. Recipients Catalog No.


ACPA Publication TB021.03P

4. Title and Subtitle 5. Report Date


Guide to Concrete Overlays: Sustainable Solutions for Resurfacing and May 2014
Rehabilitating Existing Pavements (3rd edition) 6. Performing Organization Code

7. Author(s) 8. Performing Organization Report No.


Dale Harrington and Gary Fick
9. Performing Organization Name and Address 10. Work Unit No. (TRAIS)
National Concrete Pavement Technology Center
Institute for Transportation, Iowa State University 11. Contract or Grant No.
2711 South Loop Drive, Suite 4700
Ames, IA 50010-8664
12. Sponsoring Organization Name and Address 13. Type of Report and Period Covered
American Concrete Pavement Association
500 New Jersey Ave., NW 14. Sponsoring Agency Code
7th Floor
Washington, DC 20001
15. Supplementary Notes

16. Abstract
The primary goal of this guide is to fill the knowledge gap about concrete overlays so that pavement owners can
confidently include concrete overlays in their toolbox of pavement solutions and make more informed decisions about
designing and constructing them. Another goal is to help owner agencies understand and appreciate the versatility of
concrete overlay solutions. This is not a complete step-by-step manual, nor does it provide prescriptive formulae or
specifications for designing and constructing concrete overlays. Rather, as the title suggests, this booklet provides expert
guidance that can supplement practitioners own professional experience and judgment. In particular, since the 2nd edition
was published, this edition enhances original material with updated information on the following topics:
Evaluating existing pavements to determine if they are good candidates for concrete overlays
Selecting the appropriate overlay system for specific pavement conditions
Managing concrete overlay construction work zones under traffic
Accelerating construction of concrete overlays when appropriate

17. Key Words 18. Distribution Statement


Pavements concrete overlays resurfacing pavement preservation
pavement rehabilitation
19. Security Classification (of this 20. Security Classification (of this 21. No. of Pages 22. Price
report) page) 145 plus front matter
and Notes page
Unclassified. Unclassified.

Form DOT F 1700.7 (8-72) Reproduction of completed page authorized


Guide to Concrete Overlays
Sustainable Solutions for Resurfacing
and Rehabilitating Existing Pavements

Third Edition, May 2014

Authors
Dale Harrington, Snyder & Associates, Inc.
Gary Fick, Trinity Construction Management Services, Inc.

Contributing Technical Authors


Amanda Bordelon, PhD, University of Utah
James Cable, PhD, P.E., Cable Concrete Consultation LC
Dan DeGraaf, P.E., Michigan Concrete Paving Association
Nigel Parkes, PNA Construction Technologies, Inc.
Randell Riley, P.E., Illinois Chapter, American Concrete Pavement Association
Rob Rodden, P.E., American Concrete Pavement Association
Jeff Roesler, PhD, P.E., University of Illinois at Urbana-Champaign
Julie Vandenbossche, PhD, P.E., University of Pittsburg

Project Coordinator
Melisse Leopold, Snyder & Associates, Inc.

Managing Editor
Marcia Brink, National Concrete Pavement Technology Center

Copyeditor
Carol Gostele, Birch Tree Editing

Technical Illustrator
Luke Snyder, Snyder & Associates, Inc.

Design and Layout


Mina Shin
About This Guide Abbreviations
This guide is a product of the National Concrete Pavement Technology AASHTO American Association of State Highway and
Center (CP Tech Center) at Iowa State University, with funding from Transportation Officials
the American Concrete Pavement Association. It is the third edi- ACI American Concrete Institute
tion of the Guide to Concrete Overlays since 2007. Complementary ACPA American Concrete Pavement Association
publications by the CP Tech Center include the Guide to the Design
ASR alkali-silica reactivity/reaction/reactive
of Concrete Overlays Using Existing Methodologies (October 2012),
Guide to Concrete Overlays of Asphalt Parking Lots (October 2012), ASTM American Society for Testing and Materials
and Preservation and Rehabilitation of Urban Concrete Pavements Using CRCP continuously reinforced concrete pavement
Thin Concrete Overlays: Solutions for Joint Deterioration in Cold Weather CTE coefficient of thermal expansion
States (anticipated publication June 2014). The entire series of con- FAQ frequently asked question
crete-overlays related documents is on the CP Tech Centers website, FHWA Federal Highway Administration
www.cptechcenter.org/. FRC fiber-reinforced concrete
FWD falling weight deflectometer
Acknowledgments IRI
JPCP
International Roughness Index
jointed plain concrete pavement
The CP Tech Center gratefully acknowledges the generous financial M-E PDG Mechanistic-Empirical Pavement Design Guide
support of the American Concrete Pavement Association regarding the MRD material-related distress
development and printing of this guide. Without the associations sup- MUTCD Manual on Uniform Traffic Control Devices
port, there would be no third edition. In addition, the CPTech Center NCHRP National Cooperative Highway Research Program
and the authors wish to thank the knowledgeable, experienced, and
PCA Portland Cement Association
dedicated concrete pavement experts, both public and private, who
served on the Technical Advisory Committee and contributed to the PCC portland cement concrete
development of this guide. The committee consists of the following SCM supplementary cementitious material
people: TRB Transportation Research Board
Gina Ahlstrom, P.E., FHWA TCP traffic control plan
Andy Bennett, Michigan Department of Transportation
Tom Burnham, P.E., Minnesota Department of Transportation For More Information
Jim Cable, PhD., P.E., Cable Concrete Consultation LC Tom Cackler, Director
Dan DeGraaf, P.E., Michigan Concrete Paving Association Marcia Brink, Senior Editor
National Concrete Pavement Technology Center
Jim Duit, Duit Construction Co., Inc. Iowa State University Research Park
Jim Grove, P.E., Senior Project Engineer, FHWA 2711 S. Loop Drive, Suite 4700
Todd Hanson, P.E., Iowa Department of Transportation Ames, IA 50010-8664
Kevin Maillard, P.E., OHM Advisors 515-294-9480
www.cptechcenter.org/
Kevin Merryman, P.E., Iowa Department of Transportation
mbrink@iastate.edu
Randell Riley, P.E., Illinois Chapter, ACPA
Robert Rodden, P.E., ACPA
Mission
Jeff Roesler, PhD, P.E., University of Illinois at Urbana-Champaign
The mission of the National Concrete Pavement Technology Center
Gordon Smith, P.E., Iowa Concrete Paving Association is to unite key transportation stakeholders around the central goal of
Mark Snyder, PhD, P.E., Pennsylvania Chapter, ACPA advancing concrete pavement technology through research, technology
Shannon Sweitzer, P.E., North Carolina Turnpike Authority transfer, and technology implementation.
Sam Tyson, P.E., Federal Highway Administration
Jeff Uhlmeyer, P.E., Washington State Department of For Additional Copies
Transportation
The American Concrete Pavement Association is distributing this
Julie Vandenbossche, PhD, P.E., University of Pittsburgh guide. For additional copies, contact your local ACPA chapter or
Leif Wathne, P.E., American Concrete Pavement Association affiliated state paving association (www.acpa.org/ournetwork); ask for
Matt Zeller, P.E., Concrete Paving Association of Minnesota ACPA publication no. TB021.03P.

Disclaimers
Neither Iowa State University nor this documents authors, editors, designers, illustrators, distributors, or technical advisors make any representations or warranties, expressed or implied, as to the accuracy of information
herein and disclaim liability for any inaccuracies.
Iowa State University does not discriminate on the basis of race, color, age, religion, national origin, sexual orientation, gender identity, sex, marital status, disability, genetic testing, or status as a U.S. veteran. Inquiries can
be directed to the Director of Equal Opportunity and Diversity, Iowa State University, 3680 Beardshear Hall, 515-294-7612.
Contents

List of Figures..................................................................................... ix Overlay Design.......................................................................... 27


List of Tables..................................................................................... xii Construction............................................................................. 28
Future Repairs........................................................................... 29
Ch 1. Introduction.................................................................. 1
Key Resources................................................................................ 29
Two Concrete Overlay (Resurfacing) Options......................................... 2
Bonded Concrete Overlay on Composite Pavements......................... 30
Bonded Overlay Option.................................................................. 2
Application and Uses..................................................................... 30
Unbonded Overlay Option............................................................. 3
Performance.................................................................................. 31
Benefits of Concrete Overlays.............................................................. 3
Keys to Success.............................................................................. 31
History of Concrete Resurfacing......................................................... 4
Overlay Process............................................................................. 31
Improvements in Concrete Resurfacing Technology............................... 4
Pavement Evaluation................................................................. 31
Sustainability....................................................................................... 5
Overlay Design.......................................................................... 31
Asset Management through Resurfacing Solutions................................ 5
Construction............................................................................. 32
Preventive Maintenance................................................................... 6
Future Repairs........................................................................... 33
Minor Rehabilitation....................................................................... 6
Key Resources................................................................................ 33
Major Rehabilitation....................................................................... 6
Bonded Concrete Overlay on Concrete Pavements............................ 34
Lessons Learned from Recent Concrete Overlay Projects..................... 6
Application and Uses..................................................................... 34
Project Evaluation and Selection...................................................... 6
Performance.................................................................................. 34
Concrete Overlay Design................................................................. 7
Keys to Success.............................................................................. 35
Plans and Specifications................................................................... 7
Overlay Process............................................................................. 35
Sequence of Construction and Maintenance of Traffic..................... 7
Pavement Evaluation................................................................. 35
Concrete Overlay Construction....................................................... 8
Overlay Design.......................................................................... 36
Ch 2. Evaluating Pavements and Selecting Solutions....... 9 Construction............................................................................. 36
Pavement Evaluation Process............................................................. 11 Future Repairs........................................................................... 37
Historical Data and Future Projections (Desk Review).................. 12 Key Resources................................................................................ 37
Visual Examination (On-site Review)............................................ 12 Unbonded Concrete Overlay on Asphalt Pavements.......................... 38
Existing Support and Localized Distress..................................... 12 Application and Uses..................................................................... 38
Vertical Constraints................................................................... 14 Performance.................................................................................. 39
Profile Grade............................................................................. 14 Keys to Success.............................................................................. 39
Pavement Coring........................................................................... 15 Overlay Process............................................................................. 39
Optional Analyses.......................................................................... 15 Pavement Evaluation................................................................. 39
Deflection Testing...................................................................... 16 Overlay Design.......................................................................... 39
Alternative Means of Determining Support Conditions.............. 16 Construction............................................................................. 40
Roughness and Surface Friction Tests......................................... 17 Future Repairs........................................................................... 41
Condition Assessment Profile........................................................ 17 Key Resources................................................................................ 41
Pavement Evaluation Report.......................................................... 17 Unbonded Concrete Overlay on Composite Pavements...................... 42
Selecting Appropriate Concrete Overlay Solution................................ 17 Application and Uses..................................................................... 42
Performance.................................................................................. 43
Ch 3. Overview of Concrete Overlay Options.................... 25 Keys to Success.............................................................................. 43
Bonded Concrete Overlay on Asphalt Pavements.............................. 26 Overlay Process............................................................................. 43
Application and Uses..................................................................... 26 Pavement Evaluation................................................................. 43
Performance.................................................................................. 27 Overlay Design.......................................................................... 43
Keys to Success.............................................................................. 27 Construction............................................................................. 44
Overlay Process............................................................................. 27 Future Repairs........................................................................... 45
Pavement Evaluation................................................................. 27 Key Resources................................................................................ 45

Guide to Concrete Overlays v


Contents, continued

Unbonded Concrete Overlay on Concrete Pavements....................... 46 Measurement and Payment Items for Concrete Overlays................... 63
Application and Uses..................................................................... 46 Establishing Plan Quantity for Overlay Concrete.......................... 63
Performance.................................................................................. 47 Typical Costs of Concrete Overlays................................................... 64
Keys to Success.............................................................................. 47 Miscellaneous Design Details............................................................ 64
Overlay Process............................................................................. 47 Curb and Gutter Details................................................................ 64
Pavement Evaluation................................................................. 47 Leaving the Existing Curb in Place............................................ 64
Overlay Design.......................................................................... 47 Removing Curb and Gutter....................................................... 64
Construction............................................................................. 48 Overlay Curb............................................................................. 64
Future Repairs........................................................................... 49 Vertical Grade Changes................................................................. 65
Key Resources................................................................................ 49 Overhead Clearance .................................................................. 65
Barriers and Rails ...................................................................... 65
Ch 4. Concrete Overlay Design........................................... 51
Safety Edge ............................................................................... 65
Concrete Overlay Design Variables.................................................... 51
Cross Road Drainage Structures ................................................ 65
Existing Pavement Characterization............................................... 51
Cross Slope and Superelevation ................................................. 65
Surface Considerations.............................................................. 51
In-place Pavement Structures......................................................... 66
Structural Considerations.......................................................... 52
Plate Dowel Details....................................................................... 66
Traffic Characterization.............................................................. 52
Corrosion Resistance................................................................. 67
Material Properties..................................................................... 52
Plate Dowel Installation for Construction Joints Formed with a
Climatic Factors......................................................................... 53 Bulkhead (Form).................................................................... 67
Distress Mode............................................................................ 53 Plate Dowel Installation in Slipform or Full-depth Saw Cut
Thickness Design Selection............................................................ 53 (Butt-type) Construction Joints................................................. 67
Background of Design Methodologies....................................... 53 Dowel Installation for Contraction Joints.................................. 68
ACPA BCOA Method............................................................... 53 Transitions..................................................................................... 69
BCOA-ME Method.................................................................. 55 Mill and Fill Transitions for Bonded Concrete Overlays............. 69
1993 AASHTO Guide Method................................................. 55 Transition Details for Bonded Concrete Overlays...................... 69
AASHTO Pavement ME Design Guide Method....................... 56 Transition Details for Unbonded Concrete Overlays.................. 70
ACPA StreetPave Method.......................................................... 56 Widening and Lane Addition........................................................ 71
Slabs with Optimized Geometry and OptiPave2 Design Typical Drainage Outlets for Interlayers........................................ 73
Software................................................................................. 57 Rural Conditions....................................................................... 73
Design Considerations for Bonded Overlay Systems......................... 57 Urban Conditions...................................................................... 74
Bonded Overlays of Asphalt and Composite Pavements................ 57
Bonded Overlays of Concrete Pavements....................................... 58 Ch 5. Concrete Overlay Materials and Mixtures................ 75

Design Considerations for Unbonded Overlay Systems...................... 58 Primary Concrete Materials............................................................... 75

Unbonded Overlays of Concrete Pavements.................................. 59 Cementitious Materials................................................................. 75

Suitability of Existing Pavement as a Base.................................. 59 Aggregates..................................................................................... 75

Interlayer................................................................................... 59 Admixtures.................................................................................... 76

Drainage of Interlayer................................................................ 60 Conventional Concrete Mixtures...................................................... 76

Joint Design.............................................................................. 61 Low w/cm Ratio............................................................................ 76

Unbonded Overlays of Asphalt Pavements..................................... 62 Adequate Air Void System............................................................. 76

Unbonded Overlays of Composite Pavements............................... 62 Accelerated Mixtures......................................................................... 76

Plan Development............................................................................. 62 Other Materials................................................................................. 77

Engineering Survey........................................................................... 62 Structural Fibers for Concrete Overlays......................................... 77

Survey Methods............................................................................. 62 Separation Layer Materials............................................................. 78

Laser Scanning.............................................................................. 63 Asphalt Separation Layer........................................................... 78


Nonwoven Geotextile Separation Layer..................................... 79

vi Guide to Concrete Overlays


Contents, continued

Dowel Bars and Tiebars................................................................. 80 Rubblization of Concrete Pavement................................................ 111


Joint Sealant.................................................................................. 80 Crack and Seat (Not Recommended).............................................. 112
Curing Compound........................................................................ 80
Appendix C. Fiber Reinforcement.................................... 113
Ch 6. Concrete Overlay Strategies in Work Zones............ 81 Why Fibers?.................................................................................... 113
Objectives of Work Zone Management............................................. 81 Types of Fibers................................................................................ 113
Safety............................................................................................ 82 High-volume Macro Synthetic Fiber Mixtures................................ 114
Traffic Flow................................................................................... 82 Construction Considerations When Using Fibers............................ 114
Cost Effectiveness.......................................................................... 82
Appendix D. Laser Scanning Survey................................ 116
Work Zone Space Considerations...................................................... 82
Roadway Surface 3-D Laser Scanning............................................. 116
Conventional Paving Equipment Clearances................................. 82
Scanning Applications to Pavements............................................... 116
Reducing Clearances................................................................83
Other Clearances........................................................................... 85 Planning Items to Be Considered.................................................... 116
Construction Traffic Control............................................................. 85 Data Analysis.................................................................................. 117
Concrete Overlay Staging.................................................................. 85 Static Scanning Operation............................................................... 118
Two-Lane Highway under Traffic.................................................. 85 Mobile 3-D Laser Scanning............................................................. 118
Temporary Safety Fillet.............................................................. 86 Mobile Mapping Operations........................................................... 118
Pilot Cars for Continuous Production....................................... 86
Appendix E. Factors for Constructing Concrete
Examples of Staging Sequences...................................................... 86 Overlays Under Traffic..................................................... 119
Two-Lane Highway Expanded to Three Lanes under Traffic.......... 86
Four-Lane Divided Highway without Crossovers and under Appendix F. Stringless Paving Operation........................ 127
Traffic............................................................................................ 87 Horizontal and Vertical Control Requirements and System
Limitations.................................................................................. 127
Ch 7. Construction of Concrete Overlays........................... 99 Three-step Process for Stringless Paving........................................... 128
Key Points for Concrete Overlay Construction.................................. 99 Existing Stringless Control Systems................................................. 129
Bonded Overlays: Ensuring Proper Bond........................................ 102 System No. 1.............................................................................. 129
Unbonded Overlays: Installation of Geotextile Interlayer Fabric...... 103 System No. 2.............................................................................. 130
Placing Dowel Baskets..................................................................... 104 System No. 3............................................................................... 130
Curing Concrete Overlays............................................................... 105 Stringless System Equipment Selection Criteria............................... 131
Sawing Joints................................................................................... 105
Accelerated Construction................................................................ 105 Appendix G. Considerations for Developing Project
and Supplemental Specifications................................. 132
Opening Overlay to Traffic.............................................................. 106
General........................................................................................... 132
Minimizing Early Loading Fatigue Damage.................................. 106
Contractor Submittal Considerations.......................................... 132
Strength Conversions ................................................................. 106
Scheduling and Conflicts............................................................. 132
Strength Criteria for Opening Bonded Overlay Systems ............. 106
Limitations of Operations........................................................... 132
Bonded on Concrete................................................................ 106
Method of Measurement and Basis of Payment........................... 132
Bonded on Asphalt.................................................................. 106
Materials......................................................................................... 132
Strength Criteria for Opening Unbonded Overlay Systems......... 106
Separation Layer for Unbonded Overlays.................................... 133
Repairs of Concrete Overlays.......................................................... 107
Construction................................................................................... 133
Repairs of Bonded or Thin Unbonded Concrete Overlays........... 107
Preoverlay Repairs........................................................................ 133
Repairs of Full-Depth Unbonded Concrete Overlays................... 108
Bonded Concrete Overlays Over Concrete.............................. 133
Appendix A. Evaluation and Selection Tables................. 109 Bonded Concrete Overlays Over Asphalt................................. 133
Unbonded Overlays Over Concrete......................................... 133
Appendix B. Reconstruction Options for Concrete..........111 Unbonded Concrete Overlays Over Asphalt............................ 133
In-place Recycled Concrete as a Processed Base Material................. 111

Guide to Concrete Overlays vii


Contents, continued

Surface Cleaning......................................................................... 133 Bonded Overlays Over Asphalt................................................ 134


Bonded Concrete Overlays Over Concrete or Asphalt............. 133
Unbonded Overlays................................................................. 134
Unbonded Concrete Overlays Over Concrete or Asphalt......... 133
Appendix H. Suggested Owner-Contractor Meetings
Concrete Placement..................................................................... 133 to Ensure a Quality Product.......................................... 135

Grade Control......................................................................... 133 Prebid Meeting Check List.............................................................. 135

Overlay Placement................................................................... 133 Prebid Meeting................................................................................ 135
Liquid Membrane Curing........................................................... 134 Prepour/Preconstruction Review Checklist...................................... 135
Joint Sawing................................................................................ 134

General.................................................................................... 134 Appendix I. Innovative Methods for Accelerated
Concrete Overlay Construction..................................... 138

Joint Width............................................................................. 134

Joint Seal................................................................................. 134 References.......................................................................... 141

Timing.................................................................................... 134
Bonded Overlays Over Concrete............................................. 134 Bibliography....................................................................... 144

viii Guide to Concrete Overlays


List of Figures

Figure 1. Typical concrete overlay (before and after concrete Figure 26. Bonded concrete overlay of good condition concrete
overlay placement)........................................................ 1 pavement with surface distresses.................................. 34

Figure 2. Types of concrete overlays............................................. 2 Figure 27. Bonded concrete on concrete...................................... 34

Figure 3. Milling concrete (left) and milled surface (right)........... 3 Figure 28. Photo of concrete pavement with shotblast surface
prior to concrete overlay in 1994................................. 35
Figure 4. Forty-six states where concrete overlays have been
constructed (shaded in blue)......................................... 4 Figure 29. Three-inch concrete bonded overlay (photo dated
2013).......................................................................... 35
Figure 5. Appropriate preservation solutions at various stages
of pavement service life................................................. 5 Figure 30. Width of transverse joint in bonded concrete
overlay on concrete pavement should be equal to or
Figure 6. Typical bonded and unbonded concrete solutions greater than width of crack in existing pavement......... 36
at various stages of pavement service life........................ 6
Figure 31. Crack cage over concrete pavement crack.................... 37
Figure 7. Pavement evaluation process, with examples of
existing pavement conditions...................................... 10 Figure 32. Unbonded concrete overlay (previously called
conventional whitetopping) of poor-to-deteriorated
Figure 8. Examples of existing pavement conditions, from a condition asphalt pavement......................................... 38
condition assessment profile........................................ 11
Figure 33. Unbonded concrete overlay of asphalt pavement......... 38
Figure 9. Visual inspection for MRD deterioration at the edge
of pavement................................................................ 13 Figure 34. Poor to deteriorated asphalt pavement to be
resurface...................................................................... 39
Figure 10. Moderate ASR cracking along the perimeter of slab.... 13
Figure 35. Poor to deteriorated asphalt pavement resurfaced
Figure 11. D-cracked pavement................................................... 14 with unbonded concrete overlay.................................. 39
Figure 12. Typical joint deterioration with HMA patch .............. 14 Figure 36. Consider asphalt rut depth when determining
saw-cut depth.............................................................. 41
Figure 13. Dynamic cone penetrometer....................................... 16
Figure 37. Unbonded concrete overlay of poor-to-deteriorated
Figure 14. Selecting appropriate concrete overlay solution condition composite pavement.................................... 42
for asphalt pavements.................................................. 18
Figure 38. Unbonded overlay of composite.................................. 42
Figure 15. Selecting appropriate concrete overlay solution for
composite pavements.................................................. 20 Figure 39. Composite pavement prior to unbonded concrete
overlay......................................................................... 43
Figure 16. Selecting appropriate concrete overlay solution for
concrete pavements..................................................... 22 Figure 40. Unbonded concrete overlay over composite
pavement.................................................................... 43
Figure 17. Bonded concrete overlay of fair or better asphalt
pavement with surface distresses (previously called Figure 41. Consider asphalt rut depth when determining
ultra-thin whitetopping).............................................. 26 saw-cut depth.............................................................. 45
Figure 18. Bonded overlay of asphalt pavement............................ 26 Figure 42. Unbonded concrete overlay of poor condition
concrete pavement....................................................... 46
Figure 19. SH-119 in 1991 prior to placement of an bonded
concrete overlay........................................................... 27 Figure 43. Unbonded concrete on concrete.................................. 46
Figure 20. SH-119 in 2009 after 18 years of service..................... 27 Figure 44. Route D35 existing pavement in poor condition......... 47
Figure 21. Longitudinal joints should be arranged to avoid Figure 45. Route D35 5-inch unbonded overlay.......................... 47
wheel paths................................................................. 28
Figure 46. Overlay design factors that affect one another............. 51
Figure 22. Bonded concrete overlay of fair or better condition
composite pavement with asphalt surface distresses..... 30 Figure 47. Illustration of structural capacity loss over time
and with traffic............................................................ 56
Figure 23. Bonded overlay of asphalt............................................ 30
Figure 48. Width of overlay joint saw cut must be greater than
Figure 24. Existing composite pavement...................................... 31 the crack width in the existing pavement..................... 58
Figure 25. Bonded on composite pavement................................. 31

Guide to Concrete Overlays ix


List of Figures, continued

Figure 49. Upper sketch shows concrete overlay locking up Figure 73. Mill and fill transition for concrete overlay of asphalt
with old pavement (keying), and lower sketch shows or composite pavement............................................... 69
interlayer separates overlay from existing pavement..... 59
Figure 74. New transition tapers used to meet bridge approach
Figure 50. Geotextile fabric separation layer................................. 60 slabs or maintain clearance under bridges with bonded
overlay of concrete pavement....................................... 69
Figure 51. White geotextile fabric interlayer................................. 60
Figure 75. New transition tapers used to meet bridge approach
Figure 52. Overlay blowup where expansion joint should have slabs or maintain clearance under bridges with
been cut over existing concrete expansion joint........... 60 bonded overlay of asphalt pavement............................ 69
Figure 53. Asphalt stripping of interlayer..................................... 61 Figure 76. New transition tapers used to meet bridge approach
slabs or maintain clearance under bridges with
Figure 54. Tapered plate dowel baskets in transverse contraction unbonded overlay of concrete pavement...................... 70
joints and football-shaped plate dowels for slipformed
longitudinal construction joints.................................. 61 Figure 77. New transition tapers used to meet bridge approach
slabs or maintain clearance under bridges with
Figure 55. Higher shrinkage restraint in joint intersection unbonded overlay of asphalt pavement........................ 70
with round dowel (left) versus joint intersection
with plate dowel (right)............................................... 61 Figure 78. Temporary granular transition to existing side
road/driveway.............................................................. 70
Figure 56. Digital terrain model acquired through laser
scanning...................................................................... 63 Figure 79. Asphalt wedge transition to existing side
road/driveway.............................................................. 70
Figure 57. Concrete overlay cost by thickness............................... 64
Figure 80. Bonded overlay of concrete pavement with
Figure 58. Milling detail when leaving the existing curb in widening unit.............................................................. 71
place............................................................................ 64
Figure 81. Bonded overlay of asphalt or composite pavement
Figure 59. Milling detail when removing and replacing curb......... 64 with widening unit...................................................... 71
Figure 60. Detail of curb overlay.................................................. 64 Figure 82. View of tiebars for concrete overlay widening unit.........71
Figure 61. Concrete curb overlay.................................................. 64 Figure 83. Unbonded overlay of concrete, asphalt, or
composite pavement with widening unit..................... 72
Figure 62. Typical safety edge for concrete overlay without
paved shoulder............................................................ 65 Figure 84. Bonded or unbonded overlay of asphalt or composite
pavement (previously widened with asphalt or concrete,
Figure 63. Dowel options in superelevation areas......................... 65
and to be widened again with new concrete overlay)... 72
Figure 64. Concrete overlay with standard manhole..................... 66
Figure 85. Unbonded overlay of concrete, asphalt, or composite
Figure 65. Diamond-shaped plate dowels in fixed-formed pavement with full concrete lane addition................... 72
construction joints (right side) and football-shaped
Figure 86. Interlayer outlet for concrete overlay shoulder............. 73
dowels by slipforms..................................................... 66
Figure 87. HMA interlayer outlet for asphalt shoulder................. 73
Figure 66. Detail of construction joint plate dowel for
fixed-form paving........................................................ 67 Figure 88. Geotextile interlayer outlet with new paved shoulder
(concrete or asphalt).................................................... 73
Figure 67. Taper-shaped construction joint plate dowel using
fixed forms.................................................................. 67 Figure 89. Drainage of separation layer (interlayer) into an
existing underdrain system when existing curb is
Figure 68. Detail of construction joint plate dowel for slipform
removed and replaced.................................................. 74
paving......................................................................... 67
Figure 90. Drainage of separation layer fabric into intake
Figure 69. Slots being cut to accept the football-shaped plate
when curb is not removed........................................... 74
dowels......................................................................... 67
Figure 91. Synthetic fibers (1.5 in. to 2.25 in.)............................. 77
Figure 70. Detail of plate dowel for contraction joint................... 68
Figure 92. Geotextile separation layer........................................... 79
Figure 71. Plan view of roadway with plate dowels....................... 68
Figure 93. Light-colored geotextile fabric used as a separation
Figure 72. Mill and fill transition for concrete overlay of
layer for an unbonded overlay..................................... 79
concrete pavement....................................................... 69

x Guide to Concrete Overlays


List of Figures, continued

Figure 94. Managing work zones effectively involves Figure 116. Removing overlay panels........................................... 107
balancing several priorities........................................... 81
Figure 117. Finish and cure of concrete overlay repair.................. 107
Figure 95. Stringline paver........................................................... 83
Figure 118. Typical concrete pavement milling operation............ 107
Figure 96. A three-track, zero-clearance paver placing concrete
along a median barrier................................................. 83 Figure 119. Typical concrete pavement milling operation............ 107

Figure 97. A typical four-track paver modified to three tracks, Figure 120. Typical concrete pavement millings from milling
providing zero clearance in a C/G situation operation................................................................... 108
in Oklahoma............................................................... 83
Figure 121. Recycled concrete aggregate....................................... 111
Figure 98. Controlling paving profile using a moveable stringline
on the adjacent lane.................................................... 84 Figure 122. Rubblized concrete pavement.................................... 111

Figure 99. Controlling paving profile using a paver ski on the Figure 123. Fibers in concrete mix............................................... 113
adjacent lane............................................................... 84
Figure 124. Fibers added at plant (left) and bags tossed into
Figure 100. Stringless paver............................................................ 84 ready-mix truck (right)............................................... 114

Figure 101. Zero clearance stringless paver..................................... 84 Figure 125. Finished concrete overlay with synthetic fibers.......... 115

Figure 102. Vertical traffic control panels may be used to mark Figure 126. Balling fibers............................................................. 115
pavement edge dropoff................................................ 86
Figure 127. Typical mobile scan project workflow........................ 117
Figure 103. Centerline safety edge fillets for overlays
Figure 128. Pavement DTM/detail.............................................. 117
3 in. (50 mm) or greater.............................................. 86
Figure 129. Pavement cross section detail..................................... 117
Figure 104. Overlay of two-lane roadway with paved shoulders
(conventional paver).................................................... 88 Figure 130. Static laser scanner.................................................... 118
Figure 105. Overlay of two-lane roadway with granular shoulders Figure 131. Mobile laser scanner.................................................. 118
(conventional paver).................................................... 90
Figure 132. Mobile scanner onboard quality control
Figure 106. Overlay of two-lane roadway with minimum operation area............................................................ 118
granular shoulders (zero-clearance paver)..................... 92
Figure 133. Paving machine control............................................. 127
Figure 107. Overlay of two-lane roadway widening to three
lanes with paved shoulder (conventional paver)........... 94 Figure 134. Survey existing surface to develop and build
database.................................................................... 128
Figure 108. Overlay of four-lane roadway with paved shoulders
(conventional paver).................................................... 96 Figure 135. ATV with GPS and laser profile................................ 128

Figure 109. Compare the surface texture of the nonshotblasted Figure 136. Total robotic station.................................................. 129
area (upper left half of image) to the roughened
surface texture on the shotblasted section of Figure 137. System 1Stringless paving operation using total
pavement (under the pen)......................................... 102 stations and reference points...................................... 129

Figure 110. Overlap of nonwoven geotextile material section....... 103 Figure 138. Computer controls on paving machine..................... 129

Figure 111. Fastening nonwoven geotextile fabric to existing Figure 139. Rotating laser over reference points........................... 130
concrete pavement..................................................... 103
Figure 140. System 2 paving machine.......................................... 130
Figure 112. Paving on top of nonwoven geotextile materials......... 104
Figure 141. System 2Stringless paving operation using GPS,
Figure 113. Paving on top of white geotextile fabric interlayer..... 104 a rotating laser, and reference points.......................... 130

Figure 114. Dowel basket anchor nails should be placed on Figure 142. GPS base station mobile or fixed............................... 131
the downstream side of the basket relative to the
direction of pavement................................................ 104 Figure 143. GPS paver control system.......................................... 131

Figure 115. Manually verifying dowel placement......................... 104 Figure 144. System 3Stringless paving operation using GPS..... 131

Guide to Concrete Overlays xi


List of Tables

Table 1. Recommended Optional Testing................................. 15 Table 14. Size and Spacing of Plate Dowels for Contraction
Joints........................................................................... 66
Table 2. Subgrade Soil Types and Approximate Support
Values.......................................................................... 17 Table 15. The Effect of Aggregate Gradation on Mixture
Properties.................................................................... 75
Table 3. Possible Preoverlay Repairs on Existing Asphalt
Pavement in Preparation for Bonded Overlay.............. 28 Table 16. Slab Thickness and Opening Strength......................... 77

Table 4. Possible Preoverlay Repairs on Existing Composite Table 17. Summary of Fiber Types.............................................. 78
Pavement in Preparation for Bonded Overlay.............. 32
Table 18. Michigan DOT Asphalt Separation Layer Gradation.. 78
Table 5. Possible Preoverlay Repairs on Existing Concrete
Pavement in Preparation for Bonded Overlay.............. 37 Table 19. Geotextile Separation Layer Material Properties.......... 79

Table 6. Possible Preoverlay Repairs on Existing Asphalt Table 20. Concrete Overlay Work Zone Management
Pavement in Preparation for Unbonded Overlay......... 40 Considerations............................................................ 81

Table 7. Possible Preoverlay Repairs on Existing Composite Table 21. Concrete Paving Construction Practices for
Pavement in Preparation for Unbonded Overlay......... 44 Overlays...................................................................... 99

Table 8. Typical Transverse Joint Spacing.................................. 48 Table 22. Distress Types and Severity Levels Recommended
for Assessing Concrete Pavement Structural
Table 9. Possible Preoverlay Repairs on Existing Concrete Adequacy.................................................................. 109
Pavement in Preparation for Unbonded Overlay......... 49
Table 23. Distress Types and Levels Recommended for Assessing
Table 10. Summary of Current Overlay Design Software ........... 54 Asphalt and Composite Pavement Structural
Adequacy.................................................................. 110
Table 11. Typical Weight and Thickness for Geotextile
Interlayer..................................................................... 60 Table 24. Considerations for Concrete Overlay Construction
under Traffic.............................................................. 119
Table 12. Typical Adjustment Factors for Estimating Overlay
Cubic Yard Plan Quantities......................................... 63 Table 25. Applicability, Pros, and Cons of Various Accelerated
Construction Methods.............................................. 138
Table 13. Size and Spacing of Plate Dowels for Construction
Joints........................................................................... 66

xii Guide to Concrete Overlays


Ch 1. INTRODUCTION

Chapter 1.

INTRODUCTION

The need has never been greater for engi- agencies and contractors have hesitated to ance that can supplement practitioners own
neered strategies to preserve and maintain design and construct them. One reason may professional experience and judgment.
the nations pavements. With shrinking be a lack of understanding of engineered con-
Another goal of this guide is to help owner
budgets, ever-increasing traffic volumes and crete overlays. The primary goal of the Guide
agencies understand and appreciate the versa-
loads, and the critical emerging focus on to Concrete Overlays series, therefore, is to
tility of concrete overlay solutions. A common
infrastructure sustainability and pavement fill the knowledge gap and answer pavement
misconception is that concrete overlays are
preservation, highway agencies are being owners questions so that they can confidently
limited to projects that require long-term
asked to do more with less in managing their include concrete overlays in their toolbox of
solutions (20 to 35 years) and that other
pavement networks. Concrete overlays can pavement solutions and make more informed
options may be better suited for short-term
serve as sustainable and cost-effective solu- decisions about designing and construct-
solutions (5 to 15 years). Another is that over-
tions for improved management of pavement ing them. The first (Harrington et al. 2007)
lays are expensive or difficult to build, or are
assets, including preservation, resurfacing, and and second (Harrington 2008) editions of
niche solutions with limited applicability. In
rehabilitation. In addition, they contribute this guide described concrete overlay types,
actuality, however, the following statements
to more sustainable construction practices by applications, and issues related to design and
are true:
preserving and extending pavement service for construction. This third, expanded edition
years beyond the original design life. Many enhances the original material with updated Concrete overlays can be designed to cost
concrete overlays have been in service for information: effectively accommodate all combinations
decades, effectively extending the life of the of design life and traffic loading. Their
Evaluating existing pavements to determine
original pavement structures for 30 years or thickness can vary from 2 to 10 inches
if they are good candidates for concrete
more. or greater, depending on the existing
overlays
pavement condition, anticipated traffic,
To ensure that concrete overlays provide
Selecting the appropriate overlay system for available funding, and desired design life.
durable, long-lasting maintenance and
specific pavement conditions
rehabilitation solutions, good design and Concrete overlay solutions exist for
construction practices must be followed. Managing concrete overlay construction all pavement types (concrete, asphalt,
These include designing an overlay that is work zones under traffic and composite [asphalt surfacing over
appropriate for the situation, accomplishing concrete]).
appropriate pre-overlay repairs and prepara- Accelerating construction of concrete over-
tion of the existing pavement, and using good lays when appropriate Concrete overlay solutions exist for all
construction practices like proper jointing and pavement conditions; see Figure 1. Because
Like the first and second editions, however,
curing. With thorough planning, work zones concrete distributes traffic loads over a wide
this guide is not a complete step-by-step man-
can be managed to accommodate these activi- area, the underlying pavement does not
ual, nor does it provide prescriptive formulae
ties without sacrificing project safety, traffic experience highly concentrated stresses. As
or specifications for designing and construct-
flow, or cost effectiveness. a result, as long as the original pavement
ing concrete resurfacing projects. As the title
remains stable and uniform, a concrete
Despite a demonstrated history of hundreds suggests, this booklet provides expert guid-
overlay can be placed.
of successful concrete overlay projects, some

Figure 1. Typical concrete overlay (before [left] and after concrete overlay placement)

Guide to Concrete Overlays 1


Ch 1. INTRODUCTION

Two Concrete in Figure 2, both bonded and unbonded


overlays can be placed on existing asphalt,
Factors that affect the performance of the
resurfaced pavement include the structural
Overlay (Resurfacing) composite, or concrete pavements. integrity of the underlying pavement, the
effectiveness of the bond, the ability of the
Options Bonded Overlay Option two layers to move monolithically to maintain
As Figure 2 illustrates, there are two options the bond, and overlay jointing and curing
The purpose of bonded concrete overlays is to techniques.
regarding concrete overlays: bonded and add structural capacity and eliminate surface
unbonded. This guide uses the general term distresses on existing pavements that are in The key to achieving desired performance is
concrete resurfacing when collectively dis- good to fair structural condition. Bonded to ensure the two structuresthe existing
cussing both bonded and unbonded concrete overlays generally provide resurfacing solu- pavement and the overlaybehave as one
overlay solutions. tions for routine or preventive pavement structure. Therefore, it is important to under-
Bonded overlays are designed as part of the maintenance and for minor rehabilitation. stand movement-related properties, such as
pavement thickness, whereas unbonded over- expansion and contraction properties, of both
Bonded concrete overlays are relatively thin the existing pavement and the overlay. For
lays are essentially new pavement on a stable (26 in. [50150 mm]). Bonded together,
base (existing pavement). Bonded overlay example, for a bonded concrete overlay of an
the overlay and the existing pavement per- existing concrete pavement, the coefficient of
options require that the existing pavement form as one monolithic pavement. Bonding
be in good to fair structural condition. The thermal expansion (CTE) of the overlay con-
between the overlay and the existing pave- crete mixture should be similar to or less than
overlay helps eliminate surface distresses, with ment is essential. The bond ensures that the
the new overlay and existing pavement act- that of the existing concrete pavement.
overlay and existing pavement perform as
ing as a monolithic pavement. Unbonded one structure, with the original pavement Most bonded overlay projects are more chal-
overlay options add structural capacity to the continuing to carry a significant portion of lenging than unbonded overlay projects.
existing pavement system and do not require the load. All bonded overlay projects, there- Therefore, it is important to pay close atten-
bonding to the existing pavement. Unbonded fore, are carefully designed and constructed tion to details in this guide.
overlays can be placed on poor or even deterio- to achieve and maintain a bond between the
rated pavements that are uniform. As shown overlay and the existing pavement.

Bonded Overlay Option Unbonded Overlay Option


(Preventive Maintenance/Minor Rehabilitation) (Minor/Major Rehabilitation)
In general, bonded resurfacing is used to eliminate surface In general, unbonded resurfacing is highly reliable, with
distress when the existing pavement is in good structural longer design life than rehabilitation with asphalt.
condition.
Minimal preresurfacing repairs are necessary for unbonded
Bonding is essential, so thorough surface preparation is resurfacing.
necessary before resurfacing.

OVER ASPHALT

OVER COMPOSITE

OVER CONCRETE

Figure 2. Types of concrete overlays

2 Guide to Concrete Overlays


Ch 1. INTRODUCTION

Unbonded Overlay Option


The purpose of an unbonded overlay is to FAQCan concrete pavement actually be milled efficiently?
restore structural capacity to an existing
Yes. While not commonly done, several large projects in the recent past have utilized
pavement that is moderately to significantly
milling as a means to remove up to 4 inches of the existing concrete pavement prior to
deteriorated. Unbonded overlays are minor or
constructing a concrete overlay, as shown in Figure 3, or, in limited cases, to repair an
major rehabilitation strategies.
existing concrete overlay. Modern milling machines can effectively remove concrete at
The term unbonded simply means that production rates similar to asphalt pavement; efficiency and production are influenced
bonding between the overlay and the under- primarily by the depth of cut and hardness of the aggregate.
lying pavement is not needed to achieve the
desired performance (i.e., the thickness design
procedure does not consider the existing
pavement as a structural component of the
surfacing layer). Thus, the overlay performs as
a new pavement, and the existing pavement
provides a stable base. When the underlying
pavement is asphalt or composite, partial or
full bonding between the concrete overlay
and the underlying asphalt layer should not
cause a problem. In fact, such bonding gener- b. Because of the wide range of overlay recommendations for coupling concrete
ally adds some load-carrying capacity to the thicknesses that can be used, combined overlay construction with accelerated
system. So, unbonded concrete overlays on with the preoverlay work required, construction techniques.
existing asphalt or composite pavements are concrete overlays provide cost-effective
3. Concrete overlays are easy to maintain.
not rigorously designed and constructed to solutions for almost any pavement type
prevent bonding between the layers. and condition, desired service life, and a. Repairing concrete overlays, especially
anticipated traffic loading. thin overlays, is usually much easier
When the underlying pavement is concrete,
than repairing a section of conventional
however, unbonded concrete overlays are 2. Concrete overlays can be constructed
pavement.
carefully designed and constructed to prevent quickly and conveniently.
bonding between the two concrete layers. b. Thin overlays constructed without
a. The existing pavement does not need to
That is because any bonding between the two reinforcement can be easily and eco-
be removed. In fact, it is factored into
concrete layers may stress the overlay and nomically milled out and replaced with
the overlay design to continue to help
result in undesired reflective cracking. a new concrete surface.
carry some of the traffic load.
c. Utility repair locations can be restored
b. In most cases, minimal preoverlay
to original surface elevation and ride
Benefits of repairs are necessary.
quality with ease.
Concrete Overlays c. Concrete overlays are placed using nor-
mal concrete pavement construction
4. Concrete overlays are an effective means
Agencies that regularly construct concrete to enhance pavement sustainability by
practices.
overlays derive several benefits: improving surface reflectance (albedo),
d. Many concrete overlays can be opened increasing structural longevity, enhancing
1. Concrete overlays consistently provide cost- to traffic within a day of placement. surface profile stability, and maintaining
effective solutions. Nondestructive strength indicators, like ride quality.
maturity testing, enable engineers to
a. Dollar for dollar, they are one of the 5. Concrete overlays can serve, in and of
take advantage of this benefit.
most effective long-term pavement themselves, as complete preventive main-
preservation and major rehabilitation e. Accelerated construction practices can tenance, preservation, or rehabilitation
options for existing pavements. be used. This guide provides useful solutions.

Figure 3. Milling concrete (left) and milled surface (right)

Guide to Concrete Overlays 3


Ch 1. INTRODUCTION

History of Concrete unbonded, and partially bonded overlays of


concrete pavements. Many plain and a few rein-
and increased use of high-quality concrete
overlays.
Resurfacing forced overlays also are in service as overlays of
Not surprisingly, concrete resurfacings share
asphalt concrete pavements, especially in heavy
Use of portland cement concrete (concrete) trucking corridors. Concrete overlays have been two design requirements with on-grade
to resurface existing pavements can be traced successfully constructed in 46 different states; concrete pavements: they require uniform
to as early as 1901. By the mid-1980s, many see Figure 4. support conditions and management of
new concrete overlays were being constructed, movement if satisfactory performance is to
and the technology was rapidly maturing into be realized. Nearly all the documented cases
a standard practice in some agencies. A 1994 of premature overlay failure can be traced to
National Cooperative Highway Research Improvements in some violation of these requirements, often
Program (NCHRP) Synthesis of Practice 204
showed that a relatively low-maintenance
Concrete Resurfacing a result of incorrect assessment of the exist-
ing pavement. For this reason, the evaluation
service life of 20 years can be expected and Technology of the existing pavement is paramount to
that many resurfacings have provided 30 to 40 determine if uniform support and movement
Many of the changes and improvements in
years of service. control of the underlying pavement and inter-
the technology foreseen in the earlier reviews
face layer exist or can be cost-effectively made
With the inclusion of data from NCHRP have been realized as the highway community
to exist. If so, will a bonded concrete overlay
Syntheses 99 and 204 (1982, 1994) the has cooperated in working for better design
act as a monolithic unit with the underlying
American Concrete Pavement Associations procedures, construction guidelines, and
pavement and provide the structural capacity,
(ACPA) National Concrete Overlay Explorer specifications for all types of concrete overlays.
load transfer, and drainage system required
(2013a) provides the best historical informa- Among the major advances has been the
to meet the design life? If not, an unbonded
tion on the use of concrete overlays in the better definition of how the existing pavement
overlay will be necessary to meet the same
United States. This database documents the should be evaluated and prepared for a con-
criteria but with a slightly different approach
construction of 1,152 concrete overlays in crete overlay. Another has to do with improved
toward overlay thickness, drainage, and verti-
the United States from 1901 through 2012. methods of placement of concrete overlays,
cal constraints.
Concrete resurfacings have undergone an improved design methodologies, and synthetic
impressive growth, which is evident in the fiber technology. Fiber-reinforced concrete Concrete resurfacing can be either a pres-
number of documented resurfaced highways resurfacings have been on the increase because ervation fix or a rehabilitation fix. With a
in service in the last three decades. Between they contribute to the performance of thin preservation fix, the resurfacing is normally
1980 and 2010, five times as many con- concrete resurfacing. The improved perfor- completed with a bonded overlay over exist-
crete overlay projects were constructed per mance comes from the increase in concrete ing pavement that is in good or fair condition
decade as were constructed in the previous six structural integrity through improved tough- or repaired or milled to bring it to that
decades. ness and durability of the concrete. Major condition. The preservation fix represents
research projects have been completed, pro- the lowest possible cost with possible small
This growth is evidence that concrete over- viding long-term solutions of bonded and amounts of localized failures (<1 percent)
lays are a good investment for highway unbonded overlays of concrete and hot mix within the design life. For a rehabilitation fix,
agencies seeking an additional preservation asphalt (HMA) pavements. These efforts, the resurfacing is normally completed with an
or major rehabilitation alternative. Jointed along with pricing factors and a national focus unbonded overlay over poor or deteriorated
plain and reinforced concrete overlays in on training outreach and technical guidance materials. To have a successful overlay, not
service throughout the country are bonded, development, have led to more acceptance only should the good and poor characteris-
tics of the existing pavement be understood,
but the level of expected success for dollars
expended must be realistic. The initial costs
can be minimized, but a shorter performance
and greater need for additional maintenance
in the future is normally the result, or the
initial costs can be greater with greater perfor-
mance and reduced follow-up maintenance.
Minor cracking and localized failures should
be expected when placing a concrete overlay
on existing pavements. This should not be
viewed as a lack of performance, but rather
as a cost-effective treatment that may require
some further maintenance. In many cases, it
will be more cost effective to anticipate some
maintenance costs for a concrete overlay
rather than go overboard on preoverlay repair
costs in an attempt to prevent any cracking or
localized failures.

Figure 4. Forty-six states where concrete overlays have been constructed (shaded in blue)

4 Guide to Concrete Overlays


Ch 1. INTRODUCTION

Sustainability provide societal benefits in the form of reli-


able load-carrying capacity and fewer and
A number of definitions for the terms reha-
bilitation and preservation have existed for
Many agencies are emphasizing sustainability shorter disruptions to traffic for pavement years, and these terms are constantly misused
in their pavement management decisions. resurfacing and rehabilitation. or incorrectly used interchangeably. The fol-
Quantifying the impact of pavement deci- lowing descriptions are promoted by FHWA.
sions on the primary sustainability factors of
Pavement preservation is a strategy, a net-
(1) environment, (2) society, and (3) econom-
ics is nearly impossible. We can, however,
Asset Management work-level, long-term program to enhance
look at the sustainable benefits of concrete through Resurfacing pavement performance by using an inte-
grated, cost-effective set of practices that
overlays from a qualitative perspective and
conclude the following: Solutions extends pavement life, improves safety, and
meets motorist expectations without recon-
Preserving the existing pavement has a Simply put, asset management involves a
struction. Pavement rehabilitation is defined
minimal impact on the environment (no strategic and systematic approach to manag-
as a structural or functional enhancement
waste products are produced). ing pavements; it relies heavily on pavement
of a pavement that produces a substantial
management data and life-cycle cost analysis.
extension in service life. To preserve a pave-
User delays during construction are Pavement management and pavement pres-
ment, it must be maintained and at times
reduced as compared to reconstructing a ervation activities have become extremely
rehabilitated. As shown in Figure 5, pavement
pavement. important in managing and accounting for
preservation is considered preventive mainte-
investments in highway pavements.
Concrete overlays are capable of maintain- nance plus minor rehabilitation.
ing their smoothness for many years, which First, a little explanation to eliminate
What is the difference between concrete
provides a benefit to society. confusion. For the last half century, pave-
resurfacing and concrete overlays? Resurfacing
ment rehabilitation has been defined as
Concrete overlays typically have a lower is a generic term for providing a new or
a functional or structural enhancement of
life-cycle cost than asphalt overlays of fresh surface on the existing pavement and
a pavement, which produces a substantial
equivalent design life. is considered mainly a preservation (preven-
extension in service life, by substantially
tive maintenance and minor rehabilitation)
Concrete overlay pavement systems can be improving pavement condition and ride qual-
strategy. Concrete resurfacing consists of both
sustainable for a wide range of design life ity. Over the last decade, the Federal Highway
bonded and unbonded concrete overlays. It
choices. Rather than removing and recon- Administration (FHWA) has been a strong
is an integral component of a comprehensive
structing the original pavement, the owner proponent and supporter of the concept of
asset management approach, because it cost
maintains and builds equity in it, realizing cost effectively preserving the countrys road-
effectively extends pavement life and improves
a return on its original investment as long way network. This has helped in the recent
both functional and structural characteristics.
as the original pavement remains part of the years to spur a nationwide movement of
The variety, flexibility, and cost effectiveness
system. pavement preservation and asset manage-
of concrete resurfacing, using overlay options,
ment programs.
For these and other reasons, concrete overlays make resurfacing an excellent solution for a
are cost-effective, sustainable solutions. They

Pavement Preservation
Preventive
Maintenance
Good
Pavement Condition

Rehabilitation

Reconstruction

Minor
Rehabilitation
Major
Rehabilitation
Maintenance
Poor
Time
Figure 5. Appropriate preservation solutions at various stages of pavement service life

Guide to Concrete Overlays 5


Ch 1. INTRODUCTION

full spectrum of pavement needs. Figure 6 service life of an existing pavement and/or ties without sacrificing project safety, traffic
represents a typical pavement condition curve improve its load-carrying capability. Bonded flow, or cost effectiveness.
over the life of a pavement. The preventive concrete overlays up to 6 to 7 inches are not
Like its predecessors, this third edition of
maintenance, minor rehabilitation (together, uncommon, and unbonded overlays from 6
the Guide to Concrete Overlays is the result
the preservation window), and major reha- to 10 inches have been the norm.
of collaboration between state departments
bilitation zones are noted where bonded and
To show the significance of concrete overlays of transportation (DOTs), industry, and
unbonded overlays can be used to restore
as a rehabilitation strategy, the American academia to further enhance the state of the
pavement to the original or better condition.
Association of State Highway and practice for the design and construction of
Transportation Officials (AASHTO) (2007) concrete overlays. Many of the updates to this
Preventive Maintenance recently stated that thin unbonded concrete edition are a result of the Concrete Overlay
Preventive maintenance is a major component overlays, 45 in. [100125 mm] in depth, Field Application Program conducted by
of pavement preservation. Basically, it consists have proven to be a rehabilitation option for Iowa State Universitys National Concrete
of extending the service life of structurally composite (asphalt over concrete) pavements Pavement Technology Center (CP Tech
sound pavements by applying cost-effective that exhibit significant deterioration. When Center) under a cooperative agreement with
treatments to the surface or near the surface. properly designed and constructed, unbonded the FHWA. Through this program, expert
Bonded concrete overlays of approximately 2 concrete overlays have been shown to increase teams visited 26 sites in 18 different states,
to 4 inches provide excellent preventive main- load-carrying capacity and extend pavement and concrete overlay projects were either con-
tenance strategies for all types of pavements. life. structed or scheduled for construction in nine
states. Many lessons were learned while assist-
Minor Rehabilitation ing agencies with the design and construction
Minor rehabilitation is used when structural Lessons Learned of concrete overlays, which prompted the
development of this updated edition. A sum-
capacity needs to be restored to a pavement
but major rehabilitation is not required. One
from Recent mary of the key lessons learned is provided
below:
of the major advantages of concrete overlays Concrete Overlay
as a preservation solution is that they increase
the pavements structural capacity, even if that Projects Project Evaluation and
is not the primary objective of the preserva- To ensure that concrete overlays provide Selection
tion activity. Bonded and unbonded concrete durable, long-lasting maintenance and reha- Lessons learned regarding project evaluation
overlays of 4 in. (102 mm) provide excellent bilitation solutions, basic good design and and selection include the following:
minor rehabilitation solutions. construction practices must be followed.
These include designing an overlay that is Utilize coring, falling weight deflectometers
Major Rehabilitation appropriate for the situation, accomplishing (FWDs), and as built plans to investigate
appropriate preoverlay repairs and preparation existing pavement layer conditions and
For pavements needing structural improve- thicknesses to determine what type of over-
ment, major rehabilitation is the approach of the existing pavement, and using good con-
struction practices like proper jointing and lay is appropriate for a given roadway.
typically used. Major rehabilitation calls for
structural enhancements that extend the curing. With thorough planning, work zones If existing asphalt will be milled, take cores
can be managed to accommodate these activi- of asphalt to ensure that adequate (mini-
Existing pavement condition

Bonded Bonded
Preventive on on Asphalt
maintenance Concrete or
Composite
before treatment

Minor Unbonded
on
rehabilitation Concrete
Unbonded
on Asphalt
Major or
rehabilitation Composite

Reconstruction

Time
Figure 6. Typical bonded and unbonded concrete solutions at various stages of pavement service life

6 Guide to Concrete Overlays


Ch 1. INTRODUCTION

mum 3-inch) asphalt depth will remain In designs for bonded overlays over asphalt, in conjunction with joint layout and design
after milling as a design minimum and to exercise care when milling the asphalt to for turn lanes and shoulder concrete work.
allow loaded concrete trucks to travel on prevent leaving a thin asphalt lift, which
the milled surface with minimal damage can cause delamination. Develop staging plans that allow for the use
to it. of paving equipment between existing con-
Consider two potential overlay quantity crete railings and temporary safety-related
In freeze-thaw climates and/or areas with design options: barrier walls.
expansive soils, evaluate existing pave-
For minimal preliminary work and cost Design transitions and bridge-approach
ment in spring and summer to identify
critical pavement distresses that need to be Do no preliminary surveys other than pavement sections to minimize hand place-
accounted for in the overlay design. measuring wheel-rut depth and pave- ment and detailed jointing plans.
ment cross slope at 500-foot intervals. Determine the type and amount of surface
Identify all vertical constraints (bridges,
utilities, loop vehicle detectors, curbs, bar- Develop design profiles of centerline preparation required based on agency pri-
riers, ramps and driveways, guardrails, and and pavement edges. oritization of the following goals:
other structures) that may impact construc- Estimate the quantity of concrete Pavement smoothness
tion and develop a plan to mitigate them. required to meet the profiles and pro-
vide minimum thickness at centerline Concrete quantity
and edges of pavement. Matching existing surface features
Concrete Overlay Design
Lessons learned regarding design include the Add a reasonable percentage to the Maintaining minimum cross slopes
concrete quantity to account for place-
following: Removing unstable existing pavement
ment tolerance, construction losses,
During the early phases of design, consider and surface/cross-section irregularities layers
all partial and full detour options and their and establish the new theoretical Vertical clearance site conditions
impact on construction. plan quantity. Some states use 15 to
20 percent, depending on the thick- Bond enhancement between existing and
Choose the most appropriate overlay type ness of the overlay and the amount overlay pavement layers
(bonded or unbonded) to meet existing of pavement cross-slope correction
desired. The thinner the overlay and
pavement conditions and anticipated future
the higher the cross-slope correction, Plans and Specifications
traffic loadings.
the higher the percentage. Some states Lessons learned regarding plans and specifica-
For unbonded overlays over concrete in add a maximum overrun of 2 to 3 tions include the following:
nonarid climates, provide a positive drain- percent to the new theoretical plan
quantity. Reduce plan sets to necessary quanti-
age path for surface moisture to exit the
ties, design details, plan/profile data (not
interlayer bond breaker (separation layer) For optimization of concrete quantities sheets), and survey control information.
to prevent interlayer erosion under heavy
traffic loadings. Conduct nine-shot cross sections at Require the use of vibrator frequency mon-
50-foot intervals to map the existing
surface. itor recorders on the paver.
In designs for unbonded overlays over
concrete, compare asphalt or geotextile Develop a design centerline pro- Utilize standard concrete mixes and matu-
interlayer (separation layer) costs, construc- file and cross slope that optimizes rity measurements to control opening
tion time, and performance. pavement smoothness, maintains of intersections and access points. Use
minimum overlay depth at centerline, accelerated concrete mixtures only when
Determine transition lengths from the
and optimizes concrete quantities. necessary.
existing profile elevation to the top of the
concrete overlay profile elevation on exist- Limit the contractor to an additional When existing surface milling is required,
ing profile constraints, final roadway design percent of the quantity identified by clearly define the purpose, vertical and
speeds, length and type of traffic control to the desired cross section and design cross-slope limits, and required existing
be used, and final open-to-traffic speeds. profile. Some states use 6 to 8 percent, surface survey accuracy.
depending on the thickness of the
Utilize cubic yard and square yard payment overlay.
items. Square yard covers placement, and Sequence of Construction
Evaluate the impacts of removing/replac-
cubic yard covers material, which reduces
ing medians or existing curbs versus their and Maintenance of Traffic
contractor risk and cost while paying for
retention in terms of construction time, Lessons learned regarding construction
concrete used to fill surface irregularities.
cost, and future performance. sequencing and traffic maintenance include
Based on construction economics and the following:
Carefully review the construction sequence
expected overlay performance in designs for
and maintenance of traffic in conjunction Hold a public preconstruction meeting to
unbonded overlays over concrete, correct
with joint layout. In some cases, tied lon- communicate traffic control impacts and
irregularities in cross slope and profile by
gitudinal construction joints can interfere identify public concerns that should be
varying the thickness of concrete, not the
with the maintenance of both public and addressed by the contractor and highway
depth of the asphalt bond breaker (separa-
contractor traffic. agency during construction.
tor layer). Deeper transverse joint sawing
may be necessary to achieve T/3, but final Develop the construction sequence to meet Minimize the number of gaps for inter-
overlay performance will be enhanced. closed-road or through-traffic maintenance sections and driveways to provide for
uninterrupted paving.

Guide to Concrete Overlays 7


Ch 1. INTRODUCTION

Consider paving plans that allow tempo- earthwork prior to staged surface prepa- front of the paver. Monitor dowels behind
rary access for adjacent property owners ration and paving operations. the paver for location, orientation, and
where possible and accommodate their Delete centerline safety wedge construc- depth.
daily needs. tion where pilot car operations are used Utilize software such as HIPERPAV to
Clearly state the criteria for lane closures 24/7 through the work area. anticipate paving or curing problems and
and allow for contractor alternative sugges- Allow for equipment work on shoulders mitigate their impact on operations.
tions to meet the criteria. and side ditches to proceed in the same
area as a lane closure employed for other Minimize the temperature differential
Provide for alternative detour routes to prepaving work. between the existing pavement surface
be used in the case of unforeseen circum- and the concrete overlay during placement
stances (crashes, wide loads, equipment Where bridge approaches and road inter- and curing. This is especially critical dur-
breakdowns, etc.). sections are immediately adjacent to each ing cool-weather paving for the following
other, encourage use of extended tem-
reasons:
Jointly with the contractor, develop a traffic porary barrier-rail lengths and three-leg
control plan that allows sufficient room for traffic signal setups to reduce construc- When a bonded concrete overlay is
construction operations and keeps the trav- tion/traffic delays. placed in cooler weather, the day/night
eling public and pedestrians safe. temperature differential will cause move-
Concrete Overlay ment in the existing pavement; it will
Anticipate and mitigate temporary drainage expand during the day and contract at
issues caused by milling operations. Construction night. To prevent cracking in the over-
Lessons learned regarding construction lay, the overlay must reach saw strength
In the case of construction of single-lane before the underlying pavements night-
include the following:
overlays with 24-hour pilot car operations time contraction. Specifying a minimum
on a two-lane road, apply the following Require contractor development of a overlay mix temperature of 65F has
construction suggestions: comprehensive paving plan to address con- proven to be helpful in mitigating this
struction and public impacts. set-time issue.
Allow multiple construction zones
separated by two miles between flag- When necessary, accelerate all construction In addition, when a concrete overlay is
ger stations. The 2-mile work zone area placed in cooler weather, the concrete
processes to minimize public impact. Limit can set from the bottom up, delaying the
requirement is the distance between
contract stage work times to emphasize the sawing window. Temporarily covering
flagger stations versus the outermost
warning signs. need for accelerated work if that is the goal the overlay with plastic after paving helps
of the contract. the concrete to set properly, allowing for
Consider using a 3.5-mile paving work timely sawing.
zone and allow the contractor to close Where load transfer is called for in wheel
local crossings in the work zone only paths only, use separate partial dowel bas- This guide provides updated guidance for the
when those in the adjacent zone are kets for each wheel path and do NOT cut design, construction, and maintenance of
open. the basket shipping wires. concrete overlays, which should be adapted
Allow the contractor to propose methods to fit local conditions and policies. Successful
When anchoring dowel baskets, consider
and materials to construct temporary performance of any pavement rehabilitation
the use of uniform thicknesses of separa-
access ramps (in use for less than one method requires that design, materials, and
tion layer, adequate numbers of anchors,
month). construction be considered as complementary
and the relationship of anchor length and
processes.
Encourage construction of bridge work, shot force to the separation layer depth and
transition sections, subdrains, pavement material; minimize the head of concrete in
patching, side ditch drainage work, and

8 Guide to Concrete Overlays


Ch 2. EVALUATION & SELECTION

Chapter 2.

EVALUATING PAVEMENTS AND SELECTING


SOLUTIONS
Evaluating the existing pavement condi- et al. 2001; Hoerner et al. 2001; NCHRP Optional evaluation activities include the
tion is an important part of the pavement 2007). Specifics will vary from project to following:
preservation and rehabilitation process. A project, depending on the project type and
Additional tests (including FWD, analyses
comprehensive evaluation provides valuable relative significance. For the purpose of deter-
of material-related distresses, drainage,
information about the pavements condition, mining whether or not a concrete overlay is
roughness, and surface friction) if the cause
performance capabilities, and limitations, a good candidate for an overlay, the process
of distress is unknown or if additional
including the following: can be divided into the following mandatory
information is needed to determine the
and optional steps. The steps for pavement
Identification of all in-situ pavement layers extent of distress
evaluation are shown in Figures 7 and 8 on
Characteristics and behavior of in-place the following pages. AppendixA also provides Condition assessment profile
pavement materials evaluation tables based on existing pavement
type and condition. The evaluation concludes with a profile of the
Presence, type, and extent of distress overall pavement condition assessment. See
Mandatory evaluation activities include the Figure 8.
Structural condition and load-carrying following:
capacity After a pavement has been thoroughly evalu-
Historical data collection, records review, ated, then a solution can be selected. In many
Functional characteristics of the pavement, and future projections (desk review) cases, either a bonded or unbonded concrete
such as grades, roughness, friction, and
overlay will be an appropriate and effective
noise Visual examination (on-site review)
solution. For those pavements for which a
Several activities can be performed as part of Core analysis concrete overlay is not appropriate, other
the pavement evaluation process (see Hall treatment options are discussed in Appendix B.
Pavement evaluation report

Guide to Concrete Overlays 9


Ch 2. EVALUATION & SELECTION

Initial Evaluation (steps 14)


Pavement History and Performance Goals Core Analysis
Pavement material (including Remaining life Type of distress
aggregate CTE), design, age,
Desired traffic and performance level Depth of distress
thickness, layers
Desired design life Verification of thickness for pavement
Existing traffic and performance level base/subbase
Elevations and grade restrictions
Design life
Other historical information

Visual Examination 4 Optional Analyses

Concrete Asphalt / Composite (depending on extent of problems)

4-a. Material-related Tests


(indicated by core analysis)
Conduct if (a) material or durability issues are
indicated, or (b) roadway provides service for
high levels of traffic, especially if a bonded
overlay is being considered.

Petrography analysis
Concrete material-related distress (MRD)
Poor air-void system
Good Good Asphalt stripping
CTE

4-b. Subsurface Tests


Conduct if (a) pavement or subgrade support
issues are indicated, or (b) roadway provides
service for high levels of traffic, especially if
a bonded overlay is being considered.

FWD tests
Subgrade/subbase support (k value)
Fair Fair
Subgrade/subbase variability
Pavement properties
Load transfer efficiency
Presence of voids
Asphalt stiffness
Concrete flexural strength
Subgrade tests
Freeze-thaw characteristics
Shrink-swell characteristics
Soil strength (dynamic cone penetration
Poor Poor or standard penetration test)

4-c. Surface Texture Tests

Conduct if (a) materials or durability issues


are indicated, or (b) roadway provides
service for high levels of traffic, especially if
a bonded overlay is being considered.

Deteriorated Deteriorated

Figure 7. Pavement evaluation process, with examples of existing pavement conditions (source: Snyder & Associates, Inc.)

10 Guide to Concrete Overlays


Ch 2. EVALUATION & SELECTION

Initial Evaluation (Step 5)


5 Condition Assessment Profile
Concrete Asphalt / Composite
Surface Deficiencies Surface Deficiencies
Friction loss Bleeding/flushing
Joint deterioration (low to medium) Block cracking Pavement
Map cracking (non-alkali-silica Friction loss Evaluation
reactivity [ASR]) Report
Noise
Popouts and
Corrugation
Noise Pavement
Joint reflective cracking
Scaling Condition
Roughness (not distress related)
Roughness (not distress related) Rankings
Rutting
Plastic shrinkage cracks
Weathering/raveling
Thermal shrinkage cracks
Shoving
IRI
Slippage
Other
IRI
Other
Structural Deficiencies
Corner breaks Structural Deficiencies
Joint deterioration (severe) Fatigue (alligator) cracking
Tented panels Depressions
Longitudinal cracking Heaves
Pumping/faulting Longitudinal cracking
Punchout Potholes
MRD (medium to severe) Transverse thermal cracking
Transverse cracking Rutting/shoving
Subgrade/subbase condition Subgrade /subbase condition
Other Other Figure 8. Examples of existing pavement
conditions, from a condition assessment profile

Pavement Along with looking at the historical


records, this step should include recording
tional evaluation should be considered. For
example, tests related to materials or dura-
Evaluation Process future performance requirements, such as bility distresses, possible support problems,
expected traffic loadings and overlay design or surface conditions may be necessary.
The purpose of evaluating the existing pave- life. The following questions can help the pave-
ments condition is to collect details about ment owner determine if additional tests are
any distresses and performance problems that This step should include a determination
advisable:
currently exist and their causes. This informa- of any elevation limits and/or grade restric-
tion helps the owner-agency determine if a tions that signal potential clearance issues What is the extent of pavement distresses,
pavement is a good candidate for a concrete for overlay construction. based on the visual evaluation and core
overlay and, if so, the extent of spot repairs analysis?
2. The second step is a visual examination of
required before an overlay is constructed. The
the pavements condition, noting visible What is the pavements expected service
extent of repairs needed is an important fac-
surface and structural distresses. level and life? Major highways with sig-
tor in determining if/when either a bonded
nificantly high truck volumes and/or long
or unbonded overlay will be a cost-effective 3. The third step is a more thorough exami-
service life require more extensive and com-
solution. nation of the pavement structure through
prehensive evaluations than lower-volume
a core analysis. This step will identify
Evaluating the existing pavements condition roadways.
distresses or performance problems that
involves at least three steps:
cannot be determined by a visual exam Results from all initial evaluation steps should
1. The first step is to review the pavements alone. Core analyses verify pavement thick- be recorded in a Condition Assessment
historical design and performance record ness, the subgrade/subbase material and Profile. This profile helps the agency deter-
pavement thickness and other design thickness, and the depth and perhaps type mine the pavements overall condition and
attributes, mixture materials and design, or cause of distresses. summarize it in a Pavement Evaluation
construction date and method, traffic load- Report.
Based on information learned in steps 1
ings, design life, maintenance activities to
through 3 (Figure 7), the necessity for addi-
date, etc.

Guide to Concrete Overlays 11


Ch 2. EVALUATION & SELECTION

Historical Data and Future Existing Support and Localized Drainage Surveys
Projections (Desk Review) Distress Poor drainage conditions are a major cause
One key to successful concrete overlays is of distress in pavement structures. Unless
The first step is to collect data from office files moisture-related problems are identified and
and other historical records associated with ensuring that the underlying pavement and
subgrade/subbase provide uniform support. corrected, the effectiveness of repairs and
the project. The goal is to collect as much overlays will be reduced. As part of a pave-
information about the existing pavement as Information gained from distress surveys
will have the greatest impact on identifying ment distress survey, the overall drainage
possible, such as original design data, con- conditions of the existing pavement should
struction information, subgrade/subbase data, necessary spot repairs and selecting appropri-
ate overlays. Pavement distress in the form be assessed. Excavation at the edge of the
materials testing data, traffic data, perfor- pavement may provide useful information
mance data, and so on. Possible data sources of visible defects or deterioration of the
pavement is the most basic indication of an regarding trapped water and other drainage
for this effort include the following: issues. Observations of moisture/drainage
existing pavements current performance and
Design reports structural condition. The FHWA publication problems (e.g., pumping, corner breaks,
Distress Identification Manual for the Long- standing water, etc.) may indicate the need
Construction plans/specifications (new and for a more intensive FWD test for the support
rehabilitation) Term Pavement Performance Program (2003a)
is useful when identifying pavement distresses value k or a more thorough survey of subsur-
Materials and soils properties from previous and measuring their severity. Information face drainage conditions. The purposes of a
laboratory test programs and/or published obtained in this step will be used to determine drainage survey are the following:
reports the type and extent of field testing required. Detect and identify moisture-related
Past pavement condition surveys, non- Types of distress are determined primarily distress
destructive testing and/or destructive by occurrence and appearance and can indi- Document prevailing drainage conditions
sampling investigations cate the underlying causes of deterioration. (e.g., cross slopes, cut/fill areas, depth and
Severity of distress represents the criticality condition of ditches)
Maintenance/repair histories
of the distress in terms of progression; more
Traffic measurements/forecasts severe distresses will require more extreme Assess edge-drain conditions
rehabilitation measures. The extent of each If edge drains are present, their effectiveness
Environmental/climate studies distress type and severity level must be mea- should be evaluated by observing their out-
Pavement management system reports sured when an overlay is considered. flow after a rainfall or after water is released
For example, consideration should be given to from a water truck over pavement discon-
Discussions with local design and mainte-
any deterioration of an asphalt surface course tinuities. Another way to assess edge-drain
nance engineers may also be beneficial and
(existing asphalt or composite pavement), effectiveness is through video inspections
should be included as participants in the on-
because asphalt is a good reflector of underly- (Daleiden 1998; Christopher 2000). A video
site review process. The information gathered
ing problem areas. Examples include subbase/ camera attached to a pushrod cable and
in this step can be used to divide the pave-
subgrade problems due to poor drainage, inserted into the drainage system at outlets
ment into discrete sections with similar design
material-related distresses (MRDs) such as can locate blockages like rodents nests or
and performance characteristics.
alkali-silica reaction (ASR) or D-cracking in a areas of crushed pipe. Several states have
This step also includes determining future concrete layer, and other defects that result in adopted edge-drain video inspection in their
performance requirements, such as expected isolated expansion or loss of support. pavement evaluation/construction process.
traffic loadings and overlay design life. The visual examination should include the
Consideration should be made for potential Panel tenting (early stages of blowups) location and inspection of all under-drain
future traffic generators (i.e., special events, may indicate the presence of a void under outlets.
future development along the route, etc.) that a concrete panel in an existing concrete or
composite pavement. Sections with significant It is especially important to determine the
may impact the thickness design procedure.
tenting can be repaired to relieve the pres- subgrade soils freeze-thaw and shrink-swell
sure and provide uniform support. If, during characteristics. Soil strength-related tests
Visual Examination the desk review process, an open graded base using the dynamic cone penetrometer or the
(On-site Review) (OGB) is found to be part of the pavement standard penetration test provide useful infor-
With historical information in hand, the sec- structure, an FWD analysis is warranted (see mation about subgrade stability.
ond step is a visual site inspection to obtain Optional Analyses on page 15) because of the Possible drainage problems indicated by a
initial information about the pavements likelihood of secondary consolidation of the drainage survey may suggest the need for
performance and distress issues. Members of OGB, which results in nonuniform support in-depth analysis of the pavement structures
the design team should conduct the visual conditions. This FWD testing should be done drainability. DRIP (Drainage Requirements
examination. At a minimum, the following prior to the on-site review to assure that the In Pavements), an FHWA computer program,
items should be reviewed and recorded for design team has the information at hand to can assist in such an analysis (Mallela et al.
future reference: assist in evaluating the support conditions. 2002).

12 Guide to Concrete Overlays


Ch 2. EVALUATION & SELECTION

Material-related Distress (MRD) in


Existing Concrete Layer FAQCan a pavement with MRD be an appropriate candidate for a concrete overlay?
Pavements exhibiting MRD may be viable Existing pavements that exhibit MRD should not be considered for a bonded overlay. They
candidates for unbonded concrete overlays, are, however, potentially viable as unbonded overlay candidates. Nonuniform support and
but when MRD is suspected or known to loss of support are the primary issues to consider when designing an unbonded overlay of a
exist, the extent of present and potential pavement with MRD. Because MRD requires moisture to develop, further progression can
future distress must be assessed. In many cases sometimes be slowed through improved drainage of the existing pavement by retrofitting
MRD manifests as bottom-up deterioration, pavement edge drains prior to constructing a concrete overlay.
which means that visible distresses may be
minimal to moderate while distresses at the
bottom of the pavement are severe. A quick alkali hydroxides in the paste, and moisture. Unless it can be demonstrated that all the
and inexpensive method for checking for Expansion rates may vary, causing distress alkalis have been consumed in the exist-
bottom-up deterioration is to excavate at the in years to decades depending largely on the ing pavement, limiting future reactions, it
edge of the pavement at multiple joint loca- mineralogy of the aggregates; see Figure 10. should be assumed that the existing system
tions and visually inspect for deterioration Absence of any one of the three ingredients will continue to expand. Suspect concrete
that is not visible from the surface; see Figure will prevent the reaction, but in practice this must be evaluated to assess the potential for
9. In all cases where MRD is suspected, how- may not always be possible. future expansion using approaches such as
ever, laboratory testing as referenced above is described in Report on the Diagnosis, Prognosis,
Reducing the amount of water penetrating
needed to assess the degree of deterioration as and Mitigation of Alkali-Silica Reaction (ASR)
the concrete will slow the reaction, but the
well as the potential for future deterioration. in Transportation Structures (Fournier et al.
reaction will proceed if the relative humidity
2010). The reduction of subsurface water,
When a concrete overlay of an MRD pave- in the pores is greater than approximately 80
even in slow-acting ASR, is an important
ment is deemed viable, the design life of the percent, which is almost always likely in pave-
step in the effort to mitigate the ASR dam-
overlay should take into account the remain- mentseven in arid climates. Once cracking
age before replacing the riding surface an
ing life of the existing pavement. The lower begins in a concrete layer, it is likely that dis-
unbonded concrete overlay.
the severity and rate of the MRD, the higher tress will accelerate because additional water
the chance of longer service life. can penetrate more easily.
Bonded concrete overlays over pavements
with MRD are not recommended due to the
movement of the pavement from the MRD
and subsequent reactive cracking. However,
unbonded concrete overlays have been con-
structed on pavements with MRD for years.
A good example is the 5-inch unbonded over-
lay of a concrete pavement with D-cracking
in the Kansas City metro area on Route D35
(see Figures 44 and 45 in Chapter 3). After
seven years carrying more than 9,000 vehicles
per day, the overlay is in excellent condition.
There is little, if any, information or research
documenting the condition of existing pave-
ments with MRD before concrete overlay
construction or the performance of unbonded
concrete overlays on pavements with MRD.
The three most common mechanisms that Figure 9. Visual inspection for MRD deterioration at the edge of pavement
cause MRD in concrete are alkali-silica reac-
tion, D-cracking, and freezing and thawing;
these mechanisms and their influence on
overlay performance are described below. In
principal, any continued expansion due to
the mechanisms discussed below will likely
shorten the life of an overlay.
Alkali-silica Reaction (ASR)
Alkalisilica reaction is a reaction that occurs
over time between water, alkali-hydroxides
in cement paste, and reactive noncrystalline
silica found in some aggregates (see Figure 9).
This reaction creates an alkali-silicate gel that
absorbs water and expands, exerting expansive
pressure inside the mixture and causing crack-
ing and loss of strength of the concrete.
Alkali-silica reaction requires the presence Figure 10. Moderate ASR cracking along the perimeter of slabs (source:
of three ingredients: reactive aggregates, [Thomas et al. 2011])

Guide to Concrete Overlays 13


Ch 2. EVALUATION & SELECTION

D-cracking Any mitigation strategy that reduces access Consideration should be given to the effects
D-cracking is damage incurred by the propen- of moisture will slow or prevent continued of grade change, particularly at bridge under-
sity for some limestone aggregates to absorb distress. While an overlay may provide some passes and approaches, shoulder areas, and
water when wet, but not release it under dry- degree of insulation, thus reducing the num- curb and gutter units. Design details for these
ing conditions because of the small size of ber of freeze-thaw cycles and slowing damage situations are included on pages 64, 69, and
the pores in the aggregate. The particles thus rates, the problem will not be eliminated. 70. The visual survey should include a com-
become saturated and, under freezing condi- For a potential bonded overlay in which the prehensive list of potential vertical constraints
tions, will crack and expand, causing damage existing pavement is to be brought to good such as the following:
in the mixture. The distress tends to begin at condition by spot repairs or milling, it is
Bridge structures
the bottom of a slab and at joints, and it pro- important before a selecting an overlay to
gresses inward; see Figure 11. periodically check the air content of the exist- Overhead clearance requirements
ing pavement in accordance with ASTM C
In extreme cases, all that will be left is rubble. 457. This check should be made at different Guard rail, parapet wall, cable barrier, and
Evaluation of the risk varies from state to depths of the mid-panels of the existing pave- median barrier
state, and reference should be made to local ment as part of the evaluation process. For Curb and gutter
DOT knowledge of whether or not an exist- example, if the air content is below 5 percent
ing layer is at risk. Typically, a D-cracking and the spacing factor is greater than 0.008 Storm sewer inlets
pavement will need repair in approximately inch, the details of moisture access have to be
10 years, although some pavements have Intersecting roadways and access drives
examined carefully before a bonded overlay
lasted as long as 40 years. If damage has already is considered. This is particularly true if this Drainage conduits and culverts
started, then it is likely to continue, causing condition exists in the lower depths.
damage zones at the joints to grow wider Foreshoulder slopes and ditches
over time, therefore reducing support for any For unbonded overlays, where partial- or full-
layer placed above it. Removing and replacing depth deterioration of the joint is present, Profile Grade
damaged sections may buy some time, but the the unsound concrete around the joints can A review of the existing profile grade line
distress will continue to grow in the at-risk be removed and replaced with low-strength should be conducted; areas of significant
concrete at the interfaces with the repairs. concrete (e.g., flowable mortar). No sawing or deviation will have to be investigated through
reestablishment of the joint is necessary, since analysis of core samples. Evidence of numer-
As with any MRD, the likely remaining life of the overlay will be unbonded and cracking in ous active panel movements in a concrete or
the damaged pavement must be accounted for the existing concrete will not affect the over- composite pavement may indicate potentially
when considering the design life of a concrete lay. This approach with an unbonded overlay unstable or nonuniform subgrade support
overlay. should be a practical and cost-effective solu- or MRD. These, too, will require detailed
Freezing and Thawing tion for pavements with freeze-thaw damage pavement analyses to determine the extent of
in poor or deteriorated condition. The desired distress and possible corrective action(s). For
Concrete that is saturated and subjected to
project life of the overlay must match the example, if movement is confined to isolated
freezing and thawing cycles will exhibit dam-
expected life of the existing pavement after areas, full-depth repairs in these areas may be
age, particularly at the joints. This is largely
repairs are made. considered. Irregularities in profile (signifi-
due to the expansion of water within the
system as it freezes and the lack of a proper cant dips/bumps) should be noted and the
air-void system (spacing and volume of
Vertical Constraints cause(s) should be determined. Typical cross
air). Typically with a poor air-void system, Constructing concrete overlays will raise the slope of the existing pavement and the limits
the deterioration occurs at the joints where roadway profile grade unless it is lowered of superelevated curves should be included in
moisture is most prevalent; see Figure 12. through mechanical measures such as milling. the visual survey.
The damage may continue to progress inward
from the joint as moisture finds its way
through the damaged zone.

Figure 12. Typical joint deterioration with HMA patch (source: Trinity
Figure 11. D-cracked pavement Construction Management Services, Inc.)

14 Guide to Concrete Overlays


Ch 2. EVALUATION & SELECTION

Pavement Coring FAQWhen are additional analyses really necessary?


It may be difficult to determine the cause(s)
and the extent of the cracking from a visual In general, additional analysis (testing) to refine design inputs is only necessary when the
inspection alone. Core analyses can supple- existing pavement is in poor condition and/or heavy traffic is anticipated.
ment information collected from the visual
inspection. This can be done concurrently
with the on-site review or at a later date. Core based on observations noted during the on- Therefore, when evaluating a pavements
frequency and location should be determined site review and/or analysis of pavement cores; suitability for a bonded concrete overlay, it
based on the distresses noted during the visual see Table 1. Roadway type (i.e., primary or is particularly important to characterize the
examination. secondary) and reliability of the ensuing existing cross section and pavement char-
design may drive the decision. For example, acteristics and the type, severity, and extent
At a minimum, two cores per lane per mile
a concrete overlay of a county road with of distresses. Laboratory testing may not be
should be obtained to evaluate layer thick-
moderate traffic could be designed with the required on every project. Lab tests may be
nesses and pavement condition. Whenever
information obtained in the first three steps. conducted to confirm or clarify results from
possible, members of the design team should
Conversely, a divided highway with heavy the visual examination, reveal distress mecha-
be present during the coring to observe the
traffic may require additional information to nisms, and provide additional information
condition of the pavement layers as they are
more precisely characterize the existing pave- needed to identify feasible treatments (see
cored.
ments properties. pages 1823.
Cores are beneficial in determining layer
A thorough pavement condition analysis is A detailed engineering evaluation of the
thicknesses and identifying the pavements
always necessary to assess the applicability type, degree, and state of MRD may be war-
support value; the type and condition of layer
of either a bonded or an unbonded concrete ranted to determine if an overlay is feasible.
materials; the depth of distress(es); and, if
overlay solution. In general, more informa- Unbonded overlays on concrete or composite
the existing pavement is full-depth asphalt or
tion about the existing pavement condition pavements with MRD can be expected to
composite, the condition of the existing bond
is required when bonded overlay systems are have a long life, equal to a full-depth concrete
between layers. For asphalt and composite
being considered or designed. There are sev- pavement, if the overlays are designed cor-
pavements, it is critical to evaluate the bond
eral reasons for this: rectly, taking into account any nonuniformity
between lifts and identify stripped layers
in the existing pavement. For this to be pos-
to determine whether or not the remain- 1. Compared to an unbonded overlay, the
sible, the rate of MRD progression and the
ing asphalt (after milling, if any occurs) will performance of bonded concrete overlays
potential for further deterioration (post con-
be suitable for the concrete overlay design is more dependent on the condition of the
crete overlay) needs to be understood.
assumptions. Cores that penetrate into the existing pavement
subgrade may show evidence of unstable Thicker unbonded overlays (6 in. [150 mm]
conditions, such as the beginning of fine 2. Because bonded overlays are relatively
or greater) have been used successfully on
soil migration into open-graded subbase lay- thin, they are somewhat more susceptible
ASR distressed concrete pavement (alone
ers that can lead to plugging and instability. to stresses, and the very nature of a bond
or as part of an existing composite pave-
Cores also provide samples for possible labo- imposes stress.
ment) in a variety of climates and for a wide
ratory analyses. 3. The existing pavement will become part of range of highway classes. These overlays per-
a monolithic, overlaid pavement structure form extraordinarily well when the reactive
Optional Analyses (not just a base for an unbonded overlay), aggregate expansion is near completion, has
so it needs to contribute a certain level of slowed its rate of deterioration, or is relatively
Various factors affect the necessity for and
strength and integrity and be capable of uniformly spread throughout the existing
extent of additional pavement evaluation
developing and maintaining a bond with pavement. Extreme variation in the degree
tests. Additional testing may be necessary
the overlay. of ASR distress along the length of pavement

Table 1. Recommended Optional Testing

Existing Asphalt Pavement Existing Composite Pavement Existing Concrete Pavement


Optional Testing
Bonded Unbonded Bonded Unbonded Bonded Unbonded
Falling Weight Deflectometer (FWD)

Modulus of Elasticity () of Asphalt X X


Effective Static Modulus of Subgrade Reaction (k) X X X X X X
Load Transfer Efficiency X X X X
Cores
Stripping (ASTM D 4867) of Asphalt X X X X

Pavement Layer Thickness X X X X X X

Petrographic Examination X1,2 X2 X1,3 X2


1 - Entrained air properties when low air content is the suspected cause of observed distress
2 - Identify whether detrimental MRD is present
3 - Determine aggregate type

Guide to Concrete Overlays 15


Ch 2. EVALUATION & SELECTION

Soil strength-related tests using the DCP, or


FAQWhy is optional testing for unbonded overlays necessary when the existing the standard penetration test, provide useful
pavement is characterized as a high-quality subbase in the thickness design process? information about subgrade stability.
Even though unbonded overlays are less dependent on the condition of the existing pave- The benefits of the DCP test include the
ment than bonded overlays, there may be circumstances where additional optional testing is following:
desirable. This is especially the case both for high-volume roadways where design reliability
is critical and for any time that MRD is suspected in the existing pavement. Low cost
Easy to usean operator can be trained in
minutes
Large penetration depthdata can be col-
lected up to 36 inches in depth
(particularly when distress is concentrated at A low-cost and easy on-site method for
the joints), however, can result in nonuniform determining the level of support in terms Fasta large amount of data can be col-
support and consequent performance chal- of CBR is through the use of the dynamic lected and the values converted to CBR
lenges for the overlay. cone penetrometer (DCP); see Figure 13. quickly
This instrument provides a measure of the
Since D-cracking normally occurs at or near Although the DCP does not measure density
in situ strength of fine-grained and granular
concrete joints, bonded concrete overlays on directly, it may be used to assess the density of
subgrades and granular base and subbase
concrete pavements with D-cracking (or com- a fairly uniform material by relating density
materials.
posite pavements in which the concrete layer to PR. In this way, under-compacted or soft
has D-cracking) have had mixed performance A 17.6-lb (8-kg) weight is raised to a height spots can be identified.
results. Localized joint movement and even of 22.6 in. (575 mm) and then dropped, driv-
failure can occur in the underlying pavement. ing the cone into the soil or other material The CBR value can also be important in terms
This may cause cracking in the overlay as a being tested. The output is a penetration rate of overlay thickness design. Concrete over-
result of the nonuniform base support. (PR) expressed in terms of inches (mm) per lay design methods for determining overlay
blow. (The DCP test method is defined under thickness use bearing capacity expressed in
terms of the modulus of subgrade reaction (k).
Deflection Testing ASTM D 6351: Standard Test Method for Use
of the Dynamic Cone Penetrometer in Shallow Although the k-value is difficult to measure,
Pavement deflection testing is an effective way it can be estimated relatively easily from the
to assess a pavements structural capabilities. Pavement Applications.)
CBR value.
The data can be used to estimate, through
back-calculation methods, modulus of elastic-
ity and k-value. Again, pavement deflection
tests are not required for all pavements,
especially those in fair or better condition or
on lower-volume roads. When performed, a
minimum of one test per lane per one-half
mile should be conducted.
Several deflection devices are available, but
they all operate in basically the same manner.
A known load is applied to a pavement sur-
face, and the resulting deflection is measured.
The FWD, or any device capable of applying
loads similar in magnitude and duration to
that of a moving wheel load, is commonly
used. Deflection test results are also used to
develop pavement deflection profiles, back-
calculate layer properties, determine load
transfer capabilities, and evaluate the poten-
tial for voids at slab corners.

Alternative Means of
Determining Support Conditions
In some cases, a visual examination and core
analyses provide enough information to
determine if the pavement is a good candidate
for a concrete overlay. Sometimes, however,
particularly in borderline situations, further
analysis is required. One such analysis may
include determination of the subgrade/
subbase support conditions under the pave-
ment in terms of the California bearing ratio
(CBR). Figure 13. Dynamic cone penetrometer (source: David White,
Iowa State University)

16 Guide to Concrete Overlays


Ch 2. EVALUATION & SELECTION

Table 2. Subgrade Soil Types and Approximate Support Values


Selecting
Soil Type Support k (psi/in.) CBR
Fine grained; silt and clay-size
Appropriate
particles predominate
Low 75 to 120 2.5 to 3.5
Concrete Overlay
Sand and sand-gravel mixture with moderate
amounts of silt and clay
Medium 130 to 170 4.5 to 7.5 Solution
Sand and sand-gravel mixture
Several factors should be considered when
High 180 to 220 8.5 to 12.0 selecting the type of concrete overlay solu-
relatively free of plastic fines
tion. The condition of the existing pavement
Notes: CBR (California bearing ratio); 1 psi = 0.0069 megapascal (MPa);
1 psi/in.=0.27 MPa/m
is the paramount factor. Generally, existing
Table is based on information in ACI 330R-08 regarding ranges of values for several types of subgrade soil (Portland pavements in relatively good condition, or
Cement Association 1984; NCHRP 1982) compacted to the specified density. that can be cost effectively brought to good
condition, are candidates for bonded concrete
overlays. In these cases, bonded overlays can
improve functionality (e.g., reduce roughness
In Table 2, above, CBR values are associ- Condition Assessment Profile or noise or enhance friction) and/or increase
ated with k-values expressed in pounds
When all aspects of an existing pavement have structural capacity (e.g., accommodate antici-
per square inch (psi) per inch or pounds
been evaluated, the critical distresses and drainage pated increases in truck-traffic loadings).
per cubic inch. In the table, both values
conditions should be summarized. One useful
are generally associated with subgrade soil For example, a pavement in fair to poor func-
way to summarize this information is to plot it
types and support conditions. For projects tional condition due to rutting and shoving
on a condition assessment profile, or strip chart
designed for light-traffic loads only, or can be resurfaced with a bonded overlay after
(Smith et al. 2008). In bar chart form, this profile
where extensive soil testing is impractical the pavement has been improved to good
visually indicates where various distresses occur
or economically unjustified considering condition through spot repairs or milling to
over the length of the project, as well as their
the project scope, the k-value can be esti- remove deficiencies. The bond between the
extent and severity. Distresses such as slab crack-
mated. Conservatism is advised in making overlay and the existing pavement inherently
ing, corner breaks, faulting and spalling, and
such estimates. adds structural capacity. In this situation,
continuous roughness can be displayed. Areas of
however, it may be just as cost effective to
poor drainage or significant changes in topogra-
Roughness and Surface phy (cut/fill sections) can be overlaid on the strip
place a slightly thicker unbonded overlay with
Friction Tests less preoverlay repair work and not have to
charts. Such summaries provide critical insight
depend on the bond.
Roughness and surface friction are two into a pavements structural and functional per-
key indicators of the functional perfor- formance, helping roadway owners determine if Generally, existing pavements in poor con-
mance of a pavement: its smoothness for and when pavement preservation or rehabilitation dition that exhibit significant structural
comfortable ride and its skid resistance activities are appropriate. deterioration are candidates for unbonded
for safety. Roughness testing (expressed overlays. Moreover, the presence of MRD,
in terms of the International Roughness Figures 14, 15, and 16 provide a graphical exam-
such as alkali-silica reaction ASR or
Index, IRI) at the project level can be ple of the pavement and evaluation and overlay
D-cracking, also suggests the need for an
useful to help identify localized areas of selection processes.
unbonded overlay or even reconstruction. See
roughness and to assess the effectiveness Appendix B for reconstruction options.
of treatments (pre- and post-treatment Pavement Evaluation Report
roughness comparisons). Friction (skid Concrete overlays can provide economical
The final evaluation step is summarizing the
resistance) testing is not commonly con- short- and long-term solutions for pave-
results of data collection and analyses in an evalu-
ducted for project-level evaluations but ments in a variety of conditions, as shown in
ation report. Any critical nonpavement factors,
may be meaningful on projects exhibiting Figures1416 on the following pages. Note
such as shoulder condition, ditches, right-of-
a disproportionate number of wet-weather that the overlay solutions recommended in
way, curves, bridges, ramps, and traffic patterns,
crashes. these flowcharts are generally long-term fixes,
should be identified in the report. Ultimately, this
on the order of 20 years or more of expected
information will be used in the identification and
life.
selection of appropriate spot repairs and overlays,
as described in the next section.

Guide to Concrete Overlays 17


Ch 2. EVALUATION & SELECTION

Concrete overlays can provide As with any preservation approach, the


Selecting the Appropriate economical short- to long-term principles of asset management are a
Concrete Overlay Solution solutions for asphalt pavements. cornerstone in selecting the appropriate
The recommendations provided concrete overlay solution. Three important
for Asphalt Pavements in the following flowchart are asset management questions need to be
generally long-term fixes on the answered as part of the selection process,
order of 20 years or more of for the appropriate concrete overlay
Rural Urban
section section expected life. solution to meet the needs of an agency.
First, what is the desired level of service to
be provided by the concrete overlay?

Good Condition Spot Repairs


Pavement is structurally sound but Can spot surface repairs and/or spot
needs increased structural capacity, structural repairs cost effectively YES
improved surface characteristics solve deficiencies, bring the
(smoothness, friction, and noise), pavement to Good Condition, and
Asphalt surface surface defects removed, and/or meet other constraints (i.e., vertical
improved albedo properties. clearances, shoulders, safety rails,
foreslopes, etc.) to allow for a
bonded overlay?
Fair Condition NO
Pavement is structurally sound but
has minor surface distresses such as
potholes, block cracking, or random
thermal cracking. Check for undulat- Milling/Minor Spot Repairs
ing profile grade to determine if YES
sub-drainage issues exist. Check Can milling and minor spot repairs
cores to ensure there is no measure- cost effectively solve deficiencies,
able stripping or delamination in the bring the pavement to Good
asphalt. Condition, and meet other
constrants (i.e., vertical clearance,
shoulders, safety rails, foreslopes,
etc.) to allow for bonded overlay?

NO

Milling and Patching


Poor Condition Can spot structural repairs and/or
milling cost effectively solve
Pavement has measurable distresses YES
deficiencies, meet vertical and
beyond those described under Fair
structural requirements, and bring the
Condition, such as alligator
existing pavement to a condition that
cracking, rutting, shoving, slippage,
provides a uniform subbase for an
stripping, and raveling.
unbonded overlay?
Note: Asphalt is a good reflector NO
of underlying distresses such as
poor subbase conditions.
Additional Repairs
Can existing or potential unstable
conditions or major deficiencies (e.g.,
Deteriorated Condition wet subgrade, asphalt stripping) be YES
Pavement exhibits Poor addressed cost effectively with a
Condition characteristics as combination of preservation NO
well as significant deteriora- techniques (e.g., milling, retrofit
tion, raveling, thermal subdrains, full-depth patches) and
expansion, stripping, and other contraints (e.g., vertical
structural distresses. clearence, safety rails, etc.) met with
an adequately thick unbonded
overlay?

Figure 14. Selecting appropriate concrete overlay solution for asphalt pavements

18 Guide to Concrete Overlays


Ch 2. EVALUATION & SELECTION

Second, what is the desired pavement life of the overlay, Generally, existing pavements in relatively good or fair condition, or
given the condition of the existing pavement? Third, poor-condition pavements that can be cost-effectively brought to good
what type of overlay (bonded or unbonded) will achieve condition, are candidates for bonded concrete overlays. Existing asphalt
the first two objectives at the lowest life-cycle cost? pavements that cannot be cost effectively returned to good condition are
candidates for unbonded overlays as long as significant structural repairs to
Several factors should be considered when selecting the existing pavements are not needed. Significant asphalt deterioration can
either a bonded or unbonded concrete overlay for an be overlaid with concrete as long as unstable and soft spots are repaired.
existing asphalt pavement. Two predominant factors are Unless there are unrepairable subsurface issues requiring removal of the
the condition of the existing pavement and the extent of asphalt, it is rare that a unbonded concrete overlay cannot be utilized.
pre-overlay repairs required, if any.

Bonded Concrete Overlay


Over Asphalt Pavement

3 in. min. asphalt Joint spacing

Install subdrains if needed

Note: Concrete overlay thickness must be appropriately designed consider-


ing estimated traffic, desired design life, and budget.

Unbonded Concrete Overlay


Over Asphalt Pavement
3 in. min. asphalt

Joint spacing

Install subdrains if needed

3 in. min. asphalt


FAQWhat if the existing pavement is not a candidate for a
concrete unbonded overlay? While most pavements can be preserved
with a concrete overlay, there are situations where a concrete overlay
is not appropriate. When this occurs, reconstruction is an alternative.
Reconstruction options include the following:
Recommended: Mill and fill. Remove asphalt by milling, repair
any subgrade issues, and fill with new concrete pavement.
Recycle asphalt material.
Permissible in specific situations: When the asphalt is less than
6-in. thick and is in deteriorated condition, the asphalt may be
recycled into the subgrade/subbase through full-depth
reclamation (FDR).

Guide to Concrete Overlays 19


Ch 2. EVALUATION & SELECTION

Concrete overlays can provide are a cornerstone in selecting the


Selecting the Appropriate economical short- to long-term appropriate concrete overlay solution.
Concrete Overlay Solution solutions for composite pavements. Three important asset management
The recommendations provided in questions need to be answered as part of
for Composite Pavements the following flowchart are generally the selection process. First, what is the
long-term fixes on the order of 20 desired level of service to be provided by
(Asphalt Over Concrete) years or more of expected life. the concrete overlay? Second, what is the
desired pavement life of the overlay given
Rural Urban As with any preservation approach, the condition of the existing pavement?
section section the principles of asset management Third, what type of overlay (bonded or

Good Condition
Pavement is structurally sound Spot Repairs
but needs increased structural Can spot surface repairs and/or spot
capacity, improved surface
structural repairs cost effectively solve YES
deficiencies, bring the pavement to
characteristics (smoothness, Good Condition, and meet other
friction and noise), corrected constraints (i.e., vertical clearance,
Asphalt surface
surface defects, and/or improved shoulders, safety rails, foreslopes, etc.)
albedo properties. to allow for a bonded overlay?

Concrete Fair Condition NO


Pavement is structurally sound but
has minor surface distresses such Milling/Minor Spot Repairs
as potholes, block cracking,
Can milling and minor spot repairs
random cracking, and thermal
cost effectively solve deficiencies,
cracking. Check for undulating bring the pavement to Good
profile grade to determine if sub- Condition, and meet other YES
drainage or secondary consolida- constraints (i.e., vertical clearance,
tion issues exist. Check cores to shoulders, safety rails, foreslopes, etc.)
ensure there is no measureable to allow for a bonded overlay?
asphalt stripping or delamination.

NO

Milling and Patching


Can spot structural repairs and/or
milling (asphalt layers prone to
stripping to be removed) cost
Poor Condition effectively solve deficiencies, meet
Pavement has measurable distress- other contraints (i.e., vertical YES
es beyond those described under clearance, shoulders, safety rails,
Fair Condition. These include foreslopes, etc.), and bring the existing
alligator cracking, rutting, shoving, pavement to a condition that will
slippage, stripping, raveling, and provide uniform subbase for an
possible MRD (see page 13). unbonded overlay?

Note: Asphalt is a good reflector


NO
of underlying distresses such as a
poor subbase or joint deteriora- Additional Repairs
tion in concrete pavements. Can existing or potential unstable
conditions or major deficiencies (e.g., wet
Deteriorated Condition subgrade, MRD, faulting) be addressed
Exhibits Poor Condition as well cost effectively with a combination of
as significant surface deterioration, preservation techniques (e.g., milling,
raveling, and structural distresses. retrofit subdrains, full-depth non-sawed
If severe or potentially severe joint lean concrete patches)? Can other
deterioration from freeze-thaw constraints (e.g., vertical clearance, safety
damage or material-related distress rails, etc.) be met with an adequately thick
(MRD: ASR or D-cracking) is unbonded overlay? Does the asphalt need
present and it exists 3 ft to 4 ft to be completely milled to remove major
beyond the joint at nearly every deficiencies such as stripping and a new
joint, then the pavement is not interlayer placed between the underlying
normally a good candidate for an concrete and a new unbonded overlay?
overlay unless the service life is
reduced.
Figure 15. Selecting appropriate concrete overlay solution for composite pavements
20 Guide to Concrete Overlays
Ch 2. EVALUATION & SELECTION

unbonded) will achieve the first two objectives at Generally, bonded overlays are appropriate for any composite pavement that is
the lowest life-cycle cost? either in good condition or can be improved cost effectively from fair or poor
condition to good condition. Composite pavements that cannot be repaired
Several factors should be considered when cost effectively to good condition are most likely candidates for unbonded
selecting either a bonded or unbonded concrete overlays, provided that the existing pavement can serve as a subbase that
overlay of an existing composite pavement. Two provides relatively uniform support. Significant deterioration can be overlaid
predominant factors are the condition of the with concrete as long as unstable and soft spots are repaired prior to overlay
existing pavement and the extent of necessary construction.
pre-overlay repairs, if any.
A thorough pavement evaluation should be performed to determine the
condition of the existing pavement and assess the scope of required pre-over-
lay repairs. If material-related distress (MRD: ASR, D-cracking, and/or
freeze-thaw damage) is detected during the pavement evaluation, lab testing
should be performed to assess the extent of MRD (see page 13 for further
guidance on dealing with existing pavements with MRD).

Bonded Concrete Overlay


Over Composite Pavement

3 in. min. asphalt


Joint spacing

Install subdrains if needed

Note: Concrete overlay thickness to be appropriately designed considering


estimated traffic, desired design life, and budget.

Unbonded Concrete Overlay


Over Composite Pavement
3 in. min. asphalt

Joint spacing

Install subdrains if needed

3 in. min. asphalt FAQWhat if the existing pavement is not a candidate for an
unbonded concrete overlay? While most pavements can be preserved
with an unbonded concrete overlay, there are situations where an
overlay is not appropriate. When this occurs, reconstruction is an
YES alternative. Reconstruction options are discussed in Appendix B.
In summary, they include the following:
NO
Recommended: In-place recycling of the existing pavement to
serve as a base for new pavement or shoulder material.
Permissible in specific situations: Rubblizing the existing
concrete pavement to serve as a base for new concrete
pavement.
Not recommended: Crack-and-seat to serve as a base for new
pavement.

Guide to Concrete Overlays 21


Ch 2. EVALUATION & SELECTION
Concrete overlays can provide are a cornerstone in selecting the appropriate
Selecting the Appropriate economical short- to long-term concrete overlay solution. Three important
Concrete Overlay Solution solutions for concrete pavements. asset management questions need to be
The recommendations provided in answered as part of the selection process, for
for Concrete Pavements the following flowchart are general- the appropriate concrete overlay solution to
ly long-term fixes on the order of 20 meet the needs of an agency. First, what is
years or more of expected life. the desired level of service to be provided by
the concrete overlay? Second, what is the
As with any preservation approach, desired life of the overlay given the condition
the principles of asset management of the existing pavement? Third, what type of

Good Condition Spot Repairs


Pavement is structurally sound
but needs increased structural Can spot surface repairs and/or spot
structural repairs cost effectively solve YES
capacity, improved surface
deficiencies, bring the pavement to
characteristics (smoothness, Good Condition, and meet other
friction and noise), corrected constraints (i.e., vertical clearance,
Rural Urban surface defects, and/or shoulders, safety rails, foreslopes, etc.)
section section improved albedo properties. to allow for a bonded overlay?
Concrete surface

NO
Milling/Minor Spot Repairs
Can milling and minor spot repairs
Fair Condition cost effectively remove deficiencies,
Paement is structurally sound bring the pavement to Good YES
but has minor surface distresses Condition, and meet other
such as random cracking, constraints (i.e., vertical clearance,
periodic partial-depth joint shoulders, safety rails, foreslopes,
spalling, and shadowing. Check etc.) to allow for a bonded overlay?
for undulating profile grade to
determine if sub-drainage issues
or other foundation issues such NO
as secondary consolidation of an
open-graded base exist.
Milling and Patching
Can milling and/or structural repairs
(patching) cost effectively solve
deficiencies, bring the existing
Poor Condition pavement to a condition that will
Pavement has measurable provide uniform support as a YES
surface distresses beyond those subbase, meet other constraints (i.e.,
described as Fair Condition. vertical clearance, shoulders, safety
These include full-depth joint rails, foreslopes, etc.), and bring the
existing pavement to a condition that
deterioration, working cracks,
will provide a uniform subbase for
spot structural failures, faulting, an unbonded overlay?
and/or material-related distress-
es (MRD). If deterioration is also in the bottom
half of the pavement and is located at
the joints, the joints can be milled or
removed full depth and replaced
with lower quality concrete (lean
Deteriorated Condition concrete) with no sawing of the joint.
Pavement is in Poor Condition Cracking in the removed joint will
and exhibits significant surface not affect the performance of an
deterioration and structural unbonded overlay due to the
interlayer.
distresses. If severe or potentially
NO
severe joint deterioration from
freeze-thaw damage or MRD is
present and it exists 3 ft to 4 ft
beyond the joint at nearly every
joint, then the pavement is not
normally a good candidate for an
overlay unless the service life is
reduced.
Figure 16. Selecting appropriate concrete overlay solution for concrete pavements
22 Guide to Concrete Overlays
Ch 2. EVALUATION & SELECTION
overlay (bonded or unbonded) will achieve the first can be improved cost effectively from fair or poor condition to good condition.
two objectives at the lowest life-cycle cost? Concrete pavements that cannot be cost effectively repaired to a good condi-
tion are candidates for unbonded overlays, provided that the existing
Several factors should be considered when selecting pavement can serve as a subbase that provides relatively uniform support.
either a bonded or unbonded concrete overlay for an Significant deterioration can be overlaid with concrete as long as unstable and
existing concrete pavement. Two predominant factors soft spots are repaired prior to overlay construction.
are the condition of the existing pavement and the
extent of necessary pre-overlay repairs, if any. A thorough pavement evaluation should be performed to determine the
condition of the existing pavement and assess the scope of pre-overlay repairs
Generally, bonded overlays are appropriate for any that may be required. If material-related distress (MRD: ASR, D-cracking,
concrete pavement that is either in good condition or and/or freeze-thaw damage) is detected during the pavement evaluation, lab
testing should be performed to assess the extent of MRD (see page 13 for
further guidance on dealing with existing pavements with MRD).

Intermediate
Bonded Concrete Overlay joint spacing
Over Concrete Pavement

Match existing underlying


joints with saw-cut full
depth of overlay plus in.
Install subdrains if needed

Note: Concrete overlay thickness to be appropriately designed considering:


estimated traffic, desired design life, and budget.

Unbonded Concrete Overlay


Over Concrete Pavement

Joint spacing

Install full-depth
flowable mortar Install subdrains if needed
patches. No
sawing. Place separator layer
(geotextile or 1-in. min. asphalt)

FAQWhat if the existing pavement is not a candidate for an


unbonded concrete overlay? While most pavements can be
preserved with an unbonded concrete overlay, there are
YES situations where an overlay is not appropriate. When this occurs,
Additional Repairs reconstruction is an alternative. Reconstruction options are
Can existing or potential unstable conditions or discussed in Appendix B. Following is a brief summary:
major deficiencies (e.g., wet subgrade, MRD, NO
Recommended: In-place recycling of the existing pavement
faulting) be addressed cost effectively through a and use as a base for new pavement or shoulder material.
combination of preservation techniques (e.g., Permissible in specific situations: Rubblizing the existing
milling, retrofit subdrains, full-depth patches, slab concrete pavement to serve as a base for new concrete
stabilization), and can other constraints (e.g., vertical pavement.
clearance, shoulders, safety rails, foreslopes) be Not recommended: Crack-and-seat to serve as a base for
addressed with an adequately thick unbonded new pavement.
overlay?

Guide to Concrete Overlays 23


Ch 3. OVERLAY OPTIONS

Chapter 3.

OVERVIEW OF CONCRETE OVERLAY OPTIONS

As previously described, concrete resurfacing Bonded concrete overlay: Unbonded concrete overlay:
consists of two options: bonded overlays and
1. Bonded on asphalt 1. Unbonded on asphalt
unbonded overlays. Both options are appli-
cable to all existing pavement typesi.e., on 2. Bonded on composite 2. Unbonded on composite
asphalt, composite, and concrete pavements.
This chapter provides an overview of each of 3. Bonded on concrete 3. Unbonded on concrete
the two concrete overlay options on all exist-
ing pavement types.

Guide to Concrete Overlays 25


Ch 3. OVERLAY OPTIONS

Bonded Concrete Overlay on Asphalt Pavements

Figure 17 illustrates an asphalt pavement that


may be a candidate for a bonded concrete
overlay, along with the kinds of preoverlay New 26 in. (50150 mm)
bonded concrete overlay
repairs that may be appropriate. with square panels

Milled and cleaned -


surface

Existing asphalt pavement


with surface distresses

Figure 17. Bonded concrete overlay of fair or better asphalt pavement with surface distresses
(previously called ultra-thin whitetopping)

Application and Uses


Bonded concrete overlays on asphalt
pavements
May be appropriate for asphalt roads,
streets, and intersections in fair or better
structural condition with typical distresses
such as rutting, shoving, slippage, and
thermal cracking; see Figure 18
Are generally 26 in. (50150 mm) thick
Rely on the existing asphalt pavement to
provide additional load-carrying capacity,
and bond to the existing asphalt pavement
to form a monolithic section, thereby
reducing stresses and deflections
Add structural capacity where traffic
loads have increased or are anticipated to
increase
Eliminate surface defects such as rutting
and shoving
Improve surface characteristics (friction,
noise, and smoothness)
Reduce urban heat island effect by increas-
ing pavement surface albedo Figure 18. Bonded overlay of asphalt pavement

26 Guide to Concrete Overlays


Ch 3. OVERLAY OPTIONS

Performance Thinner overlays may shorten the sawing capacity provided by the underlying pave-
window; additional saws are likely to be ment. Additional overlay thickness may be
Bonded concrete overlays of asphalt pave-
required. required in transition sections to prevent
ments have been successfully used in many
movement of the overlay panels adjacent to
states to maintain and rehabilitate asphalt Application of curing compound or other
the existing asphalt pavement and to reduce
pavements with surface defects; see Figures curing methods must be timely and thor-
the potential for cracking due to traffic impact
19 and 20. Numerous studies have shown ough, especially at the edges.
loadings.
bonded concrete overlays to offer a durable
surface course provided (1) there is a sufficient Sealing joints improves performance.
The recommended thickness design pro-
bond between the asphalt surface and concrete cedures are those used by the American
overlay, and (2) the existing asphalt pavement Overlay Process Concrete Pavement Associations Bonded
provides adequate structural support. The overlay project consists of pavement Concrete Overlay on Asphalt (BCOA)
evaluation, design, construction, and future Thickness Designer (2012) or the BCOA ME
Keys to Success repairs. (Vandenbossche 2013). For more informa-
tion on these procedures, see Table 10 in
Milling of existing asphalt may be required
Pavement Evaluation Chapter4.
to eliminate or reduce surface distortions of
2 in. (50 mm) or more and to help provide An evaluation of the existing asphalt pave- Mixture Design
a good bond. ment is necessary to
Conventional concrete mixtures have been
Minimal spot repairs may be required. Ensure it is structurally adequate to carry successfully used for bonded concrete overlays
the anticipated traffic loads of asphalt pavements. When accelerated open-
A minimum of 3 in. (75 mm) of asphalt ing is desired, conventional concrete mixtures
should remain after milling. Determine if milling is required and to
should be proportioned for rapid strength
what depths
Asphalt surface should be sprinkled with gain without increasing shrinkage properties.
water when the surface temperature is Establish the bonded overlay design For additional information on accelerated
greater than 120F (49C) during overlay thickness mixtures, see page 76.
placement. The use of high-modulus structural fibers
For information on pavement evaluation, see
A clean surface is critical to achieving an Chapter 2. Asphalt pavements with significant can improve the toughness and postcracking
adequate bond between the overlay and the structural deterioration, inadequate or non- behavior of the concrete and help mitigate the
underlying asphalt. uniform base/subbase support, or stripping of effects of plastic shrinkage cracking, should
asphalt layers due to inadequate drainage are it occur. For more information,see discussion
Appropriate panel size should be established not good bonded overlay candidates; in such beginning on page 77.
with respect to the thickness of the concrete cases, an unbonded concrete overlay should be
overlay and should preferably be sawed in considered. Joint Design
small square panels. The recommended joint pattern for bonded
Transverse joints must be sawed T/3 (with Overlay Design overlays of asphalt is small square panels,
special attention to thickened overlay over Design elements include overlay thickness, typically in the range of 38 ft (0.92.4 m),
asphalt ruts and other nonuniform areas). mixture design, joints, and drainage. to reduce differential movement between the
concrete overlay and asphalt and to reduce
When feasible, design the longitudinal Overlay Thickness curling and warping stresses. It is recom-
joints to be outside of the normal wheel mended that the length and width of joint
The design thickness for bonded concrete
paths. squares in feet be limited to 1.5 times the
overlays is typically 26 in. (50150 mm),
depending on the desired load-carrying capac- overlay thickness in inches. In addition,
No notable stripping or delamination at
ity and service life as well as the structural if possible, longitudinal joints should be
tack lines exists in asphalt pavement to
arranged so that they are not in the wheel
remain after milling.

Figure 19. SH-119 in 1991 prior to placement of an bonded concrete Figure 20. SH-119 in 2009 after 18 years of service (source: Ron
overlay (source: Ron Youngman, CO/WY chapter, ACPA) Youngman, CO/WY chapter, ACPA)

Guide to Concrete Overlays 27


Ch 3. OVERLAY OPTIONS

path; see Figure 21. The use of tiebars or the Minnesota DOT (MnDOT 2013) have resurfacing. If necessary, steps should be taken
dowels is not necessary because of the small shown improved performance when joints are to ensure adequate drainage in the future (i.e.,
panel size. sealed. Because the concrete overlay is bonded retrofit edge drains, free draining shoulder
to the underlying asphalt pavement, moisture materials, geotextiles, etc.).
Studies performed in Iowa on low-volume
that is allowed to infiltrate open joints has
roadways with bonded concrete overlays of When underdrains are present, they should
nowhere to drain, eventually weakening the
asphalt pavement have shown that, on aver- be cleaned, video inspected, and repaired as
bond and resulting in premature cracking of
age, only 5 percent of the contraction joints necessary.
the slabs.
were cracked after 10 years. These results
indicate that there are potential cost savings Drainage Construction
that could be realized on similar low-volume Stripping or delamination in the upper 3 Construction steps include preoverlay repairs,
roadways, either by increasing the slab inches of the remaining asphalt layer to be milling, surface cleaning, concrete placement,
dimensions or by reducing the concrete over- overlaid can lead to premature failure of the curing, joint sawing, and sealing.
lay thickness. bonded concrete overlay. During evaluation
and design of a bonded concrete overlay Preoverlay Repairs
In the past, bonded overlays less than or
equal to 6 inches thick have typically left project, existing subgrade drainage should Before the milling operation commences,
the joints unsealed. Studies performed by be evaluated, as would be done with asphalt areas with potholes; localized, moderate-
to-severe alligator cracking; or loss of base/
subgrade support will require partial or
full-depth spot repairs to provide uniform
wheel paths joint in wheel path bonding and to achieve the desired load-
carrying capacity and long-term durability; see
Table 3.
Outer Shoulder

The milled surface should be inspected for

Outer Shoulder
isolated pockets of deterioration that require
further repairs. For isolated areas that have
a high number of wide transverse thermal
cracks, a decision needs to be made whether
2 ft x 2 ft panels to bridge the cracks with the bonded overlay
or to clean and fill the cracks. Concrete can
4 ft x 4 ft panels span normal asphalt longitudinal and trans-
verse cracks. Filling old cracks with sand,
flowable fill, or other appropriate material is
Outer Shoulder

Outer Shoulder

necessary only for cracks that have an opening


greater than the maximum-size aggregate used
in the overlay.

Milling
3 ft x 3 ft panels Traffic 6 ft x 6 ft panels In general, milling should be minimized
direction
12 ft 12 ft because it results in loss of structural support.
There is no reason to mill off good asphalt
Figure 21. Longitudinal joints should be arranged to avoid wheel paths
that can contribute to composite action and
continue to help carry traffic loads.
Typically, milling all asphalt surfaces to
Table 3. Possible Preoverlay Repairs on Existing Asphalt Pavement in Preparation for Bonded
improve bonding is not required. The main
Overlay
objectives of milling prior to placing a bonded
Existing Pavement Distress Spot Repairs to Consider overlay are (1) to remove significant surface
Rutting 2 in. (50 mm) Mill distortions that contain soft asphaltic mate-
rial, which would result in an inadequate
Rutting < 2 in. (50 mm) None or mill bonding surface; (2) to reduce high spots
Shoving, slippage Mill to help ensure minimum overlay depth and
reduce the quantity of concrete needed to fill
Crack width maximum coarse aggregate Fill with flowable fill.
size used in the concrete overlay mixture low spots; and (3) to match curb or adjacent
structure elevations.
Crack width < maximum coarse aggregate None
size used in the concrete overlay mixture Matching existing features or minimizing the
vertical change in profile grade will often be
Low- to medium-severity pothole Remove loose material and fill integrally with the concrete
overlay. the primary criteria for determining the mill-
ing depth. When this is the case, a thorough
High-severity pothole and/or areas To prevent a single overlay panel from bonding to both evaluation of the thickness and condition of
needing full-depth repair asphalt and concrete, make full-depth repairs across a full
the existing asphalt pavement must be per-
lane width with concrete and adjust the transverse joint
spacing in the concrete overlay to match the location of formed to assure that the remaining asphalt to
the underlying patch. The full lane width prevents trying to be overlaid is sound and thick enough to pro-
match a longitudinal joint for a partial lane patch. vide structural support for carrying loads.

28 Guide to Concrete Overlays


Ch 3. OVERLAY OPTIONS

When milling the existing pavement to a Surface Cleaning lay, curing compound should be applied at
specific profile and/or cross slope is being Following repairs, the asphalt surface should twice the standard rate. The finished product
considered, assure that there is adequate pave- be cleaned to ensure adequate bonding should appear as a uniformly painted solid
ment depth to maintain a minimum 3 inches between the existing asphalt surface and the white surface, with the vertical faces along the
of sound asphalt for bonding after the milling new concrete overlay. Adequate bonding is edges of the overlay also thoroughly coated.
is completed. very important to the performance of this
Joint Sawing
Most surface distresses can be removed type of overlay. Cleaning may be accom-
plished by first sweeping the asphalt surface, Timely joint sawing is necessary to prevent
through milling. Milling may be used where random cracking. Joint sawing should com-
surface distortions are 2 in. (50 mm) or then cleaning with compressed air. If material
is subsequently tracked onto the pavement mence as soon as the concrete has developed
greater. The amount of asphalt removed sufficient strength so that joints can be cut
depends on the types and severity of distresses surface, the surface must be re-cleaned.
Pressure washing should be considered only without significant raveling or chipping.
and the thickness of the asphalt. Milling can Lightweight early-entry saws may be used to
be used to remove gross irregularities that when dust control is mandated or when mud
has been tracked onto the milled surface. In allow the sawing crew to get on the pavement
would cause quantity overruns in the volume as soon as possible. With typical joint spacing
of concrete needed for the overlay; it is not no case should water or moisture be allowed
to stand on the asphalt pavement prior to of 3 to 6 feet, extra saws will likely be needed
necessary to obtain a perfect cross section to avoid random cracking. Transverse joints
or to completely remove ruts. If a stripped overlay placement. To prevent contamination,
it is important to avoid a lengthy lag time can be sawed with conventional saws set to a
(loose) layer of asphalt is encountered, it depth of T/3. Transverse joint saw-cut depths
must be completely removed to provide a between final surface cleaning and paving.
for early-entry sawing should not be less than
sound structural layer for bonding. The mini- 1.25 in. (31 mm). Longitudinal joints should
Concrete Placement
mum thickness of structurally sound asphalt be sawed to a depth of T/3.
required for bonding is 3 inches. When the surface temperature of the asphalt
is at or above 120F (49C), sprinkling the
Construction trafficspecifically, trucks Joint Sealing
surface with water can reduce the temperature
loaded with concretecan cause significant and minimize the chance of early-age crack- Contraction and construction joints should
damage to the remaining asphalt pavement. ing. No standing water should remain on the be filled with a hot-poured joint sealant (the
An adequate layer of asphalt is required to surface at the time the overlay is placed. Water use of backer rod is not recommended).
prevent delamination, thus ensuring that trapped in the milled surface can be blown off
the asphalt will function as a load-carrying with compressed air. Future Repairs
portion of the composite section (not as Bonded concrete overlays on asphalt may be
a separation layer or shear plane, as in an Once the surface of the existing asphalt
easily repaired using full-panel replacement.
unbonded overlay). Some construction traf- pavement has been prepared, paving is accom-
Another option is simply to mill and inlay
fic, however, can be placed on the milled plished using either conventional fixed-form
with concrete. Do not patch with asphalt,
surface to identify any loose material (i.e., or slipform construction. Because of the non-
because the adjacent concrete panels will
partial lifts, deteriorated asphalt, isolated uniform thickness of concrete, the concrete
move and break the bond. If a panel is dis-
areas of stripping, etc.) remaining after the material is bid on a cubic-yard basis. Some
tressed but the ride quality of the pavement is
milling operation. All unsound areas should states also include a bid item for placement on
not compromised, the panel should be left in
be removed prior to performing any further a square-yard basis.
place. If a ride-quality problem develops, the
operations. Curing panel should be replaced before any pieces of
concrete become loose from the overlay.
While the milling machine is on site, it is Curing is especially critical on a bonded
important that the pavement surface be concrete overlay because its high surface
inspected to determine if additional milling is area-to-volume ratio makes the thin concrete Key Resources
required. overlay more susceptible to rapid moisture ACI Committee 325 (2006); ACPA (1999);
loss. Within 30 minutes of placing the over- MnDOT (2013); Rasmussen and Rozycki
(2004); Vandenbossche (2013)

Guide to Concrete Overlays 29


Ch 3. OVERLAY OPTIONS

Bonded Concrete Overlay on Composite Pavements

Figure 22 illustrates a composite pave-


ment that may be a candidate for a bonded
concrete overlay, along with the kinds of pre- New 26 in. (50150 mm)
overlay repairs that may be appropriate. thick bonded concrete overlay
with square panels

Milled and cleaned


surface

Existing composite pavement


with asphalt surface distresses

Figure 22. Bonded concrete overlay of fair or better condition composite pavement with asphalt
surface distresses

Application and Uses


Bonded concrete overlays on composite
(asphalt on concrete) pavements
May be appropriate for composite roads,
streets, and intersections in fair or better
structural condition with typical distresses
such as rutting, shoving, slippage, and ther-
mal cracking; see Figure 23
Are generally 26 in. (50150 mm) thick
Rely on the existing asphalt pavement to
provide additional load-carrying capacity,
and bond to the existing composite pave-
ment to form a monolithic section, thereby
reducing stresses and deflections
Add structural capacity where traffic loads
have increased or are anticipated to increase
Eliminate surface defects such as rutting
and shoving
Improve surface characteristics (friction,
noise, and smoothness)
Reduce urban heat island effect by increas-
ing pavement surface albedo Figure 23. Bonded overlay of asphalt

30 Guide to Concrete Overlays


Ch 3. OVERLAY OPTIONS

Performance
FAQWhat if the existing concrete pavement has MRD below the asphalt surface?
Bonded concrete overlays have been success-
fully used in many states to maintain and Material-related distresses such as D-cracking, alkali-silica reaction, and freeze-thaw
rehabilitate composite pavements with surface joint deterioration can sometimes be difficult to detect in the underlying concrete pave-
defects; see Figures 24 and 25. The key to ment. These distresses can lead to a loss of support and premature failure of the bonded
long-term performance is ensuring the two concrete overlay. Caution should be used when considering a bonded overlay when these
structuresthe existing composite pavement conditions are present. Improving the drainage of the subgrade/subbase below the exist-
and the overlaymove as one structure. ing concrete (i.e., retrofit edge drains) can slow the progression of MRDs and potentially
extend the life of a proposed bonded concrete overlay.
Keys to Success
The following actions will help ensure a suc- Transverse joints must be sawed T/3 (with (3) to establish the bonded overlay design
cessful project: special attention to thickened overlay over thickness. For general information on pave-
asphalt ruts and other nonuniform areas). ment evaluation, see Chapter 2.
An effective bond between the layers of the
composite pavement is necessary. When feasible, design the longitudinal Composite pavements are not good candi-
joints to be outside of the normal wheel dates for bonded overlays of less than 6 in.
A quality bond between the concrete over- paths. (125 mm) if they display any of the following
lay and the composite pavement system is problems:
beneficial. Thinner overlays may shorten the sawing
window; additional saws are likely to be Significant structural deterioration, inade-
Milling of existing asphalt may be required required. quate or uneven subgrade/subbase support,
to eliminate or reduce surface distortions of poor drainage conditions, or stripping or
2 in. (50 mm) or more and to help provide Application of curing compound or other
delamination of asphalt layers
a good bond. curing methods must be timely and thor-
ough, especially at edges. Problems in the underlying concrete (pos-
A minimum of 3 in. (75 mm) of asphalt sibly reflected in the asphalt layer) due to
should remain after milling. Sealing joints may improve performance.
MRD
Minimal spot repairs may be required. No notable stripping or delamination at
Indications of possible future durability
tack lines should exist in asphalt pavement
The asphalt surface should be sprinkled problems
to remain after milling.
with water when the surface temperature is
greater than 120F (49C) during overlay Overlay Design
placement.
Overlay Process Design elements include overlay thickness,
The overlay project consists of pavement mixture design, joints, and drainage.
A clean surface is critical to achieving an evaluation, design, construction, and future
adequate bond between the overlay and the repairs. Overlay Thickness
underlying asphalt. The design thickness for bonded concrete
An appropriate panel size should be estab- Pavement Evaluation overlays is typically 26 in. (50150 mm),
lished with respect to the thickness of the An evaluation of the existing asphalt pavement depending on the desired load-carrying
concrete overlay, and it should preferably be is necessary (1) to ensure it is structurally capacity and service life as well as the struc-
sawed in small square panels. adequate to carry the anticipated traffic loads, tural capacity provided by the underlying
(2)to determine required milling depths, and pavement.

Figure 24. Existing composite pavement (source: James Cable, Iowa Figure 25. Bonded on composite pavement (source: James Cable,
State University) Iowa State University)

Guide to Concrete Overlays 31


Ch 3. OVERLAY OPTIONS

The recommended thickness design pro- unsealed. Studies performed by the Minnesota The milled surface should be inspected for
cedures are those used by the American DOT (2013) have shown improved perfor- isolated pockets of deterioration that require
Concrete Pavement Associations Bonded mance when joints are sealed. Because the further repairs. For isolated areas that have
Concrete Overlay on Asphalt (BCOA) concrete overlay is bonded to the underlying a high number of wide transverse thermal
Thickness Designer (2012) or the BCOA ME asphalt pavement, moisture that is allowed to cracks, a decision needs to be made whether
(Vandenbossche 2013). For more informa- infiltrate open joints has nowhere to drain, to bridge the cracks with the bonded over-
tion on these procedures, see Table 10 in eventually weakening the bond and resulting lay or to clean and fill the cracks. Concrete
Chapter4. in premature cracking of the slabs. can span normal asphalt longitudinal and
transverse cracks. Filling old cracks with fly
Mixture Design Drainage ash slurry, concrete grout, flowable mortar,
Conventional concrete mixtures have been Stripping or delamination in the upper 3 or other appropriate material is necessary
successfully used for bonded concrete overlays inches of the remaining asphalt layers to be only for cracks that have an opening greater
of asphalt pavements. When accelerated open- overlaid can lead to premature failure of the than the maximum-size aggregate used in the
ing is desired, conventional concrete mixtures bonded concrete overlay. bonded overlay.
should be proportioned for rapid strength
During evaluation and design of a bonded Panel tenting (early stages of blowups) may be
gain without increasing shrinkage properties.
concrete overlay project, existing subgrade an indication that there is a void under exist-
For additional information on accelerated
drainage should be evaluated, as would be ing panels. Sections with significant tenting
mixtures, see page 76.
done with asphalt resurfacing. If necessary, should be repaired to relieve the pressure and
The use of high-modulus structural fibers steps should be taken to ensure adequate provide uniform support before construction
can improve the toughness and postcracking drainage in the future (i.e., retrofit edge of a bonded overlay.
behavior of the concrete and help mitigate the drains, free draining shoulder materials, geo-
effects of plastic shrinkage cracking, should it textiles, etc.). If there is vertical movement of the underlying
occur. For more information, see page 77 and concrete adjacent to a crack, the movement
When underdrains are present, they should can be stopped by replacing or retrofitting
Appendix C.
be cleaned, video inspected, and repaired as the joint. The crack can also be controlled
Joint Design necessary. without repairing the underlying pavement by
The recommended joint pattern for bonded adding fibers to the mixture or, in some cases,
overlays of asphalt is small square panels, typi- Construction by placing reinforcing steel over the joint in
cally in the range of 38 ft (0.92.4 m), to Construction steps include preoverlay repairs, the overlay. Typically, 36-in. (900-mm) long
reduce differential movements between the milling, surface cleaning, concrete placement, no. 4 bars are stapled to the existing pavement
concrete overlay and asphalt and to reduce curing, joint sawing, and sealing. at 30-in. (750-mm) spacings perpendicular to
curling and warping stresses. It is recom- the crack.
mended that the length and width of joint Preoverlay Repairs
Before the milling operation commences, Milling
squares in feet be limited to 1.5 times the
overlay thickness in inches. In addition, areas with potholes; localized, moderate- In general, milling should be minimized
if possible, longitudinal joints should be to-severe alligator cracking; or loss of base/ because it results in loss of structural support.
arranged so that they are not in the wheel subgrade support will require partial or full- There is no reason to mill off good asphalt
path. The use of tiebars or dowels is not neces- depth spot repairs with asphalt to provide that can contribute to composite action and
sary because of the small panel size. uniform bonding and to achieve the desired continue to help carry traffic loads.
load-carrying capacity and long-term durabil- Typically, milling all asphalt surfaces to
In the past, bonded overlays less than or equal ity; see Table 4.
to 6-inches thick have typically left the joints improve bonding is not required. The main
objectives of milling prior to placing a bonded
overlay are (1) to remove significant surface
distortions that contain soft asphaltic mate-
Table 4. Possible Preoverlay Repairs on Existing Composite Pavement in Preparation for rial, which would result in an inadequate
Bonded Overlay bonding surface; (2) to reduce high spots
Existing Pavement Distress Spot Repairs to Consider to help ensure minimum overlay depth and
reduce the quantity of concrete needed to fill
Rutting 2 in. (50 mm) Mill
low spots; and (3) to match curb or adjacent
Rutting < 2 in. (50 mm) None or mill structure elevations. Milling may also be
Shoving, slippage Mill considered to roughen the surface, which will
Crack width maximum coarse aggregate Fill with flowable fill. likely enhance bonding.
size used in the concrete overlay mixture Matching existing features or minimizing the
Crack width < maximum coarse aggregate None vertical change in profile grade will often be
size used in the concrete overlay mixture the primary criteria for determining the mill-
Low- to medium-severity pothole Remove loose material and fill integrally with the concrete ing depth. When this is the case, a thorough
overlay. evaluation of the thickness and condition of
High-severity pothole and/or areas needing To prevent a single overlay panel from bonding to both the existing asphalt pavement must be per-
full-depth repair asphalt and concrete, make full-depth repairs across a full formed to assure that the remaining asphalt to
lane width with concrete and adjust the transverse joint be overlaid is sound and thick enough to pro-
spacing in the concrete overlay to match the location of vide structural support for carrying loads.
the underlying patch. The full lane width prevents trying to
match a longitudinal joint for a partial lane patch.

32 Guide to Concrete Overlays


Ch 3. OVERLAY OPTIONS

When milling the existing pavement to a Surface Cleaning twice the standard rate. The finished product
specific profile and/or cross slope is being Following repairs, the asphalt surface should should appear as a uniformly painted solid
considered, assure that there is adequate pave- be cleaned to ensure adequate bonding white surface, with the vertical faces along the
ment depth to maintain a minimum 3 inches between the existing asphalt surface and the edges of the overlay also thoroughly coated.
of sound asphalt for bonding after the milling new concrete overlay. Adequate bonding is
is completed. very important to the performance of this Joint Sawing
type of overlay. Cleaning may be accom- Timely joint sawing is necessary to prevent
Most surface distresses can be removed random cracking. Joint sawing should com-
through milling; see Table 4. Milling may plished by first sweeping the asphalt surface,
then cleaning with compressed air. Pressure mence as soon as the concrete has developed
be used where surface distortions are 2 in. sufficient strength so that joints can be cut
(50 mm) or greater. The amount of asphalt washing should be considered only when
dust control is mandated or when mud has without significant raveling or chipping.
removed depends on the types and severity Lightweight early-entry saws may be used to
of distresses and the thickness of the asphalt. been tracked onto the milled surface. In no
case should water or moisture be allowed to allow the sawing crew to get on the pavement
The objective of milling is to remove gross as soon as possible. With typical joint spacing
irregularities that would cause quantity over- stand on the asphalt pavement prior to over-
lay placement. To prevent contamination, of 3 to 6 feet, extra saws will likely be needed
runs in the volume of concrete needed for the to avoid random cracking. Transverse joints
overlay; it is not necessary to obtain a perfect it is important to avoid a lengthy lag time
between final surface cleaning and paving. can be sawed with conventional saws set to a
cross section or to completely remove ruts. If depth of T/3. Transverse joint saw-cut depths
a stripped (loose) layer of asphalt is encoun-
Concrete Placement for early-entry sawing should not be less than
tered, it must be completely removed to 1.25 in. (31 mm). Longitudinal joints should
provide a sound structural layer for bonding. When the surface temperature of the asphalt
is at or above 120F (49C), sprinkling the be sawed to a depth of T/3.
The minimum thickness of structurally sound
asphalt required for bonding is 3 inches. surface with water can reduce the temperature
and minimize the chance of early-age crack- Joint Sealing
Construction trafficspecifically, trucks ing. No standing water should remain on Contraction and construction joints should
loaded with concretecan cause significant the surface at the time the overlay is placed. be filled with a hot-poured joint sealant (the
damage to the remaining asphalt pavement. Water trapped in the milled surface can be use of backer rod is not recommended).
An adequate layer of asphalt is required to blown off with compressed air.
prevent delamination, thus ensuring that Future Repairs
the asphalt will function as a load-carrying Once the surface of the existing asphalt
Bonded concrete overlays on composite pave-
portion of the composite section (not as pavement has been prepared, paving is
ments may be easily repaired using full-panel
a separation layer or shear plane, as in an accomplished using either conventional fixed-
replacement. Another option is simply to mill
unbonded overlay). When possible, however, form or slipform construction. Because of
and inlay with concrete. Do not patch with
some construction traffic should be placed the nonuniform thickness of concrete, the
asphalt, because the adjacent concrete panels
on the milled surface to identify any loose concrete material is bid on a cubic-yard basis.
will move and break the bond. If a panel is
material (i.e., partial lifts, deteriorated asphalt, Some states also include a bid item for place-
distressed but the ride quality of the pavement
isolated areas of stripping, etc.) remaining ment on a square-yard basis.
is not compromised, the panel should be left
after the milling operation. All unsound areas Curing in place. If a ride-quality problem develops,
should be removed prior to performing any the panel should be replaced before any pieces
further operations. Curing is especially critical on a bonded
of concrete become loose from the overlay.
concrete overlay because its high surface
While the milling machine is on site, it is area-to-volume ratio makes the thin concrete
important that the pavement surface be overlay more susceptible to rapid moisture Key Resources
inspected to determine if additional milling is loss. Within 30 minutes of placing the over- ACI Committee 325 (2006); ACPA (1999);
required. lay, curing compound should be applied at MnDOT (2013); Rasmussen and Rozycki
(2004); Vandenbossche (2013)

Guide to Concrete Overlays 33


Ch 3. OVERLAY OPTIONS

Bonded Concrete Overlay on Concrete Pavements

Figure 26 illustrates a concrete pavement that


may be a candidate for a bonded concrete
Monolithic pavement with
overlay, along with the kinds of preoverlay new concrete surface
repairs that may be appropriate.

Prepared surface

Existing concrete pavement


with surface distresses

Figure 26. Bonded concrete overlay of good condition concrete pavement with surface distresses

Application and Uses


Bonded concrete overlays on concrete
pavements
May be appropriate for concrete pavements
in good structural condition and with lim-
ited surface distresses; see Figure 27
Are generally 25 in. (50125 mm) thick
Eliminate surface defects such as extensive
scaling or surface cracking and/or improve
surface characteristics like friction, noise,
and smoothness
Enhance structural capacity to accommo-
date increase in traffic loads

Performance
When properly considered, designed,
specified, and constructed, bonded concrete
overlays of concrete pavements have been suc-
cessfully used for many years as a means of
strengthening existing concrete pavements, Figure 27. Bonded concrete on concrete

34 Guide to Concrete Overlays


Ch 3. OVERLAY OPTIONS

providing a new smooth surface, and repairing The thermal compatibility (assessed by and longitudinal joints must be sawed to a
surfaces with surface defects such as scaling, coefficient of thermal expansion, or CTE) depth of at least T/2.
high steel, plastic shrinkage cracks, etc.; see between the overlay and existing pavement
Joints in the overlay must align with those
Figures 28 and 29. needs to be addressed. Differential aggre-
of existing pavement because the structure
gate movement between the overlay and
They do not, however, have as high a success must move monolithically.
existing pavement can lead to debonding of
rate as other types of concrete overlays, pri-
the overlay. The width of transverse joints in the over-
marily because of the increased attention to
lay must be equal to or greater than the
detail required in all phases that is sometimes Inadequate curing and/or using oversized
underlying crack width at the bottom of
overlooked in the execution of a project. The slab dimensions will induce higher curl-
the existing transverse joint (see the follow-
goal is to ensure the layers are bonded and ing and warping stresses that can stress
ing page).
react monolithically to loads. The design, the bond between the layers and lead to
specification, construction, and field supervi- debonding. An application of a curing compound or
sion of any proposed bonded overlays over other curing methods must be timely and
concrete require a commitment to proper Keys to Success thorough, especially at the edges.
technique. For best results, projects should be
supervised by engineers and contractors expe- The following actions will help ensure a suc- To minimize curling and warping stresses,
rienced with this technology. Special attention cessful project: some agencies have successfully created
needs to be given to the following items to smaller overlay panels by sawing additional
Existing concrete pavement should either
prevent premature failure: transverse and longitudinal joints in the
be in good condition or be cost effectively
overlay between the matched joints.
A proper assessment of whether or not an brought to good condition through repairs
existing concrete pavement is an appro- or milling.
priate candidate for the technique is
Overlay Process
The existing pavement surface must be pre-
imperative. A majority of failures of bonded The overlay project consists of pavement
pared to enhance bonding to the overlay.
concrete overlays on concrete pavements evaluation, design, construction, and future
are the result of improper assessment of the The overlays aggregate thermal properties repairs.
existing pavement. (CTE) must be similar to (or lower than)
those of the existing pavement to minimize Pavement Evaluation
The existing concrete pavement must be in shear stress in bond. An evaluation of the existing concrete pave-
good condition or brought to good condi- ment is necessary to ensure that it is a good
tion and cleaned effectively in order for Working cracks in the existing pavement
should be repaired (or the overlay should be candidate for a bonded overlay and that,
the overlay and existing pavement to bond once resurfaced, it will be structurally sound
monolithically. If debonding occurs, it leads sawed over the crack) to prevent the crack
from reflecting through the overlay. enough to carry anticipated traffic loads. For
to structural failure in the form of fatigue general information on pavement evaluation,
cracking. Existing joints must be in fair condition or see Chapter 2.
Proper specifications or supplemental speci- repaired.
If an existing concrete pavement exhibits
fications adapted for the specific project are Thinner overlays may shorten the sawing cracking from expansion caused by MRD,
necessary. window. such as ASR or D-cracking, it is not a good
Poor or improper surface preparation and Transverse joints in the overlay must be candidate for a bonded concrete overlay
cleaning may also lead to debonding and sawed full depth plus 0.50 in. (12 mm), (see page 13 for a discussion of MRD). An
cracking. unbonded overlay may be considered.

Figure 28. Photo of concrete pavement with shotblast surface prior to Figure 29. Three-inch concrete bonded overlay (photo dated 2013)
concrete overlay in 1994 (source: Todd Hanson, Iowa DOT) (source: Todd Hanson, Iowa DOT)

Guide to Concrete Overlays 35


Ch 3. OVERLAY OPTIONS

Overlay Design Aggregate with CTE similar to or lower Tiebars, dowel bars, or other embedded steel
Design elements include overlay thickness, than that of the existing concrete pave- products are not used in bonded concrete
mixture design, joints, and drainage. ment will help ensure the two layers move overlays to minimize restraint forces in the
together, thus reducing stresses at the bond bond.
Overlay Thickness interface.
Except for joint design, bonded overlays on
A bonded concrete overlay relies on the Pore space in the aggregate should be existing continuously reinforced concrete
existing concrete pavement as an integral fully saturated before batching (moisture pavements (CRCP) are designed, prepared,
structural component to carry traffic loading. condition greater than saturated-surface- and constructed the same way as bonded
The overlay is bonded to the existing con- dry); otherwise, the aggregate will tend to concrete overlays on jointed plain concrete
crete pavement to form a monolithic section, pull water from the mixture at early ages, pavements (JPCP). Transverse joints are not
thereby reducing stresses and deflections. increasing the possibility of shrinkage, cut in bonded concrete overlays over CRCP
Under certain conditions, a mill and inlay which can lead to debonding. pavements. Acceptable cracking will occur
can be used if the existing pavement has in the bonded overlay, typically (but perhaps
Joint Design not immediately) over existing cracks in the
significant surface issues but is structurally
sound and the subbase/subgrade is stable The bonded overlay joint type, location, CRCP.
(Harrington et al. 2014). and width must precisely match those of the
existing concrete pavement in order to cre- Drainage
The design thickness for bonded concrete ate a monolithic structure. Matched joints During evaluation and design of a bonded
overlays is typically 25 in. (50125 mm), eliminate reflective cracking and ensure that concrete overlay project, existing subgrade
depending on the desired load-carrying the two layers of the pavement structure drainage should be evaluated, as would be
capacity and service life as well as the struc- move together, helping maintain bonding. To done with asphalt resurfacing. If necessary,
tural capacity provided by the underlying minimize curling and warping stresses, some steps should be taken to ensure adequate
pavement. Some states, such as Colorado, agencies have successfully created smaller drainage in the future (i.e., retrofit edge
have used 6-in. (150-mm) bonded overlays overlay panels by sawing additional transverse drains, free draining shoulder materials, geo-
on high-traffic roads. and longitudinal joints in the overlay between textiles, etc.).
the matched joints.
Thickness is commonly determined using When underdrains are present, they should
an established design procedure such as the An important element in transverse joint be cleaned, video inspected, and repaired as
AASHTO Guide for Design of Pavement design is joint dimensions. The depth should necessary.
Structures (AASHTO 1993, 1998). Agencies be full depth plus 0.50 in. (13 mm). To pre-
are becoming increasingly familiar, however, vent debonding, the width of the transverse Construction
with the procedure in the Mechanistic- joint should be equal to or greater than the Construction steps include preoverlay repairs,
Empirical Pavement Design Guide (M-E PDG) width of the underlying joint or crack in the milling, surface cleaning, concrete placement,
(AASHTO 2008) as well. For more informa- existing pavement; see Figure 30. curing, and joint sawing.
tion, see Table 10 in Chapter 4.
The width of the existing underlying
Preoverlay Repairs
Mixture Design pavement crack may be determined by spot-
excavating along the pavement edge. (If the Preoverlay repairs of certain distresses may be
Conventional concrete mixtures have been necessary to achieve the desired load-carrying
successfully used for bonded concrete overlays pavement system experiences expansion and
the overlay pushes against itself because the capacity and long-term durability. The surface
of concrete pavements. When accelerated should be inspected for isolated pockets of
opening is desired, conventional concrete width of the transverse overlay joint is less
than the width of the underlying existing deterioration that require repairs; see Table 5.
mixtures should be proportioned for rapid
strength gain without increasing shrinkage pavement crack, debonding may occur.) For isolated areas that have wide random
properties. For additional information on Some agencies believe that T/2 is sufficient for cracks or working joints, full-depth repairs
accelerated mixtures, see page 76. longitudinal joint depth. Others recommend may be necessary. When cracks (particularly
sawing longitudinal joints full depth plus 0.50 working cracks) exist in the pavement to be
The use of high-modulus structural fibers resurfaced, reflective cracking will almost
can improve the toughness and postcracking in. (13 mm) to cut through the bond line.
behavior of the concrete and help mitigate the
effects of plastic shrinkage cracking, should it
occur. For more information, see page 77 and
Appendix C. Width of new Note: Overlay joint width shall be equal to or
Overlay joint overlay greater than crack in the existing slab.
Regarding concrete aggregate, several issues Concrete transverse joint
should be considered: overlay If X is 0.50 in. (13 mm) or greater, the underlying
crack width in the existing slab should be
measured. If crack is 0.25 in. (6.4 mm) or greater,
A well graded aggregate will reduce the Saw cut in and existing pavement does not have dowel bars,
water and paste content of the mixture, existing slab (X) the joints should be evaluated to determine if load
thus reducing potential shrinkage and curl- transfer rehabilitation is required to eliminate
Underlying crack
faulting. If there are numerous joints of this type,
ing, as well as the related risk of debonding. in existing slab
the existing pavement may not be a good
candidate for a bonded overlay.
The maximum aggregate size of the overlay
concrete should be one-third of the overlay Figure 30. Width of transverse joint in bonded concrete overlay on concrete pavement should
thickness. be equal to or greater than width of crack in existing pavement

36 Guide to Concrete Overlays


Ch 3. OVERLAY OPTIONS

always occur. Crack cages over existing non- The most commonly used and most effective concrete, care should be taken that they do
working cracks have been successfully used to surface preparation procedure is shotblasting. not drip oil or other contaminants that could
prevent reflective cracking; see Figure 31. Although milling will roughen the concrete compromise the bond.
pavement surface, milling should not be used
When voids are detected under existing slabs, Concrete Placement
solely for that purpose because of its potential
the slabs should be stabilized through grout Grade adjustments may be made to ensure
for causing surface microcracking and fractur-
injection or other methods. Asphalt patches the required thickness of the concrete.
ing the exposed aggregate. If milling is used
should be removed and replaced with con- Conventional concrete paving practices and
to lower the pavement elevation, any resulting
crete patches (or simply filled with concrete procedures are followed for bonded concrete
microcracking should be removed by shot-
at the time of overlay placement) to ensure overlays. A bonding grout or epoxy coating
blasting or high water-pressure blasting.
bonding of the concrete layers. of the existing surface to enhance bond is not
A consideration in performing repairs is Surface Cleaning required.
whether or not movement in the underlying Following surface preparation, the concrete
pavement will cause movement in the overlay. surface should be cleaned to ensure adequate Curing
Any movement in the overlay that does not bonding between the existing concrete surface Curing is especially critical on a bonded
occur at matched joints could contribute and the new concrete overlay. Cleaning may concrete overlay because its high surface-area-
to debonding and subsequent failure of the be accomplished by sweeping the concrete to-volume ratio makes the thin concrete
overlay. surface, followed by cleaning in front of the overlay more susceptible to rapid moisture
paver with compressed air. If material is sub- loss. Within 30 minutes of placing the overlay,
Surface Preparation sequently tracked onto the pavement surface, curing compound should be applied at twice
Surface preparation of the existing concrete the surface must be re-cleaned. Paving should the standard rate. The finished product should
pavement is accomplished to produce a commence soon after cleaning to minimize appear as a uniformly painted solid white sur-
roughened surface that will enhance bonding the chance of contamination. face, with the vertical faces along the edges of
between the two layers. A variety of surface the overlay also thoroughly coated.
Vehicles should be limited on the existing
preparation procedures may be used, includ-
surface after it is prepared. If it is absolutely Joint Sawing
ing shotblasting, milling, high water-pressure
necessary to have vehicles on the existing Timely joint sawing is necessary to prevent
blasting, and sandblasting.
random cracking. Sawing should begin as
soon as the concrete is strong enough that
joints can be cut without significant raveling
or chipping.
Table 5. Possible Preoverlay Repairs on Existing Concrete Pavement in Preparation for
Bonded Overlay
If lightweight early entry saws are used for
transverse joints, it must be remembered that
Existing Pavement Distress Spot Repairs to Consider the depth of the saw cut must be the thickness
Random cracks Reflective cracking is likely if no repairs are made; use crack cages or of the overlay plus 0.5 inch and the width of
full-depth repairs for severe cracks the saw cut must be equal to or greater than
Faulting Slab stabilization the width of the underlying joint or crack
in the existing pavement. This may require
Pumping Slab stabilization resawing the transverse joint with a conven-
Asphalt patch Replace with concrete patch to ensure bonding tional saw to meet these requirements.
Joint spalling Partial-depth repair To help match transverse joint locations, place
Scaling Remove with cleaning guide nails on each edge of the existing pave-
ment at the joints; after the overlay is placed,
mark the joint with a chalk line connecting
the guide nails.

Future Repairs
The recommended repair option for bonded
concrete overlays on concrete is full-panel
replacement. Concrete panels are easily
removed and replaced. Another option is sim-
ply to mill and inlay with concrete. If a panel
is cracked or otherwise distressed but the ride
quality of the pavement is not compromised,
the panel may be left in place.

Key Resources
ACI Committee 325 (2006); ACPA (1990a);
Trevino et al. (2004)
Figure 31. Crack cage over concrete pavement crack (source: James Cable)

Guide to Concrete Overlays 37


Ch 3. OVERLAY OPTIONS

Unbonded Concrete Overlay on Asphalt Pavements

Figure 32 illustrates an asphalt pavement that


may be a candidate for an unbonded concrete
overlay, along with the kinds of preoverlay
repairs that may be appropriate. New unbonded overlay

Need for milling determined based


on degree of surface distortions

Existing deteriorated
asphalt pavement

Figure 32. Unbonded concrete overlay (previously called conventional whitetopping) of poor-to-deteriorated
condition asphalt pavement

Application and Uses


Unbonded concrete overlays on asphalt
pavements
May be appropriate for asphalt pavements
with significant deterioration such as
severe rutting, potholes, alligator crack-
ing, subgrade/subbase issues, shoving, and
pumping; see Figure 33
Are generally 411 in. (100280 mm) thick
(JPCP or CRCP)
Are essentially designed as a new concrete
pavement on a stable base course, assuming
an unbonded condition between the layers
Restore or increase the structural capacity
of existing pavement
Eliminate surface defects such as rutting
and shoving
Improve surface characteristics (friction,
noise, and smoothness)
Reduce urban heat island effect by increas-
ing pavement surface albedo Figure 33. Unbonded concrete overlay of asphalt pavement

38 Guide to Concrete Overlays


Ch 3. OVERLAY OPTIONS

Performance Partial bonding between the overlay and base, and the overlay is designed essentially as
the asphalt layer of the existing composite a new concrete pavement. The design assumes
Unbonded overlays of asphalt pavements
pavement is acceptable and may improve an unbonded condition between the layers.
have been successfully used in many states,
load-carrying capacity. There are two approaches to assessing the
with more than 30 years of good-to-excellent
potential structural contribution of the exist-
performance in states such as California and No notable asphalt stripping should exist in
ing asphalt pavement to the new pavement
Iowa. See Figures 34 and 35. Unbonded the asphalt after milling.
system. The approach in the AASHTO Guide
overlays over asphalt do not require extensive
for Design of Pavement Structures (AASHTO
preoverlay repairs, but spot repairs of certain Overlay Process Design Guide) (1993, 1998) considers the
areas may be necessary to minimize local-
The overlay project consists of pavement modulus of subgrade reaction (k-value). The
ized failures. Though this overlay type does
evaluation, design, construction, and future M-E PDG (AASHTO 2008) considers both
not rely on bonding, some partial bonding
repairs. friction and k-value.
between the overlay and existing asphalt pave-
ment may occur and can contribute to better Overlay Thickness
performance of thepavement. Pavement Evaluation
An evaluation of the existing asphalt pave- Unbonded overlay thicknesses typically range
ment is necessary to ensure it is a good from 4 to 11 in. (100 to 280 mm). Unlike
Keys to Success candidate for an unbonded overlay. The objec- bonded overlays where there is a minimum
The following actions will help ensure a suc- tives of the evaluation are to (1) estimate the thickness of asphalt required for structural
cessful project: existing pavements structural contribution as support, the existing asphalt need only pro-
a subbase, (2) determine the type and extent vide a stable and uniform subbase for the
Milling of existing asphalt may be required unbonded overlay. Regardless of whether the
to eliminate surface distortions of 2 in. (50 of preoverlay repairs, and (3) characterize key
inputs to the overlay design (e.g., the founda- asphalt will be milled because of vertical con-
mm) or more. straints or remain in its existing condition, the
tion support value should be determined to
Full-depth repairs should be considered establish a thickness design that accounts for minimum thickness of asphalt to be overlaid
only at isolated spots where structural the contribution of the asphalt layer[s]). must be adequate to provide a stable working
integrity needs restoring. platform capable of withstanding all antici-
Asphalt pavements are good candidates for pated construction traffic (specifically, trucks
Concrete patches in the existing asphalt unbonded overlays if the existing asphalt loaded with concrete); this would typically be
pavement surface should be separated from layer(s) can provide, or can be cost-effectively 34 inches of remaining asphalt or equivalent
the overlay with a thin layer of geotextile repaired to provide, a uniform, stable platform support from other underlying materials such
fabric or other bond breaker. for the overlay. as a chip seal surface(s).
Shorter joint spacing in the overlay can For general information on pavement evalua- Portions of a project with significantly differ-
help reduce curling and warping stress. tion, see Chapter 2. ent existing pavement and subbase conditions
Joints should be sawed in the overlay as can be broken into separate sections and
soon as possible because the sawing window Overlay Design designed to specifically address those given
may be shorter than it typically is for full- Design elements include using the existing conditions.
depth pavements. pavement as a base, overlay thickness, mixture The AASHTO Design Guide (1993, 1998)
design, joints, and drainage. and M-E PDG (AASHTO 2008) provide
The asphalt surface should be sprinkled
with water when the surface temperature is design procedures. For more information, see
Existing Pavement as Base
greater than 120F (49C) during overlay Chapter 4.
In an unbonded overlay design, the existing
placement. asphalt pavement is considered as a stable

Figure 34. Poor to deteriorated asphalt pavement to be resurface Figure 35. Poor to deteriorated asphalt pavement resurfaced with
(source: Todd Hanson, Iowa DOT) unbonded concrete overlay (source: Kevin Merryman, Iowa DOT)

Guide to Concrete Overlays 39


Ch 3. OVERLAY OPTIONS

Mixture Design considered if the overlay is 6 in. (150 mm) or Milling


Conventional concrete mixtures have been greater. If surface distortions in the existing pavement
successfully used for unbonded concrete over- Typical joint sealing practices should be are 2 in. (50 mm) or greater, milling may
lays of asphalt pavements. When accelerated followed. be considered prior to placing an unbonded
opening is desired, conventional concrete overlay. Milling can (1) reduce high spots to
mixtures should be proportioned for rapid- Drainage help ensure minimum overlay depth, and (2)
strength gain without increasing shrinkage Stripping of the existing asphalt can lead remove significant surface distortions that
properties. For additional information on to nonuniform support of the unbonded contain fractured asphalt material.
accelerated mixtures, see Chapter 7. overlay. During evaluation and design of an Spot milling only significant distortions, typi-
unbonded concrete overlay project, exist- cally 12 in. (2550 mm), is often adequate.
Joint Design
ing subgrade drainage should be evaluated, The objective of milling is not to obtain a
The load transfer design is the same as for new as would be done with asphalt resurfacing.
concrete pavements. Doweled joints are used perfect cross section, and it is not necessary to
If necessary, steps should be taken to ensure completely remove ruts. There is no reason to
for unbonded overlays of pavements that will adequate drainage in the future for the exist-
experience significant truck traffic, typically mill off good asphalt that can help carry traf-
ing asphalt (i.e., retrofit edge drains, free fic loads. If a stripped (loose) layer of asphalt
pavements 7 in. (175 mm) and thicker. draining shoulder materials, geotextiles, etc.). is encountered, it should be completely
For overlays equal to or less than 6 in. (150 When underdrains are present, they should removed. Matching existing features or mini-
mm) thick, the maximum spacing in feet is be cleaned, video inspected, and repaired as mizing the vertical change in profile grade will
1.5 times the slab thickness in inches. necessary. often be the primary criteria for determining
the milling depth. When this is the case, a
For overlays greater than 6 in. (150 mm), a Construction thorough evaluation of the thickness and
maximum joint spacing in feet of 2 times the
Construction elements may include direct condition of the existing asphalt pavement
slab thickness in inches is often recommended
placement, preoverlay repairs, milling, patch must be performed to assure that the remain-
for unbonded overlays. A 7-in. (175-mm)
preparation, surface cleaning, concrete place- ing asphalt to be overlaid is sound and thick
overlay would thus receive a maximum 14-ft
ment, curing, and joint sawing. enough to serve as a subbase and construction
(4.3-m) joint spacing. The maximum recom-
platform.
mended spacing is typically 15 ft (4.6 m). Direct Placement
An adequate layer of asphalt (3 in. [75 mm]
For situations where the design requires Direct placement without milling is recom-
minimum) must remain to ensure that the
mechanical load transfer across the joints and mended when rutting in the existing asphalt
asphalt will function as a uniform subbase for
the pavement is less than 7 inches in thick- pavement does not exceed 2 in. (50 mm). Any
the unbonded overlay structure. Regardless of
ness, conventional dowels cause slipform ruts in the existing pavement are filled with
whether the asphalt will be milled because of
paving clearance problems. Smaller diameter concrete, resulting in a thicker overlay above
vertical constraints or remain in its existing
dowels do not significantly help the clear- the ruts.
condition, the minimum thickness of asphalt
ance issue and may not provide long-term
Preoverlay Repairs to be overlaid must be adequate to provide
load transfer because of potential socketing in
a stable working platform capable of with-
concrete. One solution that should be con- Unbonded overlays generally require only
standing all anticipated construction traffic
sidered is the use of structural fibers to help minimal preoverlay repairs of the existing
(specifically, trucks loaded with concrete).
hold cracks and joints together. Additionally, asphalt; see Table 6. If significantly distressed
the use of plate dowels provides clearance areas are not shifting or moving and the Patch Preparation
for the paver and allows for mechanical load subgrade/subbase is stable, costly repairs
If any full-depth concrete patches exist in the
transfer. The performance of plate dowels typically are not needed, particularly with an
underlying pavement, each concrete patch
in transverse contraction joints is not well adequately designed overlay.
should be isolated to prevent its bonding to
understood in concrete overlay pavements 5
inches or less. They have, however, been suc-
cessfully used in industrial parking lots. The
effects of exposure of epoxy or galvanized Table 6. Possible Preoverlay Repairs on Existing Asphalt Pavement in Preparation for
coated plate dowels to deicing salts is also Unbonded Overlay
limited. It is recommended that a proven and Existing Pavement Condition Possible Repairs to Consider
tested corrosion-resistant surface be required.
Research on plate dowels in concrete overlays Remove and replace with stable material; correct water
Area of subgrade/subbase failure
problems.
is being conducted at the MnROAD facility
(Burnham and Izevbekhai 2012). See Chapter Severe distress that results in variation in Remove and replace with stable material; correct water
4 for additional information on plate dowels. strength of asphalt problems.
Potholes Fill with asphalt.
The use of tiebars for unbonded overlays
should follow conventional use for pavements Shoving Mill
5 in. (125 mm) thick or more. Using lane Rutting 2 in. (50 mm) Mill
tiebars may be appropriate in open-ditch (or Rutting < 2 in. (50 mm) None or mill
shoulder) sections of unbonded overlays if the
overlay is 5 in. (125 mm) or greater. In this Crack width maximum coarse aggregate
Fill with asphalt or flowable fill.
size used in the concrete overlay mixture
category, a no. 4 tiebar (0.50 in. [13 mm])
may be appropriate. The use of tiebars in Crack width < maximum coarse aggregate
None
confined curb-and-gutter sections should be size used in the concrete overlay mixture

40 Guide to Concrete Overlays


Ch 3. OVERLAY OPTIONS

the concrete overlay. If bonding occurs, the Curing When there is evidence of some wheel rut-
overlay over the patch will be restrained differ- Good curing practices are especially critical ting on the existing asphalt pavement, adjust
ently than the rest of the overlay over asphalt, to thin unbonded overlays because of their the saw-cut depth to account for distortions
potentially resulting in cracking. To isolate high surface-area-to-volume ratio. This is in the underlying asphalt pavement, which
the patch, place a geotextile fabric or asphalt accomplished by applying a curing com- effectively increases the slab thickness; see
slurry seal to the patch surface after milling. pound immediately after surface texturing; Figure 36.
if the unbonded overlay is 6 in. (150 mm)
Surface Cleaning or thinner, use twice the usual rate of cur- Future Repairs
Before concrete placement, the asphalt surface ing compound. The finished product should The recommended repair option for
should simply be swept. Remaining small par- appear as a uniformly painted solid white sur- unbonded overlays is the same as for standard
ticles are not considered a problem. face, with the vertical faces along the edges of concrete pavements.
the overlay also thoroughly coated.
Concrete Placement
When the surface temperature of the asphalt Joint Sawing Key Resources
is at or above 120F (49C), sprinkling the Timely joint sawing is necessary to prevent ACI Committee 325 (2006); ACPA (1998);
surface with water can reduce the temperature random cracking. Transverse and longitudinal FHWA (2002a)
and minimize the chance of early-age crack- joints should be sawed to a depth of T/3.
ing. No standing water should remain on the
surface at the time of overlay placement.
Conventional concrete paving practices and
procedures are followed for placing, spreading,
consolidating, and finishing the unbonded
overlay. Because of the variation of the thick-
ness of concrete, the concrete material is bid
on a volume (cubic-yard) basis. Some states
also include a bid item for placement, mea-
sured on a square-yard basis. Figure 36. Consider asphalt rut depth when determining saw-cut depth (ACPA 1998)

Guide to Concrete Overlays 41


Ch 3. OVERLAY OPTIONS

Unbonded Concrete Overlay on Composite Pavements

Figure 37 illustrates a composite pavement


that may be a candidate for an unbonded
concrete overlay, along with the kinds of pre-
overlay repairs that may be appropriate.
New unbonded overlay

Need for milling determined based


on degree of surface distortions

Existing deteriorated
composite pavement

Figure 37. Unbonded concrete overlay of poor-to-deteriorated condition composite pavement

Application and Uses


May be appropriate for composite pave-
ments with significant HMA deterioration
such as severe rutting, potholes, alligator
cracking, subgrade/subbase issues, shoving,
and pumping; see Figure 38
Are generally 411 in. (100280 mm) thick
(JPCP or CRCP)
Are essentially designed as a new concrete
pavement on a stable base course
Restore or increase the structural capacity
of existing pavement
Eliminate surface defects such as asphalt
rutting, shoving, potholes, and concrete
with mild MRD or joint deterioration
Improve surface characteristics (friction,
noise, and smoothness)
Reduce urban heat island effect by increas-
ing pavement surface albedo
Figure 38. Unbonded overlay of composite

42 Guide to Concrete Overlays


Ch 3. OVERLAY OPTIONS

Performance The asphalt surface should be sprinkled layers of the composite pavement; (2) deterio-
with water when the surface temperature is ration of the asphalt surface course (asphalt is
Unbonded overlays have the potential to
greater than 120F (49C) during overlay a good reflector of problems in the underlying
greatly extend the life of existing composite
placement. concrete); (3) existing profile grade line (pos-
pavements; see Figures 39 and 40. Uniform
sible evidence of active panel movements);
base support from the existing asphalt and No notable asphalt stripping should exist in
(4) panel tenting, which may indicate the
concrete is an important factor affecting the asphalt after milling.
existence of a void under the panel, or joint
performance. Though this overlay type does
If stripping is severe, the asphalt surface deterioration of the underlying concrete pave-
not rely on bonding, some partial bonding
may be milled off and a new interlayer ment; and (5) foundation support value.
between the resurfacing and existing asphalt
pavement can contribute to enhanced perfor- placed between the underlying concrete and
mance of the pavement. Unbonded overlays the new unbonded overlay (see unbonded Overlay Design
of composite pavements do not require exten- overlay over concrete, beginning on Design elements include using the existing
sive preoverlay repairs, but spot repairs may page46). pavement as a base, overlay thickness, mixture
be necessary to minimize localized failures. Partial bonding between the overlay and design, joints, and drainage.
the asphalt layer of the existing composite Existing Pavement as Base
Keys to Success pavement is acceptable and may improve
In an unbonded overlay design, the existing
The following actions will help ensure a suc- load-carrying capacity.
composite pavement is considered as a stable
cessful project: base and the overlay is designed essentially as
Overlay Process a new concrete pavement. The design assumes
Milling of existing asphalt may be required
to eliminate surface distortions of 2 in. (50 The overlay project consists of pavement an unbonded condition between the layers.
mm) or more. evaluation, design, construction, and future
repairs. There are two approaches to assessing the
If the existing pavement profile indicates potential structural contribution of the exist-
ing composite pavement to the new pavement
isolated areas of vertical distortion in the Pavement Evaluation
underlying concrete that could signal system. The approach in the AASHTO
An evaluation of the existing pavement is Design Guide (1993, 1998) considers the
movement from inadequate drainage or necessary to determine whether or not it can
MRDs, repairs may be necessary. k-value. The M-E PDG (AASHTO 2008)
provide a uniform platform for the unbonded considers both friction and k-value.
Full-depth repairs should be considered overlay and, if not, what actions are necessary
only at isolated spots where structural to obtain that uniformity. In addition, the Overlay Thickness
integrity needs restoring. evaluation determines the existing pavements Unbonded overlay thicknesses typically range
structural contribution as a stable platform from 4 to 11 in. (100 to 280 mm). The
Concrete patches in the existing asphalt and key inputs to the overlay design. For required overlay thickness is affected by the
pavement surface should be separated from general information on pavement evaluation, desired load-carrying capacity and service
the overlay with a thin layer of geotextile including specific information about MRDs, life, as well as the condition of the underlying
fabric or other bond breaker. see page 13. pavement.
Shorter joint spacing in the overlay can Composite pavements are good candidates for Portions of a project with significantly differ-
help reduce curling and warping stress. unbonded overlays if the existing composite ent existing pavement and subbase conditions
Joints should be sawed in the overlay as section can provide, or can be cost-effectively may be broken into separate sections and
soon as possible because the sawing win- repaired to provide, a uniform and stable designed to specifically address those given
dow may be shorter than it is typically for platform for the overlay. Special consideration conditions.
full-depth pavements. should be given to (1) the condition of both

Figure 39. Composite pavement prior to unbonded concrete overlay Figure 40. Unbonded concrete overlay over composite pavement
(source: Todd Hanson, Iowa DOT)

Guide to Concrete Overlays 43


Ch 3. OVERLAY OPTIONS

The AASHTO Design Guide (1993, 1998) The use of tiebars for unbonded overlays Preoverlay Repairs
and M-E PDG (AASHTO 2008) provide should follow conventional use for pavements Unbonded overlays generally require only
design procedures. See basic highlights of and 5 in. (125 mm) thick or more. Using lane minimal preoverlay repairs of the exist-
differences among the various procedures in tiebars may be appropriate in open-ditch (or ing composite pavement. If significantly
Table 10 in Chapter 4. shoulder) sections of unbonded overlays if the distressed areas are not shifting and the
overlay is 5 in. (125 mm) or greater. In this subgrade/subbase is stable, costly repairs
Mixture Design category, a no. 4 tiebar (0.50 in. [13 mm]) typically are not needed, particularly with an
Conventional concrete mixtures are typically may be appropriate. The use of tiebars in adequately designed overlay; see Table 7.
used in unbonded overlays of deteriorated confined curb-and-gutter sections should be
composite pavements. When accelerated considered if the overlay is 6 in. (150 mm) or Note that concrete overlays will bond with
opening is desired, conventional concrete greater. any concrete patches on the underlying pave-
mixtures should be proportioned for rapid ment. Therefore, isolate concrete patches with
strength gain without increasing shrink- Typical joint sealing practices should be a geotextile fabric or other bond-breaking
age properties. For additional information followed. material.
on accelerated mixtures, see page 76. Early Drainage Panel tenting (early stages of blowups) may be
opening can also be aided by use of maturity an indication that there is a void under exist-
During evaluation and design of an
measurements. ing panels. Sections with significant tenting
unbonded concrete overlay project, exist-
ing subgrade drainage should be evaluated, should be repaired to relieve the pressure and
Joint Design
as would be done with asphalt resurfacing. provide uniform support before construction
The load-transfer design is the same as for of an unbonded overlay.
new concrete pavements. Doweled joints are If necessary, steps should be taken to ensure
used for unbonded overlays of pavements that adequate drainage in the future (i.e., retrofit
edge drains, free draining shoulder materials, Milling
will experience significant truck traffic, typi- If surface distortions in the existing pavement
cally pavements 7 in. (175 mm) and thicker. geotextiles, etc.). When underdrains are pres-
ent, they should be cleaned, video inspected, are 2 in. (50 mm) or greater, milling may
For overlays less than or equal to 6 in. (150 and repaired as necessary. be considered prior to placing an unbonded
mm) thick, the maximum spacing in feet is overlay. Milling can (1) reduce high spots to
1.5 times the slab thickness in inches. Construction help ensure minimum overlay depth, and (2)
remove significant surface distortions that
For overlays greater than 6 in. (150 mm) Construction elements may include direct
contain fractured asphalt material.
thick, a maximum joint spacing in feet of placement, preoverlay repairs, milling, patch
2 times the slab thickness in inches is often preparation, surface cleaning, concrete place- Spot milling only significant distortions, typi-
recommended for unbonded overlays. A ment, curing, and joint sawing. cally 12 in. (2550 mm), is often adequate.
7-in. (175 mm) overlay would thus receive a The objective of milling is not to obtain a
Direct Placement perfect cross section, and it is not neces-
maximum 14-ft (4.3-m) joint spacing. The
maximum recommended spacing is typically Direct placement without milling is recom- sary to completely remove ruts. There is no
15 ft (4.6 m). mended when rutting in the existing asphalt reason to mill off good asphalt that can help
pavement does not exceed 2 in. (5.0 cm) and carry traffic loads. If a stripped (loose) layer
For situations where the design requires there is no significant surface deterioration in of asphalt is encountered, it should be com-
mechanical load transfer across the joints and the asphalt. Any ruts in the existing pavement pletely removed. Matching existing features
the pavement is less than 7 inches in thick- are filled with concrete, resulting in a thicker or minimizing the vertical change in profile
ness, conventional dowels cause slipform overlay above the ruts; saw-cut depths must grade will often be the primary criteria for
paving clearance problems. Smaller diameter be adjusted to maintain a minimum of T/3 determining the milling depth. When this is
dowels do not significantly help the clear- where thickness is increased over the ruts. the case, a thorough evaluation of the thick-
ance issue and may not provide long-term
load transfer because of potential socketing in
concrete. One solution that should be con- Table 7. Possible Preoverlay Repairs on Existing Composite Pavement in Preparation for
sidered is the use of structural fibers to help Unbonded Overlay
hold cracks and joints together. Additionally,
the use of plate dowels provides clearance Existing Pavement Condition Possible Repairs to Consider
for the paver and allows for mechanical load Remove and replace with stable material (i.e., select
Area of subgrade/subbase failure
transfer. The performance of plate dowels borrow, granular subbase, etc.); correct water problems.
in transverse contraction joints is not well Remove and replace with asphalt material or concrete
Severe distress that results in variation in
understood in concrete overlay pavements patch with slurry seal or geotextile separation layer;
strength of asphalt
of 5 inches or less. They have, however, been correct water problems.
successfully used in industrial parking lots. Full-depth repair with concrete and use asphalt or
The effects of exposure of epoxy or galvanized Reflective faulting or panel tenting
geotextile separation layer as bond breaker.
coated plate dowels to deicing salts is also Potholes Fill with asphalt.
limited. It is recommended that a proven and
tested corrosion-resistant surface be required. Shoving Mill
Research on plate dowels in concrete overlays Rutting 2in. (50mm) Mill
is being conducted at the MnROAD facility Rutting < 2in. (50mm) None or mill
(Burnham and Izevbekhai 2012). See Chapter
4 for additional information on plate dowels. Crack width maximum coarse aggregate
Fill with asphalt or flowable fill.
size used in the overly mixture

44 Guide to Concrete Overlays


Ch 3. OVERLAY OPTIONS

ness and condition of the existing asphalt Concrete Placement face, with the vertical faces along the edges of
pavement must be performed to assure that When the surface temperature of the asphalt the overlay also thoroughly coated.
the remaining asphalt to be overlaid is sound is at or above 120F (49C), sprinkling the
and thick enough to serve as a subbase and surface with water can reduce the temperature Joint Sawing
construction platform. If the remaining old and minimize the chance of early-age crack- Timely joint sawing is necessary to prevent
asphalt is too brittle or broken up to provide ing. No standing water should remain on the random cracking. Transverse joints can be
adequate separation, a new separation layer surface at the time of overlay placement. sawed with conventional saws to a depth of
should be constructed. Without an adequate between T/4 (minimum) and T/3 (maxi-
separation layer, working cracks from the Conventional concrete paving practices and mum). When there is evidence of some wheel
underlying concrete could cause reflective procedures are followed for placing, spreading, rutting on the existing asphalt pavement,
cracking of the unbonded overlay. consolidating, and finishing the concrete over- saw-cut depth is of particular concern for
lay. Because of the variation of the thickness unbonded overlays because the distortions in
An adequate layer of asphalt (3 in. [75 mm] of concrete, the concrete material is bid on a the underlying asphalt pavement can effec-
minimum) must remain to ensure that the volume (cubic-yard) basis. Some states also tively increase the slab thickness; see Figure
asphalt will function as a uniform subbase for include a bid item for placement, measured 41.
the unbonded overlay structure. Regardless on a square-yard basis.
of whether the asphalt will be milled because Longitudinal joints should be sawed to a
of vertical constraints or will remain in its Curing depth of T/3.
existing condition, the minimum thickness Good curing practices are especially criti-
of asphalt to be overlaid must be adequate to cal to thin unbonded overlays because of Future Repairs
provide a stable working platform capable of their high surface-area-to-volume ratio. This The recommended repair option for
withstanding all anticipated construction traf- is accomplished by applying a curing com- unbonded overlays is the same as for standard
fic (specifically trucks loaded with concrete). pound immediately after surface texturing; concrete pavements.
if the unbonded overlay is 6 in. (150 mm)
Patch Preparation or thinner, use twice the usual rate of cur-
If any full-depth concrete patches exist or are ing compound. The finished product should
Key Resources
placed as part of the project in the underly- appear as a uniformly painted solid white sur- ACI Committee 325 (2006); ACPA (1998);
ing pavement, each concrete patch should be FHWA (2002a)
isolated to prevent its bonding to the concrete
overlay. If bonding occurs, the overlay over
the patch will be restrained differently than
the rest of the overlay over asphalt, potentially
resulting in cracking. To isolate the patch, a
geotextile fabric or other bond breaking mate-
rial, such as an asphalt slurry seal, should be
applied to its surface.

Surface Cleaning
Before concrete placement, the asphalt surface
should simply be swept. Remaining small par-
ticles are not typically considered a problem. Figure 41. Consider asphalt rut depth when determining saw-cut depth (ACPA 1998)

Guide to Concrete Overlays 45


Ch 3. OVERLAY OPTIONS

Unbonded Concrete Overlay on Concrete Pavements

Figure 42 illustrates a concrete pavement that


may be a candidate for an unbonded concrete
overlay, along with the kinds of preoverlay
repairs that may be appropriate. New unbonded overlay

Possible preoverlay repairs

Existing concrete pavement

Figure 42. Unbonded concrete overlay of poor condition concrete pavement

Application and Uses


Unbonded concrete overlays on concrete
pavements
May be appropriate for concrete pavements
in poor condition, including pavements
experiencing MRD, but should be stable
and provide uniform support; see Figure 43
Are generally 411 in. (100280 mm) thick
(JPCP or CRCP)
Are designed essentially as a new concrete
pavement on a stable base course (with the
existing pavement acting as the stable base),
assuming an unbonded condition between
the layers
Restore or enhance the pavements struc-
tural capacity
Increase pavement life equivalent to full-
depth pavement
Improve surface friction, noise, and
smoothness Figure 43. Unbonded concrete on concrete

46 Guide to Concrete Overlays


Ch 3. OVERLAY OPTIONS

Performance FAQHave thinner unbonded overlays actually been constructed?


Unbonded overlays of concrete pavements
have been successfully used in many states, Yes. Thin, 4 in. [100 mm] thick unbonded overlays are a viable solution for existing
with more than 30 years of good-to-excellent concrete pavements that have top-down joint deterioration issues. Project specifics and
performance; see Figures 44 and 45. Critical guidance for designing and constructing this type of unbonded overlays can be found at
factors that affect the performance of www.intrans.iastate.edu/research/documents/research-reports/US_18_overlay_construc-
unbonded overlays include separation layer tion_web.pdf (Cable 2012).
design, overlay thickness, joint spacing layout,
and load transfer design. Uniform support
from the existing pavement is a key factor.
Overlay Process remove the faulting or an asphalt interlayer
should be used. Retrofitted edge drains have
Keys to Success The overlay project consists of pavement
been successfully used to reduce the progres-
evaluation, design, construction, and future
The following actions will help ensure a suc- sion of faulting.
repairs.
cessful project:
Panel tenting (at the joint) may be an indica-
Full-depth repairs should be considered Pavement Evaluation tion of bottom-up deterioration. Sections
only at isolated spots where structural An evaluation of the existing concrete pave- with significant tenting should be repaired to
integrity needs restoring. ment is necessary to determine whether or not relieve the pressure and provide uniform sup-
the existing concrete and its subbase can pro- port before unbonded overlay placement.
A separation layer (typically 1 in. [25 mm]
asphalt or geotextile fabric) is required to vide uniform support and, if not, what actions
isolate the overlay from the existing con- are necessary to obtain that uniformity if an Overlay Design
crete and eliminate reflective cracking. unbonded overlay is to be used. The evalua- Unbonded overlays are designed similarly to
tion also determines the existing pavements new concrete pavements on a stabilized sub-
Provide a drainable asphalt separation structural contribution as a stable base. For base, assuming a separated condition between
layer to prevent stripping or, in the case of general information on pavement evaluation, the layers.
geotextile fabric, daylight the fabric to the including specific information about MRDs,
foreslope or a drainage conduit. see page 13. Overlay Thickness
The depth of joint faulting should be On heavily trafficked roads, unbonded overlay
For faulted pavements, the cause can usually
checked and a determination made whether thicknesses typically range from 6 to 11 in.
be attributed to the combination of some loss
or not the concrete overlay can elimi- (150 to 280 mm); on lower-volume roads,
of load transfer between slabs and some loss
nate further faulting or other repairs are they can be as thin as 4 in. (100 mm). The
of subgrade/subbase support. If the subgrade/
necessary. required overlay thickness is affected by the
subbase is stable, the increase in the carrying
desired load-carrying capacity and service
Joints should be sawed in overlay as soon as capacity of the unbonded overlay has proven
life, as well as the condition of the concrete
possible since the sawing window may be to be adequate to overcome faulting. Faulting
pavement.
shorter than it typically is. of 3/8 in. (10 mm) or less in the existing
concrete pavement is generally not a concern Both the AASHTO Design Guide (1993,
Shorter joint spacing in the unbonded over- when the asphalt separation layer is 1 in. (25 1998) and the M-E PDG (AASHTO 2008)
lay, as compared to full-depth pavement, mm) or more. When geotextile fabric is used consider the effects of the separation layer. See
can help reduce curling and warping stress. as an interlayer, faulting should not exceed basic highlights of and differences among the
0.25 in. If geotextile is desired and faulting is various procedures in Table 10 in Chapter 4.
It is not critical to mismatch overlay joints
an issue, the pavement should be ground to
to the underlying joints.

Figure 44. Route D35 existing pavement in poor condition (source: Figure 45. Route D35 5-inch unbonded overlay (source: Todd
Todd LaTorella, MO/KS Chapter, ACPA) LaTorella, MO/KS Chapter, ACPA)

Guide to Concrete Overlays 47


Ch 3. OVERLAY OPTIONS

Separation Layer Design mixtures should be proportioned for rapid MnROAD facility (Burnham and Izevbakhai
The separation layer design is one of the pri- strength gain without increasing shrinkage 2012). See Chapter 4 for additional informa-
mary factors influencing the performance of properties. For additional information on tion on plate dowels.
unbonded overlays on concrete pavements. accelerated mixtures, see page 76.
The use of tiebars for unbonded overlays
The separation layer provides a shear plane should follow conventional use for pave-
that helps prevent cracks from reflecting up Joint Design
Load transfer can be better in unbonded over- ments 5 in. (125 mm) thick or more. Using
from the existing pavement into the new lane tiebars may be appropriate in open-ditch
overlay. In addition, the separation layer pre- lays of concrete pavements than in new JPCPs
because of the load transfer provided by the (or shoulder) sections of unbonded overlays
vents bonding of the new pavement with the if the overlay is 5 in. (125 mm) or greater.
existing pavement, so both are free to move underlying pavement. Doweled joints are
typically used for unbonded overlays of pave- In this category, a no. 4 tiebar (0.50 in. [13
independently. mm]) may be appropriate. The use of tiebars
ments that will experience significant truck
There are three properties that should be traffic, usually pavements 7 in. (175 mm) and in curb-and-gutter (C/G) sections should be
considered in the selection and design of the thicker. The load transfer design is the same as considered if the overlay is 6 in. (150 mm) or
separation layer: for new concrete pavements. greater.

1. Adequate isolation from the underlying Shorter joint spacing should be used to reduce Many states do not intentionally mismatch
pavement to prevent reflective cracking the risk of early cracking due to increased joints and have not experienced any adverse
curling caused by the stiff support provided effects. Some states, however, still intention-
2. Beddingthe separation layer provides ally mismatch joints, according to previous
a cushion for the unbonded overlay by the underlying pavement; see Table 8.
guidance, to maximize the benefits of load
pavement For situations where the design requires transfer.
3. Drainagemoisture should be able to mechanical load transfer across the joints and
the pavement is less than 7 inches in thick- Unbonded plain jointed concrete overlays
escape the separation layer over continuously reinforced concrete pave-
ness, conventional dowels cause slipform
The most common and successful separa- paving clearance problems. Smaller diameter ment (CRCP) are designed and constructed
tion layer is a conventional 1 in. (25 mm) dowels do not significantly help the clearance the same as unbonded overlays on jointed
well-drained asphalt surface mixture, which issue and may not provide long-term load plain concrete pavements (JPCP). Texas has
provides adequate coverage over irregulari- transfer due to potential socketing in con- completed many CRCP unbonded overlays
ties in the existing pavement. The thickness crete. One solution that should be considered over existing CRCP and plain jointed pave-
can be slightly increased when irregularities is the use of structural fibers to help hold ments, sometimes increasing the asphalt
are large enough to impact placement opera- cracks and joints together. Additionally, the separation layer thickness to greater than 1
tions. The separation layer does not provide use of plate dowels provides clearance for the inch.
significant structural enhancement. Thus, the paver and allows for mechanical load transfer. Drainage
placement of an excessively thick layer should The performance of plate dowels in transverse
be avoided. Without good drainage of the separation
contraction joints is not well understood in
layer, pore pressure builds up from heavy
Stripping of a dense graded asphalt separa- concrete overlay pavements of 5 inches or less.
truck traffic and can cause stripping of the
tion layer has led to premature failure of They have, however, been used successfully in
asphalt separation layer. Properly designed,
some unbonded overlays. In locations where industrial parking lots. The effects of exposure
constructed, and maintained edge drains
water and heavy truck traffic will be present, a of epoxy or galvanized coated plate dowels to
may help reduce pumping, asphalt stripping,
drainable asphalt mixture should be used. This deicing salts is also limited. It is recommended
faulting, and cracking. Deeper edge drains
can be achieved by reducing the sand content that a proven and tested corrosion-resistant
(subdrains) are used to help stabilize sub-
and increasing the volume of 3/8 in. (10 mm) surface be required. Research on plate dowels
grades/subbases. When geotextiles are used as
aggregate in the asphalt mixture. See Table 18 in concrete overlays is being conducted at the
an interlayer, they need to also drain into sub-
on page 78 for information on gradation for drains or be daylighted at the shoulder.
asphalt interlayers.
During evaluation and design of an unbonded
For the last five years, geotextile interlayers Table 8. Typical Transverse Joint Spacing concrete overlay project, existing subgrade
have substantially increased in use and geo- drainage should be evaluated, as would be
textiles have proven to be good separation Unbonded Maximum Transverse done with asphalt resurfacing. If necessary,
Resurfacing
layers. For more information, see Chapter 4, Joint Spacing steps should be taken to ensure adequate
Thickness
page 59. drainage in the future (i.e., retrofit edge
6 x 6ft (1.8 x 1.8m) panels (not
6in. (125mm) to exceed 1.5 times thickness drains, daylighting free draining subbase
Mixture Design in inches) materials, geotextiles, etc.).
Conventional concrete mixtures are typically
used for unbonded overlays of concrete pave- Spacing in feet = 2 times When underdrains are present, they should
> 6in. thickness in inches, not to be cleaned, video inspected, and repaired as
ments in poor condition. When accelerated
exceed 15-foot joint spacing necessary.
opening is desired, conventional concrete

48 Guide to Concrete Overlays


Ch 3. OVERLAY OPTIONS

Construction swept clean of any loose material either Adequately anchoring dowel baskets to the
Construction elements may include preoverlay with a mechanical sweeper or an air blower. underlying concrete pavement is important.
repairs, separation layer, concrete placement, Conventional placement practices and pro- Alternatively, pavers equipped with dowel bar
curing, and joint sawing. cedures should be followed for placing the inserters can be used. Because of the varia-
separation layer (see Chapter 7, page 103). tion of the concrete thickness, the concrete
Preoverlay Repairs material is bid on a volume (cubic-yard) basis.
Concrete Placement Some states include a bid item for placement,
Typically, only distresses that cause a major
loss of structural integrity require repair. If When the surface temperature of the sepa- measured on a square-yard basis.
significantly distressed areas are not shifting ration layer is at or above 120F (49C),
sprinkling the surface with water can reduce Curing
or moving and the subgrade/subbase is stable,
costly repairs typically are not needed, partic- the temperature and minimize the chance of Good curing practices are especially critical
ularly with an adequately designed overlay; see early-age cracking. to thin unbonded overlays because of their
Table 9. As an alternative to numerous repairs, high surface-area-to-volume ratio. This is
When cooling a black-colored geotextile
some states increase the unbonded overlay accomplished by applying a curing com-
interlayer, it should be damp and not satu-
thickness to provide additional load-carrying pound immediately after surface texturing;
rated with water. A simple test is to touch the
capacity. if the unbonded overlay is 6 in. (150 mm)
fabric and no water should show on the fin-
or thinner, use twice the usual rate of cur-
gers. No standing water should remain on the
Separation Layer ing compound. The finished product should
surface at the time the overlay is placed.
Use of a sufficient separation layer can help appear as a uniformly painted solid white sur-
ensure good performance of the unbonded Conventional concrete paving procedures are face, with the vertical faces along the edges of
overlay. Before separation layer placement, followed for placing, spreading, consolidat- the overlay also thoroughly coated.
the existing pavement surface should be ing, and finishing the unbonded overlay.
Joint Sawing
Timely joint sawing is necessary to prevent
random cracking. Transverse and longitudinal
Table 9. Possible Preoverlay Repairs on Existing Concrete Pavement in Preparation for joints should be sawed with conventional saws
Unbonded Overlay to a depth of T/3. Transverse joint saw-cut
depths for early-entry sawing should not be
Existing Pavement Condition Possible Repairs to Consider
less than 1.25 in. (31 mm). Saw longitudinal
Faulting; 0.25in. for geotextile interlayer; joints to a depth of T/3.
None
0.38in. for 1-in. asphalt interlayer
Faulting; > 0.25in. for geotextile interlayer; Grind pavement to remove faulting for geotextile or Future Repairs
> 0.38in. for 1-in. asphalt interlayer thicker asphalt separation layer.
The recommended repair options for
Significant tenting Full-depth repair unbonded overlays are the same as for stan-
Badly shattered slabs Full-depth repair dard concrete pavements.
Significant pumping Full-depth spot repair and drainage improvements
Severe joint spalling Clean
Key Resources
ACI Committee 325 (2006); ACPA (1990b);
CRCP with punchouts or other severe damage Full-depth repair
FHWA (2002b)

Guide to Concrete Overlays 49


Ch 4. DESIGN

Chapter 4.

CONCRETE OVERLAY DESIGN

With todays limited highway funding and


aging highway network, and given the cost FAQ What if less than 3 inches of asphalt will remain after milling for a bonded
effectiveness of concrete overlays for pavement concrete overlay of asphalt?
maintenance and rehabilitation, it is likely There are two issues to consider. First, the recommendation of having 3 inches of fair-
that pavement engineers will be designing condition asphalt structure recognizes that pavement thicknesses found in the field have an
concrete overlays more often and for a greater inherent variabilitythere are thicker sections and thinner sections; thus, the recommen-
variety of existing pavements and pavement dation is a nominal 3 inches. Second, if there is a quality base course or stabilized subgrade
conditions. This section provides clear, reliable below the asphalt, it may be acceptable to have less than the recommended nominal 3
guidance for designing high-quality con- inches of asphalt pavement remaining.
creteoverlays and an outline of strategies and
resources necessary to implement concrete
overlay projects as part of an overall pavement
maintenance and rehabilitation program.
Existing Pavement should be evaluated for its overallcur-
The information in this section has been rent condition, which will influence both
Characterization the selection of overlay system (bonded or
collected from several valuable resources pub-
The design and performance of a concrete unbonded) and the type, location, and extent
lished by the American Concrete Institute
overlay is affected by the condition of the of any preoverlay repairs needed.
(ACI), AASHTO, FHWA, World Road
existing pavement structure. Although both
Association, NCHRP, ACPA, Portland
bonded and unbonded overlay systems ben- Surface Considerations
Cement Association (PCA), U.S. Army
efit from the load-transfer capabilities of For a bonded overlay to be a practical solu-
Corps of Engineers, Federal Aviation
the existing pavement, bonded overlays are tion on an existing asphalt surface, a nominal
Administration, and various state depart-
influenced to a greater degree by the underly- 3 in. (75 mm) minimum of fair-condition
ments of transportation. Existing procedures
ing pavement condition. Therefore, effective existing asphalt pavement structure should
are based on a variety of underlying assump-
characterization of the existing pavement remain after any necessary preoverlay repairs
tions and design strategies. It is important for
condition is important in selecting the proper and milling. Failure to properly evaluate the
concrete overlay designers to understand the
type of concrete overlay to build. thickness and condition of an existing asphalt
interaction of design with both the selection
of mixture materials and the construction The first step in designing a concrete over- pavement that will provide structural capac-
process. Perhaps the most critical design lay project is a thorough characterization of ity in a bonded overlay can lead to areas with
principle is that the concrete overlay and the the existing pavement. At the very least, the little or no asphalt remaining after milling.
underlying pavement should be viewed as a existing pavement section should be verified This situation necessitates difficult field engi-
system. with cores or historical records. Sometimes, neering decisions, essentially thickening of
however, the historical records or plans do the concrete overlay to compensate for the
not represent the actual in-place pavement, so reduced structural contribution of the exist-
Concrete Overlay field verification of the records is important.
In addition, the existing pavement structure
ing asphalt pavement. A thorough evaluation
of the existing pavement is necessary to avoid
Design Variables time-consuming and costly delays.
Regardless of the overlay system and design
procedure used, the analysis begins with
recognition of a number of common inputs Desired service
to the design process. It is important to first life, load-carrying
define the scope of the planned project and capacity
its intended structural performance require-
ments. Expected design life will affect both
the extent of repairs required on the existing
pavement and the design inputs. This in turn
influences the thickness, the amount of repair, Design
Costs Analysis
and thus the cost of the overlay; see Figure (thickness, etc.)
46. The engineer is also required to character-
ize and understand the existing pavement
structure (see information about evaluating
the existing pavement in Chapter 2), the
Existing pavement
anticipated traffic loading, and the materials
characterization
expected to be used. In most cases, climatic
influences play a role, particularly with a
bonded concrete overlay system.
Figure 46. Overlay design factors that affect one another

Guide to Concrete Overlays 51


Ch 4. DESIGN

If the pavement evaluation finds the existing


pavement is in poor condition with many FAQ Do I really need to worry about CTE?
localized failures, significant base failures may Though the effect of CTE is increasingly being considered in thicker overlays and even new
be indicated. Depending on the potential pavements, default values are adequate for the design of unbonded overlays.
costs of repairing these failures, a bonded
overlay may not be advisable. An unbonded
overlay that is less sensitive to the underly-
ing pavement condition may be more cost
effective. Condition evaluation permits the Designers are sometimes charged with mak- Material Properties
pavement engineer to determine the quantity ing decisions based on limited amounts Certain properties of the overlay concrete
and location of preoverlay repair required. of information. This is particularly true in should be known or estimated prior to the
rehabilitation project designs. Decisions on design process (see Chapter 5 for a full discus-
It should be noted that random cracks in the the design selection should be logical and
underlying pavement do not necessarily lead sion of materials used for concrete overlays).
defendable. The designer should be aware of This provides the designer additional flexibil-
to reduction in service life. Many miles of the impact that selecting the reliability level
unbonded concrete overlays have been built ity to adjust the designs to available material
can have on the final design thickness. In options that can be used to reduce costs with-
that have performed very well with little the AASHTO Design Guide (1993, 1998),
regard or consideration to repairing the crack- out compromising performance.
the reliability level and the overall standard
ing in the underlying platform. deviation result in an increase in the effective Strength of the concrete is one of the key
multiplier on the design traffic used in deter- design inputs, but this is often misunder-
Structural Considerations mining the thickness. Appropriate selection stood. The designer should use a strength
For bonded and unbonded overlays of exist- of these parameters can build in a predictable that is consistent with the assumptions of
ing asphalt or composite pavements, the layer level of risk. the design method being used. For example,
moduli can be determined through non- all AASHTO methods require third-point
destructive testing (see Chapter 2, page16, Traffic Characterization flexural strength in 28 days, yet it is not
Deflection Testing). Cores are recommended To develop a proper pavement design, the uncommon for designers to erroneously use
for all overlay projects. anticipated future traffic loading should be the strength found in the construction speci-
known as accurately as reasonably possible. fications. Since this value is often lower, it can
When overlaying composite pavements, the result in an unnecessarily thick overlay that
condition of the asphalt layer is a good indica- Care must be taken not only to measure or
predict current traffic characteristics, but also drives up cost.
tor of the existing base support. If the joints
and other discontinuities of the underlying to assign reasonable growth characteristics. Some methods require an estimate of the
concrete are visible and extremely distressed A prediction of the number of trucks should modulus of elasticity of the materials. This is
or exhibiting evidence of severe faulting, these be made over the design life. Measures some- often of secondary importance in unbonded
should be characterized. Excessive or visibly times include a prediction of the number overlays and has negligible impact in terms of
large deflections under truck loading may of equivalent single-axle loads based on the thickness. This property, however, becomes
require full-depth repair prior to resurfacing. anticipated traffic distribution. In this case, more important in bonded overlay designs.
Regardless of the design procedure used, the the designer should not approach traffic esti- Used in sufficient dosages, macro fibers
designer should also define the degree of sup- mates with conservative estimates. It is better enhance the toughness and ductility of the
port directly beneath the structural layers. In to make a reasonable estimate and adjust for concrete and may result in reduced concrete
terms of what is defined as a structural layer uncertainty later. thickness for some bonded overlay design
(as opposed to part of the support system), Alternative mechanistic-empirical pavement procedures (see page 77 and Appendix C for a
departure from the AASHTO Design Guide design procedures use a distribution of traffic full discussion of fiber-reinforced concrete).
(1993, 1998) is becoming increasingly com- loading. This loading describes the number, In some mechanistic-based procedures, the
mon, particularly in overlays. For example, weight, and geometries of the associated axle CTE of the concrete is also used. The CTE
using the conventional AASHTO Design loads. Sometimes this is further distributed by is a measure of a materials expansion or
Guide (1993, 1998) for new concrete pave- the time of day and even the season. Highly contraction with temperature; for concrete
ments, an asphalt layer is considered a support sophisticated models include the distribution pavements this has an impact on internal
layer. The property defining this support, the by lane and the wander of the wheel within stresses, which may lead to cracks, unless
k-value, describes the response of the material the lane. A number of typical distributions accounted for in the design of proper slab
immediately beneath the concrete pavement. available in the M-E PDG (AASHTO 2008) dimensions.
When using the design procedures, it is may be adequate for most situations.
important to understand at what location in The coefficient of thermal expansion can
the pavement structure the k-value is being At a minimum, average annual daily traffic have a much more significant effect on the
considered. In other approaches to design, and percentage of trucks is needed for thick- performance of bonded overlay designs. In
principally with concrete overlay of asphalt, ness design. Most of the design software designing bonded concrete overlays for exist-
the flexural capacity of the asphalt layer is packages have default distribution models for ing concrete pavements, it is important that
considered a structural component. The spe- estimating total equivalent single axle loads the CTE of aggregates specified for the con-
cific contribution of the asphalt layer depends (ESALs). crete overlay mixture design have a similar or
on the degree of bond with the concrete. In Where special traffic generators are present for lower CTE to that of the existing concrete
this case, the k-value would describe the sup- portions of a concrete overlay project, it may pavement. This helps ensure that both layers
port provided by the materials beneath the be advisable to adjust the thickness design for experience similar thermal movements, thus
asphalt. discrete portions of the project that experi- reducing stress on the bond between the two
ence heavier traffic. layers. In most cases, using a coarse aggregate

52 Guide to Concrete Overlays


Ch 4. DESIGN

in the overlay concrete mixture with the same Technology Center for current guidance concrete overlay designs: Federal Highway
mineralogy as that used in the underlying regarding comprehensive thickness design. Administration Pooled Fund TPF 5-269
concrete is sufficient. This document provides guidance for the fol- Development of an Improved Design Procedure
lowing design procedures: for Unbonded Concrete Overlays (under
Climatic Factors development). Future developments and
Bonded Concrete Overlay on Asphalt (BCOA)
Overlay system performance depends on refinements of concrete overlay thickness
Thickness Designer (ACPA 2012) (http://
climatic factors, both during construction design methodologies can be found at www.
apps.acpa.org/apps/bcoa.aspx)
and during the service life of the overlay. cptechcenter.org/overlay.
Relatively thin bonded overlay sections are Guide for Design of Pavement Structures, 4th
Table 10 provides a summary of the cur-
more susceptible to adverse weather con- edition (AASHTO 1993) (compatible soft-
rent design procedures, typical input values,
ditions that may affect the ability of the ware at www.acpa.org/WinPAS/) (https://
and pertinent information. Two of the most
concrete to retain moisture, prevent excessive www.google.com/#q=AASHTO.+1993.+G
important aspects in concrete overlay design
heat buildup, or prevent freezing. Materials uide+for+Design+of+Pavement+Structures)
are (1) how each method handles the bond
should be selected that are compatible with AASHTOWare Pavement ME Design between the existing pavement and the con-
the anticipated climate and freeze/thaw condi- (AASHTO [no year]) (www.aashtoware. crete overlay, and (2) whether the method
tions. Joints and load-transfer systems should org) assumes the existing pavement will provide
be designed to accommodate the movements significant structural capacity or, alternatively,
of the joints due to seasonal changes in pave- Background of Design contribute to the quality of the pavement
ment temperature. For example, shorter joint foundation. With this type of information,
spacing may be appropriate. Methodologies
pavement designers are able to make an
Designing either bonded or unbonded con- informed decision about which method to
Curling and warping are also considerations crete overlays is a process that begins with
for pavement designers. Slab dimensions and apply when designing a certain type of con-
characterizing the existing pavement, defining crete overlay.
joint layout should be optimized to minimize critical design variables, and then calculating
curling and warping stresses. the required overlay thickness. This section Note: Table 10 is to be used for general ref-
presents a general overview of the most com- erence purposes only. For design purposes,
Distress Mode mon design methodologies: actual overlay thickness should be determined
Advancements in computing hardware based on specific design variables for the proj-
and the desire to better understand what is Bonded Concrete Overlay on Asphalt (BCOA) ect, using the appropriate design procedure.
occurring as pavements fail has led to newer Thickness Designer (ACPA 2012) (http://
apps.acpa.org/apps/bcoa.aspx)
AASHTO and industry-developed methods ACPA BCOA Method
that, in essence, break apart the serviceabil- BCOA ME (Vandenbossche 2013) (www. The American Concrete Pavement Association
ity model into its individual components. engineering.pitt.edu/Vandenbossche/ (ACPA 1998) developed a mechanistic
Pavement designs are evaluated for multi- BCOA-ME_DesignGuide/) procedure to design thinner (2 to 4 inch)
modal deterioration modes that consider one bonded concrete overlays of asphalt (BCOA)
or more of theparameters. Multimodal deteri- Guide for Design of Pavement Structures. 4th
ed. (AASHTO 1993) (compatible software pavements with smaller slab sizes, which are
oration models carry a number of advantages. not captured by the two AASHTO meth-
They may aid in forecasting potential mainte- at www.acpa.org/WinPAS/) (https://www.
google.com/#q=AASHTO.+1993.+Guide+ ods described earlier. This BCOA method
nance, and they may assist in developing more consists of an iterative design process, where
effective and cost-efficient designs. for+Design+of+Pavement+Structures)
the designer evaluates the proposed overlay
Mechanistic-Empirical Design GuideA thickness and joint spacing along with traf-
Thickness Design Selection Manual of Practice (AASHTO 2008) fic, concrete strength (modulus of rupture),
In most cases, the designer will have an idea (https://www.google.com/#q=4.%09AAS existing asphalt pavement thickness, and com-
of the likely feasible alternatives based on the HTO.+2008.+Mechanistic-Empirical+De posite subgrade/subbase stiffness (k-value).
initial survey of the project. In selecting the sign+Guide+%E2%80%93+A+Manual+of The procedure determines the allowable
final thickness design, however, it is important +Practice) trucks for the trial design.
for the engineer to anticipate the condition StreetPave (ACPA 2012) (http://acpa.org/ The ACPA procedure is based on calculating
of the existing section at the time of actual streetpave/) the fatigue damage in the slab for a corner
construction of the new concrete surface. In loading condition, as well as limiting the
many cases, construction will not begin for Optipave V2.0. (TCPavements 2010)
fatigue damage at the bottom of the exist-
at least 2 or 3 years. Some degradation of the (www.tcpavements.com/index.
ing asphalt pavement at the transverse joint
existing structure should be anticipated and php?op=0&lang=en)
location (ACPA 1998). Temperature curling
considered in the analysis. Allowing for this Flowable Fibrous Concrete for Thin stresses are also considered in the critical pave-
continued degradation in the surface condi- Pavement Inlays (Bordelon and Roesler ment response. One limitation of this method
tion, the designer can begin the process of 2011) (http://ascelibrary.org/doi/ is that it is based on the PCA beam fatigue
considering feasible design alternatives using abs/10.1061/41167%28398%2984) (see model, which yields very conservative esti-
the procedures recommended in Table 10. Appendix C) mates. As a result, Riley developed a modified
There are several design procedures available ACPA method in 2006 that incorporated a
Illiniois DOTs spreadsheet for bonded new probabilistic concrete fatigue algorithm.
for determining the appropriate thickness concrete inlay/overlay of asphalt design
of bonded and unbonded concrete overlays. This modified method allows for inputting
(Roesler etal. 2008) (www.dot.state.il.us/ the existing asphalt pavement properties,
Designers should consult the Guide to the desenv/pdp.html)
Design of Concrete Overlays Using Existing accounts for the type and amount of struc-
Methodologies (Torres et al. 2012) pub- In addition, there is an ongoing effort to tural fibers, and checks for a potential bond
lished by the National Concrete Pavement develop a new methodology for unbonded plane failure.

Guide to Concrete Overlays 53


Ch 4. DESIGN

Table 10. Summary of Current Overlay Design Software (developed by Dr. Jeffery R. Roesler, University of Illinois at Urbana-Champaign)

Typical Design and Software Parameters

Overlay Typical Range of Macro-


Traffic Transverse *Mainline Recommended
Type Concrete Maximum Joint Condition fibers
(Millions Joint Longitudinal Design
Slab Spacing (ft) of Existing Option (in
of ESALs) Dowel Bars Tie Bars Procedure
Thickness Pavement software)

Bonded
Concrete
Overlay of Up to 15 36in. 1.5 times thickness (in.) Fair to Good Yes No No 1, 2, 8
Asphalt
Pavement

Bonded
Concrete
Bonded Overlays

Match existing cracks


Overlay of Up to 15 36 and joints and cut Fair to Good Yes No No 3, 4, 5
Concrete intermediate joints
Pavement

Bonded
Concrete
Overlay of Up to 15 36in. 1.5 times thickness (in.) Fair to Good Yes No No 1, 2, 8
Composite
Pavement

Thin Fibrous
Overlays
Up to 15 23in. 46ft Fair to Good Yes No No 7
of Asphalt
Pavements

Unbonded Slab < 6in.use 1.5


times thickness (in.)
Concrete T 6in.
Deteriorated For slabs >
Overlay of Up to 100 411in. Slab 6in.use 2.0 Yes use agency 3, 4, 5
to Fair 7in.
Asphalt times thickness (in.) standards
Pavement Slab > 7in.use 15 ft

Unbonded Slab < 5in.use


6ftx6ft panels
Concrete T 6in.
Deteriorated For slabs >
Unbonded Overlays

Overlay of Up to 100 411in. Slab 57in. use 2.0 Yes use agency 3, 4, 5
to Fair 7in.
Concrete times thickness (in.) standards
Pavement Slab > 7in.use 15 ft

Unbonded Slab < 6in.use 1.5


times thickness (in.)
Concrete T 6in.
Deteriorated For slabs >
Overlay of Up to 100 411in. Slab 6in.use 2.0 Yes use agency 3, 4, 5
to Fair 7in.
Composite times thickness (in.) standards
Pavement Slab > 7in.use 15 ft
For 3.5in.
slabs at tied
Unbonded
concrete
Short-jointed For slabs >
Up to 100 > 3in. 48ft Poor to Fair Yes shoulders or for 6
Concrete 7in.
T 6in.
Slabs use agency
standards
*See additional guidance regarding tiebars for shoulders and widening section beginning on page 71.

Recommended Design Procedures (see previous page for links)


1. Bonded Concrete Overlay on Asphalt (BCOA) Thickness Designer (ACPA 2012)
2. BCOA ME (Vandenbossche 2013)
3. Guide for Design of Pavement Structures. 4th ed. (AASHTO 1993)
4. Mechanistic-Empirical Design GuideA Manual of Practice (AASHTO 1993)
5. StreetPave (ACPA 2012)
6. Optipave V2.0. (TCPavements 2010)
7. Flowable Fibrous Concrete for Thin Pavement Inlays (Bordelon and Roesler 2011) (see Appendix C)
8. Illiniois DOTs spreadsheet for bonded concrete inlay/overlay of asphalt design (Roesler etal. 2008)

54 Guide to Concrete Overlays


Ch 4. DESIGN

In January 2011, the ACPA released a BCOA this effective temperature gradient occurs 100 3. The equivalent temperature gradient is
thickness design web application, Bonded percent of the time to give the same fatigue defined based on local conditions.
Concrete Overlay on Asphalt (BCOA) Thickness damage as the full temperature differential
4. The prediction models have been cali-
Designer (i.e., ACPA BCOA) that incorpo- distribution.
brated with actual performance data.
rates the work by Riley (2006). The ACPA
BCOA is valid for a slab thickness of 3 to 6 BCOA-ME Method 5. The effects of fiber on the performance of
inches and a maximum panel size of 6 feet. In 2013, the University of Pittsburgh devel- the overlay are more accurately quantified.
Shorter joint spacings (both transverse and oped a new design procedure under the
longitudinal) are typically used for bonded 6. The effects of debonding are considered.
FHWA Pooled Fund Study TPF-5(165)
overlays over asphalt pavements, such as 4 (Vandenbossche 2013), the BCOA-ME. Since The BCOA-ME procedure provides an overlay
foot by 4 foot or 6 foot by 6 foot slabs for a substantial number of bonded overlays thickness after the following information is
a 12-foot wide lane. Note that the ACPA have been in service for an extended period entered into the design spreadsheet:
BCOA web application does not allow designs of time, the opportunity existed to reevaluate
outside these ranges and provides warnings Traffic
the modes of failure for these overlays. This is
to indicate that the trial design needs to be critical since the pioneering procedures that Design location
modified or that a bonded overlay of asphalt have been traditionally used for the design
pavement may not be the appropriate solu- Longitude, latitude, and elevation
of bonded concrete overlays are based on the
tion. Furthermore, when BCOA designs are limited amount of information available at Climatic zone
approaching 6 inches thick and 6 feet wide, the time of their development. The perfor-
the BCOA-ME procedure described below Existing HMA pavements
mance review revealed the failure mode is
should be considered. dictated primarily by slab size and not overlay Remaining asphalt thickness
Updates in 2012 improved the fiber reinforce- thickness, as was previously assumed.
Approximate percent fatigue cracking
ment input to the ACPA BCOA based on The BCOA-ME procedure incorporates the
work by Bordelon and Roesler (2012), which Temperature cracking (yes/no)
ACPA BCOA performance prediction model
used the residual strength ratio of the fiber- that addresses corner cracks for slab sizes Composite subgrade/subbase k-value
reinforced concrete measured according to less than or equal to 4.5 feet by 4.5 feet, the
ASTM C1609-10. In 2012, the ACPA BCOA Concrete overlay strength, modulus, fiber
Colorado DOT performance prediction
design tool was also upgraded to allow for residual strength ratio, and CTE
model that addresses transverse cracking for
structural designs in any climate zone in the slabs with a 12-foot width (Sheehan et al. Proposed slab size
United States by including site-specific effec- 2004), and a newly developed performance
tive temperature gradients (Vandenbossche et prediction model that addresses longitu- Enhancements (1) thru (4) have been
al. 2012) for approximately 200 cities. dinal cracking in 6-foot by 6-foot slabs. It incorporated into the current version of the
should be noted that at times diagonal cracks procedure (Beta Version 1.3) and is available
The input requirements for the ACPA BCOA at www.engineering.pitt.edu/Vandenbossche/
thickness design tool follow: develop in the 6-foot by 6-foot slabs, but
these diagonal cracks initiate at the intersec- BCOA-ME/. The design procedure will be
ESALs tion of the wheel path and the transverse joint finalized, including the incorporation of
in the same manner that the longitudinal enhancements 5 and 6, and available for use
Percentage of allowable cracked slabs at the same website.
cracks develop. Instead of propagating to the
Reliability adjacent transverse joint, as occurs with a
longitudinal crack, they veer off toward the 1993 AASHTO Guide Method
Design location (to determine the site- The method found in the 1993 AASHTO
lane/shoulder joint and form a diagonal crack.
specific effective temperature gradient) Design Guide is based on mathematical
Therefore, the initiation stress for both the
Existing asphalt pavement longitudinal and diagonal cracks are the same. models derived from empirical data collected
during the American Association of State
Remaining asphalt thickness and The design process also includes a check, Highway Officials (AASHO) Road Test car-
modulus based on the work of Vandenbossche and ried out in the late 1950s. Even though no
Barman (2010), to determine whether or not overlay sections were evaluated during the
Composite subgrade/subbase k-value
there is a potential for reflective cracking. This AASHO Road Test, experience has shown
Concrete overlay check does not influence the design thickness that, when used properly, this procedure
but indicates whether or not preemptive mea- provides suitable but conservative bonded
Strength, modulus, fiber residual strength
ratio, and CTE sures should be taken prior to replacing the and unbonded concrete overlay designs. The
overlay to prevent reflective cracking. AASHTO computer software for implement-
Proposed slab size and preoverlay surface ing the 1993 AASHTO Design Guide is
preparation The six primary enhancements to current
methodologies provided by the BCOA-ME called DARWin. In addition, a number of
The recent implementation of the effective procedure include the following: agencies and state DOTs have developed cus-
temperature gradient for each city was deter- tom software and spreadsheets to apply this
mined as the equivalent negative temperature 1. The predominant failure modes are rede- procedure. The ACPA has also developed the
gradient that gives the same cumulative dam- fined as a function of slab size and, unlike WinPAS software package, which implements
age as the full distribution of temperature in the other procedures, all modes are the procedure.
differentials for that particular site and inputs addressed within this one procedure.
The 1993 AASHTO Design Guide uses the
(slab thickness, slab length, asphalt thickness, 2. The variability of the asphalt stiffness with concepts of structural deficiency and effective
and concrete strength). For all site locations, temperature is considered. structural capacity for evaluating and charac-

Guide to Concrete Overlays 55


Ch 4. DESIGN

terizing the existing pavement to be overlaid. AASHTO Pavement ME Design Concrete properties (strength, mixture
The structural capacity (SC) of a pavement Guide Method proportions, CTE, etc.)
section decreases with traffic and time. In Drainage and surface properties
The AASHTO Pavement ME Design
this procedure, SC is expressed in terms of
Guide procedure was developed under Three input levels are available for pavement
the effective structural number for existing
NCHRP Project 1-37A, Development of design, depending on the quality of the input
asphalt pavements (SNeff), or the effective
the 2002 Guide for the Design of New and data. Level 1 inputs are used if project-specific
slab thickness for concrete pavements (Deff).
Rehabilitated Pavement Structures: Phase traffic data are available and if certain pave-
Figure 47, which is an adaptation of Figure
II (Transportation Research Board 2004), ment layer material properties have been
5.1 in Part III of the 1993 AASHTO Design
and the original guide and accompanying measured. Level 2 inputs are used if correla-
Guide, illustrates this concept. This figure
software were both called the Mechanistic- tions with standard tests are necessary to
shows how the structural capacity of an over-
Empirical Pavement Design Guide (M-E complete the design. Level 3 inputs assume
lay (SCoverlay) restores the structural capacity of
PDG). The procedure is implemented in national default values in the design process.
the existing pavement (SCeffective) to meet the
an AASHTO professional software package This document emphasizes Levels 2 and 3
requirements for carrying the predicted future
called AASHTOWare Pavement ME Design inputs as a recommended starting point for
traffic (SCfuture traffic).
(AASHTO [no year]) available at www.aash- using the AASHTO M-E PDG procedure.
The 1993 AASHTO Design Guide presents toware.org.
three evaluation methods for determining The AASHTO M-E PDG method predicts
The AASHTO M-E PDG procedure com- performance indicators, such as IRI, trans-
the effective structural capacity of existing
bines a mechanistic-based approach with field verse cracking, and mean joint faulting, over
pavements (SCeffective) when designing con-
performance data so that an engineer can the pavements design life for jointed plain
crete overlays: Visual Survey and Materials
confidently predict the performance of pave- concrete overlays. For continuously reinforced
Testing (Condition Survey), Nondestructive
ment systems not considered in the original concrete overlays, the procedure predicts the
Deflection Testing (NDT), and Fatigue
calibration. This method adopts an integrated mean crack spacing as well as crack width,
Damage from Traffic (Remaining Life).
pavement design approach that allows the IRI, and number of punch-outs over the
The designer should select the most feasible
designer to determine the overlay thickness design life. For all of the distress predictions,
method based on the available resources but
based on the interaction between the pave- the AASHTO M-E PDG method calculates
should recognize that each method yields dif-
ment geometry (slab size, shoulder type, load incremental damage over the life of the pave-
ferent estimates.
transfer, steel reinforcement), local climatic ment by employing transfer functions for the
Even though the Remaining Life method is factors, and concrete material and support specific distresses, which are linked with the
often used, it is important to note that the layer properties. The procedure is currently corresponding maximum pavement response
1993 AASHTO Design Guide cites major under evaluation and implementation by a (deflection or tensile stress).
deficiencies associated with this method and number of state DOTs.
explains that the method is mostly applicable ACPA StreetPave Method
Chapter 7 in Part 3 of the M-E PDG
when the existing pavement exhibits very
(NCHRP 2004), PCC [Portland Cement In 2012, the ACPA released a new version
little deterioration. The 1993 AASHTO
Concrete] Rehabilitation Design of Existing of StreetPave that includes bonded and
Design Guide explains that the Remaining
Pavements, contains detailed informa- unbonded overlay designs for existing con-
Life procedure is based on the AASHO Road
tion regarding the design of bonded and crete, asphalt, and composite pavements. This
Test equations, and estimating past traffic (in
unbonded concrete overlays. This procedure software utilizes new engineering analyses to
ESALs) may be subjective and/or uncertain.
is an iterative design process that involves produce optimized designs for city, munici-
In addition, this method does not account
analyzing a trial overlay design not only in pal, county, and state roadways. For existing
for preoverlay repairs. For these reasons, the
terms of thickness but also in terms of other concrete pavements and overlays, StreetPave
designer should use the Condition Survey
relevant design features, such as joint dimen- 12 may be used to estimate service life and/or
method or NDT when the structural capacity
sions and load transfer, steel reinforcement (if failure criteria.
estimates that result from the Remaining Life
applicable), and concrete material properties.
method are inconsistent with the observed StreetPave 12 also offers an asphalt cross sec-
The following list summarizes the AASHTO
existing pavement condition. tion design process (based on the Asphalt
M-E PDG inputs (NCHRP 2004):
Institute method) to create an equivalent to
Rehabilitation type asphalt design for the load-carrying capacity
requirement. A Life Cycle Cost Analysis
Design life
module allows you to perform a detailed cost/
Pavement failure criteria (cracking, fault- benefit analysis and make informed deci-
ing, IRI) sions on your pavement design project. With
one pavement design tool, you can design
Reliability equivalent concrete and asphalt sections and
Traffic evaluate the best possible solution(s) for your
pavement needs.
Local climate
Bonded concrete overlays on asphalt or
Pavement cross section and layer properties composite are designed using the same equa-
Pavement design features tions as the ACPA BCOA method. All other
concrete overlay design methods in StreetPave
Slab geometry use the same overlay design equations as the
Figure 47. Illustration of structural capacity Joint and shoulder type 1993 AASHTO Design Guide method. This
loss over time and with traffic

56 Guide to Concrete Overlays


Ch 4. DESIGN

includes using the same equations and factors


for determining the Deff for existing concrete FAQ How is the thickness of an asphalt surface in a composite handled?
pavements and the same overlay thickness In this approach, the same failure model is used, but the assumption is made that the asphalt
determination equations (e.g., DOL = Df Deff layer has the maximum permitted thickness of 6 in. (150 mm), which corresponds to the
for a bonded concrete overlay on concrete). limits of the current design model. The elastic properties of the asphalt surface are used in
The only differentiating factor between the model.
StreetPave and the 1993 AASHTO Design
Guide overlay designs is that the required
composite thickness (Df) is calculated using
StreetPaves core design equations, using Design Consider- Concrete corner stresses are then compared
against the ACPAs 2004 fatigue model for
faulting and cracking as the failure criteria.
StreetPave also provides functionality to ations for Bonded concrete. Strains in the asphalt are compared
to Asphalt Institute design fatigue models.
include fibers in any design. Overlay Systems Bond plane stresses are evaluated using a
With bonded concrete overlays, the bond horizontal shear data model based on data
Slabs with Optimized Geometry obtained from Iowa, Florida, and Colorado
between the overlay and the underlying pave-
and OptiPave2 Design ment assists the horizontal shear transfer at projects. The calculated stresses and strains
Software the bond plain. This horizontal shear transfer for each mode are then compared against the
A new methodology called TCP (thin con- stresses into the underlying layers, thereby probabilistic models of each mode to deter-
crete pavements) or short-jointed concrete decreasing tensile stresses in the bonded over- mine which factor is the most likely mode of
slabs has been developed to design the lay. Somewhat different considerations are failure, or the weakest link, driving failure in
concrete slab thickness by optimizing the required depending on whether the overlay the overall system.
slab size given the geometry of the truck is bonded to existing concrete or to existing The bottom line is that understanding the
axles (Covarrubias and Covarrubias 2008). asphalt. All bonded concrete overlay systems, interaction between bond plane stresses and
The key principle of the design method is however, depend on the integrity of the corner break stresses helps designers opti-
to select the slab size so that not more than underlying pavement. mize joint spacing and several other factors
one set of wheels is on any given slab at one in designs for bonded concrete overlays on
time, thereby minimizing the critical top Bonded Overlays of asphalt pavements.
tensile stress. Full-scale test sections were
constructed and tested at the University of Asphalt and Composite In addition to the probabilistic adaptation
Illinois under accelerated pavement loading Pavements of the mechanistic procedures, new advance-
conditions with a slab thickness of 3.5 to 8 A unique design consideration for bonded ments in materials were included, particularly
inches on either aggregate or asphalt base overlays on asphalt or composite pavements with regard to the inclusion of fibers. The
layer (Cervantes and Roesler 2009; Roesler is the joint spacing to mitigate curling and effect of fibers in the models is based on their
et al. 2013). The performance data from the warping stresses in the bonded overlay. The ability to enhance the fatigue resistance of
full-scale test were utilized in the development ACPAs original 1998 design procedure for the concrete. The design procedure for fibers
of the mechanistic-empirical design software this overlay type was based on a single mode is open ended in that as new fibers are devel-
called OptiPave2 (Covarrubias et al. 2010; of failurethe corner break. The ACPAs oped and properties are established, these can
Covarrubias 2011). OptiPave2 software is 2004 revised procedures incorporated proba- be incorporated accordingly.
specifically tailored to design short-jointed bilistic methods into concrete fatigue models, Probably one of the more challenging aspects
concrete pavements for any set of climate, but the procedure for this overlay type con- in the design of bonded overlays of asphalt
traffic, subgrade/subbase layer, and material tinued to be based only on the corner break and composite pavements is the consideration
property inputs, including the addition of mode of failure. of the supporting platform. For designs of
macro fibers.
The corner break model has worked this type, the classic k-value described earlier
Thin concrete pavements designs include adequately. In recent years, however, it has is based on the value at the bottom of the
unbonded concrete pavement over granular been recognized that the two most common asphalt layer rather than at the bottom of the
or stabilized base layers. Typical slab sizes for precursors to failure for bonded concrete concrete layer.
TCP are between 4.5 feet and 8 feet long by overlays on asphalt or composite pavements The joint design of thin bonded overlays over
6 feet wide with slab thickness ranging from are delamination stemming from failure in asphalt pavement is a distinguishing charac-
2.4 to 10 inches depending on traffic, climate, the bond plane or from failure in the underly- teristic when these projects are placed in the
and soil conditions. The OptiPave2design ing asphalt layer. Therefore, the most recent field. The transverse and longitudinal joint
software predicts the level of cracking, revisions of the design procedure for this type spacings are always 6 ft (1.8 m) or less in
faulting, and IRI for a given set of inputs. of overlay reflect a weakest link approach, length as determined by the design analysis.
OptiPave2 is currently the only pavement applying probabilistic techniques to all three It is important that joints in this type of over-
design software that is able to optimize the modes of failure. lay be cut as quickly as possible to minimize
slab thickness requirements for slab sizes less
First, design parameters are input into the the likelihood of curling stresses developing,
than 10 feet. Since 2006, multiple projects
design model. Then stresses are calculated triggering delamination at the edge of the
have been constructed in Latin America,
using the corner stress model. From that pavement. Early-entry saws are often used.
including Chile, Peru, and Guatemala.
OptiPave software licenses are available in information, strains in the bottom and top There are numerous examples of bonded over-
North America from PNA Construction of the asphalt layer, plus horizontal stresses lays of asphalt and composite pavements that
Technologies, Inc. (www.pna-inc.com, tele- inferred at the bond plane, are calculated are approaching 20 years of service. When
phone number 800-542-0214). based on the location of the composite neu- properly designed and constructed, these
tral axis. concrete overlays can perform satisfactorily for
any desired design life.

Guide to Concrete Overlays 57


Ch 4. DESIGN

Bonded Overlays of FAQWhat is serviceability?


Concrete Pavements
Serviceability or present serviceability rating (PSR) was developed during the AASHO Road
The AASHTO Design Guide (1993, 1998) Test. The PSR is defined as the judgment of an observer as to the current ability of a pave-
procedure for bonded overlays of concrete ment to serve the traffic it is meant to serve (AASHO 1962). The PSR scale ranges from 0
pavements uses a design deficiency or (very poor) to 5 (very good).
remaining life approach. The mode of fail-
ure most commonly used is serviceability.
This is largely due to the fact that most pave-
ment engineers today are comfortable with Maintaining the bond is especially critical lowed by classic fatigue failure at isolated joint
the concept. The existing pavements in these during the first few days when the overlay is locations. These can be repaired using partial-
cases have not failed. It is assumed, however, susceptible to curling and warping stresses, depth repair techniques if the underlying slab
that some of the pavement life has been especially at the pavement edges. Therefore, remains sound.
consumed in either fatigue or serviceability, the bond must be protected through thor-
depending on the design procedure being ough proper curing practices, particularly
used. of the pavement edge, minimizing relative
humidity and temperature differentials
Design Consider-
First, standard design methods (see existing between the two layers and keeping early ations for Unbonded
methodologies) are used to determine the traffic away from the pavement edges until
required thickness of a new pavement based adequate bond strength has been achieved Overlay Systems
on the anticipated traffic, planned materials (usually when opening strength has been Unbonded overlay designs usually do not
to be used, and other parameters typically achieved). consider bond, though in fact some bonding
considered in new pavement design. Having usually occurs and is beneficial. They are essen-
determined the overall required pavement Joints in designs of this type must be matched
tially designed as new concrete pavements,
thickness, the pavement thickness equivalent to the existing section. Transverse joints
with the pavement being overlaid acting as a
after adjusting for the life consumed of the should be cut full depth of the overlay plus
base. Adaptation of existing design procedures
existing section is estimated. This thickness 0.50 in. (13 mm) and must be as wide as or
is relatively straightforward and construction
corresponds to the thickness required to carry greater than the crack below the joint in the
relatively easy. Unbonded overlays are usually
the number of loadings to failure as defined underlying pavement; see Figure 48. Note
designed to serve 20 to 30 years.
by AASHTO. In the AASHTO Design Guide that this is different from the width of the
(1993, 1998) and earlier terminology, this is existing joint reservoir. Longitudinal joints The selection of the load transfer coefficient
simply the change in serviceability and cor- should be cut at least T/2. in the AASHTO procedure should be made
responds to the remaining life. with recognition of the character of the under-
Designs for overlays of existing CRCPs are
lying layer in addition to the intended load
Additional minor adjustments may also be also possible. In the case of CRCPs, however,
transfer system for the overlay. Consideration
made having to do with observations of there is no need to match the transverse joints
should be given to the underlying structure
existing pavement condition, but these are since none exist, with the exception of termi-
providing additional load transfer, which is not
somewhat subjective. After the adjustments, nal joints and full-depth repairs.
necessarily true of new concrete pavements.
the resulting number represents how much The use of steel reinforcement or dowels is The designer should not arbitrarily pick a
effective pavement thickness is still actually not usually a consideration for bonded over- conservative value, as this is not the intent
available to be further consumed or used lays on concrete pavements unless the overlay of the design procedure. The ACPAs WinPAS
in the new pavement system in addition to is thicker than usual, new shoulders are being software program (based on AASHTO Design
the new overlay. The difference in the thick- tied, or there is also a desire to retrofit load Guide 1993) includes an entire section for use
ness calculated for a new pavement and this transfer. in designing these types of systems.
effective section is the design deficiency or
the required thickness of the new section that Properly built, bonded overlays can reason- Care must be exercised during construction
should be bonded to the existing pavement. ably be expected to provide a minimum to ensure that the saw depth of the unbonded
For further information, see the AASHTO service life of 15 years before maintenance overlay is adequate, particularly when the over-
Design Guide (1993, 1998). is required. The first indication of problems lay thickness varies, such as in variable cross
on these overlay projects is usually early slope, transitions, etc.
Critical to the performance of this type of delamination at the bond plane, quickly fol-
overlay is the development of a bond between
the two layers. Existing design procedures for
bonded overlays do not specifically address
bond strength, treating it primarily as a Width of new Note: Overlay joint width shall be equal to or
Overlay joint overlay greater than crack in the existing slab.
construction issue. If the section is cleaned Concrete transverse joint
and constructed correctly and proper curing overlay If X is 0.50 in. (13 mm) or greater, the underlying
procedures are used, bond strength is usually crack width in the existing slab should be
measured. If crack is 0.25 in. (6.4 mm) or greater,
not a problem. Extreme daytime to nighttime Saw cut in and existing pavement does not have dowel bars,
temperature swings, however, can sometimes existing slab (X) the joints should be evaluated to determine if load
transfer rehabilitation is required to eliminate
trigger delamination failures. If ambient Underlying crack
faulting. If there are numerous joints of this type,
temperature differentials in excess of 30F are in existing slab
the existing pavement may not be a good
anticipated, from the time pavement is set candidate for a bonded overlay.
and for the next 12 to 18 hours the section
should be protected. Figure 48. Width of overlay joint saw cut must be greater than the crack width in the existing
pavement

58 Guide to Concrete Overlays


Ch 4. DESIGN

FAQWhat happens if an unbonded FAQWhy is it better to use concrete as the material for making grade corrections?
overlay bonds to the separation layer?
There are many reasons to use a nominal thickness asphalt separation layer while making
Beneficial bonding can occur when an grade corrections with concrete:
asphalt separation layer is used as part of
The cost of the two materials on a volume basis is very similar.
an unbonded overlay design. Although
not factored in the thickness design pro- When a cubic-yard pay item is used for the concrete overlay, the risk of yield loss to the
cedure, this beneficial bonding effectively contractor is nil; thus, the agency pays only for the actual quantity of material used.
increases the load-carrying capacity of
the unbonded overlay system. This is one It is very difficult to place variable thickness asphalt layers to true grade because of
reason that rubblization or crack and seat variable roll down; there will still be significant thickness variation when this approach
methods are not recommended preoverlay is used.
activities. Leaving the existing pavement With cost being nearly equivalent, an increased thickness of concrete will add
intact preserves the structural integrity significantly more life than a thicker asphalt separation layer.
of the existing pavement and maximizes
the value of the investment placed in the When dowel baskets are used in the concrete overlay, securely anchoring them into a
original pavement. variable thickness asphalt separation layer has proven to be difficult.

Unbonded Overlays of When an entire concrete pavement has ments, Texas has sometimes increased the
deteriorated severely along the length of the asphalt separation layer thickness to greater
Concrete Pavements pavement due to movement, it is probably than 1 in. (25 mm).
In many cases, an existing concrete pave- time to reconstruct the entire pavement. A
menteven one in poor conditioncan It is important not to use the asphalt sepa-
good option is to recycle the pavement in
provide a cost-effective base for a new con- ration layer as a leveling course. All grade
place and use it as an unstabilized (granular)
crete overlay. corrections, including leveling, should be
subbase for a new, full-depth pavement if the
accomplished with the concrete overlay itself.
existing subgrade is adequate (see Appendix B
Suitability of Existing Pavement for a discussion of recycling options). The geotextile should be either daylighted
as a Base past the edge of the shoulders or tied into a
The existing pavement is suitable as a base Interlayer longitudinal underdrain system to provide
for an unbonded overlay if it can meet the All unbonded concrete overlays on concrete positive drainage. Laps should be a minimum
desired design life requirements for the base. must be separated from the existing concrete of 8 inches, and the geotextile should be
The existing pavement must be stable and pavement by a stress-relief layer, or interlayer, anchored securely using nails and washers at 6
uniform; that is, it must not experience signif- to prevent reflective cracking from movement feet c/c each direction. The structural condi-
icant differential movement and there should of the existing pavement. Interlayers serve tion of the existing concrete pavement must
not be large areas lacking adequate structural multiple purposes: be carefully assessed before selecting a geotex-
support. tile instead of an asphalt interlayer.
The interlayer provides a shear plane that
When an entire concrete pavement has begun relieves stress and helps prevent cracks from There has been one documented case where
to break up, it is a good indicator of serious reflecting up from the existing pavement noise from concrete slabs rocking against each
subgrade/subbase problems that need to be into the new overlay. other was observed. This project was a 4-inch
addressed before other solutions are consid- thick unbonded overlay placed on a relatively
ered. If the subgrade is unstable, it may be The interlayer may prevent bonding of the thick (3 mm+) geotextile. No formal studies
time to replace the pavement and correct the new pavement with the existing pavement, were performed on the project, but based on
subgrade/subbase. so both are free to move independently. informal observations, the general hypothesis

Isolated areas of full-depth structural distress Drainage must channel infiltrating water
are generally not a problem if they can be along the cross slope to the pavement edge
repaired cost effectively before placing the and then be outletted.
overlay. On the other hand, areas of MRD Bedding is a cushion for the overlay to pre-
that cause movement from expansion and/or vent keying from existing faulting.
contraction in the existing pavement require
careful evaluation. The design should consider the relative
importance of each purpose based on project-
If MRD-related movement is limited primar- specific conditions and the condition of the
ily to the joints (e.g., D-cracking movement), existing pavement.
and if full-depth joint repairs can be justified
from a cost perspective, a pavement may still Over the years, many stress-relief methods
be a good candidate for an unbonded con- have been used successfully. The most com-
crete overlay. Unbonded concrete overlays on mon stress relief is a thin layer of asphalt
concrete pavements with full-depth structural material. Thickness is not critical, but 1 in.
and/or joint repairs have proven performance (25 mm) is usually adequate to eliminate
records as effective bases for unbonded con- potential problems with keying of faulted Figure 49. Upper sketch shows concrete
crete overlays. Some agencies have even had slabs (see Figure 49), localized repairs, etc. overlay locking up with old pavement
success with infilling deteriorated joints with When constructing CRCP unbonded overlays (keying), and lower sketch shows interlayer
stable material such as flowable mortar. over both CRCP and plain jointed pave- separates overlay from existing pavement.

Guide to Concrete Overlays 59


Ch 4. DESIGN

is that the compression of the fabric under For unbonded overlays of concrete pavements, All else being equal, improvements to pave-
traffic loading allowed deflection of the slabs, some agencies note the underlying pavement ment drainage can ultimately allow for a
which caused the noise. The noise was less joint locations and intentionally place the joints thinner overlay design. Such improvements
prevalent during warmer temperatures when in the new overlay away from those joints such have the additional benefit of facilitating the
the slabs were tight against each other and that they are mismatched. The rationale for this egress of water from the pavement system,
eventually subsided completely. In 2013, is that load transfer will be improved. Other which is often a key factor in the joint dete-
the Minnesota DOT started testing the dif- agencies discount this idea in favor of a more rioration being mitigated by the overlay.
ferent thicknesses of nonwoven geotextile construction-friendly approach. In this case,
For example, a change in profile and/or
fabric under 3 -inch thick (fiber-reinforced) joints are simply placed where they would nor-
cross slope can be designed in the overlay
unbonded concrete overlay over concrete. mally be according to the type of design being
so that water is more readily shed from
The test sections were at Minnesota DOTs built. Both strategies have resulted in good
the pavement surface. Joints in the overlay
pavement test track, MnROAD, and the final performance. An exception to this is existing
can be designed to resist excessive ingress
results will be available in 2014. Early obser- expansion joints, which must be matched in the
of water. This can be done by constructing
vations indicate a difference in both physical unbonded overlay; see Figure 52.
them with a narrow (single) saw cut and/
and audible behavior of the overlays for the
or filling or sealing them appropriately.
different fabric thicknesses. Drainage of Interlayer Subdrainage can also be improved if mea-
Interlayer fabric is specified by weight and The presence of water within the interlayer sures are taken to retrofit edge drains.
thickness (mils) and color; see Figures 50 system will often accelerate the development
of distress in the overlay. Water can enter a For an unbonded overlay, either a nonwoven
and 51. Table 11 provides a general rule of
pavement system from the top down or from geotextile that meets certain transmissivity
thumb for weight and thickness. The weight
the bottom up due to any of the following requirements (see Table 11) or open-graded
per square yard and thickness should be given
situations: hot-mix asphalt (HMA) can be used as an
when specifying a geotextile separation layer.
interlayer that promotes drainage, provided
See Chapter 5, Separation Layer Materials, for Longitudinal joint trapping there is an outlet. Nonwoven geotextile
additional details.
Tight, clay subgrade that does not drain interlayers do promote drainage (wicks
If joint faulting in excess of 3/8 inch for water) but must also have a proper drainage
asphalt interlayer and 0.25 inch for geotex- Densely graded subbase that does not drain outlet. See miscellaneous details for drainage
tile interlayer is present, the joints should be outlets beginning on page 72.
High water table capillary action
milled to eliminate the vertical offset or an
asphalt separation layer should be used. No subdrains, or subdrains are not working

Figure 50. Geotextile fabric separation layer (source: Missouri DOT) Figure 51. White geotextile fabric separation layer (source:
Larry Engbrecht, South Dakota ACPA)

Table 11. Typical Weight and Thickness for Geotextile Interlayer

Interlayer Fabric

4-in. overlayconsider 5-in. overlayconsider


Weather resistance > 60%
13oz/ yd2 typical thickness, 15oz/yd2 typical thickness,
130mils 170mils

Test tensile strength after


2kPa120150mils 2kPa155185mils
500hours of UV accelerator

Tensile strength after test


20kPa80110mils 20kPa110140mils must be at least 60% of
initial strength

200kPa2050mils 200kPa4070mils
Figure 52. Overlay blowup where expansion joint
should have been cut over existing concrete expansion
joint (source: Dan DeGraaf, Michigan Concrete Paving
Association)

60 Guide to Concrete Overlays


Ch 4. DESIGN

Asphalt interlayers have served as separation Joint Design There are constructibility issues (mainly
layers on concrete for many years. Occasional Because of the high stiffness of the underlying paving machine clearance to the rounded
problems, however, have been noted with platform (the existing concrete pavement) in dowel) when using load-transfer dowels in
asphalt stripping within the interlayer under unbonded overlays on concrete, it is neces- thin overlays (< 7 inches) that necessitate
repetitive loading, causing a loss of support sary to shorten joint spacing in the overlay using smaller-diameter dowels (1 inch or less)
for the unbonded overlay; see Figure 53. This compared with normal designs. The shorter when dowels are needed. The use of smaller-
can occur occasionally with high truck-traffic joint spacing is necessary to reduce the risk diameter dowels has a reduced bearing area
volumes in the presence of water in the inter- of early cracking due to temperature curling that increases the bearing stress on the smaller
layer. Usually, the stripping takes several years and moisture warping stresses, combined with concrete area under the dowel bar, sometimes
to develop. The best preventive solutions are loading stresses. Note that existing AASHTO resulting in premature socketing (enlargement
the following: methods do not consider this in design. of the area around the dowel), which defeats
Rule-of-thumb guidance for joint spacing the purpose of using dowels. In response to
Provide positive drainage for the asphalt
for unbonded overlays using these methods the need to accommodate thinner pavements
layer. Under heavy truck-traffic loading,
is based largely on experience (see Table 21, and yet meet design loading for longer joint
consider using a drainable asphalt mixture
beginning on page 99, for information about spacings, the concrete paving industry is
or the gradation used by the Michigan
maximum joint spacings). beginning to utilize plate dowels, particularly
DOT (see Chapter 5, page 78, Table 18).
in industrial parking lots; see Figure 54. The
The interlayer should be daylighted to the Transverse joints in the unbonded overlays plate dowels solve paving machine clearance
edge of the shoulders or a subdrain system can be plain, doweled or, in a continuous problems and provide the load transfer across
installed. reinforced concrete overlay, totally eliminated. the joint. Because of the larger horizontal sur-
Incorporate antistrip additives such as lime Plain undoweled joints are the most common face area of plate dowels versus round dowels,
in the asphalt. Lime was found to be more for thicknesses less than 7 inches. There are the bearing pressure (psi) on the concrete is
effective than liquid antistripping additives. conditions, however, when mechanical load reduced. The reduced restraint and stresses of
transfer is required to meet load criteria with plate dowels also minimizes random cracking
Seal joints in the concrete overlay and at certain thickness restrictions due to costs or in thinner sections. To date, there is a limited
the shoulders. vertical limits. Before dowels are used, con- number of plate dowels used in highway proj-
Utilize a geotextile separation layer with sideration should be given to shorter joint ects. In cases where thin unbonded overlays
positive drainage. spacing using synthetic fibers that help hold are desired to meet vertical restrictions and
the joints tight. If that is not possible, then load demands, however, the use of synthetic
rounded or plate dowels can be considered. fibers for shorter contraction joints in com-
Thin unbonded concrete overlays (less than bination with plate dowels in construction
5 in. [125 mm] thick) have been built under joints does have merit.
appropriate loading conditions using short
joint spacing, usually 6 ft (1.8 m) or less, and Manufacturers offer various plate dowel geo-
do not have dowels. metrics and associated installation devices.
The shrinkage restraint is reduced by using
The purpose of the dowels in transverse joints a tapered shape or formed void or by having
is to help load transfer across the transverse compressible materials on the vertical faces
joint. Dowels are typically used when heavy with a thin bond breaker on the top and bot-
truck traffic is anticipated, which normally tom dowel surfaces, per ACI 360R-10. The
drives the design thickness to 7 in. (175 mm) tapered shape, along with a thin bond breaker
or greater. The depth of the dowels is at T/2 on all sides, allows a void space to develop
except in super transition areas (see miscel- along the vertical sides of the dowel, eliminat-
Figure 53. Asphalt stripping of interlayer laneous design details for further information ing restraint as the slab shrinks from the joint;
(source: Dan DeGraaf, Michigan Concrete in supers). The transverse saw cut depth over see Figure 55. Compared to round dowels,
Paving Association) dowels is T/3 or T/4. plate dowels allow adjacent panels to move

Figure 54. Tapered plate dowel baskets in transverse Figure 56:Higher


Figure 55. Jointshrinkage
intersections - Compared
restraint to roundwith
in joint intersection dowels,
round plate
contraction joints and football-shaped plate dowels for dowels allow
dowel (left) forjoint
versus adjacent panelswith
intersection to shrink freely
plate dowel without restraint
(right)
slipformed longitudinal construction joints and can therefore be placed within 6 in. of a joint intersection
where the curling / warping stresses are the greatest.
Guide to Concrete Overlays 61
Ch 4. DESIGN

freely without restraint and can therefore be


placed within 6 inches of a joint intersection
Plan Development Engineering
where curling and warping stresses are the For DOTs that are inexperienced with the Survey
greatest. Similarly, a formed void or compress- design of concrete overlays, the approach
ible material can also eliminate restraint as the should be similar to that of designing an asphalt The determination of whether or not a sur-
slab shrinks from the joint. overlay. There is no need to add complexity to vey of existing conditions is needed during
the planning and engineering process simply the design phase of a project will primarily
Because of the various plate dowel geometries because the overlay type has changed. The loca- depend upon the presence of vertical and/
and installation devices available, the indi- tion, geometrics, and maintenance of traffic or horizontal constraints at the construc-
vidual manufacturers published engineering requirements should dictate the level of design tion site and the condition of the roadway.
reports should be consulted to determine detail that is required in the plans. When few constraints are present and
optimum dowel size and spacing for a specific mirroring existing contours is acceptable,
project. Plate load-transfer devices are also For decades, rural asphalt overlay projects have a survey is not necessary. Plans need not
useful in other pavement applications where been successfully designed and built from a include a proposed profile grade for these
joints should have load-transfer capability set of plans consisting of a title page, typical types of projects; the existing surface pro-
while allowing two-directional doweling section(s), pay quantities, notes, plan view vides significant control information. Final
and odd-shaped panels; see ACI 302-1R-04 sheets, and standard drawings. This approach is profile will be determined during construc-
(ACI2010). The use of plate dowels exposed entirely acceptable for a concrete overlay under tion through the combination of minimum
to deicing salts is limited. It is recommended the same conditions. That being said, for proj- design thickness and design cross slope(s).
that a proven and tested corrosion-resistant ects in urban or suburban locations, especially
surface be applied to these dowels when where vertical (bridge clearance, drainage inlets, If, however, the existing roadway has
exposed to deicing. See Miscellaneous Design etc.) and horizontal (barrier wall, curb, etc.) significant surface distresses, ride-quality
Details for further discussion on plate dowels. constraints are present, the plans must include issues, drainage problems, or profile and
the appropriate details and information to cross-slope corrections, an engineering
communicate how the concrete overlay will be survey is recommended. This will allow the
Unbonded Overlays of development of an optimized profile and an
treated to meet these conditions.
Asphalt Pavements accurate estimate of the volume of concrete
An example index of plans for a rural concrete required to construct the overlay. Complex
Unbonded overlays of asphalt pavements
overlay on a state route or county road would projects with multiple vertical and/or
can address existing sections that have crown
include the following: horizontal constraints should be surveyed
or ruts in the surface. Placing the concrete
directly on the surface positions the thickest during the design phase, and proposed fin-
Title sheet with location map
concrete at the points of highest load in the ished elevations should be provided to the
pavement structure and is therefore one of the Typical sectionsnote limits of any correc- contractor to assure that conflicts between
more efficient designs. If rutting is extreme tion of superelevation the overlay and existing conditions are
(greater than 2 in. [50 mm]) or the change avoided. A vertical control system should be
Estimated quantities and pay-item notes established along the highway at 1,000-foot
in cross section due to crown is significant,
care should be taken to ensure that the design Summary of quantity estimates intervals to assist in the development of the
plans call for adjusting the sawed joint depth plans and provide the construction forces
Preoverlay repairs with a basis for profile development.
accordingly.
Subdrain installation
Due to the variability in thickness across the Survey Methods
section if placed directly on the asphalt, the Pavement removal
contract documents should include provi- Regardless of technologies used such as
Separation layer (if used)
sions for payment for materials separately GPS, total stations, differential leveling, or
Concrete overlaycubic yard and square laser scanning technology the principals of
from payment for placement. These so called
yard survey and data collection apply. Horizontal
square-yard cubic-yard provisions are rec-
ommended for all concrete overlay projects Shoulders and vertical control must be established
and are important in reducing the contractors throughout the project corridor so existing
Erosion controltemporary and and proposed elevation models are relative
risk and owners cost in bidding the projects. permanent to each other and can be verified at each
Survey information in tabular formatcon- phase. The control points should be numer-
Unbonded Overlays of trol points, curve data, existing pavement ous enough to facilitate the survey work as
Composite Pavements elevations, and proposed concrete overlay well as well as be available for the construc-
Unbonded overlays of composite pavements elevations tion of the project. Normally, horizontal
follow the same design guidelines as concrete work is being performed with a total station
Sequence of construction, maintenance of and/or GPS, whereas vertical control is
overlays of concrete pavements. The primary
traffic, and traffic-control details normally is completed with total stations
difference is that the separation layer already
exists in the form of the asphalt layer of the Plan view sheets or component differential leveling. Total
composite pavement. In some cases, the stations do have limitations for vertical
existing asphalt may be unsuitable as a separa- Design details control that needs to be understood by the
tion layer and must be milled off and a new Overlay transitions at bridges, underpasses, surveyor. Therefore, component differential
separation layer placed. This primarily occurs B.O.P., and E.O.P. leveling (digital level preferred) is suggested
when the asphalt is prone to lose stability to achieve the accuracy required. Physical
Jointing details cross sections of the roadway should be per-
(resulting in a loss of support for the overlay)
due to stripping. Standard drawings formed on 25 foot intervals or less for the
whole project.

62 Guide to Concrete Overlays


Ch 4. DESIGN

The decision of which technology to use is (GPS) to record its position on the earth Establishing Plan Quantity
up to the surveyor/engineer and the avail- surface at any time and the relative position
able technology. Conventional survey is more of the objects being scanned. An inertial mea- for Overlay Concrete
labor intense when compared to LiDAR tech- surement unit (IMU) is used to account for There are two options to consider:
nologies of static and mobile laser scanning. movement (pitch, roll, and yaw) in the survey 1. For minimal preliminary work and cost
vehicle. A distance measuring instrument
Laser Scanning (DMI) is used to compute wheel rotation Do no preliminary survey other than
and measurements to aid the process. The measuring wheel rut depth and pave-
There has been a steady if not rapid pro- system is capable of repeatable 0.04- to 0.12- ment cross slope at 500-foot intervals.
gression of improvements in the surveying inch accuracy in measurements. Appendix D
industry over the last decade. The efficiency Develop design profiles of centerline and
provides further information about static or
and accuracy of collecting elevation data has pavement edges.
mobile scanning surveying.
been improved drastically over the tried and
Estimate the quantity of concrete
true rod and level method. The simplest
required to meet the profiles and provide
method of control is to perform minor mill-
ing that is controlled with a traveling ski and Measurement and minimum thickness at centerline and
edges of pavement.
cross-slope system. The advent of laser scan-
ning has opened a new avenue for mapping of
Payment Items for Add a reasonable percentage to the
pavement surfaces before overlay construction Concrete Overlays concrete quantity to account for place-
to help eliminate excessive overruns. Laser ment tolerance, construction losses,
It is strongly suggested that concrete over-
scanning (Figure 56) can offer reduction in and surface/cross-section irregularities
lays be measured and paid for by the square
survey cost, savings in time, and less interfer- and establish the new theoretical
yard for placement and by the cubic yard for
ence to the traveling public. plan quantity. Some states use 15 to 20
furnishing concrete material. This method
percent, depending on the thickness of
This increased efficiency makes it cost effec- has been used successfully for many years by
the overlay and the amount of pave-
tive to perform in-depth surveys. Based on DOTs that routinely design and construct
ment cross-slope correction desired. The
data obtained from a project constructed on concrete overlays. The purpose of providing
thinner the overlay and the higher the
US-18 in Iowa in 2012 (Cable 2012), it was a cubic-yard pay item for concrete overlays is
cross-slope correction, the higher the
found that performing a nine-line survey at to minimize the risk to both the owner and
percentage; see Table 12.
50-foot intervals provided the engineer with the contractor. The basis for using a cubic-
the data necessary to confidently adjust the yard pay item is the fact that the underlying 2. For optimization of concrete quantities
profile of the concrete overlay and avoid a surface is more irregular than a well-prepared
potential 20 percent quantity overrun in the subgrade or subbase would be. Conduct nine-shot cross sections at
cubic yards of concrete placed. 50-foot intervals to map the existing
Recognizing that DOTs are acting on behalf surface.
The latest development with laser scanning of the taxpayers and contractors are in the
is basically several existing technologies com- business of taking calculated risks, it does not Develop a design centerline profile and
bined into one unit or process. At the heart seem inappropriate for DOTs to limit their cross slope that optimizes pavement
of the unit is the light detection and ranging risk to some degree. Assuming that the vol- smoothness, maintains minimum overlay
(LIDAR) scanner, which measures the flight ume of concrete has been correctly estimated depth across the width of the pavement,
time of a beam of light to calculate the range as recommended above, a cap on concrete and optimizes concrete quantities.
to objects at predetermined angular incre- overruns of 102 to 106 percent may be con- Limit the contractor to an additional
ments, resulting in a very large-point data set sidered reasonable. The agency should make percent of the quantity identified by the
referred to as a Point Cloud. The LIDAR regular depth checks at the pavement edges, desired cross section and design profile.
or laser scanner conducts measurements to mid-lane, and centerline of the concrete Some states use 2 to 6 percent, depend-
targets and a 360-degree camera is used to overlay during construction to verify that the ing on the thickness of the overlay.
assist in identifying objects in the scan. The thickness of the concrete overlay is equal to or
unit also includes a global positioning system greater than the design thickness.

Table 12. Typical Adjustment Factors for Estimating Overlay Cubic Yard
Plan Quantities

in. Placement Additional % Total Adjustment


Concrete Tolerance As Adjustment for Gross Factor to Be
Overlay a % of Design Surface Irregularities Applied to
Thickness Thickness in the Existing Surface* Theoretical Volume
4 inches 12.5 % 5% 17.5 %
6 inches 8.3 % 5% 13.3 %
8 inches 6.3 % 5% 11.3 %
10 inches 5.0 % 5% 10.0 %
12 inches 4.2 % 5% 9.2 %

* Gross surface irregularities are not affected by the overlay thickness; this is a constant that is
entirely dependent on the existing surface condition and any other desired changes such as cross-
slope correction and profile adjustment to obtain a smooth pavement. Table 12 reflects 5 percent
as an example only. An appropriate percentage for gross irregularities should be developed from
Figure 56. Digital terrain model acquired through laser scanning the measurements of wheel rut depth and pavement cross slope at 500-foot intervals.

Guide to Concrete Overlays 63


Ch 4. DESIGN

Typical Costs of Miscellaneous Leaving the Existing Curb in Place


To leave the existing curb in place, the milling
Concrete Overlays Design Details operation stops at the base of the curb, allow-
Since the onset of the Concrete Overlay Following are design details related to curb and ing for the thickness of the concrete overlay; see
Field Application Program in 2009, gutter (C/G), vertical grade changes, and other Figure 58.
construction cost has been a common special design considerations. There is a cost savings associated with leaving
question from state DOT personnel who the existing curb in place, since driveways, side-
are inexperienced with concrete overlays. Curb and Gutter Details walks, and utility fixtures do not require raising.
To answer this question, bid tabulations The condition of the curb, however, should be
from six state DOTs that are currently Potential constraints such as surface drainage
should be considered in the design. Curb- evaluated and, if the concrete is showing signs of
utilizing concrete overlays as an integral deterioration, it should be removed and replaced.
part of their pavement rehabilitation and-gutter sections may pose challenges with
strategy were reviewed. Figure 57 shows respect to how to design a concrete overlay. Also, when utility poles and other obstructions
the cost data collected from 33 projects Projects might include removal and replace- are in close proximity to the back of the existing
with bid dates ranging from August 2008 ment of the existing C/G, construction of an curb, leaving the curb in place may prohibit the
through September 2009 (Fick 2010). inlay with the final pavement elevation match- use of conventional slipform paving equipment.
These overlay costs include furnishing ing the existing C/G, or even an encasement of
concrete, placing the overlay, and all costs the existing C/G with a new system. Removing Curb and Gutter
associated with joints. Preoverlay repairs, Curb-and-gutter sections require additional When obstructions behind the curb prohibit the
surface preparation, and separation layer details since a decision needs to be made use of conventional slipform paving equipment,
costs are not included, but note that the about jointing. (Figures 58 through 60 show it may be advantageous to completely remove the
amount of required preoverlay repairs for three possible design options.) It is possible to curb and a portion of the gutter to allow place-
a concrete overlay is significantly less than include an integral C/G, but this should be ment of the concrete overlay a few inches higher
that for a typical HMA overlay. balanced with the extent of this type of section than the existing curb; see Figure 59.
and the equipment that might be available to
construct it. The full-depth section of C/G could be milled.
When there are obstructions behind the curb,
however, a full-depth saw cut and traditional
excavation methods are preferable to minimize
disturbance of materials on the edges of the road-
way. In this case, a new C/G section can then
be constructed after the overlay has been placed,
using a curb paving machine.

Overlay Curb
It is possible to place a concrete overlay that
encases the existing curb; see Figures 60 and 61.

Figure 57. Concrete overlay cost by thickness (source: [Fick 2010])

Figure 60. Detail of curb overlay (source: Snyder & Associates, Inc.)

Figure 58. Milling detail when leaving the existing curb in place (source:
Snyder & Associates, Inc.)

Figure 59. Milling detail when removing and replacing curb (source: Figure 61. Concrete curb overlay (source: Jim Amundsen, Grace
Snyder & Associates, Inc.) Construction Products)

64 Guide to Concrete Overlays


Ch 4. DESIGN

It should be noted, though, that this option 30- to 35-degree recommendation from the lays with full-depth reconstruction to address
raises the profile grade of the existing curb FHWA. All safety edge requirements should extreme corrections in superelevation.
and may require adjustment of adjoining and follow state agency requirements.
Typically, the desired results are not achieved
adjacent roadway features.
See Chapter 6 for temporary centerline fillets. when an asphalt separation layer is utilized
for correcting cross slope and profile (smooth-
Vertical Grade Changes Cross Road Drainage Structures ness) deficiencies. This is because variable
Depending on the vertical change in profile When safety slopes are regraded to meet asphalt thickness, when compacted, creates
grade, there are numerous constraints that appropriate design criteria, it may be neces- variable roll down; the result is a nonuniform
need to be considered in the overlay design sary to extend drainage structures to match surface that still must be corrected with addi-
process. the new foreslopes. tional concrete thickness. The most effective
and economical way to make corrections is to
Overhead Clearance Cross Slope and Superelevation make cross slope and smoothness adjustments
Depending on the location of the project, in the concrete overlay; see Figure 63. There
Changes to cross slope and superelevation can
various regulations for minimum overhead are some considerations to make, however,
lead to thicker concrete overlay sections. For
clearance may apply. The final pavement when correcting cross slope and profile fea-
cost effectiveness, designers should consider
elevation and thickness may need to be tures through a variable thickness concrete
matching existing cross slopes whenever pos-
limited or measures taken to raise overhead overlay:
sible. When crown and/or superelevation
obstacles. Alternatively, it may be preferred to corrections are required, adequate informa- The depth of saw cut for contraction joints
conduct full-depth reconstruction or build an tion on the depth of material to meet the final must be adjusted through the thicker areas
alternative section (i.e., mill down and place a grade is also required. The type of fill materi- of concrete placement.
thinner but higher-strength concrete overlay) als to use (concrete, asphalt, flowable fill,
at such locations. Dowels should be placed (baskets or
cement-treated base, etc.) should be selected
mechanical inserters) so that a minimum
based on the depth of fill, installation and
Barriers and Rails cover of 2 inches is maintained around the
construction issues, initial costs, and future
dowel bar (see Snyder 2011 for additional
Safety barriers, guardrails, and cable barriers removal costs. Some projects combine over-
information).
may need to be raised/reconstructed depend-
ing on the change in profile grade and the
horizontal distance between the edge of pave-
ment and the safety feature.

Safety Edge Concrete Overlay 30 New Graded


Material
When the roadway is raised, it is necessary
to determine whether or not the new safety
slopes can fit to the existing ditches and
remain within the appropriate safety design 1 in. Min.
Concrete Overlay
criteria. In some cases, it may be necessary Old Shoulder
Old Pavement
to regrade the ditches to meet safety slope
criteria. The safety edge is a beveled pavement
edge to help lessen the severity of roadway Subbase
departures; see Figure 62. When a driver
Note: To allow proper finishing with paver a minimum 1-inch vertical Figure _: Typical S
drifts off the paved surface, the safety edge face is required at the end of the safety edge.
provides greater ease in reentering the road-
way and reduces the risk of oversteering and Figure 62. Typical safety edge for concrete overlay without paved shoulder
loss of control of the vehicle. Figure _: Typical Safety Edge for PCC Overlay Without Paved Shoulder

Most likely, the projects that will need a safety


edge will be two-lane, rural highways without
paved shoulders. Most of these projects would
be resurfacing projects. The angle of the bevel
is important for the safety edge to function Inserted dowels (min. 2-in. cover)
properly. Measured from level, the bevel is 30
with an equivalent run-to-rise ratio of 10.5
to 6.
Concrete overlay
Note the 30 angle does not account for sur- Separation layer
face slope. Existing surface slopes range from
Existing pavement
2 to 8 percent, which add an additional 1.1 to or Dowel baskets (min. 2-in. cover)
4.6 degrees to the bevel angle when measured
from level. The resultant angle is within the Figure 63. Dowel options in superelevation areas

Guide to Concrete Overlays 65


Ch 4. DESIGN

In-place Pavement Plate Dowel Details


Structures Unbonded concrete overlays can be con- See Table13 for plate dowel size and spacing
Existing manholes, inlets, and utility struc- structed with different construction practices, for construction joints and Table14 for dowel
tures must be raised to match the new installation procedures, and joint types, size and spacing for contraction joints.
pavement elevation. Figure 64 shows typical requiring different installation procedures and
details for raising a manhole. plate geometries; see Figure 65.

(0.81.1 m)

Figure 64. Concrete overlay with standard manhole

Slipform Diamond shape


football shape construction joint
construction joint (used fixed form)
(used slot cutter)

Figure 65. Diamond-shaped plate dowels in fixed-formed construction joints (right side) and football-shaped
dowels by slipforms

Table 13. Size and Spacing of Plate Dowels for Construction Joints

Plate Dowel Thickness Plate Spacing for Heavy Traffic, Plate Dowel Spacing for Light
Pavement Depth
and Width at Joint Wide Joint Openings, or Both Traffic or Narrow Joint Opening
125 to 174 mm 6 mm x 160 mm 450 mm 600 mm

175 to 224 mm 10 mm x 160 mm 450 mm 600 mm


225 mm+ 20 mm x 160 mm 450 mm 600 mm

Table 14. Size and Spacing of Plate Dowels for Contraction Joints

Plate Dowel Thickness and Plate Spacing for Heavy Traffic, Plate Dowel Spacing for Light
Pavement Depth
Width at Center Line of Plate Wide Joint Openings, or Both Traffic or Narrow Joint Opening

125 to 174 mm 10 mm x 50 mm 450 mm 600 mm

175 to 224 mm 13 mm x 65 mm 450 mm 600 mm

225 mm+ 20 mm x 65 mm 450 mm 600 mm

66 Guide to Concrete Overlays


Ch 4. DESIGN

Corrosion Resistance Dowel installation devices that remain in the should recognize that when new concrete
Where corrosion resistance for plate dowels pavement and transfer load to the concrete topping, with an inherent tendency to shrink,
is required, they are generally either galva- by bearing should be made of thin, rigid is tied to previously placed concrete topping
nized or electroplated with zinc, but other material to help minimize the vertical deflec- that has already gone through the shrinkage
methods such as epoxy coating may also be tion. Dowel installation devices that are loose process, stresses will develop that can cause
appropriate. fitting or made of soft material can result in cracking; see Figures 68 and 69.
significant initial vertical deflection that may
Load transfer between previously placed
Plate Dowel Installation for cause early joint deterioration (Walker and
sections and newly placed concrete can be
Holland 2007).
Construction Joints Formed obtained through the use of football-shaped
with a Bulkhead (Form) plate dowels. In this application, slots can be
Plate Dowel Installation in
cut into the existing slab to receive the plate
Alignment or installation devices should be Slipform or Full-depth Saw Cut dowels. An epoxy or similar material should
incorporated into the bulkhead (forms) to (Butt-type) Construction Joints be used to rigidly grout the plate into the slot
ensure that dowels are centered in the joint,
In slipform or full-depth saw cut construction to ensure a tight fit.
horizontal with the pavements surface, and
perpendicular to the joint; see Figures 66 joints (as would be encountered in a remove-
and67. and-replacement area of topping), designers

Tapered shape with a thin bond


breaker on top and bottom
surfaces allows slab to shrink
without being restrained and joint
to activate

Taper-shaped plate dowel


installed when a construction Figure 67. Taper-shaped construction joint
joint is formed with a hand form
plate dowel using fixed forms (source: Nigel
Parks, PNA Construction Technology)

Figure 66. Detail of construction joint plate dowel for fixed-form paving

Plate Dowel Construction Joint (by form)


Tapered shape with a thin bond
breaker on top and bottom surfaces
allows slab to shrink without being
restrained and joint to activate

Football-shaped plate dowel


installed in a cut in a previously
slip formed slab edge of existing
or new construction Figure 69. Slots being cut to accept the
football-shaped plate dowels (source: Nigel
Figure 68. Detail of construction joint plate dowel for slipform paving Parks, PNA Construction Technology)

Plate Dowel Construction Joint (by slot cutter)

Guide to Concrete Overlays 67


Ch 4. DESIGN

Dowel Installation for contraction joints. In this application, the


Contraction Joints tapered plate dowels allow for horizontal
misalignment of the dowels without lock-
Dowel baskets or mechanical dowel bar inser-
ing joints, inducing restraint or cracking in
tion equipment should be used to maintain
the overlaid concrete topping; see Figures 70
alignment of tapered plate dowels in saw-cut
and71.

Alternating taper shape with a


factory-applied thin bond breaker
on top and bottom surfaces allows
slab to shrink without being
restrained and joint to activate

Figure 70. Detail of plate dowel for contraction joint

Transverse construction joint


Alternating taper shape with a
factory-applied thin bond breaker
As
on top and bottom surfaces allows Specified
slab to shrink without being
restrained and joint to activate

6 in.
6 in. Min.
Min.

Transverse contraction joint


Longitudinal construction joint

Football-shaped plate dowel


installed in a cut in a previously
formed slab edge of existing or
new construction

Figure 71. Plan view of roadway with plate dowels

68 Guide to Concrete Overlays


Ch 4. DESIGN

Transitions concrete sections, conventional reinforcement Figures 72 through 79 provide details for vari-
or wire mesh, and structural macro fibers. ous transitions used for overlay construction.
A concrete overlay design often requires tran-
Transitions must be designed and constructed In general, transition length should be based
sition details that link the concrete overlay
to connect the new overlay pavement with (1) upon the design speed40:1 for roadways
with the pavement structure adjacent to the
existing pavement, (2) existing structures, and posted at 45 mph (miles per hour) or greater
project length. Since these locations are often
(3) driveways. and 25:1 for speeds less than 45 mph.
subject to additional stress, , including thicker

Mill and Fill Transitions for Bonded Concrete Overlays


Figure 72. Mill and fill transition for concrete
overlay of concrete pavement (adapted from
ACPA 1998)

(50 mm) min.

Figure 73. Mill and fill transition for concrete


overlay of asphalt or composite pavement
(adapted from ACPA 1998)
(75 mm)

Transition Details for Bonded Concrete Overlays


Figure 74. New transition
tapers used to meet bridge
approach slabs or maintain
clearance under bridges with
bonded overlay of concrete
pavement (adapted from
ACPA 1990b)

Figure 75. New transition


tapers used to meet bridge
approach slabs or maintain
clearance under bridges with
bonded overlay of asphalt
pavement (adapted from
ACPA 1991)
(75 mm)

8 in. (200 mm)

Guide to Concrete Overlays 69


Ch 4. DESIGN

Transition Details for Unbonded Concrete Overlays


Figure 76. New transition
tapers used to meet bridge
approach slabs or maintain
clearance under bridges
with unbonded overlay of
Separation concrete pavement (adapted
layer from ACPA 1990b)

Figure 77. New transition


tapers used to meet bridge
approach slabs or maintain
clearance under bridges with
unbonded overlay of asphalt
pavement (adapted from
ACPA 1991)

Temporary Transition
Constructed with Asphalt Transition
Concrete Overlay
Granular Material R.O.W.
Concrete Overlay
R.O.W.

Existing Pavement Existing Side Road


or Driveway
Existing Pavement Existing Side Road
or Driveway

Figure 78. Temporary granular transition to existing side road/ Figure 79. Asphalt wedge transition to existing side road/driveway
driveway

Temporary Transition

Asphalt Wedge Trans

70 Guide to Concrete Overlays


Ch 4. DESIGN

Widening and Lane of pavement

Addition Keep joint out of


wheel path
Adding new lanes or shoulders can also where possible
present issues unique to concrete pavement
design, especially if there is a change in
the underlying support of the overlay or if
the overlay is to join a full-depth concrete Ove
rlay
pavement. Joint load transfer systems are
frequently used in these cases. Tiebars are Bonded
used to help ensure aggregate interlock. Exis
ting
Additional measures should be taken in the con
cret
e
design to minimize differential settlement or
water infiltration at these locations. For the
same reasons, intersections and blockouts for
utilities need to be understood, and joint pat-
36-in. tiebars: staple, epoxy or insert;
terns need to be developed that will minimize if inserted, must have enough overlay
uncontrolled cracking. thickness to accomodate max.-sized 3-6 ft (0.9-1.8 m)
aggregate under the bar and min. 2-in. concrete widening unit
Concrete overlay projects provide a good cover above the bar
opportunity for the widening of an old pave-
Figure 80. Bonded overlay of concrete pavement with widening unit
ment with narrow traffic lanes, the addition
of new travel lanes, or the extension of ramps.
of pavement
Adequately designed and constructed widen-
ing can improve both faulting and cracking Keep joint out of
wheel path
performance of the pavement. where possible

Widened slabs should be used with care with


concrete overlays on stiff foundations (such
as on concrete pavements) because of the Ove
rlay
increased risk of longitudinal cracking.
Three- to six-foot (0.9- to 1-8-m) widening Bonded
units are illustrated in Figures 80 through 84. Exis
ting
The intent of the tiebars shown in Figures asp
halt
80 to 82 is to tie the widening unit to the Exis
ting
existing pavement. In Figure 82, note that con
cret
care must be exercised not to loosen stapled e

tiebars with truck tires; when horizontal lane


restrictions exist that require driving over the
stapled bars, a better option may be to use a
tiebar inserter. 36-in. tiebars: staple, epoxy or insert;
if inserted, must have enough overlay
Following are some rules of thumb for widen- thickness to accomodate max.-sized 3-6 ft (0.9-1.8 m)
ing units: aggregate under the bar and min. 2-in. concrete widening unit
cover above the bar
Where possible, keep joints out of wheel
paths, especially for bonded overlays on Figure 81. Bonded overlay of asphalt or composite pavement with widening unit
asphalt or composite pavements.
For concrete overlays 5 in. (125 mm) or
thicker at open-ditch (shoulder) sections,
tie longitudinal joints with no. 4 tiebars to
prevent pavement separation.
The width of widening rather than depth
has more of a positive effect in reducing
stresses in the overlay section.
Not every detail shown will fit a specific
project. Apply the principles illustrated in the
details to address specific project issues.
Lane addition design details are illustrated in
Figure 85, on the following page. To prevent
cracking related to differential expansion and
contraction between a concrete overlay and a
full-depth adjacent concrete lane addition, use
a butt joint with no tiebars.
Figure 82. View of tiebars for concrete overlay widening unit

Guide to Concrete Overlays 71


Ch 4. DESIGN

of pavement
Figure 83. Unbonded overlay of concrete,
Keep joint out of asphalt, or composite pavement with
wheel path widening unit
where possible

Ove
rlay

Unbonded
Exis
t
sep ing as
arat p
ion halt or
laye
r
Exis
ting
con
cret
e

36-in. tiebars: staple, epoxy or insert;


if inserted, must have enough overlay
thickness to accomodate max.-sized 3-6 ft (0.9-1.8 m)
aggregate under the bar and min. 2-in. concrete widening unit
cover above the bar

Figure 84. Bonded or unbonded overlay of


36-in. tiebars: staple, epoxy or insert;
if inserted, must have enough overlay asphalt or composite pavement (previously
of pavement thickness to accomodate max.-sized widened with asphalt or concrete, and to be
aggregate under the bar and min. 2-in. widened again with new concrete overlay)
cover above the bar

Keep joint out of wheel path


where possible

Saw cut joint


New
ov
Exis erlay
t
( 3 ing asp
i h
( 1 n. (7.62 alt
in. ( c
2.54 m) if b
cm) on
if un ded);
bon
Exis ded
ting )
con
cret
e

Cold joint or
full-depth
Remove existing asphalt saw cut
widening to depth of existing -no tie bar
3-6 ft (0.9-1.8 m)
asphalt or to the depth of the concrete widening unit
new concrete widening unit,
whichever is greater, and Previously widened with asphalt or concrete
replace with concrete
widening unit

Figure 85. Unbonded overlay of


concrete, asphalt, or composite
Cold joint or pavement with full concrete lane
full-depth
saw cut
addition
-no tie bar

72 Guide to Concrete Overlays


Ch 4. DESIGN

Typical Drainage Outlets


for Interlayers
Figures 86 through 90 illustrate various drain-
age outlets for separation layers.

Rural Conditions
Figure 86. Interlayer outlet for concrete
overlay shoulder
Travel lane(s) New concrete overlay
shoulder

New concrete overlay

Daylight innerlayer/fabric
or install vertical subdrain

HMA innerlayer or
Geotextile fabric

Existing concrete pavement

Existing concrete or
asphalt shoulder

Figure 87. HMA interlayer outlet for asphalt


shoulder

Travel lane(s) New paved HMA


shoulder

New concrete overlay


Daylight HMA
shoulder

HMA innerlayer
Place 4 to 6 in.- thick
permeable
Existing concrete pavement
HMA shoulder

Figure 88. Geotextile interlayer outlet with


new paved shoulder (concrete or asphalt)

Travel lane(s) New paved


shoulder

New concrete overlay

Geotextile fabric innerlayer Daylight geotextile


fabric or install
Existing concrete pavement vertical subdrain

Guide to Concrete Overlays 73


Ch 4. DESIGN

Urban Conditions Curb Remaining


Curbs Removed and Replaced If the curb is not removed for construction
Water pressure in a geotextile fabric separation of an unbonded overlay, the geotextile layer
layer can be reduced by draining the fabric that separates the underlying concrete pave-
into storm sewer inlets. If the existing curb ment from the overlay can be drained into an
is removed and replaced with the overlay, the intake. The fabric will need to be tied into the
geotextile layer can be daylighted out to an wall of the intakes; see Figure 90.
existing or new subdrainage system; see Figure
89.

Construct 12 in.- wide x 26 in.- deep Porous


Drainage Trench Adjacent to the Existing Subgrade
Underdrain Trench
Excavation
Thin Concrete Unbonded Overlay

Interlayer

Existing Concrete Pavement


Existing Lane Tie Bars

Existing Granular Subbase

Existing Subgrade Underdrain


6 in. in a 1.0-ft x 1.0-ft Trench Backfilled with
CL-II Granular Material

Figure 89. Drainage of separation layer (interlayer) into an existing underdrain system when existing curb is
removed and replaced (source: Dan DeGraaf, Michigan Concrete Association)

Figure 90. Drainage of separation


Previous Pavement Height before Milling layer fabric into intake when curb
is not removed (source: Snyder &
New Unbonded Concrete Overlay
Associates, Inc.)

Existing Pavement

Single Open-Throat
Curb Intake

Geotextile Wrapped and Pinned

74 Guide to Concrete Overlays


Ch 5. MATERIALS & MIXTURES

Chapter 5.

CONCRETE OVERLAY MATERIALS AND MIXTURES

A majority of concrete overlay mixtures are crete. Typical replacement rates with SCMs well graded systems allow use of higher aggre-
designed and constructed using standard are 15 to 35 percent, depending on the gate and lower paste contents. Because paste
materials. These materials include cement, chemistry of the system. Commonly used is more permeable than aggregate, reducing
supplementary cementitious materials SCMs include Class C fly ash, Class F fly paste content while maintaining workability
(SCMs), aggregates, water, and admixtures. ash, and ground granulated blast furnace slag will lead to reduced permeability (Yurdakul
(GGBFS). 2010). Third, better workability will lead
Concrete mixtures can be either conventional to better consolidation of the mixture, also
or, in special circumstances, accelerated; Setting times for concrete may be retarded
improving (reducing) permeability (Tayabji et
both types of concrete mixtures can be fiber when SCMs are used, especially in cool
al. 2007) and reducing the risk of overvibra-
reinforced. Other materials associated with weather conditions, which can cause difficulty
tion and the attendant problems. Finally, the
concrete overlays include dowel bars, tiebars, in sawing joints before random cracking
improved workability of well graded concrete
curing compound, joint sealant, and separator occurs. Therefore, heating of the concrete
mixtures allows for more efficient placement,
layers. and/or the use of accelerating admixtures is
especially in handwork, which means that the
recommended during periods of extended
This guide classifies concrete mixtures as pavement is able to be finished earlier while
cool weather. Ensure that the strength gain
either conventional or accelerated. The pri- the mix is still fresh.
of the mixture is compatible with the sawing
mary difference is that accelerated mixtures plan (HIPERPAV can assist in assessing the The maximum coarse aggregate size used in
are designed for a faster rate of strength gain, risk of random cracking). More information concrete mixtures for overlays is a function of
allowing earlier opening of the concrete is available in the Integrated Materials and the overlay thickness. Some thinner concrete
overlay to construction and/or public traffic Construction Practices for Concrete Pavement overlays may require a reduction in size of the
(see page 105 for comprehensive guidance (Taylor 2006). standard aggregate used in concrete paving.
on accelerated construction techniques). It is recommended that the largest practical
Producing a durable concrete mixture should Since SCMs can retard set time in cold
maximum coarse aggregate size be used in
be the primary objective regardless of whether weather, some agencies restrict their use in
order to minimize paste requirements, reduce
the mix is conventional or accelerated. This colder seasons of the year. Supplementary
shrinkage, minimize costs, and improve
guide provides general recommendations for cementitious materials can, however, aid con-
mechanical interlock properties at joints and
developing durable concrete mixtures to be struction during hot weather by extending
cracks.
used in concrete overlays. The design and the placement time. They typically improve
production of concrete mixtures for concrete the workability of the mix and also increase Although maximum coarse aggregate sizes of
overlays should adhere to best practices for concrete durability; they also can increase the 0.751 in. (1925 mm) have been common
local requirements (i.e., aggregate durability, long-term strength of the concrete, although in the last two decades, smaller maximum
air entrainment, etc.). the short-term strength may be lower. In coarse aggregate sizes may be required for
addition, fly ash and GGBFS are effective
in reducing ASR (ASR mitigation should be
Primary Concrete confirmed by ASTM 1567). Table 15. The Effect of Aggregate Gradation
on Mixture Properties
Materials Aggregates Well Graded Aggregates
The primary materials in concrete are Concrete mixtures produced with well graded,
Aggregates used in concrete mixtures range dense aggregate matrix tend to
cementitious materials, water, aggregate, and
from crushed stones to river gravels and gla-
admixtures. Reduce the water demand
cial deposits. To help ensure the longevity of
the pavement, the aggregate should not only Reduce the cementitious material demand
Cementitious Materials possess adequate strength but also be stable Reduce the shrinkage potential
Type I and Type II cements are commonly physically and chemically within the con- Improve workability
used in concrete mixtures for concrete over- crete mixture. Agencies generally require that Require minimal finishing
lays. When high early strength is desired, aggregates conform to ASTM C 33 for physi- Consolidate without segregation
higher amounts of Type I can be used. Since cal properties; a well graded mixture should Enhance strength and long-term performance
conventional Types I and II cements are nor- be specified. Extensive laboratory testing Gap-graded Aggregates
mally adequate, the use of Type III cements or demonstrated field performance is often
required to ensure the selection of a durable Concrete mixtures produced with a gap-graded
with overlays is not recommended because of
aggregate combination may
increased thermal shrinkage and potential for aggregate.
thermal shock. As with conventional paving, Segregate easily
The use of well graded aggregates helps to Contain higher amounts of fines
SCMs normally improve durability and can
improve permeability in several ways; see Require more water
enhance the ease of construction.
Table 15. First, mixtures made with well
Require more cementitious material to meet
Replacement of some cement with SCMs graded systems tend to be more work- strength requirements
in well-cured concrete has multiple ben- able, which in turn means that less water Increase susceptibility to shrinkage
efits ranging from improved workability to is required to achieve the same workability, Limit long-term performance
reduced permeability of the hardened con- allowing use of a lower w/cm ratio. Second,

Guide to Concrete Overlays 75


Ch 5. MATERIALS & MIXTURES

concrete resurfacing. For nonreinforced of the components used in a concrete mixture Adequate Air Void System
pavement structures, a maximum aggregate should be carefully selected so that the result-
Freeze-thaw durability is primarily affected
size of one-third of the slab thickness is ing mixture is dense, relatively impermeable,
by the environment (wet freezing conditions)
recommended. and resistant to both environmental effects
and the air void system of the concrete. An air
and deleterious chemical reactions over the
When selecting aggregate for a bonded void system consisting of many small, closely
length of its service life.
concrete overlay on an existing concrete spaced voids is a common means of providing
pavement, the CTE becomes a particularly There are numerous references for developing protection against freeze-thaw damage. An
important parameter. Because aggregate durable concrete mixtures; the following sec- adequate air void system in the as-placed con-
composes a majority of the concretes mass, tion is adapted from the Guide for Optimum crete is vital. Air void systems can be affected
its CTE is a good indicator of concrete Joint Performance of Concrete Pavements by varying the composition of concrete con-
movement due to thermal expansion and (Taylor et al. 2012), which provides recom- stituents, placing techniques, and finishing
contraction. Using an aggregate in the overlay mendations for designing and constructing activities. For concrete that is exposed to deic-
mixture with a CTE similar to that of the durable concrete pavements. ing chemicals or high water saturation (which
existing pavement helps ensure that the two is considered severe exposure), a spacing
The permeability of a concrete mixture factor equal to or below 0.008 in. (0.2 mm)
layers move together, thus minimizing stress
determines how easily moisture can infiltrate is recommended, along with a specific sur-
at the bond line due to differential movement
the paste structure of the concrete. A lower face area of air voids equal to or greater than
and helping to maintain the bond between
permeability is desirable to slow the rate at 600 in./in. (24 mm/mm). PCA Bulletin
the layers. The CTE can be determined using
which concrete will become saturated. Recent EB001.15 recommends a minimum of 5 per-
AASHTO provisional test TP-60 (Coefficient
work led by the South Dakota DOT includes cent to 8 percent air content in the in-place
of Thermal Expansion of Hydraulic Cement
recommendations to achieve durable, dense, concrete to prevent damage (Kosmatka and
Concrete).
and impermeable concretes that withstand the Wilson 2011). In addition, Sutter and Ley
If not similar to the CTE of the underlying deleterious effects of deicing chemicals (Sutter have reported that these values are still appro-
concrete pavement, the CTE of the overlay et al. 2008) and prevent or reduce joint dete- priate based on recent laboratory work (Ley et
should be less than that of the underlying rioration caused by water saturation at the al. 2012).
pavement. The overlay surface is exposed to joints. Recommendations include designing
greater temperature swings than the under- mixtures with low w/cm ratio, adequate air Test procedures to determine air content in
lying pavement. Therefore, the lower the void systems, appropriate use of SCMs, and fresh concrete include the pressure method
overlays CTE, the less the differential move- well graded aggregates. (ASTM C 231/AASHTO T 152), the volu-
ment between the overlay and underlying metric method (ASTM C 173/AASHTO T
Target permeability at 56 days should be less 196), and the gravimetric method (ASTM
pavement.
than 1,500 coulombs when tested in accor- C 138/AASHTO T 121). The air content
dance with the rapid chloride permeability should be checked in samples taken in front
Admixtures test (ASTM C 1202) or 25 k-cm when of the paver, and periodically from behind the
Various admixtures and additives are com- tested using surface resistivity measured in paver, to quantify how much air content is
monly introduced into concrete mixtures. accordance with AASHTO TP 95. lost during placing. By periodically comparing
These include the following: air content difference between samples taken
Air entrainment protects the hardened con- Low w/cm Ratio from the same hauling unit both before and
crete from freeze-thaw damage and deicer The permeability of a concrete mixture after the paver, the stability or quality of the
scaling. Air entrainment, however, also is primarily governed by the amount of air system can be estimated. When the differ-
helps increase the workability of fresh con- water in the concrete at the time of mixing. ence between the two test results is less than 2
crete, significantly reducing segregation and Permeability will decrease as less water is percent, the hardened air-determined spacing
bleeding. The typical entrained air content used. The w/cm ratio should not exceed 0.45; factor is usually acceptable. If the difference
of concrete for overlays is in the range of 5 ideally, the w/cm ratio should be between is greater than 2 percent, then admixture dos-
to 7 percent. 0.38 and 0.42 (especially for wet freeze-thaw age of the mixture should be adjusted and/or
environments). the placement processes modified to ensure
Water reducers are added to concrete adequate protection of the in-place system.
mixtures in order to reduce the amount There are a number of ways to achieve uni- Concrete performance can be assessed in the
of water required to produce concrete of a formly lower w/cm ratios while retaining laboratory (during design stage) using ASTM
given consistency. This allows for a lower- satisfactory workability, including combina- C 666/AASHTO T 161.
ing of the w/cm (water-cementitious) ratio tions of the following:
while maintaining a desired slump and
Using SCMs in appropriate dosages
thus has the beneficial effect of increasing
strength and reducing permeability. Using water-reducing admixtures Accelerated
Using aggregate systems with combined Mixtures
gradation, which promotes reduced paste Although the use of accelerated mixtures and
Conventional volume and improved workability expedited paving practices has become more
Concrete Mixtures Controlling concrete temperature
common in concrete overlay projects, there
has been some concern regarding potential
Conventional concrete paving mixtures are Not adding water to a ready-mix truck at detrimental effects of faster-setting concrete
typically used in the construction of concrete the point of delivery, which exceeds the mixtures and reduced construction times on
overlays. As with conventional concrete pave- design w/cm the long-term durability of concrete due to
ments, an effective mixture design is essential excessive shrinkage, heat generation, and poor
to the performance of a concrete overlay. Each microstructure.

76 Guide to Concrete Overlays


Ch 5. MATERIALS & MIXTURES

FAQHow do I determine the appro- FAQWhat are the concerns when using accelerated mixtures?
priate opening strength?
Mixtures that gain strength quickly and generate high heat of hydration have had long-term
Opening strength should be determined performance issues. There is a trade-off between early opening and long-term durability
based on the anticipated early loading that needs to be evaluated when deciding whether or not to use an accelerated mixture.
traffic, concrete overlay thickness, and Accelerated opening can often be achieved through good construction scheduling and
ability to mitigate early edge loading coordination, which negates the need for accelerated concrete mixtures. Thus, durability
using traffic control devices. Table 16 and speed of construction are factors that should be considered together during the design
provides general guidance regarding phase. In general, emphasis should be given to using conventional mixes whenever possible.
opening strength and concrete thickness.

Table 16. Slab Thickness and Opening


Strength
FAQWhy do some accelerated mixtures have premature failures?
Strength for Opening
Slab to Traffic (psi) Accelerated mixtures typically have a higher potential for shrinkage and warping com-
Thickness (in.) pared to a conventional mixture due to their higher paste content. Increased shrinkage and
Comp Flex
warping stresses at early ages can cause early cracking and can be detrimental to bond devel-
6 3600 540
opment, which will result in premature overlay failures.
7 2700 410
8 2150 340
9 2000 300
10+ 2000 300 the performance of thin concrete overlays. temperatures, etc. (allowing longer joint
Whether the use of macro fiber in concrete spacing)
overlays is warranted should be determined
Increase concretes resistance to plastic
based on the existing pavement base thickness
shrinkage cracking (enhancing aesthetics
Some agencies use rapid-strength concrete and condition, the owners desired finish, the
and concrete performance)
mixtures with a high cementitious material engineers expected design life, overlay thick-
content, low w/cm ratio, and smaller top size ness, and cost. In appropriate dosages, fibers Hold cracks tightly together (enhancing
aggregate (typically 0.75 in. [19 mm]). can perform the following functions in a con- aesthetics and concrete performance)
crete mixture:
These mixtures can be used with accelerat- Although steel fibers have a long, successful
ing admixtures to provide the early strength Help increase concrete toughness (allowing history in paving applications, in the last two
required to place traffic on the overlay within thinner concrete slabs) decades synthetic fibers have become pre-
a short time period. A water-reducing admix- dominant due to their ease of handling, better
Help control differential slab movement
ture is used to reduce the w/cm ratio and dispersion characteristics (i.e., less balling),
caused by curling/warping, heavy loads,
provide the desired workability properties.

Other Materials
Other materials that may be introduced to
the mixture or used as part of the construc-
tion process include fibers, separation layers,
dowels and tiebars, joint sealant, and curing
compound.

Structural Fibers for


Concrete Overlays
In general, the use of fiber reinforcement is
not normally necessary for most concrete
overlays. In certain situations, however
where, for example, vertical restrictions limit
the overlay thickness, heavier-weight traffic
loads are expected, increased joint spacing is
desirable, or conventional dowels cannot be
usedthe use of fibers may be warranted.
During the last two decades, there has been
resurgence in the use of fiber reinforcement
in concrete; see Figure 91. The reason for this
is when properly used, newer fiber-reinforce-
ment technology can and does contribute to Figure 91. Synthetic fibers (1.5 in. to 2.25 in.)

Guide to Concrete Overlays 77


Ch 5. MATERIALS & MIXTURES

and resistance to rust damage. Structural Separation Layer Materials Asphalt Separation Layer
macro synthetic fibers (ASTM C-116 Type Until 2010, the most common and success-
A separation layer (or interlayer) is an impor-
III, Section 4.1.3) are commonly used at 3 to ful separation layer used in the United States
tant feature of unbonded concrete overlays on
4 lb/yd3. was a conventional asphalt mixture. On most
existing concrete pavements. The performance
For current design technology, the dosage of these overlays depends largely upon using projects, a nominal 1-in. (25-mm) thick layer
of fiber, whether synthetic, steel, or some a separation layer to isolate the two concrete provides adequate coverage over irregularities
blend, is specified to produce certain behav- layers. All unbonded concrete overlays on in the existing pavement. The thickness can
ior characteristics in the hardened concrete. concrete must be separated from the existing be slightly increased when irregularities are
These characteristics correlate with forecasts concrete pavement by a stress-relief layer, or large enough to impact placement operations.
of increased performance such as flexural separation layer, to prevent reflective cracking Asphalt mixtures that contain higher percent-
strength, and hence fatigue capacity is from movement of the existing pavement. The ages of oil combined with smaller maximum
enhanced. It should be noted that the actual separation layer provides a shear plane that nominal aggregate size have contributed to
strength of the concrete given the current relieves stress and helps prevent cracks from movement of dowel baskets during the paving
technology increases only slightly, if at all. reflecting up from the existing pavement into operation because of concrete sliding on top
Concrete will still crack if the load exceeds the new overlay. of the asphalt separation layer. Typical base
that which can be borne mechanically at its mixtures with lower oil content that do not
Separation layers may serve three purposes: seal up completely provide additional friction
upper strength limit, given the geometric
properties of the section, but it will carry a 1. Isolation from movement of the underly- during the concrete placement operation,
much greater number of lesser loads up to ing pavementa shear plane that relieves which may alleviate this condition.
that point and will continue to carry loads stress, mitigates reflective cracking, and The separation layer does not provide signifi-
beyond that point. A simple analogy is to may prevent bonding with the existing cant structural enhancement; therefore, the
think of the concrete as being effectively pavement placement of an excessively thick layer should
stronger than that measured in a beam test; be avoided.
this effect varies as a function of dosage, not 2. Drainagethe separation layer either must
on weight, but by volume of fibers in the con- be impervious so that it prevents water When an unbonded concrete overlay pave-
crete mixture. from penetrating below the overlay or must ment is poorly drained and experiences heavy
channel infiltrating water along the cross truck traffic, scouring (stripping) of the
Table 17 provides a summary of current slope to the pavement edge asphalt separation layer with a conventional
categories of fibers, with general descriptions asphalt mix may occur. In an effort to reduce
and application rates. For a more detailed 3. Beddinga cushion for the overlay to
reduce bearing stresses and the effects of the scour pore pressure and increase stability,
discussion of fibers, see Appendix C, Fiber some states modify the asphalt mixture to
Reinforcement. dynamic traffic loads and to prevent keying
from existing faulting make it more porous. In particular, the sand
content is reduced and the volume of 0.38
in. (10 mm) chip aggregate is increased. This
modified mixture has a lower unit weight and
Table 17. Summary of Fiber Types lower asphalt content, and it is comparable in
cost to typical surface mixtures. The Michigan
Size Years Typical Fiber
Fiber DOT has designed an asphalt mixture with
(D = dia.) Used in Volume Comments
Type modified aggregate gradations to address strip-
(L = length) U.S. (lb/yd3)
D< To reduce plastic shrinkage cracking and
ping of separation layers; see Table 18.
Micro
0.012in. (0.3mm) settlement cracking; limited effect on Other materials have been utilized for separa-
Synthetic 35 1.0 to 3.0
concrete overlay overall performance; more
Fibers tion layers; however, the performance of these
L 0.50 to 2.25in. workability issues when using higher rates
materials has been inconsistent (for details on
D> Increases post-crack flexural performance, other separation layers, see Smith et al. (2002)
Macro 0.012in. fatigue-impact endurance; thinner concrete
and Rasmussen and Garber (2009).
Synthetic (0.3mm) 15 thickness; longer joint spacing; tighter
3.0 to 7.5
Fibers joints, cracks; better handling properties,
L 1.50 to 2.25 in. dispersion characteristics than steel fibers;
not subject to corrosion Table 18. Michigan DOT Asphalt Separation
Increases strain strength, impact Layer Gradation
Macro
resistance, postcrack flexural performance,
Steel Fibers L 0.75 to 2.50in. 40 33 to 100 Sieve Size Percent Passing
fatigue endurance, crack width control per
(carbon)
ACI 544.4R inch 100
Blend of small dosage of micro synthetic inch 85100
Blended 15 Varies fibers and larger dosage of either macro
synthetic fibers or macro steel fibers No. 4 2238

Synthetic (polymer) fiber materials No. 8 1932


Polypropylene No. 16 1524
Monofilament (cylindrical)Fibers of same length
MultifilamentMonofilament fibers of different lengths No. 30 1118
Fibrillated (rectangular)Net-shaped fiber collated in
interconnected clips No. 50 814
Polyester No. 100 510
Nylon
No. 200 47

78 Guide to Concrete Overlays


Ch 5. MATERIALS & MIXTURES

Nonwoven Geotextile the concrete slabs, hence reducing stresses due when the fabric reaches 110F or greater.
Separation Layer to temperature and moisture gradient. They Cooling the fabric with a water mist is then
also reduce pumping processes and prevent required under this condition. To prevent
An alternative to an asphalt interlayer is a
origination of reflected cracks from bonded heat absorption, white-colored fabric has
nonwoven geotextile interlayer; see Figure92
base courses without notching them. been developed recently to help reflect ultra-
(see also design details in Figures 8890 on
violet energy in hot and sunny weather; see
pages 7374). The use of nonwoven geotex- Leykauf and Birmann (2006) also state that
Figure93. In the fall or spring, however,
tile fabric as an interlayer has been on the concrete roads with a separation layer of
white fabric is not the best choice to prevent
increase since 2010. The structural condition geotextiles are especially recommended for
heat transfer from the concrete overlay to the
of the existing concrete pavement must be concrete overlays on old concrete pavements,
fabric.
carefully assessed before selecting thin geo- in tunnels and on rigid base courses.
textile instead of a thicker asphalt interlayer, Material specifications for a geotextile used
In colder weather (spring and fall) black-
particularly when heavy faulting exists in the as a separation layer for unbonded overlays
colored interlayer helps maintain a warmer
pavement to be overlaid. are shown in Table 19. The weight/yd2 and
temperature for the placement of the overlays
thickness should be given when specifying
According to Leykauf and Birmann (2006) of because it has carbon molecules that absorb
a geotextile interlayer. Following are two
the Munich University of Technology, geotex- ultraviolet energy. This is not, however, desir-
examples:
tiles have provided uniform, elastic support of able in hot weather conditions, particularly

Figure 92. Geotextile separation layer (The Transtec Group [no date]) Figure 93. Light-colored geotextile fabric used as a separation layer
for an unbonded overlay

Table 19. Geotextile Separation Layer Material Properties (Modified from Material Specifications (The Transtec Group [no date]))

Property Requirements Test Procedure


Nonwoven, needle-punched, no thermal treatment to
Geotextile Type EN 13249, Annex F (Certification)
include calendaring
Color Uniform/nominally same color fibers (Visual Inspection)
450g/m2 (13.3oz/yd2)*
Mass per unit area 500g/m2 (14.7oz/yd2) ISO 9864 (ASTM D 5261)
550g/m2 (16.2oz/yd2)
[a] At 2kPa (0.29psi): 3.0mm (0.12in.)
Thickness under load (pressure) [b] At 20kPa (2.9psi): 2.5mm (0.10in.) ISO 9863-1 (ASTM D 5199)
[c] At 200kPa (29psi): 0.10mm (0.04in.)
Wide-width tensile strength 10kN/m (685lb/ft) ISO 10319 (ASTM D 4595)
Wide-width maximum elongation 130 percent ISO 10319 (ASTM D 4595)
Water permeability in normal direction
1x10-4m/s (3.3x10-4ft/s) at 20kPa (2.9psi) DIN 60500-4 (modified ASTM D 5493)
under load (pressure)

[a] 5x10-4m/s (1.6x10-3ft/s) at 20kPa (2.9psi) ISO 12958 (ASTM D 6574)*


In-plane water permeability
or
(transmissivity) under load (pressure) [b] 2x10-4m/s (6.6x10-4ft/s) at 200kPa (2.9psi) ISO 12958 (modified ASTM D 4716)
EN 12224 (ASTM D 4355 @ 500hrs exposure for
Weather resistance Retained strength 60 percent
grey, white, or black material only)

Alkali resistance 96 percent polyproplene/polyethylene EN 13249, Annex B (Certification)

*Added to Material Specifications (The Transtec Group [no date]) for overlays
Calendering is a process that passes the geotextile through one or more heated rollers during the manufacturing process. The surface of the geotextile is modified during
this process. Calendering may reduce the absorption properties of the geotextile on the calendered side.

Guide to Concrete Overlays 79


Ch 5. MATERIALS & MIXTURES

4 in. overlay13.0 oz/yd2 @ 130 mils transfer efficiency is adequate with a mini- D2628, AASHTO M220, or a governing
(3.3 mm) mum of a 2-inch cover). Specify a single state specification. The need for seals depends
height basket for each nominal overlay on whether or not the design allows water to
5-in. overlay15 oz/yd2 @ 170 mils (4.3
thickness that will provide adequate cover. leave the pavement jointing system.
mm)
In some cases, because of the underlying
Each highway agency is encouraged to
support of the old pavement, dowels are Curing Compound
develop their own weight and thickness cri-
not used in the overlay, or their size or White-pigmented liquid membrane-
teria for geotextile interlayer based on their
numbers are reduced. forming curing compounds (ASTM C309
experiences and environmental conditions.
or AASHTO M148) are recommended.
Tiebars are typically billet steel, grade-40
Coverage should be at double the manu-
Dowel Bars and Tiebars bars that meet ASTM A615 or AASHTO
facturers recommendations for all concrete
M31 specifications. No. 4 or No. 5 (used
When needed for heavy traffic (typically pave- overlays with a thickness of 6 in. or less.
for slab thickness 10 inches) deformed
ment thickness of 7 inches or greater), dowel tiebars are typically spaced at 30 in. (76.20 Some agencies have implemented the use of
bars are usually billet steel, grade-60 bars cm) apart, but greater spacing may be used curing compounds containing poly-alpha-
that conform to ASTM A615 or AASHTO in some cases. methylstyrene (AMS) resin. Their use has
M31. The dowel bar size, layout, and coatings
been based on studies that have shown better
should be selected for the specific project loca-
tion and traffic levels. Joint Sealant moisture retention properties. Application
methods and coverage rates are similar to nor-
Joint sealant materials, if used, are either hot-
Dowels should be nominally positioned mal white-pigmented curing compounds. A
poured rubberized materials conforming to
in the middle third of the depth of the typical material specification for AMS curing
ASTM D6690, AASHTO M301, or per nor-
slab. Because of the variable thickness of compound can be found at www.dot.state.
mal design; silicone materials conforming to
concrete overlays, dowel placement at mn.us/products/concrete/pdf/curing_com-
a governing state specification; or preformed
mid-depth is not always possible (guidance pound_specifications_3753_3754_3755.pdf.
compression seals conforming to ASTM
provided by Snyder [2011] states that load

80 Guide to Concrete Overlays


Ch 6. WORK ZONES

Chapter 6.

CONCRETE OVERLAY STRATEGIES


IN WORK ZONES

This section discusses several issues related


to work zone management, including clear-
as other resurfacing projects have been for
decades. This section provides guidance on
Objectives of Work
ances, traffic control, and staging. By their specific details for optimizing constructibility Zone Management
nature, concrete overlays are accelerated of the concrete overlay and maintaining traf-
projects because demolition, excavation, and fic. See Appendix E for more information A checklist of considerations in overlay work
base work are not necessary. In short, concrete about constructing overlays under traffic. zone management is provided in Table 20.
overlays can be executed in the same manner

Table 20. Concrete Overlay Work Zone Management Considerations

Areas of Consideration Items to Consider


Traffic Management 1. Capacity analyseslanes required, length of queues 7. Warning sign locationsdetours, long queues, intersecting
anticipated roads
2. Time restrictionspeak hours, seasonal peaks 8. Railroad crossings and train schedule
3. Limits to work areas 9. Nighttime delineation and illumination
4. Capacity of detour routes 10. Signals, turning lanes, bus stops
5. Work vehicle access and worker parking 11. Traffic serviceresidential/business
6. Bicycle and pedestrian traffic 12. Future rehabilitation

Concrete Pavement 1. Accelerated constructionplanning, concrete materials, 7. Prepaving and paving restrictions
Construction construction requirements, curing, jointing 8. Special contract provisions needed
Requirements 2. Opening to trafficmaturity, pulse velocity, strength 9. Short-duration closures anticipated
requirements, cure time
10. Temporary drainage
3. Rehabilitation considerations
11. Lights for night work
4. Off-peak traffic hours for increased production
12. Temporary roadway lighting
5. Phasing of worklength of work zone, project limits
6. Special conditions such as dropoffs, sign bridge installation,
etc.

Safety 1. Work zone crash rates 6. Large trucks


2. Traffic management strategies 7. Workers on foot
3. Interstate system 8. Pedestrians
4. Congestion 9. Local experience
5. Nighttime

Constructibility 1. Structural capacity of bridges, shoulders, and pavement


2. Timing of phases versus probable starting date
3. Strategy to allow contractor to finish project
4. Status of existing traffic control devicessignals, signs, railroad crossings, etc.
5. Wintertime restrictionssnow removal, etc.

Emergency Planning 1. Incident management plans 5. Emergency closures


2. Emergency medical assistance 6. Utility interruptions
3. Accidents, breakdowns, tow trucks 7. State police
4. Severe storms and storm-water runoff 8. Local law enforcement

Public Information 1. Public informationpublic hearings, media, motorist service agencies, residents, local businesses, motor carriers
Coordination 2. Local officialspolice, fire, hospitals, schools, environmental agencies, utilities, toll facilities, ferries, railroads, airports
3. Special events
4. Intra-agency coordinationmaintenance crews, permits section, adjacent project
5. Transit

Guide to Concrete Overlays 81


Ch 6. WORK ZONES

Managing work zones for concrete overlay Safety Cost Effectiveness


projects is no more challenging than for any Strategies used to manage traffic in work
Promoting worker and traveler safety should
other paving project under traffic, as long as zones can significantly affect project costs.
be an integral, high-priority element of every
certain straightforward practices are followed. Therefore, it is important to carefully evalu-
project, from planning through construction.
Effective work zone management for all con- Roadway users (vehicles, bicycles, pedestrians, ate road use demands and select the most
crete pavement projects, including concrete etc.) must be clearly guided by traffic control cost-effective strategies to accommodate the
overlays for maintenance and rehabilitation, devices and markings while approaching, demands. Traffic control costs and construc-
involves designing a comprehensive plan of passing through, and leaving temporary traffic tion costs should be balanced against the
action that balances several equally important control zones. Traffic control elements should impact on the public, especially adjacent
priorities; see Figure 94: be regularly inspected. All people involved businesses and residents. In many cases, a
in selecting, placing, and maintaining work short full-road closure has far less impact than
Ensure safety of workers and motorists zones should be trained in safe traffic control maintaining traffic through a construction
Minimize inconvenience to the traveling practices. zone for extended durations.
public The exposure of highway workers and trav- Many urban intersections have been overlaid
Maintain or enhance cost effectiveness of the elers to traffic risks can be minimized by with concrete utilizing only weekend work
project reducing the frequency with which work hours, which has mitigated the impact on sur-
zones are established, reducing the length rounding businesses.
Balance maintenance of traffic concerns of time work zones are in place, and, where
with long-term pavement performance Partly or completely closing a work zone to
possible, reducing the volume of traffic
traffic can help minimize traffic management
The basic elements of these priorities are dis- through the work zone. When compared
costs. Informal project reviews that have been
cussed below. A checklist of considerations in to reconstruction options, concrete overlays
performed on constructed concrete overlay
overlay work zone management is provided in have a significantly shorter construction dura-
projects utilizing pilot car operations indicate
Table 20. tion, which reduces public and construction
that there could have been an approximate
worker exposure.
20 to 30 percent cost and time savings had
A detailed emergency response plan should the roadway been closed to through traffic.
be in place to deal with any injury that might If closing the roadway to through traffic is a
occur in the work zone. The plan should viable option, the contract documents should
Safety of the include protocols for emergency medical clearly state that the contractor is responsible
traveling public and services. for maintaining local access for residents and
highway workers businesses. Putting the onus on the contrac-
Traffic Flow tor, yet allowing flexibility in their methods
for providing local access, is a preferred
Minimizing disruption to traffic in work strategy rather than explicit details regarding
Minimal Successful Cost-
Cost-
zones requires a proactive, partnership how and when the access shall be maintained.
disruption work zone effective approach to work zone management. By When a roadway cannot be closed, higher
to traffic management solutions involving officials and the public during early costs are probably justifiable. Potential ways
stages of project planning, the designer and to manage costs include, where possible,
contractor can gain a better understanding of reducing traffic volume through work zones,
traffic issues related to the project. As a result, reducing the frequency and duration of work
Superior they can develop better, more coordinated zones, and minimizing detours and crossover
pavement solutions. In addition, broadly publiciz-
performance construction elements. For long (> 7 miles)
ing the work zone well before construction two-lane overlay projects, allowing for mul-
begins helps ensure that motorists have every tiple work zones simultaneously can improve
Figure 94. Managing work zones effectively opportunity to plan travel routes and times construction operation efficiencies and cost
involves balancing several priorities accordingly. effectiveness.

82 Guide to Concrete Overlays


Ch 6. WORK ZONES

Work Zone Space Reducing Clearances stringless paving technology can reduce the
clearance required for paving equipment to
In some situationsnarrow roadways,
Considerations minimum or no shoulders, traffic in adjacent 3 ft (0.9 m). It also allows the traffic cones to
lanes, obstacles like retaining walls or safety be placed at the edge of the new lane directly
Constructing any overlay requires occupy-
barrierspaving equipment clearances may behind the texture/cure operations, which
ing some part of the traveled portion of the
need to be reduced. These situations are fairly maximizes the width of the existing lane for
roadway to accommodate work activities
common with all maintenance and rehabilita- pilot car operations.
and provide traffic control and other safety
provisions for workers and motorists. This tion projects. With adequate planning, zero Paving machine manufacturers have devel-
will affect traffic capacity through the work paving equipment clearance can be achieved oped special paving machines designed to
zone for the duration of the work activities. to accommodate specific project needs, execute minimum clearance projects. In
In some cases, safety considerations may such as paving next to a median barrier; see addition, many contractors around the
require partial or even complete closure of the Figure96. (As with asphalt paving, zero pav- country have made various modifications to
roadway. ing equipment clearance in concrete paving standard pavers to achieve zero clearances; see
does not include the 68 in. [150200 mm] Figure97.
When overlay projects are constructed under for the paving machine edge form.)
traffic, space and traffic capacity consider- Instead of specifying a certain manufacturers
ations impact three primary elements of a Two-lane roads with wide (810 ft [2.43.1 machine, owner-agencies are advised to define
work zone management strategy: construction m]) shoulders of granular or stabilized base the maximum allowable clearance zone and
clearances, traffic control, and project staging. will allow room for pilot car traffic and let the contractor select or modify the equip-
two lanes of construction traffic. The use of ment and operation to meet project needs.
Conventional Paving
Equipment Clearances
When work zones are set up under traf-
fic, adequate clearance must be provided to
accommodate the paving machines tracks
and frame, as well as the paving stringline.
For a standard concrete paver operation, the
typical paving equipment clearance is 4 ft
(1.2 m) on each side of the paving machine
(3 ft [0.9 m] for the paver track and 1 ft
[0.3 m] for the paver control stringline); see
Figure 95. Paving equipment clearances do
not include space for traffic control devices or
workers or space for highway users (vehicles,
pedestrians, bicycles, etc.). Additional clear-
ances needed should be determined on a
project-by-project basis.
Figure 96. A three-track, zero-clearance paver placing concrete along
a median barrier (source: Kevin Klein, Gomaco)

Figure 95. Stringline paver Figure 97. A typical four-track paver modified to three tracks,
providing zero clearance in a C/G situation in Oklahoma (source:
Jim Duit, Duit Construction Co., Inc.)

Guide to Concrete Overlays 83


Ch 6. WORK ZONES

Mechanical Methods (e.g., reduced survey costs, fewer construction paving reference hubs or pins at 12- to
Alternative paving control options may be hours) while still meeting smoothness require- 50-foot intervals. Surface surveys are now
used to reduce clearance as long as smooth- ments. Details regarding various stringless conducted by one- to two-person crews
ness criteria are met. For example, an average paving systems are provided in Appendix F. versus three to four persons. Typically,
profiler, a movable stringline, or a ski can these persons are replaced by one surface
Stringless paving is a technology that elimi-
be used in tight areas, each relying on the modeler and two persons to establish laser,
nates the installation and maintenance of
smoothness of an existing lane to ensure a total station, or GPS base stations on the
stringlines and has the potential to decrease
smooth profile on the new pavement; see project.
the need for surveying and increase the
Figures 98 and 99. smoothness of the pavement profile; see Reduced time and manpower. Surface and
Figures 100 and 101. Any technology prob- reference point surveys are now conducted
Stringless Methods
lems can arise, however, and lessons learned in much less time and with reduced man-
Several companies have developed stringless can take time and may cause delays. Field power. Many highway agencies do not have
equipment control and guidance systems research on stringless paving was first started the manpower or time to conduct string-
using technologies such as GPS, robotic total in 2003 by the National Concrete Pavement line operations, but they can prepare for
stations, and laser positioning. Stringless tech- Technology Center at Iowa State University the stringless control operation.
nology replaces the traditional stringlines with (Cable et al. 2004).
an electronic tracking process that controls Construction access. Removal of the
the horizontal and vertical operation of the The benefits that can result from stringless stringlines opens up the site to both the
slipform paver. The construction industry has paving include the following: contractor and/or adjacent public. No
been using stringless technology for eleva- longer must the contractor worry about
Reduced construction costs. The stringless
tion and steering control of equipment for a damage to the stringline during construc-
systems eliminate the need for stringline
number of years. Stringless paving, however, tion or the workers tripping over the
crews to place, maintain, and remove
is now an emerging technology for concrete stringline. Construction vehicles can enter
stringlines. The stringless system requires
paving because it can allow contractors and and leave the site at any location without
the survey crew to establish the project ref-
owner/agencies to receive production benefits fear of stringline damage.
erence points but removes the need to place

Figure 98. Controlling paving profile using a moveable stringline on the adjacent Figure 100. Stringless paver (source: Jim Cable, Iowa
lane (source; Kevin Klein, Gomaco) State University)

Figure 99. Controlling paving profile using a paver ski on the Figure 101. Zero clearance stringless paver (source: GOMACO)
adjacent lane (source: Wouter Gulden, southeast chapter, ACPA)

84 Guide to Concrete Overlays


Ch 6. WORK ZONES

Public access. Those living along the con- Such an analysis answers specific questions: Two-Lane Highway under
struction site can enter and leave their
residence or business at all times except
Is the capacity of the existing roadway Traffic
adequate for existing traffic levels? When construction will be completed
during the actual pavement placement and
curing time without concern for stringline How will capacity be affected if some lanes under traffic and certain lanes need to carry
interference. are shut down and other lanes kept open? additional traffic, various options regarding
preoverlay spot repairs should be considered.
Urban and rural application. No longer Comparing existing traffic levels to the For example, if spot repairs can be made
must the contractor and highway agency under-construction capacity, are there any quickly (and, if appropriate, a separation
be concerned about narrow roadway tops, capacity deficiencies? layer can be placed immediately after the
ground-level vegetation, or earthwork that repairs), then it is normally acceptable to
limits the location of the stringline or opera- The analysis should consider both the lat-
eral clearance (availability and need) and put temporary additional vehicle traffic on
tion of both it and the paver. the existing pavement until the overlay is
the length of roadway needed to provide
efficient, cost-effective paving production. It constructed. Another option is to wait and
Other Clearances must also factor in peak and off-peak traffic make final spot repairs after the temporary
In addition to paving equipment clearances flows. additional traffic is moved off the existing
on all construction operations, clearance must pavement. This approach should be used only
be allowed for traffic control devices and con- If deficiencies will occur, the work zone man- when the extent of additional repairs needed,
struction workers. The width of this clearance agement plan must address them to prevent the additional thickness of overlay required,
zone varies depending on adjacent traffic vol- congestion and increased project costs. For and related costs are clearly understood.
ume, traffic speed, and agency requirements. example, the plan might include variable Alternatively, it is possible to temporarily
In addition, the location of workers with work times (e.g., off-peak hours, nighttime) close the roadway (preferably during off-peak
long-handled floats should be restricted to the or construction sequencing to meet produc- hours), make the critical repairs and complete
nontraffic side of the pavement. tion and safety demands. the overlay at least on one lane, and open it
to traffic as soon as possible.
An increasingly popular alternative is to com-
pletely close the facility briefly to complete When staging a two-lane concrete overlay
Construction Traffic the project or a critical phase of the project. project under traffic, the widths of the vehicle
In some cases, this alternative has reduced lane and the construction lane must be con-
Control the overall project duration significantly. sidered. Typically, the minimum desirable
All work zone traffic control, including width for the vehicle lane is 11 ft (3.4 m).
speed restrictions, should follow jurisdic- Some jurisdictions may allow as little as 10
tional requirements and the latest Manual on Concrete Overlay ft (3.1 m) under certain circumstancesfor
example, in very short segments (less than
Uniform Traffic Control Devices (FHWA 2009).
The fundamental principles of work zone traf- Staging 100 ft [30.5 m]).
fic control are given in Part 6. In addition, Many easy-to-use approaches exist for stag- The width of the construction lane depends
the Traffic Management Handbook for Concrete ing concrete overlay projects in almost any on several factors, including thickness of over-
Pavements Reconstruction and Rehabilitation situation. A system approach that considers lay, maximum allowable centerline dropoff
(ACPA 2000) is a good reference on traffic work zone safety, traffic requirements, and or edge fillet, slope of fillet, type of traffic
control strategies for common roadway reha- key elements of construction should be used control device, type of paving machine, and
bilitation categories, including overlays. See, in in staging concrete overlay plans for fast, automobile and truck traffic.
particular, Chapter 4 on traffic control strate- cost-effective construction projects. When
gies for concrete pavement. construction acceleration is desired, it should Concrete overlays can be successfully con-
begin in the design phase with an analysis of structed under traffic with conventional
The ACPA handbook explains that as traffic paving machines; in some cases, where
volumes increase, the window of time where alternative maintenance of traffic schemes,
advance planning, and tailoring of project minimum clearances are required, minor
the traffic demand is below the capacity of the adjustments may be necessary.
work zone will become smaller. When the time details to facilitate shortened construction
is too short to allow for daytime work, the durations. The plans and specifications The length of the temporary traffic control
work is usually moved to nighttime. In some should provide the contractor with clear cri- zone is another important factor. Typically,
cases even the nighttime hours are restricted. teria for maintenance of traffic requirements when the length of traffic control zones is
(e.g., two lanes open in each direction at all less than 0.25 mi (0.40 km), a pilot car is not
For situations such as recreational routes, times, pilot car queues shall not exceed 10 used. In rural areas, however, it may be more
the peak traffic hours may be on Friday and minutes, etc.). Given the requirements for feasible to pave longer sections. In such situ-
Sunday afternoons. The allowable window of maintenance of traffic, the contractor should ations, a pilot car and flaggers are often used
time for road construction in this case may be be given the responsibility to plan and pros- and the maximum length of the traffic con-
noon Monday to 6:00 p.m. Thursday. ecute the project to meet the objectives for trol zone is established by the jurisdiction.
accelerated construction and maintenance
For roadways under high traffic demands, a Other traffic control measures, including
of traffic. This approach of allowing the con-
traffic analysis should be conducted to identify flaggers and traffic control signals, may
tractor to innovate and plan the project to
which parts of the roadway can be occupied be warranted according to jurisdictional
meet their resources results in more efficient
by construction and public traffic at any point requirements.
workflow, shorter durations, and less impact
during the construction time period. The goal
on the road users. When granular shoulders of adequate widths
is to identify congestion points that could
affect traffic capacity and safety as well as con- Some common staging scenarios are are available to accommodate a conventional
struction production levels. described below. paver, it is recommended that the shoulders
be treated with calcium chloride (3 ft [0.9 m]

Guide to Concrete Overlays 85


Ch 6. WORK ZONES

wide) before opening the road to vehicular The third stage includes opening the newly Pilot Cars for Continuous
traffic. The calcium chloride treatment is a placed overlay to traffic and shifting traffic Production
successful way of stabilizing the shoulder in control for work on the opposite lane. The
Pilot cars can be used to keep one lane of
case errant vehicles leave the pavement. Also, final stage includes placing pavement mark-
traffic adjacent to the paving operation open
vertical traffic control panels or a permanent ings, rumble strips if shoulders are paved, and
at all times. To minimize traveler delays,
safety edge may be used to designate the pave- final shouldering.
many jurisdictions limit the length of such
ment edge; see Figure 102.
work zones. Contractors must balance those
Temporary Safety Fillet
If shoulder paving is part of the project, the limitations with their need for continuous
trenching of paved shoulder base widening If two-way traffic is desired on the roadway production so that crews do not stand idle at
should be completed in the first stage along after the first lane is cured, and agency- any time.
with surface preparation of the initial lane to established dropoff criteria require a dropoff
mitigation, construction of temporary cen- The following are some considerations
be overlaid. Once this is completed, this lane
terline and outside safety fillets may be an for staging a project using pilot cars cost
can be opened to traffic and the adjacent lane
option; see Figure 103. An outside safety edge effectively:
can be prepared for paving.
fillet should be considered if shouldering will Typically, a contractor can prepare and pave
During the second stage, the second lane not be completed before opening the roadway 2,500 yd3 (1,911 cm) in one lane per work-
is paved. A thickened edge may be paved if to traffic. ing day. For thinner overlays, the rate of the
pavement widening is part of the project.
sawing operation may be the limiting factor
on production.
Constructing an edge fillet may make it
possible to open the lane to traffic before
the shoulder backfill is completed.
A new overlay can be opened in 24 hours
or less.
Leaving gaps in or staggering construction
areas (that is, leapfrogging over a section of
pavement) can allow the contractor to stage
work in ways that use crews and machinery
more efficiently.
Using multiple paving machines may make
it possible to stagger work zones more
Vertical traffic efficiently.
control panel The direction of the initial pour is impor-
tant to make sure the paver ends each pour
in the optimum position to begin the next.
Calcium chloride treatment
Examples of Staging
Figure 102. Vertical traffic control panels may be used to mark pavement edge dropoff
Sequences
(source: Dan DeGraaf, Michigan Concrete Paving Association) Figures 104108 on pages 8897 illustrate a
variety of potential staging sequences. Note
that each half of a four-lane divided highway
is treated like a two-lane section.
Traffic control device

Full-depth saw cut Traffic control device


Two-Lane Highway
or fabric or
formed gap of Expanded to Three Lanes
1/4 in. or more Saw cut or fabric or
2 in.
(50 mm) 1 in. Min.
formed gap of 1/4 in.
or more
under Traffic
Overlay 30 When constructing a concrete overlay and
T T/2 or greater widening a pavement from two lanes to three
Fillet T lanes, some states require that the remaining
Match existing centerline 1 in. Min.
for overlay on concrete shoulder after pavement widening be at least
Unbonded separation layer
4 ft (1.2 m) wide. Therefore, using both exist-
ing shoulders for staging and widening has
Bonded and unbonded overlay 3 in. 4 in. Unbonded overlay greater than 4 in. (100 mm) distinct advantages.
(50100 mm) thick
Traffic control and slope of fillet depends on jurisdictional requirements. First, base shoulder widening on one-half
of the road is accomplished. The overlay is
Figure 103. Centerline safety edge fillets for overlays 3 in. (50 mm) or greater constructed in halves similar to the two-lane

86 Guide to Concrete Overlays


Ch 6. WORK ZONES

staging example. The existing shoulder is Four-Lane Divided Highway is increased. The existing shoulders usually
trimmed and properly compacted. The first provide adequate room for the paver track,
concrete overlay section is then placed with without Crossovers and stringline, and workers between the paver and
a thickened edge. The other half of the over- under Traffic traffic.
lay can be placed directly on top of the base Staging a concrete overlay on a four-lane A possible staging sequence for this type of
shoulder constructed first. divided highway is similar to that on a two- construction is shown in Figure 108. Because
A possible staging sequence for this type lane highway. Both two-lane sides may be each half of the four-lane divided highway is
of construction management is shown in under construction at the same time, and treated like a two-lane section, any of the stag-
Figure107. crossovers are eliminated. By eliminating ing sequences from Figures 104107 may be
crossovers, project costs are reduced and safety used on either half of the section.

Guide to Concrete Overlays 87


Ch 6. WORK ZONES

COMPLETED OVERLAY (Two-Lane Roadway with Paved Shoulders, Conventional Paver)

Applied to:

Bonded concrete overlay of concrete pavements Unbonded concrete overlay of concrete pavements
Bonded concrete overlay of asphalt pavements Unbonded concrete overlay of asphalt pavements
Bonded concrete overlay of composite pavements Unbonded concrete overlay of composite pavements

STAGE 1. Repair surface, prepare for overlay, and construct base shoulder
widening and separation layer
Install traffic control and close the left lane. Follow Prepare for shoulder widening by trenching the
jurisdictional requirements for traffic control. Check existing shoulder and trimming to the specified
with jurisdiction regarding allowable lane closure width. The trench should be rolled and compacted
length. If surface repair and preparation for the as necessary to obtain a firm and stable platform as Typically
specified in the contract documents. A continuous less than
overlay are minimal, then slow-moving traffic control 0.25 mi
may be appropriate. Closing the lane may require progression approach with the shoulder trencher (0.40 km)
additional traffic control (e.g., signals, flaggers, and/or and placement of the base shoulder widening without
pilot cars). material is encouraged. pilot car

Repair the surface as appropriate. Prepare the surface Construct separation layer (only for unbonded
for the overlay (or, in the case of concrete overlay on overlay on concrete).
concrete, the separation layer) as described in the
contract document.

STAGE 2. Construct right shoulder and concrete overlay

Shift the traffic control to the left lane and close the typical machine adjustment. Speeds should be
right lane to traffic. The length of the closure will additionally restricted adjacent to paver when
depend on the jurisdictions maximum closure length clearance between the paver and vehicle traffic is
with pilot car. Traffic controls and traffic control tight.
signals will be based on jurisdictional requirements. Construct concrete overlay on the existing
Repair and prepare the surface for the overlay or the pavement. Complete right PCC shoulder widening
separation layer and subsequent overlay as described with the overlay. Bull float work shall operate from
in the contract documents. Construct separation layer the outside shoulder only.
(for unbonded overlay). The X dimension between the roadway centerline
Normal space for the paver stringline is 11.50 ft (0.30 and vertical panel is for the paving machine track
0.46 m) and the paver track is a minimum of 2.503 ft and stringline.
(0.760.91 m). 1 ft (0.3 m) incremental encroachment
reduction (up to 2 ft (0.6 m) total) is common through

STAGE 3. Construct left lane concrete overlay

Close the opposite lane to traffic and place the If the outside edge dropoffs at the shoulder exceeds
concrete overlay according to contract documents, the jurisdictional allowance for a 1:1 fillet, then
using the same procedures as described in stage construct the granular shoulders in this stage.
2. Note that stringline may not be necessary for the Complete shouldering. Install (mill) rumble strips
right edge of the paving when the paved overlay in the paved shoulders and complete pavement
constructed in stage 2 is used as the paver control in marking and regulatory signing in accordance with
this stage. If the right stringline is not used, the X contract documents.
dimension could possibly be reduced to 3 ft (0.9 m).

Figure 104. Overlay of two-lane roadway with paved shoulders (conventional paver)

88 Guide to Concrete Overlays


Ch 6. WORK ZONES

LEGEND
Remaining Paved Paved Remaining
shoulder shoulder shoulder shoulder
12 ft (3.7 m) lane 12 ft (3.7 m) lane Stage work area
Pavement (Typical) (Typical)
marking Pavement Concrete
Rumble strip marking
Finished Base shoulder widening materials
shoulder (e.g., cement-treated base, porous
concrete, roller compacted con-
Saw joint crete (RCC), asphalt, or concrete)
12 ft (3.7 m) existing lane with tied steel Granular material
Existing pavement
Concrete overlay
Separation layer Existing subbase
(only for unbonded overlay on concrete)
COMPLETED OVERLAY

NOTES:

Traffic 1 Follow jurisdictional requirements


Construction area for traffic control devices.
control
device
Existing Existing 2 Treat 3 ft (0.9 m) area outside of
shoulder Vehicle traffic shoulder proposed paved shoulder with
11 ft (3.4 m) lane calcium chloride. If the existing
(Typical) shoulder outside the proposed
paved shoulder is less than 3 ft
(0.9m), it may be necessary to
adjust the slipform paver and/or
paver control to accommodate the
Base shoulder Surface repair Existing pavement reduced space.
widening and overlay surface
material
Varies Existing subbase 3 Minimum lane width next to the
preparation
paver may be reduced for short-
Separation layer (only for term, stationary work on low-
unbonded overlay on concrete) volume, low-speed roadways when
STAGE 1 vehicular traffic does not include
longer and wider heavy commercial
vehicles.
4 If the overlay is opened to traffic
Vehicle traffic Construction area in this stage, and final shoulder
11 ft (3.4 m) lane backfill is delayed, place fillet as
(Typical) shown or (if overlay creates a
Shoulder Varies
dropoff greater than jurisdictional
allowance) place granular shoulder.
12 ft (3.7 m) lane Concrete
(Typical) fillet placed 5 See centerline fillet illustration and
Traffic Varies
control
with overlay subsequent removal on figure 103.
device 6 For X less than 4 ft (1.2 m),
adjustments to paver may be
necessary to accommodate paver
Concrete thickened control and paver track.
Concrete paved shoulder
Varies Varies
overlay placement 7 The X dimension can be reduced
Surface repair to 3 ft (0.9 m) minimum when the
Existing pavement right lane is used as paver control.
Separation layer 8 Mark edgelines and centerlines per
(only for unbonded overlay on concrete) MUTCD (FHWA 2009) section 6F.77
STAGE 2
(mark both lanes).
9 Construct longitudinal joint.
Construction area Vehicle traffic
11 ft (3.4 m) lane
Remaining Paved 12 ft (3.7 m) lane (Typical) Remaining
Concrete shoulder shoulder shoulder
(Typical)
fillet placed
with overlay Concrete
9 overlay 8 9 8
placement

Overlay of
Two-Lane Roadway
Separation layer Existing pavement
(only for unbonded
overlay on concrete)
Varies Varies with Paved Shoulders
STAGE 3
(Conventional Paver)

Guide to Concrete Overlays 89


Ch 6. WORK ZONES

COMPLETED OVERLAY (Two-Lane Roadway with Granular Shoulders, Conventional Paver)

Applied to:

Bonded concrete overlay of concrete pavements Unbonded concrete overlay of concrete pavements
Bonded concrete overlay of asphalt pavements Unbonded concrete overlay of asphalt pavements
Bonded concrete overlay of composite pavements Unbonded concrete overlay of composite pavements

STAGE 1. Repair surface, prepare for overlay, and construct left shoulder
and separation layer
Install traffic control and close the left lane. Follow trench should be rolled and compacted as
jurisdictional requirements for traffic control. Check necessary to obtain a firm and stable platform.
with jurisdiction regarding allowable lane closure Compact shoulder material as specified in the
length. If surface repair and preparation for the overlay contract documents. A continuous progression Typically
are minimal, then slow-moving traffic control may be approach with the shoulder trencher and less than
appropriate. Closing the lane may require additional placement of the base shoulder widening is 0.25 mi
(0.40 km)
traffic control (e.g., signals, flaggers, and/or pilot cars). encouraged. without
pilot car
Repair the surface as appropriate. Prepare the surface Construct calcium chloride treated granular
for the overlay (or, in the case of concrete overlay on shoulder as outlined in contract documents. The
concrete, the separation layer) as described in the treated shoulder shall be firm and stable to support
contract document. vehicular traffic at low speeds.
Prepare shoulder widening by trenching the existing Construct separation layer (only for unbonded
shoulder and trimming to the specified width. The overlay on concrete).

STAGE 2. Construct right shoulder and concrete overlay


Shift the traffic control to the left lane and close the paver when clearance between the paver and
right lane to traffic. The length of the closure will vehicle traffic is limited.
depend on the jurisdictions maximum closure length Construct concrete overlay on the existing
with pilot car. Traffic controls and traffic control pavement. Construct right shoulder base with 6 in.
signals will be based on jurisdictional requirements. (150 mm) thick granular shoulder. Bull float work
Repair and prepare the surface for the overlay or the shall operate from the outside shoulder only.
separation layer and subsequent overlay as described Place 6 in. (150 mm) minimum thickness calcium
in the contract documents. Construct separation layer chloride treated granular shoulder to help stabilize
(for unbonded overlay on concrete). shoulder and minimize heavy dust that can impair
Normal space for the paver stringline is 11.5 ft (0.30.5 vision.
m) and the paver track is a minimum of 2.53 ft (0.80.9 The X dimension between the roadway centerline
m). 1 ft (0.3 m) incremental encroachment reduction (up and vertical panel is for the paving machine track
to 2 ft [0.6 m] total) is common through typical machine and stringline.
adjustment. Speeds should be restricted adjacent to

STAGE 3. Construct left lane concrete overlay

Close the opposite lane to traffic and place the If the outside edge dropoffs at the shoulder
concrete overlay according to contract documents, exceeds the jurisdictional allowance for a 1:1 fillet,
using the same procedures as described in stage 2. then construct the granular shoulders in this stage.
Stringline may not be necessary for the right edge of Complete shouldering. Complete pavement marking
the paving when the paved overlay constructed in and regulatory signing in accordance with contract
stage2 is used as the paver control in this stage. If the documents.
right stringline is not used, the X dimension could
possibly be reduced to 3 ft (0.9 m).

Figure 105. Overlay of two-lane roadway with granular shoulders (conventional paver)

90 Guide to Concrete Overlays


Ch 6. WORK ZONES

Remaining Remaining LEGEND


shoulder Granular Granular shoulder
shoulder 12 ft (3.7 m) lane 12 ft (3.7 m) lane shoulder
Stage work area
Pavement (Typical) (Typical)
marking Pavement
marking Concrete
Finished
shoulder Granular material

12 ft (3.7 m) existing lane


Existing pavement
Concrete overlay
Existing subbase
Separation layer
(only for unbonded overlay on concrete) COMPLETED OVERLAY

NOTES:

1 Follow jurisdictional requirements


Traffic
Construction area control
for traffic control devices.
device 2 When the existing shoulder is less
Existing Existing
shoulder Vehicle traffic shoulder than 4 ft (1.2 m), adjustment to the
11 ft (3.4 m) lane slipform paver and/or paver control
(Typical) may be necessary to accommodate
(10 ft [3 m] min.) 10 the reduced space for paver control
and paver track.
3 Minimum lane width next to the
paver may be reduced for short-
Construct 6 in. (150 mm) Existing pavement term, stationary work on low-
thick granular shoulder Surface repair
treated with calcium and overlay surface Existing subbase volume, low-speed roadways when
Varies preparation vehicular traffic does not include
chloride 4 ft (1.2 m)
min. Separation layer longer and wider heavy commercial
(only for unbonded overlay on concrete) vehicles.
STAGE 1 4 If the completed overlay in this
stage opens to traffic and the final
shoulder backfill is delayed, place
fillet as shown. If overlay creates a
Vehicle traffic Construction area dropoff greater than jurisdictional
allowance, place granular shoulder
11 ft (3.4 m) lane
10 (Typical)
in lieu of concrete fillet.
Remaining
Shoulder (10 ft [3 m] min.) Varies shoulder 5 See centerline fillet illustration and
12 ft (3.7 m) lane
subsequent removal on figure 103.
Traffic (Typical) Varies 6 For X less than 4 ft (1.2 m),
control
device adjustments to paver may be
necessary to accommodate paver
control and paver track.
7 The X dimension can be reduced
to 3 ft (0.9 m) minimum when the
Concrete Construct 6 in. (150 mm) right lane is used as paver control.
Varies Varies overlay placement thick granular shoulder
Base shoulder
widening Surface repair base if needed 8 Mark edgelines and centerlines per
Existing pavement MUTCD (FHWA 2009) section 6F.77
Separation layer (mark both lanes).
(only for unbonded overlay on concrete)
9 Use calcium chloride for dust
STAGE 2 control.
For low-volume roads only
10
Construction area Vehicle traffic
11 ft (3.4 m) lane
Remaining 12 ft (3.7 m) lane (Typical)
Remaining
shoulder Shoulder (Typical) (10 ft [3 m] min.) shoulder
10
Concrete 8
overlay 8 9
Temporary
concrete fillet placement
placed with
overlay Overlay of Two-
Lane Roadway with
Separation layer Existing pavement Granular Shoulders
(only for unbonded overlay on concrete) Varies Varies
STAGE 3 (Conventional Paver)

Guide to Concrete Overlays 91


Ch 6. WORK ZONES

COMPLETED OVERLAY (Two-Lane Roadway with Minimum Granular Shoulders, Zero-Clearance Paver)

Applied to:

Bonded concrete overlay of concrete pavements Unbonded concrete overlay of concrete pavements
Bonded concrete overlay of asphalt pavements Unbonded concrete overlay of asphalt pavements
Bonded concrete overlay of composite pavements Unbonded concrete overlay of composite pavements

STAGE 1. Repair surface, prepare for overlay, and construct left shoulder
In order to construct an overlay on a roadway with with jurisdiction regarding allowable lane closure
a minimum of 2 ft (0.6 m) wide existing shoulders, length. If surface repair and preparation for the
adjustments to typical slipform pavers are necessary overlay are minimal, then slow-moving traffic
in order to meet existing clearances adjacent to the control may be appropriate. Closing the lane may
paver. The width of the clearance zone is dependent require additional traffic control (e.g., signals, Typically
on traffic control, paver track, and paver control flaggers, and/or pilot cars). less than
0.25 mi
(stringline). When there is not enough clearance for the
Repair the surface as appropriate. Prepare the (0.40 km)
paver track, paving molds may be installed on typical without
surface for the overlay (or, in the case of concrete
two-track pavers to provide zero clearances. The pilot car
overlay on concrete, the separation layer) as
outside edges of the mold are brought out behind the
described in the contract document.
rear tracks and then the material from the front of the
paver is moved to the back by an auger to be spread Construct calcium chloride treated granular
and paved. shoulder as outlined in contract documents. The
treated shoulder shall be firm and stable to support
Install traffic control and close the left lane. Follow
vehicular traffic at low speeds.
jurisdictional requirements for traffic control. Check
Construct separation layer (only for unbonded
overlay on concrete).

STAGE 2. Construct right shoulder and concrete overlay


Shift the traffic control to the left lane and close the necessary to achieve these dimensions. Speeds
right lane to traffic. The length of the closure will should be restricted adjacent to paver when
depend on the jurisdictions maximum closure length clearance between the paver and vehicle traffic is
with pilot car. Traffic controls and traffic control signals limited.
will be based on jurisdictional requirements.
Construct concrete overlay on the existing
Repair and prepare the surface for the overlay or the pavement. Bull float work shall operate from the
separation layer and subsequent overlay as described outside shoulder only.
in the contract documents. Construct separation layer
Place 6 in. (150 mm) minimum thickness calcium
(for unbonded overlay).
chloride treated granular shoulder to help stabilize
Normal space for the paver stringline is 11.5 ft (0.30.5 shoulder and minimize heavy dust that can impair
m) and the paver track is a minimum of 2.53 ft (0.80.9 vision.
m). 1 ft (0.3 m)incremental encroachment reduction (up
The 1.5 ft (0.5 m) dimension between the roadway
to 2 ft [0.6 m] total) is common through typical machine
centerline and vertical panel is for the stringline
adjustment. Modification to a conventional paver is
and fillet.

STAGE 3. Construct left lane concrete overlay

Close the opposite lane to traffic and place the


concrete overlay according to contract documents,
using the same procedures as described in stage 2.
Complete shouldering. Complete pavement marking
and regulatory signing in accordance with contract
documents.

Figure 106. Overlay of two-lane roadway with minimum granular shoulders (zero-clearance paver)

92 Guide to Concrete Overlays


Ch 6. WORK ZONES

24 ft (7.3 m) LEGEND
Granular
Granular shoulder
shoulder Stage work area
12 ft (3.7 m) lane 12 ft (3.7 m) lane
(Typical) (Typical) Concrete
Pavement Pavement
marking marking
Granular material
Finished
shoulder

Existing pavement
Concrete overlay Existing subbase
Separation layer
(only for unbonded overlay on concrete)
COMPLETED OVERLAY

NOTES:

Traffic 1 Follow jurisdictional requirements


Construction area control Existing for traffic control devices. Outside
device shoulder shoulder traffic control may depend
Existing shoulder
Vehicle traffic on width of shoulder.
11 ft (3.4 m) lane 2 Existing shoulder should have
(Typical)
(10 ft [3 m] min.) 8
minimum 6in. (150 mm) of granular
material and should be treated with
calcium chloride.
3 Minimum lane width next to the
paver may be reduced for short-
Existing pavement
Surface repair
term, stationary work on low-
and overlay surface preparation Existing volume, low-speed roadways when
Separation layer subbase vehicular traffic does not include
Varies (only for unbonded overlay on concrete) longer and wider heavy commercial
2 ft (0.6 m) min. vehicles.
4 Place granular shoulder with
STAGE 1 calcium chloride in two lifts. The
first lift is for the paver track. The
second lift is for final shoulder. If
Vehicle traffic Construction area the completed overlay in this stage
opens to traffic and the final lift
11 ft (3.4 m) lane is delayed, place concrete fillet
(Typical)
1.5 ft (0.46 m) min. as shown. If overlay creates a
(10 ft [3 m] min.) 8
Varies dropoff greater than jurisdictional
12 ft (3.7 m) lane allowance, place second lift before
Traffic Traffic (Typical) opening overlay to traffic.
control control Granular
device device shoulder 5 See centerline fillet illustration and
subsequent removal on figure 103.
6 Requires minimum to zero
clearance paver. 1.5 ft (0.5 m)
Concrete dimension is for the paver ski or
overlay placement stringline.
Surface repair 7 Mark edgelines and centerlines per
Existing pavement MUTCD (FHWA 2009) section 6F.77
Separation layer (mark both lanes).
(only for unbonded overlay on concrete)
STAGE 2 8 For low-volume roads only

Construction area Vehicle traffic


Granular 11 ft (3.4 m) lane
(Typical) Traffic
shoulder 1.5 ft (0.46 m) min. control
12 ft (3.7 m) lane (10 ft [3 m] min.) device
(Typical) Concrete 8 6 in. (150 mm) plus
overlay 7
placement
7 overlay thickness
granular shoulder Overlay of Two-
treated with
calcium chloride Lane Roadway with
Minimum Granular
Separation layer
(only for unbonded
Existing
pavement
Shoulders (Zero-
overlay on concrete) STAGE 3
Clearance Paver)
Guide to Concrete Overlays 93
Ch 6. WORK ZONES

COMPLETED OVERLAY (Two-Lane Roadway Widened to Three Lanes with


Paved Shoulders, Conventional Paver)

Applied to:

Bonded concrete overlay of concrete pavements Unbonded concrete overlay of concrete pavements
Bonded concrete overlay of asphalt pavements Unbonded concrete overlay of asphalt pavements
Bonded concrete overlay of composite pavements Unbonded concrete overlay of composite pavements

STAGE 1. Repair surface, prepare for overlay, and construct base shoulder
widening and separation layer
Install traffic control and close the left lane. Follow to obtain a firm and stable platform. Compact
jurisdictional requirements for traffic control. Check shoulder material as specified in the contract
with jurisdiction regarding allowable lane closure documents. A continuous progression
length. If surface repair and preparation for the overlay approach with the shoulder trencher and
Typically
are minimal, then slow-moving traffic control may be placement of the base shoulder widening is less than
appropriate. Closing the lane may require additional encouraged. 0.25 mi
traffic control (e.g., signals, flaggers, and/or pilot cars). (0.40 km)
Pave the existing shoulder a minimum of 6 ft without
Repair the surface as appropriate. Prepare the surface (1.8 m) with concrete. pilot car
for the overlay (or, in the case of concrete overlay on
Use excavated granular material to widen
concrete, the separation layer) as described in the
existing shoulder. Treat 3 ft (0.9 m) area of
contract document.
shoulder with calcium chloride.
Prepare shoulder widening by trenching the existing
Construct separation layer (only for unbonded
shoulder and trimming to the specified width. The
overlay on concrete).
trench should be rolled and compacted as necessary

STAGE 2. Construct thickened shoulder and concrete overlay

Shift the traffic control to the left lane and close the Construct concrete overlay on the existing
right lane to traffic. The length of the closure will pavement. Complete right PCC shoulder
depend on the jurisdictions maximum closure length widening with the overlay.
with pilot car. Traffic controls and traffic control signals
The X dimension between the roadway
will be based on jurisdictional requirements.
centerline and vertical panel is for the paving
Repair and prepare the surface for the overlay or the machine track and stringline.
separation layer and subsequent overlay as described
in the contract documents. Construct separation layer
(for unbonded overlay).

STAGE 3. Construct left lane concrete overlay

Close the opposite lane to traffic and place the If the outside edge dropoffs at the shoulder
concrete overlay according to contract documents, exceeds the jurisdictional allowance for a 1:1
using the same procedures as described in stage 2. fillet, then construct the granular shoulders in
Stringline may not be necessary for the right edge of this stage.
the paving when the paved overlay constructed in
Complete shoulders. Install (mill) rumble strips
stage 2 is used as the paver control in this stage.
in the paved shoulders and complete pavement
marking and regulatory signing in accordance
with contract documents.

Figure 107. Overlay of two-lane roadway widening to three lanes with paved shoulder (conventional paver)

94 Guide to Concrete Overlays


Ch 6. WORK ZONES

Remaining LEGEND
Remaining shoulder
shoulder 4 ft (1.2 m) 12 ft (3.7 m) 12 ft (3.7 m) 12 ft (3.7 m) 4 ft (1.2 m)
(Typical) (Typical) (Typical) (Typical) (Typical) Stage work area

Pavement Concrete
marking Pavement Rumble
marking strip Base shoulder widening
Rumble materials
strip (e.g., cement-treated
base, porous concrete,
roller compacted con-
Tiebars optional crete (RCC), asphalt, or
Finished shoulder concrete)
Overlay
6 ft (1.8 m) min. placement Granular material
Separation layer
(only for unbonded overlay on concrete) Surface repair
Existing pavement
Existing subbase COMPLETED OVERLAY

NOTES:

Traffic
1 Follow jurisdictional
Construction area control requirements for traffic
device control devices.
Existing shoulder Vehicle traffic Existing shoulder 2 Use excavated granular
10 ft (3 m) 11 ft (3.4 m) material to widen existing
(Typical) (Typical) shoulder. Treat 3 ft (0.9
m) area of shoulder with
calcium chloride.
3 Minimum lane width
next to the paver may
Surface repair Existing pavement be reduced for short-
Subbase 6 ft (1.8 m) min. and overlay surface Existing subbase term, stationary work on
widening preparation low-volume, low-speed
Separation layer roadways when vehicular
(only for unbonded overlay on concrete) traffic does not include
longer and wider heavy
STAGE 1 commercial vehicles.
4 If the completed overlay in
Construction area this stage opens to traffic
and the final shoulder
4 ft (1.2 m) back fill is delayed,
4 ft Vehicle traffic 4 ft shoulder
(1.2 m) 11 ft (3.4 m) (1.2 m) 11 ft (3.4 m) 6 ft (1.8 m)
place fillet as shown. If
(Typical)
overlay creates a dropoff
(Typical) (Typical) (Typical) (Typical) (Typical) greater than jurisdictional
Traffic
allowance, place second
control lift before opening overlay
device to traffic.
5 See centerline fillet
illustration and
Concrete
Subbase subsequent removal on
Subbase widening
widening overlay placement figure 103.
Existing pavement Surface repair 6 Mark edgelines and
Separation layer centerlines per MUTCD
(only for unbonded overlay on concrete) (FHWA 2009) section 6F.77
STAGE 2
(mark both lanes).

Construction area
Remaining Remaining
shoulder shoulder
4 ft 6 ft 4 ft Vehicle traffic Paved shoulder
(1.2 m) (1.8 m) (1.2 m) 11 ft (3.4 m) 4 ft (1.2 m)

(Typical) (Typical)
12 ft (3.7 m)
(Typical) (Typical) (Typical)
Overlay of Two-
6
Traffic 6 Lane Roadway
control device
Widened to Three
Lanes with Paved
Separation layer
(only for unbonded
Concrete
overlay placement
Shoulders
Subbase
widening
overlay on concrete )
Existing pavement
Surface repair (Conventional
STAGE 3
Paver)

Guide to Concrete Overlays 95


Ch 6. WORK ZONES

COMPLETED OVERLAY (Four-Lane Roadway with Paved Shoulders, Conventional Paver)

Applied to:

Bonded concrete overlay of concrete pavements


Unbonded concrete overlay of concrete pavements
Bonded concrete overlay of asphalt pavements
Unbonded concrete overlay of asphalt pavements
Bonded concrete overlay of composite pavements
Unbonded concrete overlay of composite pavements

STAGE 1. Repair surface and prepare for overlay

Install traffic control and close the Repair the surface as appropriate.
inside lanes. Follow jurisdictional Prepare the surface for the overlay
requirements for traffic control. Check (or, in the case of concrete overlay
with jurisdiction regarding allowable on concrete, the separation layer) as Typically Typically
lane closure length. If surface repair described in the contract document. less than less than
0.25 mi 0.25 mi
and preparation for the overlay are
Evaluate the structural condition of (0.40 km) (0.40 km)
minimal, then slow-moving traffic without without
the existing shoulder. Mill existing
control may be appropriate. Closing pilot car pilot car
shoulder or reconstruct shoulder to
the lanes may require additional traffic
carry traffic load if necessary.
control (e.g., signals and flaggers).
Construct separation layer (only for
unbonded overlay on concrete).

STAGE 2. Construct concrete overlay on outside lane

Shift the traffic control to the inside Construct temporary shoulder for
lanes and close the outside lanes paver track.
to traffic. Traffic controls and traffic
Construct concrete overlay on the
control signals will be based on
existing pavement. Bull float work
jurisdictional requirements.
shall operate from the outside
Repair and prepare the surface for shoulder only.
the overlay or the separation layer
and subsequent overlay as described
in the contract documents. Construct
separation layer (for unbonded
overlay).

STAGE 3. Construct concrete overlay on inside lane

Shift the traffic control to the outside If the right stringline is not used,
lane and close the inside lane to the X dimension could possibly
traffic. Place the concrete overlay be reduced to 3 ft (0.9 m).
according to contract documents,
Complete shoulder finish
using the same procedures as
grading. Install (mill) rumble
described in stage 2. Stringline may
strips in the paved shoulders and
not be necessary for the right edge
complete pavement marking and
of the paving when the paved overlay
regulatory signing in accordance
constructed in stage 2 is used as the
with contract documents.
paver control in this stage.

Figure 108. Overlay of four-lane roadway with paved shoulders (conventional paver)

96 Guide to Concrete Overlays


Ch 6. WORK ZONES

LEGEND
10 ft (3 m)
Paved 12 ft (3.7 m) lane 12 ft (3.7 m) lane paved shoulder
shoulder varies Stage work area
(Typical) (Typical) (Typical)

Pavement Concrete
Pavement marking
marking
Rumble strip
Rumble Existing shoulder
strip
(Reconstructed
if necessary)

Concrete shoulder Concrete


Existing pavement shoulder
Concrete overlay NOTES:
12 ft (3.7 m) existing lane
Separation layer 1 Follow jurisdictional
(only for unbonded overlay on concrete) Existing subbase
requirements for traffic
COMPLETED OVERLAY control devices.
2 Evaluate the structural
condition of the existing
shoulder. If necessary,
12 ft (3.7 m) 10 ft (3 m) reconstruct shoulder with
vehicle traffic existing shoulder PCC or asphalt to carry
Construction area (Typical) (Typical) the traffic load.
6 ft (1.8 m) Traffic
(Typical)
Separation layer
control
3 See centerline fillet and
(for unbonded
overlay) device subsequent removal
illustration on figure 103.
4 When the existing
shoulder outside of the
Surface repair Existing pavement proposed paved shoulder
Existing and overlay surface Existing subbase is less than 3 ft (0.9 m),
shoulder preparation adjustment to the paver
may be necessary to
accommodate paver
STAGE 1 control and paver track.
5 If the completed overlay
Vehicle traffic Construction area in this stage opens to
traffic and the final
Remaining 11 ft (3.4 m)
shoulder (Typical)
shoulder backfill is
22 ft (6.7 m) delayed, place fillet as
(Typical) shown. If overlay creates
12 ft (3.7 m) 10 ft (3 m) a dropoff greater than
Traffic (Typical) (Typical) jurisdictional allowance,
control place second lift before
device
opening overlay to traffic.
6 For X less than 4 ft
(1.2 m), adjustments to
paver may be necessary
Concrete to accommodate paver
Separation layer overlay Concrete shoulder control and paver track.
(only for unbonded overlay on concrete) placement
7 The X dimension can
Surface repair be reduced to 3 ft (0.9 m)
Existing pavement STAGE 2 minimum when the right
lane is used as paver
control.
Construction area Vehicle traffic 8 Mark edgelines and
11 ft (3.4 m) centerlines per MUTCD
12 ft (3.7 m) (Typical) Remaining (FHWA 2009) section 6F.77
Temporary Varies (Typical) shoulder (mark both lanes).
concrete fillet
placed with Concrete 8 8
overlay overlay placement
Overlay of Four-
Lane Roadway
with Paved
Concrete shoulder
Existing pavement Varies Varies Shoulders
Separation layer
(only for unbonded
overlay on concrete)
(Conventional
STAGE 3
Paver)
Guide to Concrete Overlays 97
Ch 7. CONSTRUCTION

Chapter 7.

CONSTRUCTION OF CONCRETE OVERLAYS

Concrete overlays are constructed using con-


FAQ Is there anything different about constructing a concrete overlay?
ventional equipment and procedures. See
Appendix G for information about developing Typically, no; the same methods and equipment are used as in new concrete pavement
project and supplemental specifications and construction. There are, however, some considerations for placement during cooler periods
Appendix H for suggestions regarding owner- (spring and autumn). Under these conditions, the existing base and pavement will expand
contractor meetings. and contract with the daily change in ambient temperature. Cracking may occur if the
concrete mixture has not gained enough strength to withstand the stresses caused by differ-
Total construction time for concrete overlays ential movement between the underlying pavement structure and the new concrete overlay.
is significantly shorter than reconstruction Accelerating the rate of strength gain in the concrete mixture is the recommended way to
of a roadway because earthwork is limited mitigate the effects of differential movement due to changes in ambient temperature. There
to minor quantities. Resurfaced streets and are a number of methods that can be used to accomplish this; they may be used alone or, in
highways can be opened to traffic within short many cases, in combination:
periods of time with adequate planning, expe-
dited staging, and efficient operations. Heat the concrete to maintain a fresh concrete temperature of at least 75F.
Use a nonchloride accelerating admixture.
Cover the new overlay pavement with insulating blankets, burlap, and/or polyethylene
Key Points for sheeting.

Concrete Overlay When possible, reduce the quantity of supplementary cementitious materials in the mixture.

Construction
Normal concrete paving construction prac- HIPERPAV is a software tool available to Payment is typically based on two items:
tices can be used to complete concrete overlay predict stresses in concrete. It is especially square yards and cubic yards. The surface
projects as quickly and efficiently as any useful when there is a need for more infor- is measured to account for the square-yard
other paving method. Resurfaced streets and mation in less-than-desirable conditions, surface area, and batch tickets are collected to
highways can be opened to traffic within a such as inclement weather conditions, when account for the cubic-yard concrete volume,
short period of time with adequate planning, an overlay is particularly thin, or when a including variable depths.
expedited staging, and efficient operations. project does not have much flexibility in
See Table 21. scheduling.

Bonded Overlays Unbonded Overlays


Table 21. Concrete Paving Construction Practices for Overlays

Bonded Unbonded
Bonded Unbonded
Overlays of Overlays of
Construction Consideration Overlays of Overlays of
Asphalt or Asphalt or
Concrete Concrete
Composite Composite
1. Mixture Design
Aggregate:
Physically and chemically stable and durable X X X X
Well-graded mix X X X X
Match aggregate thermal properties with existing pavement X
Maximum aggregate size should be D/2.5 in relation to the new overlay thickness X X X X
Use conventional mixtures with Type I or II cement. X X X X
Use fly ash and slag to reduce permeability with w/cm ratio not to exceed 0.42. X X X X
Use water reducer to help maintain w/cm ratio and desired slump, as well as to increase strength. X X X X
If accelerated construction is desired, accomplish this through careful scheduling and diligent
execution; accelerated concrete mixtures should only be used in limited areas where early opening
X X X X
cannot be achieved through other means.

Fibers may be used to increase the toughness of concrete (measure of its energy-absorbing
capacity), improve resistance to deformation, hold concrete together in case of cracking, and serve as X X
an insurance policy that protects the surface from unseen base conditions.

Verification testing in the laboratory of nonstandard mixes (trial batches) and specifications of testing at
X X X X
temperatures representative of site conditions is encouraged to flag any mix problems.

Guide to Concrete Overlays 99


Ch 7. CONSTRUCTION

Bonded Overlays Unbonded Overlays


Table 21. Concrete Paving Construction Practices for Overlays, continued

Bonded Unbonded
Bonded Unbonded
Overlays of Overlays of
Construction Consideration Overlays of Overlays of
Asphalt or Asphalt or
Concrete Concrete
Composite Composite
2. Grade Control
Mill and
Centerline profile only (as-built) with uniform finished cross section X concrete
overlay
Little or no
Three-line profile (edges and centerline) when cross slope varies or surface distortions exist X Inlays only Inlays only
milling
Measure off existing pavement or top of milled surface to set stringline or form. Adjust individual points
X X X X
up to produce a smooth line.
Survey 100500ft (30.5152m) cross sections when shouldering, foreslopes, and backslopes need
adjusting. If the existing profile grade is irregular, additional centerline elevations may be necessary for X X
grade corrections in certain locations for smoothness.
Survey bridge tie-ins or bridge clearance conditions and extreme superelevations. X X X X
To prevent thicker asphalt separation layer and thus compaction, stability, and grade control issues, use
concrete to make up any 3in. (75mm) or greater variances in grade and a nominal 1in. (25mm) asphalt X
separation layer.
3. Preoverlay Repairs for Uniform Support
Minimal minor repairs of surface defects. Remove deteriorated area and replace with overlay. X
An engineer should observe final condition of subbase pavement prior to overlay construction. For
minimal isolated distress that causes some loss of structural integrity that cannot be overcome with X
milling, thicken the overlay in this area.
Replace isolated areas of subbase pavement when there is evidence of active movement. X X
Joint deterioration with little or no faulting can be bridged with the overlay. X
To widen the roadway, excavate the shoulder to allow for the widened thicker section to be placed with
X X X X
the overlay.
Fill cracks in the HMA with sand or flowable mortar when the crack width exceeds the maximum coarse
X X
aggregate size used in the concrete overlay mixture.
4. Surface Preparation
Surface roughness for bonding:
Shotblasting (even after milling) X
Milling to remove significant distortions or reduce high spots X X
Surface cleaning:
Sweeping followed by high-pressure airblasting
X X
(waterblasting may be needed to remove dirt tracked onto surface)
Surface sweeping only X X
Maintain a clean and dry surface. X X
Sprinkle (mist) the existing pavement when the surface temperature exceeds 120F; use
X X X X
compressed air to remove any standing water directly ahead of the concrete-placing operation
Place nominal 1in. (25mm) asphalt layer to separate concrete layers and prevent bonding.
When heavy truck traffic is anticipated, it is advisable to consider a drainable asphalt layer and X
drainage system.
If the existing asphalt surface of a composite pavement section remains intact, it can serve as a
X
separation layer.
5. Concrete Placement
When the surface temperature of the asphalt is at or above 120F (49C), surface watering can be used
to reduce the temperature and minimize the potential for shrinkage cracking. No standing water should X X X
remain at the time the overlay is placed.
The bonding of the overlay can be affected by the climatic conditions at the time of placement.
Significant stresses that develop due to rapid changes in temperature, humidity, and wind speed may
X X
reduce the bond strength under severe conditions. HIPERPAV can predict interface bond stress based
on numerous factors.
Feeding concrete consistently into the paver requires an adequate number of batch delivery trucks.
The number of trucks will often dictate the slipform or placement speed. The entire cycle of mixing,
discharging, traveling, and depositing concrete must be coordinated for the mixing plan capacity, X X X X
hauling distance, and spreader and paving machine capabilities. Extra trucks may be needed as the haul
time increases.
Do not track paste or dirt onto the existing surface ahead of the paver because it can cause bond
X X
failure.

100 Guide to Concrete Overlays


Ch 7. CONSTRUCTION

Bonded Overlays Unbonded Overlays


Table 21. Concrete Paving Construction Practices for Overlays, continued

Bonded Unbonded
Bonded Unbonded
Overlays of Overlays of
Construction Consideration Overlays of Overlays of
Asphalt or Asphalt or
Concrete Concrete
Composite Composite
The manner in which the crew deposits concrete in front of the paving operation is an important factor
for creating a smooth pavement surface in overlay projects. Placement in front of slipform paver should X X X X
be done in small overlapping piles so as to minimize lateral movements.
Properly established, secure, and maintained stringline is very important for smoothness; constant and
X X X X
continuous paving prevents interruptions that lead to bumps.
Tiebars may be appropriate in an open-ditch situation when constructing 3- to 6-ft (0.9- to 1.8-m)
widening units and overlay thickness is 5in. (125mm) or greater. Normally, tiebars are not used for lane X X
widening to prevent cracking from stresses due to differential expansion and contraction between lanes.
Dowel bar use should follow full-depth pavement requirements. Pavements less than 7inches thick
should not use load transfer dowels. When used for thicker pavements, they should be located
X X X
approximately in the mid-third of the overlay thickness. Isolated thicker sections should not dictate a
change in basket height or dowel bar insertion depth.
Texturing needs to be performed at the right time so as not to disturb setting of the concrete. Shallow
longitudinal tining or burlap/turf are two effective textures. Burlap/turf drag has shown adequate friction X X X X
with a quiet surface when hard sands are used in the mix.
6. Curing to Prevent Rapid Loss of Water from Concrete
Proper curing of bonded and thin unbonded overlays is particularly important because they are thin
with a large surface compared with the volume of concrete. The curing rate may be increased from the 1.52 times 1.52 times 1.52 times
2 times normal
normal rate to provide additional protection. Standard curing compound rates may be used for thicker normal normal normal
unbonded overlays.
During hot weather, steps should be taken to reduce the evaporation rate from the concrete. For
significant evaporation, provide a more effective curing application, such as fog spraying, or apply an X X X X
approved evaporation retarder.
Adequate curing of overlays on a stiff support system (especially on underlying concrete pavement) is
X X X X
important to minimize curling and warping stresses.
7. Joints
Joint spacing for concrete overlays requires special consideration for each type:
Joints are to be matched with underlying concrete to prevent reflective cracking. X
When feasible, it is a good policy to mismatch joints and/or cracks to maximize load transfer from
the underlying pavement. Some states that have not intentionally mismatched joints, however, X X
have not experienced any adverse effects.
Slab dimensions match the underlying pavement. X

The recommended joint pattern for bonded overlays of asphalt should not exceed 1.5 times the
X
overlay thickness in inches.
For overlays less than or equal to 6inches thick, the slab dimensions (in feet) should not exceed
X X
1.5 times the overlay thickness in inches (e.g., 4in. x 1.5ft/in. = 6ft).

For overlays greater than 6inches, the slab dimensions (in feet) should not exceed 2.0 times the
X X
overlay thickness in inches, not to exceed 15ft.

Because of the potential for higher curling and warping stress from a rigid underlying pavement,
X X
shorter than normal spacing is typical (see pages 40, 44, and 48).
Joint sawing:
The timing of sawing is critical. Sawing joints too early can cause excess raveling. HIPERPAV
may be useful in helping to predict the appropriate time window for joint sawing, based on the X X X X
concrete mix design, construction times, and environmental conditions.

Sawing must be completed before stresses exceed the strength developed. Sawing too late can
X X X X
lead to uncontrolled cracking.
Full depth +
Transverse joint saw-cut depth for conventional saws T/3 T/4 min.-T/3 max.
0.50in. (13mm)
Full depth + Not < 1.25in.
Transverse joint saw-cut depth for early-entry saws Not < 1.25in. (32mm)
0.50in. (13mm) (32mm)
Longitudinal joint saw-cut depth T/2 (at least) T/4 T/3 T/4 T/3
Transverse joint width must be equal to or greater than the underlying crack width at the bottom of
X
the existing transverse joint.
Sealing:

Seal joint using low-modulus hot-pour sealant with narrow joint. X * ** **

* Joint between overlay and curb and gutter should be sealed.


** Some states have experienced problems with asphalt stripping of the separation layer, particularly under heavy truck traffic and high speeds. Therefore, sealing is important
in these conditions. On lower speed roads without a heavy traffic loading, some states successfully do not seal.

Guide to Concrete Overlays 101


Ch 7. CONSTRUCTION

Bonded Overlays: FAQIf the mean texture depth of the existing pavement is in the recommended
Ensuring Proper range or higher, do I have to shotblast or mill the pavement?

Bond Yes; although the mean texture depth is a consideration, the shotblasting or milling is
necessary to remove laitance buildup from rubber, grease, and oil over many years of use.
When bonding a concrete overlay to an exist-
ing concrete surface, the necessity for a sound
bond cannot be overstated. Both theory and
with a thermal coefficient lower than that of loose material to ensure adequate bonding.
practice show that without this bond, the
the aggregates in the existing pavement. Cleaning may be accomplished by sweeping
overlay will develop secondary distress quickly,
the concrete surface, followed by cleaning
thus significantly compromising the life of Surface preparation of the existing concrete
in front of the paver with compressed air.
the pavement system. Research has attempted pavement is accomplished to produce a
Airblasting and waterblasting should be used
to measure and characterize bond strength roughened surface that will promote bond-
only as supplementary cleaning procedures to
during early ages of the concrete overlay. To ing between the two layers; see Figure 109. A
remove loose material from the surface after
date, however, no simple and reliable test has variety of surface preparation procedures may
shotblasting or milling. No visible moisture
been developed. As a result, bond strength is be used, including shotblasting and milling.
should remain on the pavement surface when
typically characterized using a surrogate test, A bonding grout or epoxy is not required.
the overlay is placed. Paving should com-
namely strength (compressive or flexural) of The most commonly used and most effective
mence soon after cleaning to minimize the
the overlay. The strength of the bond between surface preparation procedure is shotblasting.
chance of contamination.
the overlay and the existing concrete pave- Although milling will roughen the concrete
ment can be correlated with the flexural/ pavement surface, milling should not be used Vehicles should be limited on the existing
compressive strength of the overlay. If the solely for that purpose because of its poten- surface after it is prepared. If it is absolutely
recommended construction procedures have tial for causing surface microcracking and necessary to have vehicles on the existing
been performed correctly, and the early open- fracturing the exposed aggregate. If milling concrete, care should be taken that they do
ing strength criteria have been met, then the is used to lower the pavement elevation, any not drip oil or other contaminants that could
bond strength should also be adequate to resulting microcracking should be removed compromise the bond. When the surface
allow the pavement to be open without bond by shotblasting. temperature of the concrete is at or above
failure, provided that care has been taken to 120F (49C), water misting can be used to
prepare the existing pavement surface properly In some cases, a surface roughness or mean
reduce the temperature and minimize the
and the overlay has been adequately cured. texture depth is specified. The sand patch test
chance of shrinkage cracking. Water stand-
(ASTM C 965) is often used to measure and
ing on the surface should be blown off with
Several elements (beyond those common to verify the mean texture depth. Typically, a
compressed air.
a typical concrete pavement) are particularly mean texture depth in the range of 0.040.08
important in ensuring a good bond between in. (0.92.0 mm) is deemed adequate for Curing also can have a pronounced impact
the concrete overlay and the underlying con- proper bond development. on concrete overlay bond. The diligent and
crete pavement. There are issues related to thorough application of a curing compound
the concrete mixture, joint spacing, surface Following surface preparation, the surface
(sometimes at twice the normal applica-
preparation and cleaning, curing, sawing, should be thoroughly cleaned to remove all
tion rate) is an effective method to control
and strength measurement. While several of
these factors are currently considered in con-
ventional concrete paving, specific emphasis
should be placed on certain key factors of
these elements, since bonded concrete over-
lays are particularly sensitive to volumetric
changes.
Concrete mixtures used in bonded concrete
overlays should shrink as little as possible and
have similar thermal properties, or CTE (see
page52 for more information). This typi-
cally means optimizing the cement content
to minimize shrinkage while maintaining an
adequate strength. Another mixture-related
consideration is aggregate gradation (which
helps in reducing cement factors without
sacrificing strength), as well as aggregate
type. To help minimize the thermal strains
and stresses experienced at the bond line of
bonded overlays over concrete, the overlay
should have aggregate thermal properties simi-
lar to the aggregate in the underlying concrete
pavement. If local aggregate sources make Figure 109. Compare the surface texture of the nonshotblasted area (upper left half
matching the thermal coefficient difficult, an of image) to the roughened surface texture on the shotblasted section of pavement
effort should be made to use only aggregates (under the pen) (source: Leif Wathne, ACPA)

102 Guide to Concrete Overlays


Ch 7. CONSTRUCTION

moisture loss and thus lower shrinkage and Both pervious (geotextile fabric or open- Roll the material onto the base or other sur-
early-age cracking potentials. This is particu- graded asphalt) and impervious (densely face, keeping the nonwoven geotextile tight
larly true for thin bonded overlays. More graded HMA) types of separation layers must with no wrinkles or folds.
extreme measures, such as wet or blanket drain at the pavement edges or risk trapping
Roll out sections of the material in a
curing, can help to minimize the risks of poor water, which can be very damaging. The layer
sequence that will facilitate good over-
performance when proper curing compound can either be daylighted at the edges (allowing
lapping, prevent folding or tearing by
application is either difficult or doubtful. the egress of water) or terminate in a subdrain
construction traffic, and minimize the
These types of more extreme curing regimes or other layer (allowing the water to flow
potential that the material will be disturbed
are typically only applicable for short paving away from the pavement structure).
by the paver.
sections such as intersection rehabilitation.
In general, the following construction prac-
Overlap sections of the nonwoven geotex-
Good construction sawing practices can also tices have resulted in successful installations of
tile material a minimum of 6 inches and a
greatly reduce early pavement stresses and geotextile separation layers:
maximum of 10 inches, and ensure that no
help accommodate early opening to traffic.
Place the material as shortly before paving more than three layers overlap at any point;
As mentioned elsewhere in this document,
as possible (ideally no longer than 2 to 3 see Figure 110.
sawing the transverse joints in the new over-
days) to reduce the potential for it to be
lay full depth plus 0.5 inch, exactly over the Ensure that the edge of the material along
damaged.
joints in the existing pavement, is absolutely drainage areas extends at least 4 inches
critical for proper bonding. There have been Before placing the nonwoven geotextile beyond the pavement edge and terminates
examples of early bonded concrete overlay material, these actions should be taken: above, within, or adjacent to the pavement
failures due to debonding as a result of not drainage system.
Repair the existing pavement to correct
sawing the joints completely through the any significant cracking.
depth of the overlay or failing to match the Secure the material with pins (nails)
location of the underlying joint. The width When faulting greater than 0.25 inch (or punched through 2.0- to 2.75-inch diam-
of the initial saw cut in the overlay should as specified by the engineer) is present, it eter galvanized discs placed 6 feet apart or
be equal to or greater than the width of the may be reduced by milling. less, depending on conditions; see Figure
cracks under transverse joints in the existing 111.
Sweep the pavement surface clean.
pavement; see Figure 48 on page 58.
When all of these factors have been properly
considered and executed during construction,
the overlay strength can be used to character- Figure 110. Overlap
ize the bond with some confidence. Strength of nonwoven
monitoring of the overlay concrete can be geotextile material
done in a fashion similar to that of conven- section
tional concrete paving. Maturity methods
for early-age strength prediction (ASTM C
1074) can be particularly helpful. If all recom-
mended construction procedures are followed,
and knowing that bond strength correlates
reasonably well with concrete strength, early
opening decisions can be made relatively reli-
ably, in-place, and in a timely fashion.

Unbonded Overlays:
Installation Figure 111.

of Geotextile Fastening
nonwoven
Interlayer Fabric geotextile fabric to
existing concrete
If an unbonded overlay is being constructed, pavement
an asphalt or geotextile fabric separation layer
must be placed before the overlay is placed.
Geotextile separation layers require some spe-
cial installation practices.
Before placing the geotextile, the surface of
the existing pavement should be swept clean
of loose material with either a mechanical
sweeper or an air blower. Then conventional
placement practices and procedures should be
followed for placing the separation layer.

Guide to Concrete Overlays 103


Ch 7. CONSTRUCTION

A limited number of projects have used an


adhesive for securing the geotextile to the Placing Dowel There are several recommendations for
securely anchoring baskets and monitoring
existing pavement; for more information, Baskets their placement:
see 3M (2013).
If dowel baskets are included in the overlay Shipping wires should be left intact, unless
Construction traffic on the geotextile design, good construction practices should be a MIT SCAN2 is used for dowel place-
should be limited to only that necessary to followed. Anchoring dowel baskets securely to ment verification.
facilitate concrete paving; see Figures 112 the existing pavement is essential to provid-
and 113. If construction traffic is placed on Use six anchors per basket for existing con-
ing the intended load transfer at contraction
the geotextile, precautions should be taken crete surfaces.
joints. Movement of the dowel baskets has
to mitigate tears and wrinkles in the fabric: been observed on some concrete overlay proj- Use eight anchors per basket for existing
Leave temporary gaps in the geotextile ects. This movement has been attributed to a asphalt and composite surfaces.
where trucks are crossing and making number of factors:
Place an equal number of anchors on both
sharp turns. Variable thickness asphalt separation layers sides (paver side and downstream) of the
Minimize sharp turns and heavy braking, require different length nails and differ- baskets; see Figure 113.
which can cause tearing and wrinkling. ent velocity shots as the asphalt thickness
changes across the pavement width. Place the nails on the downstream side of
Reduce the travel speed of construction the basket; see Figure 114.
traffic. Newly placed, fine-graded asphalt mixtures
provide less friction than a milled surface Avoid excessive loading from the concrete
or existing concrete; reduced friction can head in front of the paver.
cause the dowel baskets to move as the con- Dowel placement should be periodically man-
crete head in front of the paver slides along ually verified after the paver has passed over
the surface of the separation layer instead of the baskets; see Figure 115. Suspend paving
rolling as the paver moves forward. if the baskets are moving during the paving
Excessive concrete head in front of the operation until a plan for securely anchoring
paver can move the dowel baskets. the baskets is approved. There are numerous

Figure 112. Paving on top of nonwoven


geotextile materials

Paving Direction

Figure 114. Dowel basket anchor nails should be placed on the downstream side of the
basket relative to the direction of pavement

Figure 113. Paving on top of white geotextile


fabric interlayer (source: Larry Engbrecht,
South Dakota chapter, ACPA)

Figure 115. Manually verifying dowel placement

104 Guide to Concrete Overlays


Ch 7. CONSTRUCTION

methods available for checking the placement


of dowels once the concrete has hardened (MIT
Sawing Joints queues shall not exceed 10 minutes, etc.).
Given the requirements for maintenance of
SCAN-2, MIT SCANT2, ground-penetrating Particular attention should be paid to the traffic, the contractor should be given the
radar, coring, etc.). Although the precision of number of saws required to saw the joints responsibility to stage and prosecute the
these methods varies, it is recommended that before cracking occurs. Most overlay projects project to meet the objectives for accelerated
dowel placement be verified through some will require both earlier sawing and more construction and maintenance of traffic.
means. saws to accomplish this. Concrete overlay
placement rates can easily be limited by the Accelerated construction often uses con-
number of saws available; proper planning ventional concrete pavement materials
and procedures, but key changes can sig-
Curing Concrete is necessary to assure that production is not
adversely impacted by the capability to effec- nificantly expedite projects; see Appendix
Overlays tively saw the joints before cracking can occur. I. These changes add flexibility for the
contractor. They often involve contract
There are a number of factors that contribute
While curing is critical (yet often overlooked) incentives, modifying pavement equipment
to the need for earlier sawing and an increased
for all concrete pavements, it requires particular for minimum to zero clearance, materials
number of saws:
attention for overlays less than 8 inches thick. proportioning modifications, accelerated
The ratio of surface area to volume is greater for Stiffer underlying layers increase internal curing methods, construction staging,
thinner overlays than that of typical concrete stresses in the early-age concrete. changes to pavement joint construction,
pavements, thus the same rate of evaporation and revisions to opening criteria.
will have greater detrimental effects on thinner The ratio of lineal feet of joints to square
overlays if not properly cured. Excessive drying yards of paving is typically higher for con- Road user costs should be evaluated when
shrinkage caused by late and/or inadequate cur- crete overlays; thinner overlays can have determining the type of rehabilitation that is
ing can lead to reduced bond strengths due to significantly more (three to four times) to be implemented. When deciding if accel-
moisture warping within the concrete overlay. lineal feet of joint per square yard of paving erated construction is to be implemented,
There are two primary issues to consider regard- than conventional concrete paving. it is important that there is a benefit to be
ing curing of concrete overlays: gained such as reducing road user costs
Paving production (square yards per hour)
and delays. The implementation of acceler-
1. TimingThe curing compound must be is higher for thinner concrete overlays.
ated construction techniques on concrete
applied before any surface evaporation Thinner overlay sections have a higher ratio overlays is based on project and user needs.
occurs. of surface area to volume. This can lead to The techniques may be used on critical
faster strength gain due to solar radiation parts of a project (such as intersections and
2. MaterialsA good quality curing
and also makes the sections more sensitive crossovers), the final segment, or the entire
compound should be used; some state
to drops in ambient temperature, which project.
DOTs have had good success with alpha-
methyl-styrene curing compounds, but at can increase the risk of random cracking
Typically, standard mixtures used in con-
additional material cost (see page 80 for unless the joint sawing operation is timely.
junction with accelerated construction
more information). techniques are capable of meeting project
accelerated opening requirements. In some
Evaporation retardant should be on hand and
available for use as emergency protection when
Accelerated critical areas, accelerated concrete mixtures
the curing operation is delayed. Evaporation Construction are used for concrete overlays. AppendixI
outlines a variety of details for planning,
retardant should not be used as a finishing aid,
Road improvements not only have direct designing, and constructing concrete over-
but applied when necessary after all finishing
construction costs, but they also have indirect lays in an accelerated process. Not all items
operations are completed. A typical coverage
time-related costs. Construction delays and listed are needed for every accelerated over-
rate for thinner overlays (less than 7 inches) is
road closings are generally not well accepted lay project. The following topics, however,
100 square feet per gallon, applied in two coats.
by the road users. One of the significant should be considered for most projects:
This heavier coverage of curing compound
benefits of accelerated concrete overlay con-
can cause difficulty in sawing on steep hills, Staging and maintenance of traffic
struction is decreasing total construction time,
especially when lighter early entry saws are uti-
which in turn reduces road user costs and Public relationscoordinating with adja-
lized, where there is a tendency for the saws to
increases driver safety. In addition, concrete cent businesses and residents to optimize
slip on the curing compound. When this is an
overlays offer confidence that the improve- access and constructibility
issue, the second coat of curing compound can
ments will provide a long-life pavement.
be applied after the initial saw cuts have been Implementing the use of time-related
made. One of the main goals during accelerated incentives and disincentives to encour-
overlay construction is to maintain successful age concurrent scheduling and timely
Differential temperature and moisture values
traffic management throughout the duration completion
throughout the slab can result in early-age curl-
of the project. Acceleration should begin in
ing and warping stress. When these stresses are Concrete mixtureusing accelerated
the design phase with analysis of alterna-
added under certain conditions to early-age mixtures only where critical
tive maintenance of traffic schemes, advance
loading stress, cracking can occur. This can
planning, and tailoring of project details to Accelerated curing through the use of
be mitigated through proper curing and saw-
facilitate shortened construction durations. insulating blankets
ing techniques. Large variations in ambient
The plans and specifications should provide
temperature and relative humidity at the time Maturity methods for early opening
the contractor with clear criteria for mainte-
of overlay placement can contribute to these
nance of traffic requirements (e.g., two lanes
stresses. When feasible, the overlay placement
open in each direction at all times, pilot car
should be scheduled around these conditions.

Guide to Concrete Overlays 105


Ch 7. CONSTRUCTION

Opening Overlay to FAQWhen can I open a bonded overlay to traffic so that the loading will not com-
Traffic promise the bond?

Guidance on concrete strength require- The answer is related to minimum concrete strength and not an arbitrarily selected time
ments for opening concrete roadways to from placement. Concrete opening strength (compressive or flexural) directly relates to
traffic is readily available. For example, concretes load-carrying capacity and provides an indication of the bond strength.
the Flexural Strength Criteria for Opening
Concrete Roadways to Traffic, as published
by the Transportation Research Board (Cole
and Okamoto 1995), bases its opening flex- of fatigue damage. Many states use flexural Bonded on Asphalt
ural strengths on thickness, k-values, and strength (modulus of rupture) for concrete
estimated ESALs, whereas the FHWA and Bonded concrete overlays on asphalt have one
opening strength criteria, and others use distinct advantage over bonded concrete over-
ACPAs Traffic Management Handbook (2000) compressive strength. The following equation
is based on thickness, foundation support, lays on concrete. The concrete panels can be
is sometimes used to convert compressive cut into small squares or rectangles in order
and the number of ESALs between the time strength to third-point flexural strength,
of opening and the time concrete reaches to reduce the curling and warping stresses and
although it is widely recognized that this rela- the expansion and contraction of concrete at
strength. Other methods are available (FHWA tionship is mixture dependent:
1994) and depend on the type of traffic, early the bond interface because there are no joints
loading locations on the slab, pavement thick- that need to be matched in the underlying
MR = ( )0.667 psi pavement. The result is a reduction in shear
ness, and subbase support.
where at the bond interface. This technique has
been successfully used for a number of years.
Minimizing Early Loading MR = flexural strength Overlays over asphalt, however, are typically
Fatigue Damage (modulus of rupture), psi relatively thin and are therefore susceptible
The fatigue life of concrete pavement is to excessive temperature-related stresses,
f'c = concrete compressive strength, psi
sensitive to early wheel loading. A fatigue- particularly when the existing asphalt is hot
consumption approach (Okamoto, et al. from solar heating. If accelerated methods are
Note: This empirical equation was developed used, extreme care must be taken to mini-
1994) theorizes that concrete pavement has a
using data from four different studies, con- mize shrinkage cracking through diligent
finite life and can withstand some maximum
ducted between 1928 and 1965 (Raphael and thorough curing (sometimes at double
number of load repetitions, N, of a given traf-
1984). Also, the equation is contained in the ordinary rate of curing compound, or,
fic loading before fracture. Every individual
reports from ACI Committee 330 (2008). in short sections, wet curing and/or blankets
traffic loading applied decreases the life of the
pavement by an amount proportional to the Since early-age strength can change rapidly may be necessary). Some states have incorpo-
load. This damage value provides the percent- in a short time, and since some agencies use rated fibers to increase the toughness of the
age of life that is consumed by the actual a variation of the above referenced equation, concrete as well as to improve its resistance to
number of traffic loads up to a given point it is recommended that each agency develop cracking.
in time. It is important to avoid decreases its own relationship between the compressive Determining a reasonable value for opening
in fatigue life caused by heavy early loadings strength and flexural strength (modulus of bond strengths for these types of overlays may
until the concrete has reached 3,000 psi. rupture) for the mixture they intend to use. prove difficult, as described above. Typically,
Certain techniques can be employed to con- As described earlier, nondestructive tests such a value for opening strength of the concrete
trol early loading that reduces fatigue damage as maturity can be used to determine opening of 420 psi (2.9 MPa) flexural (2,500 psi [17.2
until the concrete strength can accommodate strength since it provides real-time results. MPa] compressive) to 480 psi (3.3 MPa) flex-
normal traffic loadings. ural (3,000 psi [20.7 MPa] compressive) has
One of the most important techniques is Strength Criteria for proven adequate. An additional consideration
for accelerated construction is to encour-
restricting wheel loads to no closer than 34 Opening Bonded Overlay age bond via milling of the existing asphalt
ft (0.91.2 m) from the edge of the pavement
(and ideally 6 ft [1.8 m]) to minimize stress.
Systems surface. If shear failures do occur, they will
Research has shown that allowing only inte- Strength criteria for bonded overlay systems likely occur in the asphalt since concrete shear
rior early slab loadings greatly reduces fatigue depend on whether an overlay is placed on strength is greater than asphalt shear strength.
damage (FHWA 1994). Traffic cones are an concrete or on asphalt.
effective way of restricting construction traffic Strength Criteria for
along the pavement edges until the pavement Bonded on Concrete
reaches the desired full opening strength. In
Opening Unbonded
If proper surface treatment, curing, and
addition to restricting early edge loadings, the sawing are employed in the construction of Overlay Systems
use of higher modulus of subgrade reaction, k, concrete overlays, the bond strength at the Because unbonded overlays are essentially a
can help minimize early-age stress. With con- time of opening should be adequate if 540 psi concrete pavement on a high-quality subbase,
crete unbonded overlays, this is a particular (3.7 MPa) flexural or 3,600 psi (24.8 MPa) it is appropriate and somewhat conserva-
plus, since the underlying pavement provides compressive strength is achieved. As a rule tive to use opening strength criteria that are
a high level of base support. of thumb for bonded concrete overlays, the commonly used for conventional paving. For
bond tensile strength may be on the order of example, a minimum flexural strength (3rd
Strength Conversions 2 to 10 percent of the compressive strength, point) of approximately 340 psi (2.3 MPa) or
and the bond shear strength approximately 4 1,800 psi (12.4 MPa) compressive strength
The modulus of rupture, or flexural strength,
to 20 percent of the compressive strength. can be used for noninterstate traffic. The state
is an important parameter in the estimate
of Georgia for example, uses a concrete open-

106 Guide to Concrete Overlays


Ch 7. CONSTRUCTION

ing compressive strength criteria of 1,400 psi Repairs of Bonded or placed in a separate layer or poured mono-
(9.7 MPa) compressive strength, anticipating lithically with the overlay. Asphalt should not
that the approved mixture reaches 2,500 psi Thin Unbonded Concrete be used as a patching material because con-
(17.2 MPa) in 24 hours and 3,500 psi (24.1 Overlays crete does not bond well with new asphalt.
MPa) in 3 days. Full-depth panel replacement rather than Replacing an overlay panel(s) is easily accom-
partial-depth panel replacement is typical for plished using typical overlay procedures and
bonded and thin unbonded overlays, because materials; see Figure 117.
Repairs of Concrete the panels are small and relatively thin. After Thin concrete overlays at the end of their
full-depth sawing of the panel perimeter, the
Overlays panel can be removed easily by jack hammers
service life can be milled and refilled easily;
see Figures 118 and 119. Removal by mill-
Concrete overlays can be expected to provide or a backhoe; see Figure 116. ing (also referred to as carbide milling, cold
excellent performance and long life. Their per- When the overlay has been removed, the planning, and rotomilling) is a good option
formance is directly related to the uniformity existing base should be examined. If the old for concrete overlays, because they rely on
and quality of the existing pavement base. existing pavement is determined to be defi- the existing pavement base for load transfer
Isolated weak or thin spots in the existing cient, it should be removed and replaced with and therefore do not typically require steel
pavement may not be discovered during the concrete; the pavement replacement may be reinforcement.
pavement evaluation, overlay design, or over-
lay construction phases, and, like all pavement
systems, some repairs may be necessary during
its service life. If a bonded or unbonded over-
lay panel becomes distressed, overlay repairs
are relatively straightforward and, in many
cases, easier to perform than repairs of con-
ventional concrete pavements.

Figure 118. Typical concrete pavement milling operation (source:


Randell Riley, Illinois chapter, ACPA)

Figure 116. Removing overlay panels (source: Randell Riley, Illinois


chapter, ACPA)

Figure 117. Finish and cure of concrete overlay repair (source: Dan Figure 119. Typical concrete pavement milling operation (source: Dan
DeGraaf, Michigan Concrete Paving Association) DeGraaf, Michigan Concrete Paving Association)

Guide to Concrete Overlays 107


Ch 7. CONSTRUCTION

Generally, the productivity of milling concrete Milling can be performed under wet or dry Repairs of Full-Depth
is very good, depending on aggregate hard- conditions. The milling depth can be feath-
ness, bit configuration, and removal depth. For ered into adjacent pavements. Milling can Unbonded Concrete
example, removal of a concrete overlay at a 2-in. be completed on specific selected sections. Overlays
(50-mm) depth has been reported as high as The coarseness of the surface after milling Full-depth unbonded overlays typically are
8,000 ft2/hr (720 m2/hr) and for a 4-in. (100- and the fineness of the millings can vary constructed with dowel basket and lane ties,
mm) depth, as low as 2,700 ft2/hr (243 m2/hr). based on the type and spacing of milling so common concrete pavement repair tech-
teeth on the drum; see Figure 120. niques are used. These include partial- or
The method of removal is similar to that used
for asphalt layers, particularly when there are no full-depth repairs, diamond grinding, and
steel tiebars in the overlay. joint resealing. With thicker overlays (8 in.
[200 mm]) subject to heavy traffic, load trans-
fer restoration can also be applied to restore
load transfer and mitigate joint problems.
When a uniform separation course is used,
overlay thickness will likely vary, especially
where superelevation changes are encountered;
repairs made in these areas may require provi-
sions to account for additional saw-cut depth.
Standard full-depth concrete removal tech-
niques are used on thicker overlays. Eight- to
nine-inch (200- to 250-mm) concrete overlays
have been successfully removed by milling.

Figure 120. Typical concrete pavement millings from milling operation (source: Dan DeGraaf,
Michigan Concrete Paving Association)

108 Guide to Concrete Overlays


APPENDICES

APPENDIX A.

EVALUATION AND SELECTION TABLES

Tables 22 and 23 are tools for evaluating the conditions of concrete pavements and asphalt/composite pavements, respectively.

Table 22. Distress Types and Severity Levels Recommended for Assessing Concrete Pavement Structural Adequacy

Highway Current Distress Level


Load-Related Distress Classification Adequate Marginal Inadequate
Interstate/Freeway <5 5 to 10 > 10
Jointed plain concrete medium- and high-
severity transverse and longitudinal cracks and Primary <8 8 to 15 > 15
corner breaks (% slabs)
Secondary < 10 10 to 20 > 20
Interstate/Freeway < 15 15 to 40 > 40
Jointed reinforced concrete medium- and high-
severity transverse cracks and corner breaks (#/ Primary < 20 20 to 50 > 50
lane-miles)
Secondary < 25 25 to 60 > 60
Interstate/Freeway < 0.10 (2.5mm) 0.100.15 (2.53.8mm) > 0.15 (3.8mm)
Jointed plain concrete mean transverse joint/
Primary < 0.125 (3.2mm) 0.130.20 (3.35.1mm) > 0.20 (5.1mm)
crack faulting (in.)
Secondary < 0.15 (3.8mm) 0.150.30 (3.87.6mm) > 0.30 (7.6mm)
Interstate/Freeway < 0.15 (3.8mm) 0.150.30 (3.87.6mm) > 0.30 (7.6mm)
Jointed reinforced concrete mean transverse
Primary < 0.175 (4.5mm) 0.180.35 (4.68.9mm) > 0.35 (8.9mm)
joint/crack faulting (in.)
Secondary < 0.20 (5.1mm) 0.200.40 (5.110.2 mm) > 0.40 (10.2mm)
Interstate/Freeway <5 5 to 10 > 10
Continuously reinforced concrete
medium- and high-severity punchouts Primary <8 8 to 15 > 15
(#/lane-miles)
Secondary < 10 10 to 20 > 20
Applicability of Bonded Concrete Overlays
Applicability of Unbonded Concrete Overlays

Guide to Concrete Overlays 109


APPENDICES

Table 23. Distress Types and Levels Recommended for Assessing Asphalt and Composite Pavement Structural Adequacy

Highway Distress Level


Distress Type Classification Adequate Marginal Inadequate
Interstate/Freeway <5 5 to 20 > 20

Fatigue cracking (% of wheel path area) Primary < 10 10 to 45 > 45

Secondary < 10 10 to 45 > 45

Interstate/Freeway < 265 (50.2m/km) 2651060 (50.2200.8m/km) > 1060 (200.8m/km)

Longitudinal cracking in wheel path (ft/mi) Primary < 530 (100.4m/km) 5302650 (100.4501.9m/km) > 2650 (501.9m/km)

Secondary < 530 (100.4m/km) 5302650 (100.4501.9m/km) > 2650 (501.9m/km)

Interstate/Freeway < 0.50 (12.7mm) 0.250.50 (6.412.7mm) > 0.50 (12.7mm)


Composite pavement reflection cracking crack
Primary < 0.50 (12.7mm) 0.500.75 (12.719.1mm) > 0.75 (19.1mm)
width (in.)
Secondary < 0.50 (12.7mm) 0.500.75 (12.719.1mm) > 0.75 (19.1mm)
Interstate/Freeway > 200 (61.0m) 100200 (30.561.0m) < 100 (30.5m)
Transverse crack spacing (ft) Primary > 120 (36.6m) 60120 (18.336.6m) < 60 (18.3m)
Secondary > 120 (36.6m) 60120 (18.336.6m) < 60 (18.3m)
Interstate/Freeway < 0.25 (6.4mm) 0.250.40 (6.410.2mm) > 0.40 (10.2mm)

Mean depth of rutting in both wheel paths (in.) Primary < 0.35 (8.9mm) 0.350.60 (8.915.2mm) > 0.60 (15.2mm)

Secondary < 0.40 (10.2mm) 0.400.80 (10.220.3mm) > 0.80 (20.3mm)

Interstate/Freeway None 1 to 10 > 10


Shoving (% of wheel path area) Primary < 10 10 to 20 > 20
Secondary < 20 20 to 45 > 45
Applicability of Bonded Concrete Overlays
Applicability of Unbonded Concrete Overlays

Installation cost is on the order of $0.50 per yd2 (circa 2008)

110 Guide to Concrete Overlays


APPENDICES

APPENDIX B.

RECONSTRUCTION OPTIONS FOR CONCRETE

Should the existing asphalt or concrete of a quality material for unbound or stabilized from the fines and CH, clogging pipes, and
composite pavement section or plain concrete applications such as bases when compared other elements of the drainage system.
pavement have major deficiencies that cannot to conventional new aggregate. An RCA has
Effluent from drainable bases containing RCA
be overcome with preservation techniques rougher surface texture, higher shear strength,
can have pH values greater than 7.0 due to
(i.e., concrete overlays), the existing pavement higher rutting resistance, and higher resilient
the leaching of CH. This has not been found
can be recycled in place to serve as a granu- modulus (Van Dam et al. 2012). These excep-
to be problematic in ecosystems. Although
lar base. The two acceptable methods are as tional qualities allow for unrestricted use of an
effluent from an RCA drainable base can have
follows: RCA as a base material up to and including
increased pH, especially during the first flush-
100 percent substitution of new aggregate.
1. Recycled concrete aggregate (RCA) as base ing cycle of water, it has no buffering capacity
material (preferred option) It is generally accepted that after unbound and is equivalent to adding lime to stabilize
RCA base is compacted, its strength and the effect of acid rain on a lawn. In stagnant
2. Rubblization of concrete pavement (only
stiffness increase. A misinterpretation of this flow conditions, the leachate could reach a
used under certain conditions if severe
phenomenon is that this is due to hydration pH as high as 12.4; however, this will quickly
MRD [ASR or D-cracking] exists or the
of unhydrated concrete contained within dissipate as the leachate encounters soils and
concrete pavement has failure due to unsta-
the paste portion of the RCA. Instead, the organic materials commonly present in soils
bilized open graded base)
increased stiffness is credited to the carbon- (Van Dam et al. 2012).
ation of very soluble calcium hydroxide
Pavements with an MRD such as ASR,
(CH) released by the RCA in the presence of
In-place Recycled moisture, which is constantly available in the
D-cracking, or freeze-thaw distress have been
effectively used as unbound base material.
Concrete as a subsurface base.
Before using these materials, however, it is
When using RCA as a drainable base, cer- recommended that testing be performed
Processed Base tain contained design conditions must be to determine the severity of the ASR in
Material considered. The mortar fraction of the RCA
contains CH as a by-product of concrete
accordance with the FHWAs Report on
the Diagnosis, Prognosis, and Mitigation of
Recycling concrete pavements into an RCA is hydration, which, when in the presence of Alkali-Silica Reaction (ASR) in Transportation
a viable alternative for unbound base course water, goes into solution. This solution can Structures (FHWA 2010).
construction. To be successfully utilized, recy- react with atmospheric carbon dioxide and
cled concrete must be viewed as a source of form a solid material called tufa (leachate),
aggregate with characteristics and value equiv-
alent to the aggregate material it replaces ton
which, in the presence of fines, can reduce the
flow in improperly designed drainage systems
Rubblization of
for ton; see Figure 121. The quality of RCA
concrete depends on the amount of mortar
using RCA. Conditions that lead to this are Concrete Pavement
easily prevented in drainable bases (Wade et
that remains attached to the original aggre- Rubblization is a technique that was devel-
al. 1995). A proper design places all RCA
gate. If processing is such that little mortar oped to minimize reflective cracking in HMA
above the water table, below the elevation of
remains and no fines smaller than #4 sieve are overlays. The intent of this technique is to
the inlet of the drainage system, and, if geo-
used, the properties of the RCA will be simi- reduce the existing concrete pavement into
textiles are used, the flow must be parallel to
lar to the properties of the original aggregate. small sections to prevent reflecting into the
the geotextile and not through it. Improper
An RCA, as a rule, is considered a high- HMA overlay; see Figure 122.
design will result in the formation of tufa

Figure 121. Recycled concrete aggregate (source: Jonathan Gene Pitre, Figure 122. Rubblized concrete pavement (source: Todd Hanson,
University of New Hampshire) Iowa DOT)

Guide to Concrete Overlays 111


APPENDICES

Rubblization effectively destroys the existing when the existing pavement is sitting on a concrete. Some of the reinforcement may
pavement structural condition and reduces stable subgrade. The rubblization operation surface during the rubblization opera-
the support for the overlay to the least com- must not be allowed to destroy the integrity tion, and steps should be taken to remove
mon denominator. It results in the loss of the of the support layers below the pavement. exposed reinforcement.
existing pavements structural carrying capac- When base is soft, the rubblization process
An aggregate choke stone layer is required
ity, and thus requires a thicker, more costly under certain conditions can drive concrete
to fill voids and minimize the potential for
overlay. pieces into the subgrade, forcing water
pavement quantity overruns.
upward and reducing subgrade stability.
Rubblization may serve as a base for an
Soft and yielding subgrade conditions result
unbonded concrete overlay when the exist-
in incomplete and nonuniform rubbliza-
ing concrete slab exhibits fast-acting material
distress problems such as ASR, D-cracking, or
tion. Moisture/water present under the Crack and Seat (Not
freeze-thaw damage. These material problems
existing pavement may create a condition
that prevents the rubblized concrete par-
Recommended)
cause the concrete pavement to deteriorate Crack and seat should be limited to isolated
ticles from seating and locking together.
and lose structural integrity. Before these locations like tented panels. It results in a
The ability of a particular pavement to
pavements are rubblized, however, they nonuniform support condition when applied
withstand rubblization and retain its drain-
should be tested in accordance with the refer- over large areas, and this can be problematic
age and support functions is typically
enced FHWA criteria. for both HMA and concrete overlays.
not known until the pavement is actually
The conditions for rubblization to be consid- rubblized.
Crack and seat concrete does not serve well
ered for a base for an unbonded overlay are as a subbase for either concrete or asphalt
Prior to rubblization, all HMA surfacing
concrete pavements that have failed due to because it has no gradation or density con-
and joint filler material must be removed.
unstabilized open graded bases. Many of these trol. During the crack and seat operation, the
pavements have migration of the subgrade Underdrains should be installed prior to wire mesh must be severed or the crack that
material into the open graded base layer, rubblizing the pavement. is tied by mesh may cause reflecting cracking
creating voids and differential support condi- into the concrete overlay. The choke stone
Care must be taken not to damage utilities
tions. This differential settlement of the open and crack and seat material must be drained
or underdrains with minimal cover.
graded layer results in failed support condi- to prevent trapped water. Subgrade support
tions and ultimately mid-panel cracks, corner Rubblization must shatter the existing con- influences the size of the cracked pieces.
cracks, and significant faulting. crete for the full depth of the pavement. A Presence of water in the subgrade will cause
testing protocol should be established to loss of subgrade support, which leads to rock-
Rubblizing a concrete pavement successfully
determine the quality and completeness of ing of the slabs and subsequent distress in the
is predicated on a number of conditions, and
the rubblization operation as well as actual overlay. The quality of the subsurface materi-
there are several cautions to consider as well
gradation. als is highly suspect in the same areas that
when contemplating this technique:
Steel reinforcement in the existing pave- the slabs in the concrete were in very poor
First and foremost, a complete and uniform condition.
ment should be debonded from the
rubblization can only be accomplished

112 Guide to Concrete Overlays


APPENDICES

APPENDIX C.

FIBER REINFORCEMENT

Why Fibers? load-induced movement in the underlying


pavement. As a result, joints may open up
Types of Fibers
Fiber reinforcement in concrete overlays or not line up; this is principally an issue of The type of fiber to be used and the recom-
(FRC) can increase the concrete structural aesthetics, but it can affect performance when mended dosages for specific types are evolving
integrity. It contains short, discrete fibers that materials and conditions exacerbate curling/ fairly rapidly. Although steel fibers have a long
are to be uniformly distributed and randomly warping. history in paving applications, their addi-
oriented. The most common of these fibers tion to the concrete using current technology
include synthetic and steel fibers. Synthetics In extreme cases, joints may fault in high- requires significant manpower, which raises
have played a predominant role for the last traffic-volume areas. Synthetic fibers have cost. Steel fibers also require more care to pre-
two decades as the technology has improved. been used successfully in helping to control vent balling of the fibers as a result of their
Other fiber types such as glass, cellulose, and these problems for several years, although tendency to sometimes clump together when
natural fibers are occasionally used, but these long-term (greater than 15 years) duration exposed to cement and water. The latter prob-
are relatively rare and are outside the scope of of the benefit is not yet well established, par- lem can be prevented with proper charging
this document; see Figure 123. ticularly for synthetic fibers. Steel fibers have of the mixers, which may vary with the other
been around much longer and, provided cor- materials in the concrete mixture. Steel fibers
Characterization of the fibers with different rosion can be kept in check or is not found to are considerably heavier than synthetic fibers
concrete is normally based on fiber materi- be objectionable on the surface, can be quite and can settle near the bottom of the overlay
als, geometries, distribution, and densities. effective as well, but they have other disadvan- if not properly mixed.
Used in sufficient dosages with uniform tages compared to synthetics.
distribution, fibers help increase, in engineer- Synthetic fibers are broadly classed as macro
ing terms, the toughness and ductility of Fibers have the ability to hold the inevitable fibers rather than micro fibers, which are also
concrete. Enhancing the toughness and duc- cracks tightly together. These cracks can occur common in the industry. Generally speaking,
tility provides some flexibility to the designer, from a variety of causes, but the fibers render synthetic fibers have been favored compared
since longer joints and/or thinner sections the cracks more an annoyance than an actual to steel fibers in the last few years because of
of concrete can be considered. A good problem. Such tight cracks will usually per- the ease of handling and better dispersion
understanding of the several different fiber form better than typical sawed joints. Good characteristics. The volume of fibers added to
technologies permits the designer to better performance across cracks has been observed a concrete mix is expressed as a percentage of
optimize designs for specific conditions. since fibers have been used in roadway appli- the total volume of the composite (concrete
cations. In the concrete plastic state, fibers and fibers), termed volume fraction (vf ). The
Sufficient fibers provide an additional benefit also offer the advantage of increased resistance vf typically ranges from 0.1 to 3.0 percent.
in controlling differential slab movement to plastic shrinkage cracking. This type of The aspect ratio (l/d) is calculated by dividing
because the fibers span the cracked portion cracking can occur in all concrete applications fiber length (l) by its diameter (d). Fibers with
below the sawed joints. Plain concrete in when wind blows across the paved surface a noncircular cross section use an equivalent
overlay applications occasionally exhibits dif- and the rate of evaporation exceeds the rate of diameter for the calculation of l/d.
ferential movement of the individual slabs as bleed water coming to the surface of the con-
a result of temperature, curling/warping, or crete prior to set. Steel fibers with a much higher density
than synthetic fibers will weigh much more
than synthetic fibers at the same volume in
the concrete mixture. It may also, however,
take a higher volume of one fiber compared
to another to provide the same increase in
pavement performance. For this reason, it is
important to know the type of fiber being
used, the volume of the fiber needed in the
mixture to produce the desired properties,
and the fibers specific gravity. This informa-
tion is essential so that the concrete producer,
who batches concrete by weight rather
than volume, can produce a unit volume of
concrete having the appropriate behavior
characteristics upon setting.
Macro synthetic fibers starting at a minimum
dosage of 4 lb/yd3 have worked well on con-
crete overlays where they have been used.
For a typical concrete mix, this is about 0.26
percent volume. For comparison, the same
volume of steel fibers would weigh about 34
Figure 123. Fibers in concrete mix (source: Randell Riley, Illinois chapter, ACPA) lb/yd3 but yield somewhat different char-

Guide to Concrete Overlays 113


APPENDICES

acteristics in the concrete. Fiber producers


and suppliers can be of assistance in this area
(or inlay) through improved crack resistance
and improved residual load-carrying capac-
Construction
since, as mentioned earlier, the technology ity, the mixture contained higher macro-fiber Considerations
is undergoing a rapid evolutionary phase. content (up to 0.5 percent by volume). To
Various blends of fiber technologies are being retain workability at these higher fiber con- When Using Fibers
introduced that combine steel and synthetic tents, the mixture required a higher content The fibers length and large volume will often
fibers. Also, higher modulus synthetics are of cementitious material in order to coat the reduce slump from 4 inches to 2 inches in a
under development that may further advance fibers. concrete mixture. With everything else being
the technology in the next few years. A good equal, there is not a corresponding reduction
For example, a cementitious material content
reference and some minimum recommended in workability. To a concrete finisher or ready-
of around 790 pounds/yd3 was utilized for
dosages for a specific class of fiber based on mix concrete truck driver casually observing
achieving twice the fracture toughness with
the current state of understanding can be the discharge of the first load of concrete, this
0.56 percent volume fraction of fiber content.
found at www.dot.state.il.us/materials/syn- can trigger their natural instinct to add water
In addition, other material proportions were
theticfibers.pdf (IDOT-BMPR 2013). to the mixture to make it easier to place. In
found to enhance the mixtures workability
and stability against segregation: reality, an appropriately designed and batched
concrete and suitable fiber will actually place
High-volume Macro Smaller maximum coarse aggregate size,
such as less than 3/8 inch (9.5 mm), in
similarly to normal concrete and responds
especially well to mechanical vibration; if
Synthetic Fiber order to be placed as a 2-inch (50-mm) needed, a moderate dose of a polycarboxylate
Mixtures overlay or inlay or other water reducer typically is used to off-
set any loss in workability, especially for fiber
Certain types of macro synthetic fibers in Higher percentage of sand
dosages 5.0 lb/yd3 and greater. The admixture
quantities greater than that mentioned earlier Use of micro-fiber supplier should be contacted for recommen-
can provide for reduction in overlay thickness, dations. During construction, a few other
enhance postcrack flexural performance, and, Use of a high-range water reducer
items may warrant attention when using
in some cases under high doses, actually allow A 325-foot long full-scale FFC inlay was fibers, and these characteristics are further
the concrete to become yielding in nature constructed in 2009 in Rantoul, Illinois, exacerbated as the dosage of fibers increases:
and to flex somewhat under loads. Work still to demonstrate and observe any challenges
needs to be done to better define the optimal Fibers can be added at the batch plant or
related to the placement of the FFC material
amount of macro synthetic fibers to add or placed in the ready-mix truck; see Figure
and to monitor the cracking and bonding per-
the optimal performance volume, based on 124.
formance of the hardened concrete pavement
current records of thin pavements with FRC. inlay. The 2-inch FFC inlay sections were cast Fiber use may require slightly delayed
The 4 lb/yd3 dosage mentioned earlier is on a milled asphalt pavement in good condi- contraction joint sawing due to the fibers
enough to impart the proper characteristics tion and demonstrated good bond strength tendency to increase susceptibility to joint
in hardened concrete to improve postcracking between layers. The residual strength ratio of raveling if not timed properly.
performance and increase the load-carrying the mixture was measured between 4050
The use of macro fibers adds costs to the
capacity of the entire slab. Higher dosages can percent, which was at least twice as high as
concrete mixture. For this reason, their use
further improve this performance, but care recommended in the standard BCOA calcula-
must be weighed against other costs and
must be taken to avoid clumping of the fibers tor. Different size slab panels were attempted
factors such as increasing the overlay thick-
in the mix. Mix adjustments such as chang- at 4 feet, 5.5 feet, and 11 feet in the longitu-
ness without the fibers, possible reduced
ing aggregate gradation, cement content, dinal direction. The widest transverse joint
number of sawed joints, better joint perfor-
and admixture type and dosage are necessary was around 0.05 inches (1.25 mm), and the
mance, ability to minimize grade changes,
to accommodate the higher fiber contents. average joint crack remained tight at 0.016
and benefits of increased design life. The
Concrete mixtures with a high volume (5.0 to inches (0.4 mm) for the 4-foot slab size.
7.5 lb/yd3) of macro synthetic fibers (typically
with lengths of 1.5 to 2.25 inches) ideally
should utilize well-graded aggregates. In addi-
tion, because of the fibers large surface area
compared to their volume, such mixtures may
require slightly more cementitious material
(20 to 50 lb/yd3) and slightly more water
to keep the same w/cm ratio; they also may
require adjustment to the amount of fine
aggregates.
Research on a concrete overlay wearing sur-
face using high fiber content was conducted
by Dr. Amanda Bordelon at the University of
Illinois, and published as Flowable Fibrous
Concrete for Thin Pavement Inlays (wearable
surface) (Bordelon 2011). A flowable fibrous
concrete (FFC) mixture with high workabil-
ity was developed, to be placed rapidly as a
2-inch (5-cm) thick concrete overlay or inlay. Figure 124. Fibers added at plant (left) and bags tossed into ready-mix truck (right)
To extend the service life of the thin overlay (source: Randell Riley, Illinois chapter, ACPA)

114 Guide to Concrete Overlays


APPENDICES

price of synthetic fibers can increase materi- that manages to find its way up through Do not place or finish if rain is eminent
als costs +/- $0.08/ft2 ($0.70/yd2) per inch the surface. If this dosage rate is reduced because surface water will make the fibers
based on a 4.0-lb dosage/yd3. The increase back down to maybe 0.2 to 0.4 percent, more prominent.
in cost is, however, significantly driven by the FRC can be easier to finish. Over time,
Limit the use of older types of high-range
the size of the project and the volume of the fiber itself will wear away and disap-
water reducers (HRWRs) (naphthalenes
fibers being used; large projects can cost less pear, but the small roughness immediately
and melamines) to reduce the water-cement
and small projects can be more than this around the fiber may be evident. This is
ratio, as they tend to bleed and exacerbate
amount based on 2012 prices. not something that is noticed at highway
spotty concrete setting, thereby possibly
speeds, but for pedestrians walking across
Macro fibers can negatively affect the finish causing fibers to be more prominent. The
commercial applications, it can be evident.
appearance compared to concrete without newer HRWR (polycarboxylates) are gener-
If it is objectionable, it can be removed
fibers, if care is not taken with the fiber ally better and reduce segregation effects
using a simple pan flame torch.
type, mix design, and texturing technique; in the mixture (both fiber and aggregate
however, with proper care, the finish Often skid-resistant or higher-friction sur- related).
appearance will be acceptable. Owners need faces are specified for paving applications.
Some solvent-based curing compounds will
to be made aware up front that the concrete Some fibers can create unsightly finishes
make the fibers more prominent.
surface will appear slightly different than depending on which fiber and dosage
the clean smooth surface usually expected amount are chosen. With the addition Finally, know the product you are using.
of concrete paving. Some contractors will of fibers, it is more difficult to get a good The use of fibers is an excellent tool for
pan finish the surface to embed the fibers broom finish. Generally, an acceptable enhancing concrete overlays, but the
prior to texturing. This is not recom- broom finish can be achieved with a proper products are rapidly evolving and many
mended since the humidity, wind, sun, mix design, suitable fiber, appropriate owners, contractors, and producers are still
shade, temperature, and rain can all affect broom kept relatively clean, one-directional learning how to best apply the technol-
this operation; furthermore, if the panning broom passes, and no jiggling of the ogy. When using macro synthetic fibers, a
is not properly done, a significant amount broom. trial mix should be batched and placed at
of the entrained air can be removed, the ready-mix producers facility or placed
Unless care is taken to prevent them, macro
thereby reducing the concrete freeze-thaw elsewhere using the ingredients and propor-
fibers may occasionally ball up and create
durability. The hairy surface can occur tions approved for the project so that all
a surface defect even if added to the ready-
with fiber volume rates near 0.5 percent or know and understand what is expected.
mix discharge load under the utmost care;
more if the care noted above is not taken; Communication with the owner, general
see Figure 126.
see Figure 125. contractor, and inspectors is important to
Some contractors drill out the hair balls let them know what to expect during and
Heavy doses of macro fiber can make the
with a 4-inch core drill to a depth of an after construction. It is important to under-
surface more difficult to keep clean because
inch or so. This allows for the hair ball to stand the fiber product being used.
of the slight roughness created by each fiber
be removed and replaced with a grout or
concrete mixture.

Figure 125. Finished concrete overlay with synthetic fibers Figure 126. Balling fibers

Guide to Concrete Overlays 115


APPENDICES

APPENDIX D.

LASER SCANNING SURVEY

Roadway Surface area ahead or behind the vehicle at a prede-


termined vertical angle. These are designed
Planning Items to
3-D Laser Scanning to gather large amounts of data from right- Be Considered
of-way to right-of-way as well as high-quality
One of the problems experienced with digital photo images so closely spaced that Preplanning of the GPS control-point mea-
concrete overlays is minimizing quantity over- it is similar to a video. They are a step for- surements along the roadway or the use of
runs due to the lack of survey of the existing ward from the traditional photolog van that known points throughout the project corridor
pavement. The advent of laser scanning has provides basic relative elevations on the should be done with care to assure that the
opened a new avenue for mapping of pave- pavement, but they are not sufficient for con- amount of data is adequate for the accuracy
ment surfaces before overlay construction to trolling concrete yield. desired. The scan data is only as accurate as
help eliminate excessive overruns. To date, the control-point data.
pavement surface mapping has been done The type of laser from the traditional pho-
tolog van relevant to pavement overlays is Traffic interference can be a problem with
with conventional survey equipment such
that contained in the units currently used to static scans from the shoulder of the road.
as a total station, rod and level, GPS rover
measure finished pavement profile. These are This can be overcome with proper planning
unit, or vertical (looking down) sonic units
downward-looking lasers (perpendicular to and the fact that multiple scans will find the
that double as profile measuring devices.
the surface) and are used to measure pave- gap in the traffic. The same goes with mobile
These methods are labor intensive and often
ment surface texture or a very narrow profile scanning; using additional vehicles for block-
require traffic control to obtain the data. Laser
line. The type of laser (bandwidth) and the ing and considerations to time of day for
scanning can offer reduction in survey cost,
height of the laser are used to measure a very off-peak traffic is beneficial.
savings in time, and less interference to the
traveling public. fine line or area of the surface. Sun angles can impact the photo quality. This
Mobile lasers and those used for pavement item requires that the operators use the sun
profiling are usually not found on the same angle to their advantage in determining what
Scanning Applica- unit. Mobile lasers should be mounted to scan and when during the day.

tions to Pavements as high as possible on the unit to see over


obstructions, and the profiling type laser
Scan runs can be arranged in the planning
phase to collect all the mainline data in one
Either static or mobile scanning will provide units are mounted at bumper height or lower pass and the ramps or exits in a second or
a map of the surface of the roadway. Most to maximize accuracy and minimize light separate pass if the distances from the main-
mobile units are developed to look at the interference. line become too great.
Start and stop areas need to be identified both
on paper and on the ground to assure that all
possible data is collected in one visit to the site.

116 Guide to Concrete Overlays


APPENDICES

Data Analysis the transportation engineer or technician can


now see a grid of 0.5 to 1.0 foot, as shown
and still preserve the original data set for
future uses and historical documentation. An
Figure 127 provides a step process of the in Figure 128. This will allow detection of example of this is shown in Figure 129 and
elements involved with 3-D scanning. The various types of pavement failures that were shows cross sections that provide data on rut-
larger portion of the scanning survey process, previously not visible and enable highly accu- ting across the slab and extent of deterioration
regardless of static or mobile data collection, rate concrete quantity measurements. Data in the longitudinal direction, which can be
is carried out in the office. The office process- filtering systems and other routines have been measured from the data. The edited data can
ing consists of establishing a digital terrain developed to assist in the analysis and extrac- then be output in CAD or geographic infor-
model (DTM) at accuracies unachievable via tion of data from the point clouds for specific mation systems (GIS) files to meet the need
conventional survey methods. With scanning, purposes, such as pavement rehabilitation, of the user.

Figure 127. Typical mobile scan project workflow


Control/ Trajectory
Mobile Point CAD
Target Post Data
Data Cloud
Network
Capture
Processing Registration
Extraction Export
Layout QA/QC

Figure 128. Pavement DTM/detail

Figure 129. Pavement cross section detail

Guide to Concrete Overlays 117


APPENDICES

Static Scanning Mobile 3-D Laser Mobile Mapping


Operation Scanning Operations
Scanning can be performed in a static mode Laser scanning is basically several exist- This system allows the surveyor to collect data
by placing a unit such as the one seen in ing technologies combined into one unit at highway speeds in a single pass without
Figure 130 in a position so that it can refer- or process. At the heart of the unit is the being a traffic hazard. The equipment is syn-
ence itself to at least two or more known light detection and ranging scanner, which chronized to allow multiple sensors to feed
points of X,Y,Z coordinates. Control is criti- measures the flight time of a beam of light data on the targeted road surface simultane-
cal in the use of this device, just as in other to calculate the range to objects at predeter- ously. It does require the equipment used for
surveying techniques. Referencing to three or mined angular increments, resulting in a very storage to handle terabytes of information in
more known points or setting a geometrically large point data set referred to as a Point short periods of time. This system also picks
sound control system along the project cor- Cloud. The laser scanner conducts measure- up right-of-way hardware such as above-
ridor is highly recommended to increase the ments to targets, and a 360 camera is used to ground utilities and other infrastructure
accuracy of the data. A network of control assist in identifying objects in the scan. The devices that can be problems in construc-
points 250 to 300 feet apart should be used to unit also includes a GPS to record its posi- tion if not identified in the planning process
establish the control system. tion on the earths surface at any time and the (anything you can see is collected). One such
relative position of the objects being scanned. device developed is shown in Figure 131.
With the inclusion of the laser and camera,
An IMU is used to account for movement
this device resembles a Total Station on This device can gather 600,000 to 1,000,000
(pitch, roll, and yaw) in the survey vehicle. A
Steroids. This device operates in a 360 points per second and capture photos at 3- to
DMI is used to compute wheel rotation and
radius to gather object and photo data. It 10-foot intervals to give you a stereo view of
measurements to aid the process. The system
locates itself relative to the earth by sighting the front, sides, and downward-looking pho-
is capable of repeatable 0.04- to 0.12-inch
two or more points of known location (X,Y) tos of the pavement at the back. The IMU,
accuracy in measurements.
and elevation (Z). In roadway scanning, these GPS, and DMI units gather all the data about
points are part of a survey traverse. This type the pavement and surrounding area in one
of scan requires planning for a traverse of con- pass. This unit is controlled from the view
trol points and locations of scans in order not shown in Figure 132 and allows quality con-
to be put in a position of missing key data in trol of the data collection on the fly.
a scan by shadows or objects.
The static system can be used to survey pave-
ments from the shoulder for a distance of up
to 250 to 300 feet in radius, depending on
conditions from the survey unit.

Figure 131. Mobile laser scanner

Figure 130. Static laser scanner

Figure 132. Mobile scanner onboard quality control operation area

118 Guide to Concrete Overlays


APPENDICES

APPENDIX E.

FACTORS FOR CONSTRUCTING CONCRETE


OVERLAYS UNDER TRAFFIC
Table 24 provides information about various considerations when constructing concrete overlays under traffic.

Table 24. Considerations for Concrete Overlay Construction under Traffic


Factors to Consider Objectives / Expectations Considerations / Limitations
Incentives/Disincentives An effective way of managing successful accelerated Incentives and disincentives should be considered for the
construction is to offer its incentives for the contractor. If the project to encourage the contractor to perform within the
schedule is very critical, the contractor may likely consider given schedule when a competitive bidding environment is
innovative pavement techniques to complete the project on time expected. Use of disincentives should not deter potential
or even ahead of schedule. The use of incentives also allows for bidders when the schedule is critical.
a better competitive bidding environment for the owner.

Grade Control Grade control for the project should be considered early. In If payment is based on the plan area, then the contractor
the planning of the project, the type of overlay and existing may want a more detailed survey and additional cross
pavement conditions will often dictate the level of survey sections to ensure proper thickness and yield. If the
required for the design and stakeout of the project. Resurfacing payment is based on the volume of concrete supplied and
projects historically have required little in the way of surveying. the area paved, less survey is required.
A vast number of them are even constructed without detailed
When milling machines are used to remove existing
construction plans; they are referred to in many states as log
pavement, it is advisable to have them either follow the
jobs. When concrete is used as the resurfacing material, there is
same control as the concrete paver or wait to establish
no need to increase the level of surveying required on a project.
the paving control until the milling has been completed.
With all resurfacing projects, it is advisable to visit the project
One point of caution for multi-lane construction is that
site during a rain event and verify that there is no drainage issue.
on many pavements, the cross-slope of each existing
A drive through the project at the posted speed limit will alert
lane may differ, and the paver should have crowning
you to adverse cross-slope issues. For rural areas, surveying
adjustment capability located at the intermediate lane
is only required when you determine that there is some type
lines or actively remove any cross-slope differences
of a drainage, cross-slope, or profile issue that needs to be
between the lanes with the milling operation.
corrected.
The elevation of the concrete paver can be controlled by either a
traveling ski or by a stringline that is referenced from the existing
pavement. When stringline control is used, establish grades
at each stringline pin by projecting the existing cross-slope,
sight the string longitudinally, and adjust individual grades up to
produce a smooth profile.

Materials/Mixtures
Reliability of Material Supply All materials that are required on the project need to be available Materials that are prone to delivery delays need to be
or scheduled or properly stored for use prior to constructing the stockpiled.
overlay project.

Material Schedule Under an accelerated schedule, there is little time for deviation Contingency plans need to be developed to address
from the intended plan. As such, representative samples from all potential changes in critical material properties.
material supplies should be made with proper certification.

Concrete Mixture Normal concrete paving mixtures are typically used for concrete The mixture needs to match the opening requirements and
overlay projects. Rapid strength gain to meet accelerated construction methods to obtain opening requirements.
construction schedules does not require special blended However, the mixture should not be accelerated to a point
cements or sophisticated material. It is possible to proportion where there is a high probability of early-age cracking
a mixture using locally available aggregates, type I and from shrinkage and curling and warping. Each crew
type II cements, SCMs, and certain admixtures. Some initial member will have to be accustomed to the accelerated
adjustments will probably be required by the paving crew as they duties that accompany expedited construction.
become accustomed to the mixture characteristics.

Guide to Concrete Overlays 119


APPENDICES

Table 24. Considerations for Concrete Overlay Construction under Traffic, continued

Factors to Consider Objectives / Expectations Considerations / Limitations


Cementitious Materials Hydraulic cements include portland cement and blended The Integrated Materials and Construction Practices for
cements which contain SCMs. Other types of hydraulic cements Concrete Pavement Manual (IMCP Manual) is a very good
are rapid-setting calcium sulfo-alumina cements used for reference in order to understand the importance of the
repair materials or for pavements where fast turnaround times proper blend of cementitious materials.
are critical. Cements and SCMs play a major role in both heat
and strength development, and these properties depend on
the interaction of the individual compounds that constitute the
mixture.

Type I/II Cements Type I/II cements can reach opening strength without increasing More cement does not necessarily mean higher strength
the risk of shrinkage cracks. but it does increase shrinkage, as well as curling and
warping.

Slag Cement Slag cement can reduce ASR expansion, increase long-term Slag cement may reduce rate of strength gain and
strength, reduce permeability, reduce concrete temperature, and hydration rate.
slow hydration.

Fly ash Fly ash will increase long-term strength, reduce permeability, In the past, some states impose restrictions on the use
and reduce set temperature. Some fly ash can slow hydration on of fly ash in cold weather and may restrict the use of fly
accelerated construction projects. ash to 10% on accelerated construction projects even in
warm weather months. Mixtures should be tested in the
lab to determine the appropriate replacement rates and
temperature restrictions.

Type C Type C fly ash will increase long-term strength and reduce water Type C fly ash can affect strength gain. Mixtures must be
demand and permeability. This may or may not slow hydration or tested to determine how much class C fly ash is required
reduce ASR expansion. to reduce ASR-related expansion. Too high a dosage may
increase the risk of rapid stiffening and/or damage due to
salt scaling.

Type F Type F fly ash will increase long-term strength and reduce Type F fly ash delays setting and reduces rate of strength
permeability. It will also slow hydration and mitigate ASR gain. High loss-on-ignition affects air entrainment. Type F
expansion. is generally effective at reducing ASR-related expansion.
Availability may be a limitation.

Chemical Admixtures Chemical admixtures are added to the concrete mixtures to The effects of set-modifying admixtures on other
modify certain concrete properties such as strength. Adding properties of concrete, like shrinkage, may not be
chemical admixtures can achieve these properties more predictable. Therefore, acceptance tests of set modifiers
efficiently than adjusting other mixture ingredients such as the should be made with job materials under anticipated job
type of cement. Admixtures that are combined and contain both conditions. Compatibility of the admixtures with other
water reducers and accelerators are available. ingredients should be tested as it relates to potential
constructibility problems.

Water reducers Water reducers can reduce water demand through reduced Confirm that water reducers are compatible with other
paste content (lowers w/cm) to help minimize shrinkage, chemical admixtures and cements, particularly under
temperature, and cracking without sacrificing workability. Water harsh environmental conditions. Confirmed laboratory
reducing admixtures can also increase early strength gain by testing is essential to determine if the admixtures will
lowering the quantity of water necessary for cement hydration develop the desirable properties. Type F and G water
(by as much as 10% in 28 days). The w/cm ratio typically are at or reducers (superplasticizers) are not normally used in
lower than 0.43 for accelerated construction. pavements because of their high cost and because it is
difficult to control the slump range required for slipform
paving with their use. Overdoses of water reducers,
particularly normal-range products, may severely retard or
prevent setting.

Accelerators Accelerating admixtures are used to increase the rate of Long-term strength may be lower. Excess acceleration
strength development of concrete at an early age, including in may result in cracking before finishing and/or saw cutting
cold weather. It is important to test both fresh and hardened can be completed. Care must be exercised in using
concrete properties before using accelerators in overlays, accelerators in thin overlays so as not to cause early
particularly bonded overlays. shrinkage, cracking, and high curling and warping.

Air entrainment Air entrainment will dramatically improve the durability of Need to check compatibility with other admixtures. For
concrete exposed to moisture during cycles of freezing and about every 1% of air entrained, about 5% of concrete
thawing. It improves concrete resistance to surface scaling compressive strength is lost. Loss of air through the
caused by chemical deicers. It also tends to improve the paver is acceptable up to 1.50% to 1.75%. However, when
workability of concrete mixtures, reduce water demand, and the loss of air through the paver approaches 3%, the air
decrease mixture segregation and bleeding. system (quantity and distribution) is not acceptable.

120 Guide to Concrete Overlays


APPENDICES

Table 24. Considerations for Concrete Overlay Construction under Traffic, continued

Factors to Consider Objectives / Expectations Considerations / Limitations


Retarders Retarders are useful in extending set times. They increase the Retarders delay early strength gain, but do not change
bleeding rate and capacity and may be accompanied by some workability properties. Under certain conditions, retarders
reduction in early-age strength gain (one to three days) but can cause early stiffening and reduce workability.
higher later strengths.

Aggregates It is critical that aggregates be well graded (that is, there An aggregates CTE is a measure of how much the
should be a wide range of aggregate sizes). Well-graded material changes in length (or volume) for a given change
aggregates have less space between aggregate particles, in temperature. For bonded overlays over concrete,
therefore reducing paste demand without loss of workability. use aggregates that as closely as possible matches
Reduced paste content reduces shrinkage and early-age the underlying pavement CTE. The material is subject
cracking, particularly with accelerated mixes. With all to varying conditions in storage and handling. At the
construction, aggregate moisture content needs to be constantly very least, these changes should be anticipated, and
monitored since it can change significantly during the course accommodations made to adjust the water content in the
of construction. Physical properties of the aggregate such as mixture as necessary. Ideally, real-time monitoring of
absorption may be one source of change. the aggregate moisture content would allow for on the
fly changes. In most circumstances, a well-regulated
sampling program using rapid evaluation equipment will
improve this component of the process considerably.

Separation Layer A separation layer provides a necessary separation plane A separation layer does not provide structural support.
between overlay and underlying pavement. For asphalt Heavy truck traffic may decrease stability and strip the
separation layers under pavements carrying heavy truck traffic, asphalt due to pore pressure. Consider drainable asphalt
decrease sand content and increase 0.13 in. (3.3 mm) aggregate layer and drainage system under heavy truck traffic.
in order to reduce stripping the asphalt due to pore pressure.
Geotextiles may also be used as a separation layer.

Fibers Although not typically required for concrete overlays, Placement of fibers in the mixture must be accomplished
consideration needs to be given to the use of fibers for thinner so as to prevent balling of the fibers into clumps. In some
overlays (4 or less). Fibers improve the toughness of the cases, water-soluble bags are added to the final batch.
concrete overlay and resistance to plastic and dry shrinkage A staging area may be needed with adequate capacity
cracking, particularly with bonded overlays. Fibers also can to avoid a queue. In other cases, individual (bulk) fibers
increase the flexural strength of the concrete. may be introduced into the mixture, where a blower
appropriate to the application should then be considered.

Batching Batching of concrete used in concrete overlays is usually no Depending on the size of the job, a dedicated mobile
different from conventional concrete paving, or even other batch plant is a benefit to the project. In fact, this is
ready-mix applications. recommended when at all possible due to the potential for
increased concrete uniformity.

Capacity Having adequate batching capacity is a critical link in the Contingency plans should include preparation for rapid
process of constructing concrete overlays. Both mixing time and responses (repairs) of the more common equipment
the availability of transport equipment should be balanced along malfunctions
with cost.

Consistency During batching, consistency and uniformity are critical. Overlays are particularly vulnerable to changes in material
Adequate mixing time should be balanced with the need for properties due to their commonly thin sections.
increased production rates. If possible, a continuous type or
high-speed twin-shaft mixer could be used to accommodate both
objectives.

Concrete Transportation
Traffic Separation In an ideal situation, a separation of the transit vehicles from In most situations, however, circumstances deviate from
both the traveling public and other construction vehicles is the ideal, which warrants appropriate measures to ensure
helpful. continuous, uninterrupted delivery.

Transit Time Transit time is one variable that must be known. If a mobile Caution must be exercised if a retarder is used as it may
batch plant is used, transport of the concrete from the batch also affect the strength gain of the mixture, thus affecting
plant to the paver may be quick. As a result, deviations from a the time of opening to traffic. Curing may also become
conventional concrete mixture (including the admixtures that are more critical in these situations as fresh concrete will be
used) may not be necessary. However, if there is a potential for exposed for longer.
delay (e.g., due to traffic congestion), or if a ready-mix plant is
used for supply with a longer travel time,
a modified mixture may be necessary.

Protection Protection of the mixture from environmental factors may also be Dry and windy conditions can lead to rapid moisture loss
a consideration, particularly in long transit times from any exposed concrete. Conditions that are marginal
for the risk of freezing or rain must also be addressed. In
each case, protection of the concrete in transit may be
warranted, and can often be done by use of tarps. If ready-
mix trucks are used, protection is often less critical as the
concrete is protected by the drum.

Guide to Concrete Overlays 121


APPENDICES

Table 24. Considerations for Concrete Overlay Construction under Traffic, continued

Factors to Consider Objectives / Expectations Considerations / Limitations


Haul Roads The condition of the haul roads is another consideration when Care must be taken to ensure that the repeated heavy
constructing concrete overlays. axles of the trucks will not excessively rut the haul road.
Evaluation of a haul road in questionable areas should be
done prior to the first batching.

Preoverlay Repairs Prior to the construction of overlays, there may be a need for a If the preoverlay repairs dictate the accelerated overlay
variety of spot repairs on the existing pavement to be overlaid. schedule, the repairs should be considered under a
The timing of these repairs will affect the schedule of the overlay separate project or completed in off-peak hours.
construction.

Dowel Bar Retrofit Typically, dowel bar retrofit is not done in conjunction with Slots should be cut by special diamond slot cutters that
unbonded overlays since both can serve many of the same are capable of making multiple cuts at a time. Modified
functions. Dowel bars have been used in conjunction with milling machines are not recommended due to associated
thin bonded overlays when you want to significantly increase spalling and variable cut widths that effect chair width
load-carrying capacity. Good candidate projects for dowel requirements. Slots should be cut parallel with the
bar retrofits have the following characteristics: pavements direction of traffic. To properly prepare the slots, material
with adequate slab thickness, but showing significant loss of should be removed with a lightweight jackhammer, and
load transfer due to lack of dowels, poor aggregate interlock, the slot should be sandblasted and cleaned. Re-establish
or subbase/subgrade erosion. Relatively young pavements, the working joint with a joint insert. When choosing
because of insufficient slab thickness, excessive joint spacing, a repair material, select a material with the following
inadequate steel reinforcement at transverse cracks, and/or characteristics: little or no shrinkage, good ultimate
inadequate joint load transfer, are at risk of developing faulting, strength, thermal compatibility, freeze-thaw durability, and
working cracks, and corner cracks unless the load transfer is good bond to existing concrete.
improved. Typically, 3 to 5 smooth round steel dowel bars are
used in each wheel path.

Drainage Drainage improvements are sometimes warranted to Since the equipment used for drainage improvements
complement the construction of a concrete overlay. These often works on or near the pavement edge, their operation
improvements may include cleaning adjacent ditches, increasing before the overlay is complete would decrease the
their capacity, or even retrofitting subdrains. likelihood of premature damage to the young concrete
but also results in less stable material under the track
line, thereby risking reduced smoothness. In addition, if
retrofit subdrains are to stabilize the subbase, they should
ideally be installed prior to the overlay in order to reduce
movement of the existing pavement. However, be careful
not to damage the subdrains during overlay construction.

Utilities Utility work is also sometimes done prior to overlay construction. New patches can be particularly troublesome as they may
This may include relocation of utilities from beneath the not have adequate time to settle prior to the overlay
pavement to off of the pavement edge. If trenching or other construction. As with drainage improvements, all utility
disturbance of the existing pavement is required, care should be work should be completed prior to the overlay in order to
taken to ensure proper construction of patches. minimize interference or early-age damage.

Spot Repairs Some concrete overlays will require spot preoverlay repair to In all cases, quality of the spot repairs will often be critical
the existing concrete or asphalt pavement structure. If there are to the success of the performance of the pavement.
extensive repairs, the roadway may not be a good candidate for
an overlay.

Partial-depth repairs Good candidates are sections where slab deterioration is Poor candidates for partial depth repairs are those
contained to the upper one-third of the slab and where the with distress caused by compressive stress buildup
existing load transfer devices (if any) are still effective. in long-jointed pavements, spalling caused by dowel
bar misalignment or lockup, transverse or longitudinal
cracking caused by improper joint construction
techniques, working transverse or longitudinal cracks,
and spalls caused by D-cracking or reactive aggregate.
It is important to verify that all delaminated concrete
is removed, and that no concrete around the repair
boundaries has been damaged during the process. For
bonded overlays, it may be possible to fill in the partial
depth repair areas as a part of the overlay paving
operation.

Full-depth repairs Full-depth repairs of existing concrete or asphalt pavements are The effectiveness of a repair is dependent on the proper
effective at correcting many different types of localized distress. sizing of the repair. Most agencies specify a repair with
However, there are a few cases that limit the effectiveness of a a minimum length of 4 to 6 ft (1.2 to 1.8 m). Salvaging
full-depth repair. the existing dowel system is not recommended. It is
also important to verify that all delaminated concrete
is removed, and that no concrete around the repair
boundaries has been damaged during the process.

122 Guide to Concrete Overlays


APPENDICES

Table 24. Considerations for Concrete Overlay Construction under Traffic, continued

Factors to Consider Objectives / Expectations Considerations / Limitations


Retrofitted edge drains A good candidate project for retrofitted edge drains is a Retrofitted edge drains are not recommended on
pavement that is showing early signs of moisture damage, pavements where base contains more than 15% to 20%
is relatively young (i.e., less than 10 years old), and is only fines. However, they may be used in these types of soils
exhibiting a minimal amount of cracking (less than 5% cracked to provide a drainage pathway for separation layers
slabs) (Mathis 1990; FHWA 1992). Many studies have concluded used in unbonded overlays. When placing corrugated
that retrofitted edge drains are not effective at prolonging polyethylene pipes, extra care is also required to prevent
the service life of pavements that have already experienced overstretching of the pipes during installation. To avoid
significant moisture-related deterioration (Wells and Wiley 1987; damage to the pipes during compaction, a minimum of 6 in.
Young 1990; VDOT 1990). (150 mm) of cover over the drainage pipe is recommended
before compacting.

Slab stabilization Slab stabilization restores support beneath concrete slabs, Watch the maximum pressure to make sure it does not
thereby reducing progression of support-related distresses such exceed
as pumping, joint faulting, and corner breaks. Slab stabilization
100 psi (0.69 MPa). Monitor slab lift closely. Lift is typically
is not intended to raise depressed or settled slabs to the desired
limited to <_ 0.13 in. (3.3 mm). Stop grout injection when
elevation. Cement grout mixtures and polyurethane are the most
the grout is seen flowing from holes, cracks, or joints. Stop
commonly used materials.
injection if one minute has elapsed, regardless of pressure
or lift changes.

Surface Preparation/Cleaning Surface preparation and cleaning are required to prepare the The techniques used will vary depending on the surface
existing surface for the concrete overlay. type. The equipment used for repair should be sized to
provide not only adequate production rates but also to
minimize the disruption to the traveling public and to assist
with the accelerated schedule.

Traffic on Prepared Surface Phasing of the surface preparation operation can allow for If trafficking is allowed on the prepared surface prior
intermediate trafficking of the surface prior to the overlay to the paving of the overlay, subsequent cleaning of the
placement. surface, particularly for bonded overlays, is required in
order to remove any potential contamination.

Bond on Concrete Existing pavement surface preparation typically consists of Paving should commence soon after cleaning (i.e. minutes)
shotblasting followed by sweeping the concrete surface. to minimize the chance of contamination of the surface.
Cleaning consists of compressed air. Milling is used to lower the concrete elevation where
required and is not used as a concrete surface preparation
by itself since it can cause surface microcracking and
fracturing of the exposed aggregate.

Bond on Asphalt Existing pavement milling may be used where surface distortions Water or moisture cannot be allowed to stand on the
are 2 in. (50 mm) or greater to remove soft asphaltic material asphalt surface prior to the bonding resurfacing. In order
that would result in inadequate bond surface or to roughen the to prevent contamination of the surface, it is important to
surface to enhance bond development. Cleaning consists of avoid a large lag time between the final surface cleaning
sweeping the asphalt surface then cleaning with compressed air. and paving.

Unbonded on Concrete Only the distresses that cause a major loss of structural capacity The existing pavement needs to be stable and not shifting
require repair. or moving, particularly at the subbase level.

Unbonded on Asphalt Milling may be used where surface distortions are 2 in. (50 mm) Spot milling of only parts of the projects with significant
or greater to remove distortions that contain soft or fractured distortions or structural problems is often adequate.
asphalt. Before concrete placement, the asphalt surface should
be swept. Remaining small particles are not considered a
problem.

Traffic Considerations
Vehicle Access Meet needs of user. May want to open pavement to cars earlier Use accelerated mixtures only when necessary. Opening
and open to trucks later. strengths are those typically specified.

Pedestrian Access in Channel pedestrian movements around construction zone. In areas where heavy pedestrian traffic must be
Intersections/Urban Areas accommodated, detouring the pedestrian path may be
necessary.

Traffic Control Devices Traffic can be accommodated during construction. Fit traffic Too many times concrete overlays are eliminated as
control to user needs and follow the MUTCD (FHWA 2003b). rehabilitation options when the project is to be built under
traffic. The limitation of clearance requirements for paver
tracks and stringline are no longer valid since many
options are now available.

Lighting Lighting allows night work. Lighting must be movable with Number of lights and control of light patterns within work
construction. zone must be considered.

Guide to Concrete Overlays 123


APPENDICES

Table 24. Considerations for Concrete Overlay Construction under Traffic, continued

Factors to Consider Objectives / Expectations Considerations / Limitations


Nighttime Construction Nighttime construction is increasing. It provides an off-peak Nighttime visual limits must be utilized. They include
construction period that lessens disruption to the traffic. shorter spacing of channelizing devices, longer transitions,
changing colors nearing off-ramps, , widening pavement
markings, using glare screens, using more truck-mounted
attenuators, using real-time information on signs and
changeable message signs, and covering signs when
work is not being done.

Lane Capacity Examine lane capacity of construction zone speed and not Must deal with existing traffic flows in a safe manner for
design speed of roadway. the driver and construction worker.

Large Trucks Limited data show that tractor-trailer crash involvement in work Special attention should be given to accommodate
zones is higher than the national average for these vehicles, tractor-trailer combinations, both in work zones and
particularly on the interstate system. their transitions, especially where there are large truck
volumes. Items to consider are lane widths in curves with
runs of barrier on both sides and stopping distance where
congestion is expected.

Detours Must be conveniently located and have effective signage. May have negative impact on users. Always minimize the
out-of-distance travel where possible.

Events

School Coordinate schedule with bus routes and events. The schedule may be difficult to control because of limit
changes.
Commuters Plan project to minimize disruption. Normally limits can be relied upon.

Holiday Normally work stops during holidays. Holidays present an uncontrollable increase of traffic.

Visibility Provide adequate stopping distance, which increases overall Equipment and traffic control must be considered in
safety. regard to visibility.

Construction Staging
Staging Area The project limits should be evaluated to determine adequate A dedicated ready mixture plant or mobile batch plant
staging areas. The staging areas are necessary for ready located near the project site will also cut down on the haul
mix truck washouts, storage of equipment and materials, times to the site, and the quality of the mixture will be more
construction trailers, and possibly a portable concrete mixing easily controlled.
plant.

Incremental Lane Closure Allows for continuous single lane paving in one direction, leaving Requires multiple traffic control setups and pilot cars.
(Leap Frog) opened areas for traffic recovery.

Mobilization It is important that the project is planned to minimize staging Remobilizing of the paving crew on the project site takes
operations. Every time a stage comes to an end, there are time, and time not paving increases costs. A preferred
mobilizations necessary to regroup and prepare for the next step approach is to minimize the staging operations and
in the paving process. mobilizations.

Work Production To keep paving crews busy and provide cost-effective work, it Length based on curing time and production rates and
is important to keep construction crews effectively utilized in acceptable traffic delays when under traffic.
construction projects involving overlays. That requires the crews
to utilize effective work schedules that provide continuous and
uninterrupted results.

Number and Type of Lane Closure Traffic control must meet acceptable standards. Methods and Number and type of closures will depend on traffic
materials used must meet project restriction. demands, lane capacity, adjacent access requirements,
and number of available traffic lanes.

Paver Encroachment All encroachment restrictions can be met. Normal stringline and track paver widths per side is
typically 4 ft (1.2 m). One foot incremental encroachment
reduction (up to 3 ft [0.9 m] reduction total) is common
through typical machine adjustment. These do not
require specialized pavers, but may require adjustment
or modifications to an existing paver. Stringless paving
minimizes this problem.

Construction Under Traffic Versus A thorough analysis comparing road user costs and construction Additional construction cost and delays to users when
Lane Closure durations and construction costs should be performed for design construction is under traffic must be compared to travel
alternatives (full closure vs. maintaining traffic through the delay and out-of-distance travel for detours.
construction zone).

124 Guide to Concrete Overlays


APPENDICES

Table 24. Considerations for Concrete Overlay Construction under Traffic, continued

Factors to Consider Objectives / Expectations Considerations / Limitations


Overlay Construction
Thickness of Overlay Thinner overlays cure quicker, causing stresses to form earlier. Thin overlays are subject to higher risk of cracking
Therefore, early sawing is important. (shrinkage, curling, and warping stresses).

Weather
Cold weather (below 40F Consider covering pavement to help achieve opening strength. Develop a QC plan that addresses cold weather placement
[4.4C]) issues. Specifically, insulation methods to assure that the
pavement will not freeze until it reaches opening strength.

Normal weather 40F to 85F Overlays have fast strength gain and high production rates with There should only be project restrictions and not normal
(4.4C to 29C) reduced early-age cracking potential. material or equipment limits.

Hot weather > 85F (29C) Faster strength gain exists during hot weather. There is a higher risk of surface cracking during hot
weather. Proper curing is important. Also, bottom up
cracking needs to be considered when the underlying
pavement is too hot.

Construction Equipment One of the most important aspects of accelerated construction In the event of failure to the concrete paver, a plan should
that is often overlooked is the availability and performance of be available to continue operations. The plan could be
the equipment on the site. All equipment should be in working simple, such as keeping a mechanic on call, or it may
condition and properly maintained. The contractor should be more complex, such as having a backup paver in the
present a back up plan in the event of equipment failure during vicinity. A staging plan should be part of the back up
construction. Proper parts, hydraulic fluids, oil, and fuel should plan to properly rout traffic in the event of scheduling
be readily available. Concrete saws should be abundant and disruptions. If the pavement is to be open in a matter of
readily available on the job site. hours after paving, the critical stage is often the sawing. It
is important to have the adequate manpower and saws on
the job site when constructing a concrete overlay on an
accelerated schedule.

Curing Curing is arguably more critical for overlays than for most other While cost should be a consideration, the incremental
paving. The relatively thin nature of concrete overlays increases quality improvements, such as high production curing from
their surface area with respect to the volume of concrete. The an effective curing program, will often far outweigh the
result is more susceptibility to excess moisture loss and the additional cost.
distresses that can result from this. To avoid problems including
plastic shrinkage cracking, full-depth shrinkage cracking, wide
joints, and surface distresses, a rapid and effective curing
program should be adopted that includes using twice the
recommended compound rate for thin overlays.

Special curing For overlays that require a very short opening to traffic and are Special curing is normally not required in summer months
relatively short in length, special curing in addition to curing for accelerated construction, but it does have an effect
compound is used. It normally consist of insulating blankets that on strength gain when air temperatures are less than 65F
provide a uniform temperature environment for the concrete. (19C), and it has a pronounced effect when temperatures
are less than 55F (13C) in colder months.

Sawing Sawing concrete overlays is also typically a more critical The timing of the saw cutting should be done to balance
operation as compared to more conventional concrete paving. the potential for uncontrolled cracking with the potential
The thin section will often gain stresses rapidly, and thus require for excessive joint spalling during sawing. Bonded
accelerated sawing. Sometimes the need for accelerated concrete overlays over concrete require the most effective
sawing is underestimated and the sawing operations fall too far sawing operations to prevent overlay failures. Not only
behind the paver. To respond to this, the contractor should be does the transverse joint require full depth saw cut plus
prepared with the proper type and number of saws. In the case 0.50 in. (13 mm) over the existing joint, the width of the
of sawing, redundancy in equipment is also important. cut should not be less than the existing transverse crack
below the existing saw cut. This allows the two monolithic
pavements (overlay and existing pavement) to contract the
same way. For overlays on asphalt, particularly when there
is wheel rutting in the asphalt, the depth of the saw should
be increased to account for the extra depth in the wheel
rut areas.

Fillets Provide fillets for a level of safety precaution at dropoffs. Placement of form fillets may require sawing.

Guide to Concrete Overlays 125


APPENDICES

Table 24. Considerations for Concrete Overlay Construction under Traffic, continued

Factors to Consider Objectives / Expectations Considerations / Limitations


Opening Pavement Considerations
Public Relations Where construction will affect adjacent homeowners and Construction needs to follow the schedule and, during
businesses along with the traveling public, an effective public construction, signing to business access is very important,
relations campaign should be implemented. Flyers, media along with daily communication between the contractor
coverage, and public meetings regarding the project schedule and the impacted business. Informed local drivers can
and the reason for the schedule timeline need to be developed avoid the area when possible, thus reducing delays.
and implemented. Preconstruction meetings between the
government and the citizens, with the contractor in attendance,
help keep the public well informed and allow the contractor to
understand any concerns.

Schedule The project schedule must be reachable and realistic. The Proper equipment and staffing, mixture, construction
schedule affects public acceptance, contractors methods, methods, curing, and sawing are all considerations. There
payment and incentives, quality of work, and safety. Most is a need to understand the impact of traffic controls and
accelerated construction projects are moving more to calendar openings, staging, material requirements, and isolated
days and days when work is not usually done in order to address restricted spot locations on the construction schedule.
critical completion dates where a large volume of traffic is
affected. It also allows for the counting of weekends when
necessary and eliminates working day issues of whether a
contractor could or could not work.

Maturity Method Utilizing maturity testing for concrete paving provides a reliable Development of a maturity curve is an important element
technique for estimating in-place strength and thus the time of maturity testing. As construction proceeds on a project,
of opening. Maturity testing provides a reliable technique validation of the maturity curve may be necessary when
for continuous monitoring of concrete strength gain. Most changes occur in mixture constituents, material sources,
importantly, maturity testing enables any pavement to be opened mixture operations, and the watercementitious materials
to traffic as soon as it meets strength criteria. Concrete maturity ratios. Also some states set an automatic validation
concepts are being applied by 32 states. criterion based on a time period. Most states that use a
maturity curve have validation criteria established which
allows some flexibility in mixture changes without the
development of a new maturity curve.

Opening Strength See Early Opening of Overlays to Traffic section. See Early Opening of Overlays to Traffic section..

126 Guide to Concrete Overlays


APPENDICES

APPENDIX F.

STRINGLESS PAVING OPERATION

In the stringline operation, the paving


equipment gets horizontal and verti-
moved horizontally by the paving crew to
meet local needs. They can also manually
Horizontal and
cal guidance through the locations and adjust the paving surface up or down on Vertical Control
elevations of the stringline relative to a set the paving machine. The paving hubs or
centerline profile and pavement cross sec- reference points at predetermined distances Requirements and
tion. The stringless operation compares
the elevation and position of the paving
(usually 12 to 25 feet) along the route
become the reference for any disputes over
System Limitations
machine to a predetermined computer the final product. Changes in stringless paver Tight vertical and horizontal control is essential
surface model or electronic set of cross sec- operations are all made from a touchscreen in either stringline or stringless paving. The ver-
tions of the required final pavement surface on the paver to raise or lower any of the four tical control must be within 0.03-foot accuracy
at any given time and location. The paving corners of the machine. Reference points at to provide the acceptable ride for incentive pay
machine computer processes its exact X, 250500 feet to 2 miles (dependent on the in most states. Minimum vertical curve lengths
Y, and Z location and position in relation system) along the route become the reference of 150 feet and desirable curve lengths of greater
to a computer model of the new pavement for the stringless operation. than 350 feet are suggested to meet profile
surface. The onboard computer first adjusts criteria.
Base and concrete surface elevation checks
the alignment of the slipform paver relative Coordination of sensor sensitivity in the paver
for the stringline operations are usually done
to the existing roadway. It then adjusts the hydraulic system and in the response of the
through the use of a string being pulled
elevation of the machine on each of the four paver to an electrical impulse both must be
between the two stringlines and vertical
corners of the paver to achieve the correct coordinated to achieve the desired profile results.
measurements being obtained between the
pavement thickness, crossfall, and mainfall; Retrofits of the hydraulic systems on older slip-
string and the surface in question. In the
see Figure 133. The stringless system directs form pavers may be necessary to provide smooth
case of the stringless system, a rover unit
the paver to make necessary changes to vertical movements in the paving operation.
(GPS locator and hand-held computer) is
meet these values.
used to check any location on any surface In the case of any system that relies on GPS
Just as with stringline paving, the field staff within the model area, in front of or behind horizontal control, it is important to have
can make adjustments in the operation of the paving equipment. The rover must be constant communication between the ground
the stringless system to improve the final in contact with a total station, laser, or GPS receivers and the satellites. Loss of signal may
surface profile or adjust for local situations. positioning unit. stop the machine or put it into a constant direc-
Stringlines can be adjusted up or down or tion and profile slope to allow it to pass under a
bridge, tree, or other item blocking the satellite
reception.
The operation of total stations can be affected by
the following environmental conditions:
Heavy surface wind vibration of the
instrument
Spring and fall low-sun-level interference with
line of sight
Paver exhaust system location relative to
prisms
Location of nighttime lighting systems relative
to the paver and instrument
Fog limiting or halting paving until clear
communication between prisms and instru-
ment is established
Each of the systems has the ability to be used on
each of the items in the paving train from the
bulldozer, grader, and trimmer on the construc-
tion of the subgrade and base to the spreader/
belt placer and slipform paver. The number of
control units required varies with the length of
Figure 133. Paving machine control this portion of the paving train. Texture/cure
equipment behind the paver is usually controlled
mechanically with sensors on the side and top of
the finished product.

Guide to Concrete Overlays 127


APPENDICES

Three-step Process see Figure 135. The utility vehicle is driven


along the pavement at 5 to 15 mph, record-
and drafting) software. Data is streamed from
both units to a central computer for storage.
for Stringless ing the existing pavement profile at 25- to
The ground reference system should contain
50-foot intervals along the pavement edges,
Paving wheel paths, lane quarter points, and center-
reference points with known X,Y,Z values,
spaced on alternating sides or one side of the
Utilizing stringless paving technology involves line. It needs to be noted that GPS accuracy
roadway depending on the system used. The
a three-step process. The first step is col- is good vertically to only 1 inch, so to obtain
Z value should be obtained through elec-
lecting survey data of the existing surface to the proper accuracy in the Z coordinate, the
tronic three-wire leveling just in advance of
develop and build a roadway surface map; see ATV had to be augmented with a laser system
the construction to verify the overlay design
Figure134. Step two is to design the road- or software correction. An alternate to the
assumptions and assure that the final prod-
way and create the proposed 3-D computer ATV is to survey the existing pavement with a
uct will meet the designer and contractor
model using the existing surface and proposed total station.
requirements. The data management method
profile and cross sections. The third and final The data collected are used to produce a 3-D involves translating data to a project coordi-
step is to construct the proposed pavement by plot of the pavement surface utilizing read- nate system.
transferring the computer model to the pav- ily available CADD (computer-aided design
ing machine and utilizing a noncontact X,Y,Z
guidance system.
In order to map the existing roadway surface, Ref point #2
an all-terrain vehicle (ATV) can be used,
equipped with a laser profiler (Z coordinates)
or GPS receiver and GPS (X,Y coordinates);
/-
0 +
25

25 ft +/- Spacing or shorter

ATV with GPS unit Ref point #3

4 ft
Ref point #1
(4 ft rod with plate (TYP)) Center line
Wheel line
1/4 point
Wheel line
Edge

Figure 134. Survey existing surface to develop and build database

Figure 135. ATV with GPS and laser profile

128 Guide to Concrete Overlays


APPENDICES

Existing Stringless the same figure. The screen in Figure 138


represents the controls the contractor has
communicate with the paving train equip-
ment. Each total station locates itself through
Control Systems to monitor the operation or make manual sighting three known and previously estab-
changes. It relies on an initial reference system lished reference points (approximately 250
Currently there are three systems in use to established by the highway agency at 1,000- feet apart) inside the primary control or
partially or fully utilize stringless paving foot intervals with X,Y,Z coordinates; see 1,000 foot points of the highway department.
technology. Field training and support are Figure 137. X and Y may be established with Lasers on the total stations locate a prism on
required for each of the systems and should GPS survey equipment, but Z must be estab- the paving equipment, and a specific radio
be requested in any agreement with the lished through the use of digital or three-wire frequency for each total station communicates
contractor. level circuit operations to provide an accuracy the relative position of each to the computer
of 0.01 to 0.03 foot. Contractor surveys are model in a computer on the paving machine.
System No. 1 required to provide intermediate control The paver onboard computer contains the
The first such system, shown in Figures136 points, map the existing pavement surface, pavement surface model and instructs the
138, utilizes surveying total stations, lasers, establish a final surface with profiles of the paving device on changes in direction and
and radio communications to provide centerline and pavement edges, and calculate elevation for the paver. Similar equipment can
machine control. Two total stations are shown concrete quantities and pavement depths to be installed on a spreader/belt placer for hori-
in Figure 136. Prisms on the two masts shown meet highway owner requirements. zontal control only or in conjunction with
on the paver in Figure 137 form the receiv- vertical control. Other paving train equip-
The paving equipment in this operation is
ing ends of transmissions from the two total ment such as the cure/texture carts are usually
controlled by two total stations that may be
stations on the backslope of the roadway in controlled by mechanical means.
set on one or opposite sides of the road to

Figure 138. Computer controls on paving


machine

Figure 136. Total robotic station

Ref point #2
(x,y,z)

360 Prism (back)


Robotic total station (TS)
Concrete overlay
Other Reference Points
ingline
360 Prism (front)
and Total Stations
Elec tronic st

Ref Point #1
(x,y,z)

Slope sensor

nder
lane u
Single ction.
u
constr

affic
nder tr l. Ref point #3
lane u o (x,y,z)
Single ot car contr
il
with p Robotic total station (TS)

Figure 137. System 1Stringless paving operation using total stations and reference points

Guide to Concrete Overlays 129


APPENDICES

System No. 2 The paving equipment in this operation is con- System No. 3
trolled by a rotating laser unit that may be set
A second stringless system, shown in The third system, shown in Figures
on either side of the road to communicate with
Figures139141, utilizes GPS and laser 142144, is a new emergence of stringless
the paving train equipment; see Figure 139. The
communications to achieve horizontal and paving technology and is a blend of the ele-
equipment locates itself over one known and
vertical guidance of the paving equipment. It ments currently being used in the first two
previously established reference point (approxi-
relies on an initial reference system inside the systems and the additions of items that can
mately 500600 feet apart) inside the primary
primary control or 1,000 foot points of the reduce the time of survey prior to and dur-
control or 1,000 foot points of the highway
highway department with X,Y,Z coordinates. ing paving. It is based on the use of GPS
department. Elevation of the laser (Z coordi-
Coordinates X and Y may be established to guide the paving train and a computer
nates) is established through the use of a vertical
with GPS survey equipment, but Z must be program that can react quickly enough
pole, of set vertical length, under the laser and
established through the use of digital or three- to give real-time corrections from the
over the point. The laser is self-leveling and legs
wire level circuit operations to provide an elevation portion of the GPS signal to the
are adjusted vertically to allow the tip of the ver-
accuracy of 0.01 to 0.03 foot. Contractor or slipform paver or belt placer, in order to
tical pole to touch the point and the laser frame.
owner surveys are required to map the exist- provide accurate elevation data to 0.01 foot
The rotating laser emits a 10-degree vertical band
ing pavement surface, establish a final surface for development of profile information
to the units on the paver.
with profiles of the centerline and pavement necessary to meet highway agency needs.
edges, and calculate concrete quantities and Paver receivers consist of two devices as shown The GPS system requires a base station on
pavement depths to meet highway owner on the paver masts in Figure 141. The top part site with a 2+ mile radius of influence and
requirements. of the mast is a GPS receiver (X,Y coordinates) known X,Y,Z coordinates at the begin-
that is used to communicate horizontal guid- ning, ending, and third points of a typical
ance information to the paver onboard computer 5-mile project. The base station location
and surface model. Below the GPS receiver is a can also be tied to other known survey
1 mm correction receiver that relates paver and points outside the pavement corridor. The
reference point locations to the computer. The slipform paver or spreader is equipped with
paver onboard computer contains the pavement one GPS mast and two-way slope sensors
surface model and instructs the paving device on to adjust the paver movement. The opera-
changes in direction and elevation for the paver; tor can manually observe the action of the
see Figure 141. The same rotating laser can be paver from an onboard computer screen
used to guide the spreader/belt placer with only and make manual adjustments.
the GPS receiver and an onboard computer with
One of the advantages of this system is the
surface program installed. Other paving train
use of the four-wheel ATV equipped with
equipment such as the cure/texture carts are usu-
a GPS base station receiver and software
ally controlled by mechanical means.

360 Prism (back)

360 Prism (front) Concrete overlay


Figure 139. Rotating laser over reference
points

Slope sensor
on.
cons tructi
lane under
Single
trol.
ar con
with pilot c
nder traffic
lane u
Single Rotating laser unit

Figure 141. System 2Stringless paving operation using GPS, a rotating laser, and reference
points

Figure 140. System 2 paving machine

130 Guide to Concrete Overlays


APPENDICES

that contains the design centerline profile and


cross section; see Figure 142. By driving the
Stringless System Agency goals in profile and concrete yield.
Can the system under consideration pro-
ATV along a known and set location on the Equipment vide the agency and contractor with profiles
roadway (515 mph), the GPS on the ATV that meet or exceed agency goals and pro-
determines the existing surface elevations. Selection Criteria vide accurate information on yield of the
Using the vehicles software, the surface eleva- The decision regarding the type of stringless concrete?
tions are then compared to the design profile paving system to be used should be made by Contractor options to meet owner goals.
at given points to create a 3-D model. This the contractor. This decision should be based Can the system provide information for
model is then provided to the stringless paver. on several factors, such as the following: machine control that allows for staged con-
This particular view of the vehicle contains
Site control provided by the owner. The struction of pavement sections and meet
both the data collection equipment on the
highway agency may not have the resources the overall goals of the finished product in
machine and the separate GPS base station
or desire to set paving hubs. It may request terms of construction and profile?
that acts as the reference point for data col-
lection and communication with the paving the contractor to develop the horizontal Research, test, and demonstrate perfor-
train. The information from the existing sur- and vertical control for paving. mance. The contractor should test the
face profile, a design overlay centerline profile, Construction site accessibility. The highway equipment on the paving train for some
and a typical pavement surface cross section agency may not allow stringlines along the 500 to 1,000 feet or more without the
is fed to a program that cuts cross sections at centerline or outside edges because of traf- inclusion of concrete. Paving hubs and
specified stations along the route. fic control requirements. Tight working stringline should also be in place to assure
areas can limit the access by the public and all parties that the system is working
The output is a set of pavement surface cross
construction equipment when stringlines properly.
sections by station rather than a surface
model as in the first two systems. It interpo- are used. Level of training and support available. The
lates changes between stations as the other Accuracy and repeatability specification on contractor should understand the amount
systems do between points in the model. The equipment. The contractor must weigh the of training required to operate the system
software is built on the concepts used by the ability of the stringless system to meet the and the amount that will be given prior to
early geodimeters and total stations, but it agency profile, accuracy, and repeatability paving.
relies heavily on the manipulation of the GPS specifications for the quality product the
signal through mathematical models to gain The contractor should retain access to a ready
agency requires. response system during the paving season that
the vertical accuracy of 0.01 foot. The control
equipment on the paver shown (Figure 143) minimizes work stoppage due to an unfore-
is similar to that used on the other systems. seen system problem.
Keep in mind this system does not require
any laser or radio communications between
reference points and the paving equipment
only GPS communications.
GPS base station
(within a 2-mile range)

360 Prism (back)

360 Prism (front) Concrete overlay

Slope sensor
on.
cons tructi
lane under
Single
l.
ontro
t car c
c with pilo
nd er traffi
lane u
Figure 142. GPS base station mobile or fixed Single

Figure 144. System 3Stringless paving operation using GPS

Figure 143. GPS paver control system

Guide to Concrete Overlays 131


APPENDICES

APPENDIX G.

CONSIDERATIONS FOR DEVELOPING PROJECT


AND SUPPLEMENTAL SPECIFICATIONS
Every jurisdiction has its own project devel- elevations and locations of each and verify yards. Sweeping and cleaning with com-
opment process and concrete pavement clearance for proposed construction. pressed air is a surface preparation task but
specifications. The following guidelines can is most often incidental to paving.
Complete elements of the work that can
be used in overlay project development and
affect line and grade in advance of con- Concrete overlay, furnish only: The quan-
in developing supplemental specifications
struction unless noted on plans. tity of concrete furnished will be measured
or special provisions. They apply to bonded
in cubic yards. This quantity should include
and unbonded concrete overlay projects on Traffic control plan: The contractor
concrete placed in widening sections and
existing concrete, asphalt, and composite should develop a traffic control plan where
partial depth patches. The contractor can
pavements. required based on the MUTCD (FHWA
be paid the contract unit price per cubic
2003b) and approved by the engineer.
The guidelines are specific only to concrete yards. This payment should be full com-
overlay projects and do not represent every pensation for furnishing all raw materials,
item that needs to be considered in a concrete Limitations of Operations and for proportioning, mixing, and delivery
paving project. In addition to the limitations of operations of concrete to the paving machine.
for the placement of standard concrete pave- Concrete overlay, placement only: The
ment, the following limitations for concrete quantity of concrete overlay, placement
General overlays apply: only, should be measured and paid for
At air temperatures below 55F (13C), in square yards. This will be the quantity
Contractor Submittal the opening of the pavement should be shown in the contract documents. The
Considerations established using in-place strength mea- area of concrete overlay placement can
surement devices, such as the maturity be determined from the length and pave-
Maturity method for strength determina- ment width, including widening sections.
method (ASTM C-1074). In order to place
tion prior to opening to traffic. Payment should be full compensation for
concrete in cold weather, air temperature
Paving mixture design for each source requirements for the jurisdiction should labor and equipment necessary to place,
of aggregate to be used for review and apply. finish, texture, protect and cure the pave-
approval by the engineer. ment, including sawing and sealing (if
The engineer may impose a restriction on required) joints, furnishing, and installing
Provide material certifications to the edge loading of construction equipment on reinforcement (if required).
engineer. the finished slab until opening strength is
reached. Separation layer: Hot mix asphalt or other
Where required, submit a plan for con- approved separation layer material should
struction sequence and schedule prior to Bonded concrete overlays should be placed be measured and paid by area or weight.
commencing construction. If the plans according to the local jurisdictions sched-
show a specific sequence/schedule, the con- ule, based on seasonal temperatures. If the contract documents require accelerat-
tractor may need to verify compliance with ing curing, such as wet or blanket curing,
Unbonded overlays should not be placed the curing area should be measured and the
the schedule or submit an alternate plan to
when the asphalt or concrete pavement contractor should be paid per square yard.
the engineer for approval. A detailed stag-
surface temperature exceeds the maximum
ing and sequencing plan is recommended
temperature allowed by the engineer.
for concrete overlay projects when using an
Typically, this temperature is around 120F
expedited construction process and sched-
(49C). Water may be added to cool the Materials
ule of opening. pavement ahead of the paver. The surface The CTE of the bonded overlays over
should be dry and free of standing water concrete need to be similar to that of
Scheduling and Conflicts prior to paving. the existing concrete pavement. This is
Construction sequence: A preconstruction typically accomplished by using similar
meeting is recommended to discuss critical Method of Measurement aggregates in the concrete mixture. If it is
items such as staging, opening strengths, not possible, a coarse aggregate should be
time of placement, and overall schedule.
and Basis of Payment used in the overlay that has a lower CTE
The quantity of the various items of work than in the existing pavement.
Typically, a concrete overlay schedule is involved in the construction of concrete
much shorter than a standard concrete pav- overlay will be measured by the engineer in The largest particle size of the coarse
ing project. accordance with the following provisions: aggregate should be less than or equal to
one-third of the overlay thickness.
Conflict avoidance: Expose possible con- Surface preparation may include milling,
flicts in advance of construction. Verify air, water, and sand- or shotblasting; these Refer to contract requirements for concrete
should be measured and paid in square mixture parameters.

132 Guide to Concrete Overlays


APPENDICES

Separation Layer for have standing water prior to placement of to remove or when mud or other debris is
the overlay. tracked on the surface. If pressure washed,
Unbonded Overlays no standing water should be allowed prior
If asphalt is used as the separation layer Bonded Concrete Overlays Over to paving. Paving should commence soon
material, it should be designed with the Asphalt after cleaning to minimize contamination.
intention of preventing asphalt stripping
from the build up of pore pressure from A guideline to determine whether milling
is required is if asphalt surface distortions Unbonded Concrete Overlays
heavy traffic. Special consideration should Over Concrete or Asphalt
be given to pavements where high speeds are 2 in. (5.08 cm) or greater. If milling
and heavy trucks are expected. These vari- is specified, it is important that there is Surface cleaning is provided by sweeping of
ables are known to contribute to stripping. at least 3 to 4 in. (7.62 to 10.16 cm) of the existing asphalt surface with a mechani-
asphalt remaining prior to the overlay. cal sweeper or air blower. Paving should
Fabric: Technology is evolving rapidly on Milling should remove the asphalt to the commence soon after cleaning to minimize
the use of geotextile fabric for the separa- nearest tack line. contamination.
tion layer. Care should be exercised in
selecting geotextile fabric, however, because After milling, the surface should be
inspected for further preoverlay repairs. Concrete Placement
not all products perform equally well for
The milling operation may expose wide
this application. Grade Control
thermal cracks. If the cracks are wider than
the maximum overlay aggregate size, they The engineer will review and approve the
may be filled with fly ash slurry, sand, or control system. Information detailing the
Construction other appropriate material. pavement thickness at the various survey
points and material quantities should also
Following any milling, partial or full depth
Preoverlay Repairs repairs should be completed with concrete
be provided.
Preoverlay repairs include: slab stabiliza- to ensure bonding with the overlay. Concrete paver should place in single lane
tion and slab jacking, partial depth repairs, width or be capable of adjusting the crown
full-depth repairs, retrofitted edge drains, All concrete patches plus the overlay should at each plan lane line when placing mul-
load transfer restoration, and milling. If be isolated from the rest of the overlay tiple lanes.
milling is part of the repairs, it should be using normal joint patterns.
completed prior to other repairs. When appropriate, grade control for the
Unbonded Overlays Over paving operation should be referenced
Materials removed in the preparation off the milled surface, unless the milling
operation may be temporarily placed in
Concrete
machine is controlled by a previously estab-
the shoulder area unless otherwise specified For uniform support of the overlay, all lished paver control line.
in the contract documents. The removal partial and full-depth repairs should be
of materials must take place prior to the completed with concrete. Overlay Placement
removal of approved construction signage. The concrete surface should be cleaned Surface watering may be allowed by the
Surface preparation equipment used prior to the placement of the separation engineer to help cool the pavement in
should be subject to approval of the engi- layer. If a leveling course is required, it extremely warm conditions and when the
neer. Milling, air, water, sandblasting, and should be completed with the concrete existing pavement surface condition is at
shotblasting equipment should be power overlay and not with the asphalt separation or exceeds 120F (48.89C). The pavement
operated and capable of preparing and layer. surface should not be moist or wet prior to
cleaning of the existing surface in accor- placement of the overlay.
dance with the contract documents. Unbonded Concrete Overlays
Conventional concrete paving procedures
Over Asphalt should be followed for placing, spreading,
Bonded Concrete Overlays Over All partial and full-depth patching should be consolidating, and finishing the unbonded
Concrete completed with asphalt. Existing concrete overlay when required. When dowels
The surface of the existing pavement should patches in the existing asphalt pavement are specified, anchoring dowel baskets to
be prepared by shotblasting, sandblasting should be isolated to prevent bonding to the the underlying pavement must be done
and/or milling. Milling, if used, should concrete overlay. A debonding agent, fabric, according to the jurisdictions requirements.
be followed by shotblasting or high pres- or other bond-breaking material should be Alternatively, paving machines equipped
sure water blasting to remove concrete applied to the patch before the overlay is with dowel bar inserters can be used.
damaged during milling (evidenced by placed.
A quality control plan should dictate the
microcracking). time of placement with consideration
Preparation should be adequate to remove
Surface Cleaning given to air and pavement temperatures.
all dirt, oil, and other foreign materials, as Bonded Concrete Overlays Over For bonded overlays on concrete, it is not
well as any laitance or loose material from desirable to have the overlay pavement
Concrete or Asphalt contracting, due to shrinkage, at the same
the surface and edges against which new
concrete is to be placed. The surface of the existing pavement should time as the existing underlying concrete is
be cleaned by sweeping and followed expanding due to the heat of the day. The
Airblast surface to remove loose debris and by compressed air in front of the paver. best time to place a bonded overlay over
prevent resettlement of debris into cleaned Paving should commence soon after clean- concrete is when the temperature differen-
area. The surface should be free of oil or ing to minimize contamination. tial between the existing pavement and new
other automobile fluids. The pavement overlay is minimal.
surface should not be moist or damp or Pressure washing should only be consid-
ered when surface contaminants are hard

Guide to Concrete Overlays 133


APPENDICES

Liquid Membrane Curing Joint Sawing marked on both sides of the pavement by a
reliable method.
Apply curing compound immediately
General
after surface moisture has disappeared but Transverse joints should be placed in the
typically no later than 30 minutes after The contractor should provide a joint saw- overlay pavement directly over existing
finishing/texturing. Apply liquid curing ing plan that demonstrates how all saw cuts transverse joints.
compound in a fine spray to form a con- will be accomplished within a shortened
tinuous, uniform film on the horizontal sawing window. Details should include Transverse joint width must be equal to or
surface and vertical edges of pavement, the number of saws and anticipated sawing greater than the underlying crack width at
curbs, and back of curbs. production rates, as well as estimated start- the bottom of the existing transverse joint
ing and finishing times. All sawing must to prevent debonding due to movement.
Use a white pigment liquid curing com- be completed within the first one-half of
pound for concrete. Saw all transverse joints to full depth of
the sawing window.
overlay plus 0.50 in. (13 mm).
For overlays with a thickness of 6 in. (150 The contractor should exercise care in
mm) or less, apply curing compound at Saw longitudinal joints to T/2.
placing, consolidating, and finishing the
2 times the manufacturers recommended concrete at and around all joints.
application rate for a standard concrete Bonded Overlays Over Asphalt
pavement. Do not dilute the compound. Wet sawing should be used when required Saw transverse joints to a minimum depth
by the contract documents for dust control. of T/4.
For overlays with a thickness greater than
6 in. (150 mm), curing compound should Joint Width Saw longitudinal joints to a depth of T/3.
be applied at 1.5 times the manufacturers
All conventional sawing widths are nor- Early entry saws may be required unless
recommended rate for a standard concrete
mally 0.19 in. (4.8 mm) +/- 0.06 in. (1.5 otherwise specified in contract documents.
pavement.
mm).
When 0.13 in. (3.3 mm) wide saw cuts
When white pigment curing compound is
All early entry sawing are normally 0.13 in. are used and sealing is required, follow the
employed correctly, the surface of the con-
(3.3 mm) +/- 0.06 in. (1.5 mm) in width jurisdictional requirement for low modulus
crete pavement should be solid white with
and a minimum T/4 inches in depth. hot-pour sealant.
no visible grey.
If forms are used, apply to pavement edges Joint Seal Unbonded Overlays
and back of curbs within 30 minutes after Joint sealing should follow the jurisdic- Saw transverse joints to a depth of T/4
forms are removed. tional requirements. When narrow (.13 in. (minimum) or T/3 (maximum). For early
Protect concrete pavement during cold [3.3 mm]) saw cuts are used and sealing is entry, saw depth will be 1.25 in. (31 mm)
weather for at least 5 days, or protect for required, follow jurisdictional requirements or greater.
a minimum of 24 hours and until flexural for low modules hot-pour sealant.
Saw all longitudinal joints to a depth of
strength of 340 psi (2.3 MPa) is achieved T/3.
for unbonded concrete overlays, 420 to 480 Timing
psi (2.9 to 3.3 MPa) for bonded concrete Timely sawing is necessary to prevent ran- Sealing will follow jurisdictional
overlays over asphalt, and 540 psi (3.7 dom cracking due to shrinkage. This is requirements.
MPa) for bonded concrete overlays over particularly important for overlays less than For unbonded overlays over asphalt, the
concrete. 6 in. (150 mm). saw cut depth may need adjustment over
rutted asphalt location in order to maintain
Bonded Overlays Over Concrete a depth of T/4 to T/3 requirements.
Prior to construction of a concrete bonded
overlay, the exact location of each contrac- When 0.13 in. (3.3 mm) saw cuts are used
tion and expansion joint in the existing and sealing is required, follow jurisdictional
pavement, including joints created by full- requirement for low modulus hot-pour
depth patches, should be identified and sealant.

134 Guide to Concrete Overlays


APPENDICES

APPENDIX H.

SUGGESTED OWNER-CONTRACTOR MEETINGS


TO ENSURE A QUALITY PRODUCT
The following information is provided as a
starting point or guide for ensuring quality
Prebid Meeting II. Alternative Bid Provisions

I. Overlay Project Items of Special 1. Materials selection


concrete performance in concrete overlays.
Key elements are identified that are required Attention 2. Management method (conventional,
of the pavement owner and contractor for A+B, etc.)
1. Construction differences between con-
each project. This is an outline for success but
ventional paving and overlays III. Discussion of Questions from the
is not detailed in nature so that items can be
added or deleted according to common prac- 2. Phasing and staging plan Prospective Contractors
tice in a given state or local government. IV. Issuance of Addenda to Clarify Questions
3. Scheduling criteria, including which
To accomplish the construction objectives areas are accessible, restrictions on site Raised at the Prebid Conference
in concrete overlay projects, it is necessary access, and working hours 1. Minutes of the meeting to all who
to have meetings during the design (prebid) attended and those who call for plans
and construction (prepour/preconstruction) 4. Scheduling milestones with incentives/
disincentives on the project
period between the contracting agency and
the contractor(s) to work out the details. The 5. Allowable mixes and special condi-
purpose of the prebid, prepour, and precon-
struction conferences and the key elements
tions such as fibers
Prepour/
(checklists) of each are shown below. 6. Strength requirements and strength-
testing measurement methods
Preconstruction
7. Traffic control, clearances, stag- Review Checklist
Prebid Meeting ing requirements, and edge-drop Prepour or preconstruction meetings can
restrictions be very productive when the contractor is
Check List tasked with addressing the pertinent items.
8. Expected and unexpected delay
Prebid meetings provide an opportunity for They may be conducted as one combined
resolution
the owner to review project requirements meeting or two separate meetings, depending
and receive input from contractors who may 9. Plant and staging area locations on the level of detail the contractor is able
have an interest in bidding for the project. to provide at the preconstruction meeting.
10. Paving sequence, paver clearance, and The contractor should be able to present the
Although prebid meetings tend to be primar-
pavement dropoff limitations plan for addressing each of the items on the
ily a review of administrative and contractual
matters, it is important to use them to high- 11. Haul road locations review checklist for review and comment at
light modifications implemented in the plans this meeting. Forcing the contractor to think
and specifications. 12. QA acceptance testing and QC about the project and build it on paper before
requirements the prework meeting will pay big dividends.
The prebid meeting gives the contracting The overlay team should be involved in the
agency an opportunity to identify new and 13. Issuance of design and specification
changes prework so they can receive guidance and
different items in the areas of specifications, answers to unresolved issues and/or identify
materials, and construction processes that 14. Pre-overlay repairs and surface potential problems with the contractors
are expected in the construction project. preparation approach.
It is also a good time to receive input from
the contractors on important design and 15. Special conditions such as tie bar loca- I. General Items
construction items such as jointing, surface tions, widening details, etc.
1. Identify the chain of command in the
preparation of the existing pavement, paving 16. Saw cut depths as well as timing and decision-making process
exceptions, schedules, and staging. It is also importance of early joint development
an opportunity to discuss the intent of the 2. Identify roles and responsibilities of
work changes. Critical material supply/avail- 17. Curing, particularly curing for thin key staff for all involved parties
ability issues and specific acceptance testing pavement sections
3. Review of all design and construction
requirements also need to be addressed. 18. Incentives and disincentives applied to changes issued since bid
Minutes of the meeting should be distrib- overlay construction
4. Certification of materials sources
uted to all potential bidders (those who have 19. Pavement ride requirements on the
requested bid documents) whether they are finished product 5. Mix design submittals
in attendance or not. Paving-related items for
discussion are listed below. 20. Importance of reducing the length of 6. QMP/CQC laboratory and personnel
time for job completion certifications
7. Batch plant certification and mixer

Guide to Concrete Overlays 135


APPENDICES

efficiency tests a. Methodcontract or owner e. Maximum allowable concrete haul


times
8. Construction schedule b. Type and amount of available
information f. Placement procedures (equipment
9. Payment schedules
and methods)
c. Stringline or stringless construction
10. Subcontractor activities
g. Estimated mix temperature at the
d. Development of the profile grade
11. Construction survey time of placement
and concrete quantity by whom
12. Haul roads and access points and when (Is there an approval pro- h. Thickness verification during
cess and timeline before placement
13. Traffic control plan for each phase of construction?)
the work i. Estimated time from placement to
e. Reestablishment of land corners time that allows for joint sawing
14. Working days allowed and method of and centerline control points
counting j. Hot/cold weather specifications and
13. Public information notification pro- precautions
15. Expected start date cess to be used during construction
1) Changes in mix for weather or
16. Phone numbers and email addresses of material changes
key personnel such as contractor and
agency representatives, traffic control III. Utility Concerns: Locations in the proj- 2) Identification of method and
manager, material suppliers, and util- ect limits, key personnel for location materials to be used to protect
ity location representatives contact, and expected plans for relocation the concrete in case of changes
where necessary in weather (rain, snow, or hot/
17. Liquidated damages cold)
IV. Local Jurisdiction Concerns:
18. EEO/AA requirements Coordination with local road projects k. Temperature control of existing
19. Public information notification pro- or city/county special activities (e.g., asphalt surfaces
cess to be used during construction festivals)
l. Vibrator testing/consolidation
20. Pollution control plans V. Concrete Placement Activities (This can issues
be part of the preconstruction conference
21. Safety inspections m. Curing and texturing equipment,
or a separate prepour conference.)
rates, and construction procedures
22. Change order process 1. Batching activities
n. Tie bar/dowel location, inser-
23. Conduct of a half-day overlay a. Identification of central mix or tion, alignment, spacing, offset
workshop ready-mix supply source verification
II. Contractor Project Plan b. Stockpile management to eliminate o. Straight edge and edge slump
1. Identify the chain of command in the segregation tolerances
decision-making and construction c. Batch plant certification and mixer p. Plastic shrinkage cracking, edge
process efficiency testing slump, joint spalling, and full-depth
2. Work schedule breakdown by major cracking treatments
d. Anticipated plant production rates
task, starting date, and expected 3. Joint development (longitudinal and
duration e. Concrete haul route identification
transverse)
and estimated truck number
3. Field lab location needed for existing traffic along a. Review of contractor saw cut-
4. Field office location the route ting QC plan (number, type, and
method of sawing)
5. Subcontract documentation f. Consideration of alternative mixes
to meet weather changes b. Consideration of employing early
6. Material source and quality entry saws
certifications g. Aggregate stockpile moisture
c. Backup saw availability (number,
7. Material testing lab and technician h. Identify washout areas for trucks
personnel, and location to project)
certifications 2. Concrete paving (placement, finishing,
d. Rain conditions and skip-sawing
8. Submittal of concrete mix design texturing, and curing)
procedures
9. Water sources and testing a. Overlay temperature planning and
e. Joint reservoir size, shape, and
management (on-site weather con-
depth-cut dimension tolerances and
10. Traffic control plan for each phase of dition monitoring and who and
dimensions
the work how it entered into the decision to
pave and cover or not to pave) f. Joint sealing installation and accep-
11. Haul road and access point location
tance procedures
and duration identification b. Placement and filler lane scheduling
g. Saw-cutting sequence and accept-
12. Construction survey c. Base preparation (patching, milling,
able degree of saw-cut raveling
recycling)
d. Equipment breakdown procedures

136 Guide to Concrete Overlays


APPENDICES

h. Joint sealant and backer-rod mate- tor responsibilities in testing and j. Documentation of test results and
rial certification submittals sampling deviations
i. Requirements on removal and b. Review of contractors QC plan k. Verification of failing acceptance
flushing of joint-sawing residue tests, retesting, and referee testing
c. Aggregate durability, soundness,
j. Joint beveling procedures (if abrasion, and gradation test data l. Actions to be taken if specification
required) and requirements requirements are not met
k. Joint sealant and concrete curing d. Reinforcing steel and dowel bar m. Pavement smoothness (ride) test-
time requirements and methods submittals ing and timing
l. Joint sandblasting, reservoir clean- e. Materials sampling and testing n. Treatment of premature cracking
liness, and moisture condition procedures and spalling
requirements before sealing
f. Development and use of control o. Resolution procedures for expected
m. Joint sealant surface depth toler- charts and unexpected delay
ances, sealant pump, water truck,
g. Concrete mixture designs and
and saw-cutting equipment
water-cementitious ratio effects on
n. Allowable ambient temperatures strength
during sealing operations and com-
h. Concrete sampling, fabrication,
pression seal reservoir requirements
curing, and testing procedures
o. Joint inspection procedures
i. Sampling and pay factor computa-
4. QA/QC activities tion overview
a. Delineation of owner and contrac-

Guide to Concrete Overlays 137


APPENDICES

APPENDIX I.

INNOVATIVE METHODS FOR ACCELERATED


CONCRETE OVERLAY CONSTRUCTION
Table 25 provides a summary of innovative accelerated construction methods (adapted from Simon et al. 2003).

Table 25. Applicability, Pros, and Cons of Various Accelerated Construction Methods
Method Applicability/Limitations Pros(+)/Cons()
Formal partnering with design This method has not been used very much + P
rovides a faster and cheaper construction process due to reduction of
consultants, contractors, local with designers or other agencies. conflicts, litigation, and claims (win-win situation)
authorities, and regulatory agencies + Brings about continuous improvement in the quality of services and
Little training has been done and much
skepticism is in place regarding this method. products
+ Utilizes resources more effectively
+ Implements easily because already being used on an informal basis
+ Improves communications
Limits completive market strategy
Creates strong dependency on the partners

Methods for expediting utility In highway construction, the need for the + Encourages project managers to develop more economical means and
relocation work relocation of utilities often arises, particularly methods
in urban areas. + Shortens project execution by using less formal documentation and
Relocation is handled primarily by utility improving communication
companies. + Reduces executive personnel
Currently, there is little recourse that can be + Produces more continuity during the project
taken against utilities for delays. Brings about need for independent engineers to check PMs work
Utilities have to pay for relocations. Encourages overcoming the specialist mindset of the organization

Intelligent transportation systems and Applicable areas include but are not limited + Increases safety
work zone traffic control to traffic control, route guidance, automated + Reduces congestion
highway systems, collision avoidance,
+ Enhances mobility
en-route driver information, transportation
demand management, etc. + Minimizes environmental impact
+ Increases energy efficiency
+ Promotes economic productivity for healthier economy
Requires additional training of employees
Includes costs to implement

Public input on phasing of This method is applicable on construction + Allows for more expeditious construction methods to be employed
construction projects where there is a significant impact Requires more public relations effort earlier
on the public.

Multiple approaches to traffic control TCP solutions for small simple jobs are + Reduces both construction costs and user costs through optimal TCPs
plans (TCPs) often apparent, but otherwise they should Requires larger consultant fees for development because of more
be thoroughly investigated earlier in the thorough TCP analysis
process.

Descriptive catalog of construction Applicability of new technologies could + Provides an online catalog that could easily be accessed and
technologies be widespread, but specifications may be supported by FHWA and other states
affected. Requires effort for maintenance and upkeep of the catalog

Contractor preparation of the TCP This approach will encourage contractor + Reduces efforts
based on minimum requirements innovation but may be possible only on + Provides incentive for construction innovation
smaller, simpler projects.
Increases costs
Excludes impact on local businesses
Means that contractor compliance with safety standards may be
challenging

138 Guide to Concrete Overlays


APPENDICES

Table 25. Applicability, Pros, and Cons of Various Accelerated Construction Methods, continued

Method Applicability/Limitations Pros(+)/Cons()


Linear scheduling method (LSM) and This method can be used for repetitive + Provides a better understanding of the project
accurate productivity to rate data and projects in which there are no strict
establish project target duration dependencies/constraints between project + Enables the planner to determine when and where a change in
activities. resources must take place to satisfy the goals set by the project

Resurfacing overlays and shoulder + Helps identify existing relationships and encourages the project team
improvement are good types of projects for to try different alternatives
the LSM.
+ Shortens schedule by overlapping activities instead of sequencing

Scheduling projects involving large cuts and fills might be more difficult
to schedule with LSM

A+B contracting (costs plus time) A+B bidding can be used to motivate the + Includes consideration of the time component of a construction
contractor to minimize the delivery time for contract
high-priority and highly trafficked roadways. + Includes favorable treatment of contractors with the most available
There must be a balance between the resources to complete the project
benefits of early completion and any + Involves incentives for contractors to compress the construction
increased cost of construction. schedule
This approach requires incentives and + Includes greater potential for early project completion
disincentives to be effective. Requires that incentives and disincentives are carefully managed
Means that costs are defined whereas benefits are distributed to the
public

Contractor milestone incentives Incentives must be relevant. + Encourages contractors to finish on time
Goals must be reachable. Causes impacts to contractors to be highly scrutinized
Incentives cannot be conflicting. Causes disagreements over compensable delays that may be
problematic

Packaged multiprimes contracting This method can be used when a specific + Increases competition among construction bidders
highway project is composed of several + Reduces pyramiding of costs, particularly overhead and profit
major segments or is very large.
+ Reduces project time through overlap of design and construction or
from multiple work forces
+ Requires more direct control by the project owner
Presents interface management challenges for the agency
Leads to physical interferences between contractors

Prequalified bidders based on past Bidders qualify based on several key items, + Provides a shorter and easier selection process
schedule performance including specific project type experience, + Provides possibly better contractors
individual experience, past performance,
Reduces the competition
capacity of the firm, and primary firm
location. Requires that schedule performance data are well kept
Requires that agency and other noncontractual schedule impacts are
recognized and equitably settled

Incentives for TCP development with a To use this method, seek involvement of local + Leads to innovative ideas for successful TCPs
contractor who values an engineering municipalities in funding the incentive (e.g., Means that savings are difficult to estimate
cost-savings sharing provision 5percent of estimated user cost savings).
This method requires close scrutiny to
determine actual time savings.

Incentives for contractor work Incentives must be explicitly described in the + Leads to innovative ideas for successful TCPs
progress with a lane-rental approach bid package. + Minimizes contractor impact on the traffic
Rental rates have to be significant and should Causes administration to be difficult
address high-impact lanes.

Increased amount of liquidated Just as important as the damages happening + Motivates better contractor performance
damages and routine enforcement in the contract are the claims made for Requires rigorous documentation and quick request for information
damages. The time and effort involved response to enforce
in pursuing these claims is, however, a
limitation. This should be weighed against
potential benefits.
Possibly provide incentives to finish projects
ahead of time.

No excuse incentives These incentives preclude delay claims by + Results in considerable improvements in schedule performance
contractors, give contractors incentives to Transfers risk to contractor and therefore may increase costs on the
finish early, and require a realistic schedule. average over time

Guide to Concrete Overlays 139


APPENDICES

Table 25. Applicability, Pros, and Cons of Various Accelerated Construction Methods, continued

Method Applicability/Limitations Pros(+)/Cons()


Tools and best practices for New technologies (such as intrusion + Increases safety for road users and workers
implementing multiple work shift and/ alarms), modified traffic control plans, and + Reduces user costs
or night work new methods to monitor traffic provide
+ Provides faster completion time
improvements in night work zone safety.
Requires research and design costs
These improvements will lead to high
nighttime productivity.

Exploitation of web-based team To be efficient, access to information is + Enhances project communication


collaboration system needed quickly and without hassle. A web- + Eases collaboration with project managers, designers, contractors,
based system can be used to track project vendors, and the public
deliverables, track project tasks online,
+ Keeps everyone in the loop
receive email alerts as items become due,
share documents, and reduce administrative + Allows tracking of project online, which minimizes time taken and
document production and delivery cost by enhances performance
uploading documents. This is handy for CAD Requires high installation and learning costs
drawings or anything else that needs to be Lacks standards
shared with the project team.

Encouragement of the use of Numerous research and implementation + Results in possible savings
automated construction technologies efforts are currently under way to automate + Presents opportunity for significant schedule compression
conventional infrastructure construction,
Requires some training
condition assessment, and maintenance
actives such as earth moving, compaction, Requires contractor implementation
road construction, and maintenance.
Commercial systems are available.

Employment of methods for These methods can be used where road + Decreases duration and unit costs
continuous work zones geometry and weekend or night scheduling + Increases safety
permit.
Results in possible higher user costs and traffic congestion

Use of windowed milestone This method can be used where milestone + Lowers project costs
dates are not based on hard constraints. + Lowers user costs
Milestones should be related to allow the
Reduces ability to hold contractors feet to the fire
contractor maximum flexibility in efficiently
allocating project resources.

Schedule of calendar day projects Scheduling calendar day projects is + Produces better weather management
applicable to projects where the completion + Provides a direct method of expediting
is critical and a large volume of traffic is
Requires strict adherence to the schedule for credibility with the
affected.
public, even with breakdowns or weather problems

Construction time shortened by full Full closure could be used in areas where + Shortens construction time
closure of the roadway instead of there is at least one alternative route for Causes possible traffic congestion on alternative routes
partial closure drivers and where volume is limited.

Duration and productivity effects Data collected can be very useful in cost and + Produces quicker and more dependable exploitation of new
tracked and associated with different time estimation for optimal plans. technologies
technologies Requires personnel to devote time to properly monitor and record data
Technology choices may be limited, however,
by project conditions and logical equipment Can be perceived as costly
spreads.

Optimal approaches to crew shifts The schedule can be shortened through use + Provides possible cost savings
and scheduling to eliminate long work of additional crews on regular shift, multiple + Increases productivity
hours shifting, or selective overtime.
+ Reduces cycle time of tasks, which improves the schedule
Scheduled overtime can be used where Creates possible negative results if planning is done carelessly
appropriate, but effects should be evaluated
carefully. Creates a necessity for contractor to implement

Selected field personnel trained in Schedule flexibility may be minimal in + Creates a flexible and quick-to-adapt project team
scheduling methods and claims practice, but for complex jobs a broad + Leads to faster project completion
understanding of scheduling issues should
Leads to possibly too many people trying to manage
help expedite progress.

Lessons-learned database on ways to This database would be broadly applicable + Requires quick reference for implementation of expediting measures
expedite schedules but limited by legal and policy constraints. Creates a need for the database to be maintained

140 Guide to Concrete Overlays


SOURCES

SOURCES

REFERENCES

3M. 2013. Geotextile Seaming Cylinder . 1998. WhitetoppingState of the Burnham, T. R. and B. I. Izevbekhai. 2012.
Spray Adhesive. Tech Data Sheet. Industrial Practice. Engineering Bulletin EB210.02P. Performance of Thin Jointed Concrete
Adhesives and Tapes Division. Skokie, IL: American Concrete Pavement Pavements Subjected to Accelerated Traffic
Association. Loading at the MnROAD Facility, in
American Association of State Highway
Advances in Pavement Design through Full-scale
Officials (AASHO). 1962. The AASHO Road . 1999. Construction Specification
Accelerated Pavement Testing, ed. David Jones,
Test. Report 5 Pavement Research. Washington, Guideline for Ultra-Thin Whitetopping.
John Harvey, Angel Mateos, Imad Al-Qadi,
DC: Highway Research Board. Information Series IS120P. Skokie, IL:
289297. Monograph of 4th International
American Concrete Pavement Association.
. 1993. Guide for Design of Pavement Conference on Accelerated Pavement Testing.
Structures. 4th ed. Washington, DC: . 2000. Traffic Management Handbook Boca Raton, FL. CRC Press.
American Association of State Highway and for Concrete Pavement Reconstruction and
Cable, J. K. 2012. Concrete Overlay Field
Transportation Officials. Rehabilitation. Publication EB213P. Skokie,
Application Program, Iowa Task Report: US 18
IL: American Concrete Pavement Association.
. 1998. Supplement to the AASHTO Concrete Overlay Construction under Traffic.
Guide for Design of Pavement Structures. . 2012. Bonded Concrete Overlay on Ames, IA: National Concrete Pavement
Washington, DC: American Association of Asphalt (BCOA) Thickness Designer. (http:// Technology Center, Iowa State University.
State Highway and Transportation Officials. apps.acpa.org/apps/bcoa.aspx, accessed (www.intrans.iastate.edu/research/documents/
March9, 2014) research-reports/US_18_overlay_construc-
. 2007. TransportationInvest in Our tion_web.pdf, accessed March 9, 2014)
Future: A New Vision for the 21st Century. . 2012. StreetPave. (http://acpa.org/
Washington, DC: AASHTO. streetpave, accessed March 9, 2014) Cable, J. K., C. Bauer, E. J. Jaselskis, and L.
Li. 2004. Stringless Portland Cement Concrete
. (no year). AASHTOWare Pavement . 2013. National Concrete Overlay Paving. Iowa Department of Transportation/
ME Design. www.aashtoware.org [accessed Explorer. (www.overlays.acpa.org/webapps/ Iowa Highway Research Board Project
March 9, 2014) overlayexplorer/index.html, accessed March9, TR-490. Center for Portland Cement
2014) Concrete Pavement Technology.
ACI Committee 302. 2010. Guide for
Concrete Floor and Slab Construction. Applied Pavement Technology, Inc. 2002a. Cervantes, V., and J. R. Roesler. 2009.
Publication ACI 302-1R-04. Farmington Conventional Whitetopping Overlays. Performance of Concrete Pavements with
Hills, MI: American Concrete Institute. Technical Brief. Publication FHWA IF-03- Optimized Slab Geometry. Final Report,
008. Washington, DC: Federal Highway FHWA ICT-09-053. Urbana, IL: Illinois
ACI Committee 325. 2006. Concrete Overlays
Administration. (http://isddc.dot.gov/ Center for Transportation, University of
for Pavement Rehabilitation. Publication ACI
OLPFiles/FHWA/010933.pdf, accessed Illinois.
325.13R-06. Farmington Hills, MI: American
March 10, 2014)
Concrete Institute. Christopher, B. R. 2000. Maintenance of
Applied Pavement Technology, Inc. 2002b. Highway Edgedrains. NCHRP Synthesis of
ACI Committed 330. 2008. Guide for the
Unbonded Portland Cement Concrete Highway Practice 285. Washington, DC:
Design and Construction of Concrete Parking
Overlays. Technical Brief. Publication Transportation Research Board. (http://
Lots. Publication ACI 330R-08. Farmington
FHWA-IF-03-006. Washington, DC: Federal ntl.bts.gov/lib/17000/17600/17652/
Hills, MI: American Concrete Institute.
Highway Administration. (http://isddc.dot. PB2001102763.pdf, accessed March 10,
American Concrete Pavement Association gov/OLPFiles/FHWA/010935.pdf, accessed 2014)
(ACPA). 1990a. Guidelines for Bonded March 10, 2014)
Concrete Overlays. Technical Bulletin Cole, L. W., and P. A. Okamoto. 1995.
Bordelon, A. C. 2011. Flowable Fibrous Flexural Strength Criteria for Opening
TB-007P. Skokie, IL: American Concrete
Concrete for Thin Concrete Inlays. PhD diss., Concrete Roadways to Traffic. Transportation
Pavement Association.
Department of Civil and Environmental Research Record 1478:5361.
. 1990b. Guidelines for Unbonded Engineering, University of Illinois at Urbana-
Concrete Overlays. Technical Bulletin Champaign. (https://www.ideals.illinois.edu/ Covarrubias T and Covarrubias V. 2008.
TB-005P. Skokie, IL: American Concrete handle/2142/29805, accessed March 10, TCP Design for Thin Concrete Pavements.
Pavement Association. 2014) 9th International Conference on Concrete
Pavements, San Francisco, CA.
. 1991. Guidelines for Concrete Bordelon, A. and J. Roesler. 2011. Flowable
Overlays of Existing Asphalt Pavements Fibrous Concrete for Thin Concrete Inlays. Covarrubias V, J. P. 2011. Optipave2
(Whitetopping). Technical Bulletin TB-009P. 1st Transportation and Development Institute v 1.0. (www.tcpavements.com/index.
Skokie, IL: American Concrete Pavement Congress 2011. Ed. I. Al-Qadi and S. Murrell. php?op=4_1&lang=en, accessed March 14,
Association. Chicago, Illinois: American Society of Civil 2014)
Engineers. pp. 874-883.

Guide to Concrete Overlays 141


SOURCES

Covarrubias V, J. P., Covarrubias, and T. Hoerner, T. E., K. D. Smith, H. T. Yu, D. . 2007. AASHTO Mechanistic-
Roesler. 2010. Design of Concrete Slabs G. Peshkin, and M. J. Wade. 2001. PCC Empirical Design Guide. Version 1.0
with Optimized Geometry. 11th International Pavement Evaluation and Rehabilitation: NCHRP Project 1-37a. Washington, DC:
Symposium on Concrete Roads, October Reference Manual. NHI Course 131062. Transportation Research Board.
2022, Sevilla, Spain. Arlington, VA: National Highway Institute.
Okamoto, P.A., P. J. Nussbaum, K. D.
Daleiden, J. 1998. Video Inspection of Illinois Department of TransportationBureau Smith, M. I. Darter, T. P. Wilson, C. L. Wu,
Highway Edgedrain Systems. Publication of Materials and Physical Research (IDOT S. D. Tayabji. 1994. Guidelines for Timing
FHWA SA-98-044. Washington, DC: Federal BMPR). 2013. Approved/Qualified Product Contraction Joint Sawing and Earliest Loading
Highway Administration. List of Synthetic Fibers. Springfield, IL: Illinois for Concrete Pavements, Volume 1: Final
DOT. (www.dot.state.il.us/materials/synthet- Report. FHWA RD-91-079. Washington,
Federal Highway Administration (FHWA).
icfibers.pdf, accessed March 10, 2014) DC: Federal Highway Administration.
1994. Guidelines for Timing Construction
Joint Sawing and Earliest Loading for Concrete Kosmatka, S.H., and M. L. Wilson. 2011. Portland Cement Association. 1984. Thickness
Pavements. Volume 1. FHWA-RD-91-079. Design and Control of Concrete Mixtures, 15th Design for Concrete Highway and Street
Washington, DC: FHWA. Edition. PCA Bulletin EB001.15. Skokie, IL: Pavements. Skokie, IL: Portland Cement
Portland Cement Association. Association.
2003a. Distress Identification Manual
for the Long-Term Pavement Performance Ley, M.T., R. Felice, and J. M. Freeman. Raphael, J. M. 1984. Tensile Strength of
Program. 4th revised ed. Publication FHWA 2012. Assessment of Air Void System Concrete. ACI Journal 163:158165.
RD-03-031. Washington, DC: Federal Requirements for Durable Concrete. Ames, IA:
Rasmussen, R. O., and S. I. Garber. 2009.
Highway Administration. National Concrete Pavement Technology
Nonwoven Geotextile Interlayers for Separating
Center, Iowa State University (www.intrans.
. 2009. Manual on Uniform Traffic Cementitious Pavement Layers: German
iastate.edu/research/documents/research-
Control Devices. 2003 ed. with revisions 1 and Practice and U.S. Field Trials. International
reports/mda_air_void_w_cvr.pdf, accessed
2 incorporated. Washington, DC: Federal Technology Scanning Program. Washington,
March 17, 2014)
Highway Administration. DC: Federal Highway Administration.
Leykauf, G., and D. Birmann. 2006.
Fick, G. 2010. Concrete Overlay Cost: Rasmussen, R. O., and D. K. Rozycki.
Concrete Pavements with Geotextile
Frequently Asked Questions. Concrete Overlay 2004. Thin and Ultra-Thin Whitetopping.
Interlayer in Germany: Measurements
Field Application Program. Ames, IA: NCHRP Synthesis of Highway Practice 338.
and Long-term Behavior. Proceedings,
National Concrete Pavement Technology Washington, DC: Transportation Research
10th International Symposium on Concrete
Center, Iowa State University. Board.
Roads. Brussels, Belgium: European Cement
Fournier, B., M-A Berube, K. J. Folliard, and Organisation (CEMBUREAU), World Road Riley, R. 2006. Modified ACPA Ultra-Thin
M. Thomas. 2010. Report on the Diagnosis, Association (PIARC). CD-ROM. Whitetopping Design Software.
Prognosis and Mitigation of Alka-silica Reaction
Mallela, J., G. Larson, T. Wyatt, J. Hall, Roesler, J., A. Bordelon, A. Ioannides, M.
(ASR) in Transportation Structures. FHWA-
and W. Barker. 2002. Users Guide for Beyer, and D. Wang. 2008. Design and
HIF-09-004. Washington, DC: Federal
Drainage Requirements in Pavements: DRIP Concrete Materials Requirements for Ultra-
Highway Administration. (www.fhwa.dot.
2.0 Microcomputer Program. DTFH61- Thin Whitetopping. Urbana, IL: University of
gov/pavement/concrete/pubs/hif09004/
00-F-00199. Champaign, IL: ERES Illinois at Urbana-Champaign.
hif09004.pdf, accessed March 10, 2014)
Consultants. (http://isddc.dot.gov/OLPFiles/
FHWA/010942.pdf, accessed March 10, Roesler, J. R., V. G. Cervantes, and A. N.
Hall, K. T., C. E. Correa, S. H. Carpenter,
2014) Amirkhanian. 2013. Accelerated Performance
and R. P. Elliott. 2001. Rehabilitation
Testing of Concrete Pavement with Short
Strategies for Highway Pavements. NCHRP
Minnesota Department of Transportation Slabs. International Journal of Pavement
Project C1-38. Washington, DC:
(MnDOT). 2013. The Effect of Joint Sealing Engineering, doi:10.1080/10298436.2011.5
Transportation Research Board.
on the Performance of Thin Whitetopping 75134.
Harrington, D. 2008. Guide to Concrete Sections at MnROAD. MnROAD [Safer,
Smarter, Sustainable Pavements through Simon, E., G. E. Gibson, C. T. Haas, J. T.
Overlays: Sustainable Solutions for Resurfacing
Innovative Research]. (www.dot.state.mn.us/ OConnor, B. Somali, and Z. Zhang. 2003.
and Rehabilitating Existing Pavements. 2nd
mnroad/reports/PDF%27s/jointsealing.pdf, Development of a Tool for Expediting Highway
ed. Ames, IA: National Concrete Pavement
accessed March 10, 2014) Construction While Retaining Quality. FHWA/
Technology Center, Iowa State University.
TX-03/4386-1. Austin, TX: Center for
Harrington, D, D. DeGraaf, R. Riley, R. O. National Cooperative Highway Research Transportation Research, University of Texas
Rasmussen, J. Grove, and J. Mack. 2007. Program (NCHRP). 2004. Development of at Austin.
Guide to Concrete Overlay Solutions. Ames, the 2002 Guide for the Design of New and
Rehabilitated Pavement Structures: Phase Smith, K. D., H. T. Yu, and D. G. Peshkin.
IA: National Concrete Pavement Technology
II. NCHRP 01-37A. Washington, DC: 2002. Portland Cement Concrete Overlays:
Center, Iowa State University.
Transportation Research Board. (http:/apps. State of the Technology Synthesis. Publication
Harrington, D., G. Fick, and P. Taylor. 2014 trb.org/cmsfeed/TRBNetProjectDisplay. FHWA IF-02-045. Washington, DC: Federal
(tentative). Preservation and Rehabilitation of asp?ProjectID=218, accessed March 10, 2014 Highway Administration.
Urban Concrete Pavements Using Thin Concrete
. 1982. Resurfacing with Portland Smith, K. D., T. E. Hoerner, and D. G.
Overlays: Solutions for Joint Deterioration
Cement Concrete. Synthesis 99 (discontinued). Peshkin. 2008 (draft). Concrete Pavement
in Cold Weather States. Ames, IA: National
Preservation Reference Manual. Ames, IA:
Concrete Pavement Technology Center, Iowa
. 1994. Portland Cement National Concrete Pavement Technology
State University.
ResurfacingA Synthesis of Highway Practice. Center, Iowa State University.
Synthesis 204 (discontinued).

142 Guide to Concrete Overlays


SOURCES

Snyder, M. B. 2011. Guide to Dowel Load The Transtec Group. No date. Material Vandenbossche, J. M. and M. Barman. 2010.
Transfer Systems for Jointed Concrete Roadway Specifications. (www.transtecgroup.com/ Whitetopping Overlay Design Considerations
Pavements. Ames, IA: National Concrete nonwoven-geotextile-interlayers-concrete- for the Development of Reflective Cracks
Pavement Technology Center, Iowa State pavements/ [search www.concreteontop.com], and Joint Sealing. In Transportation Research
University. accessed February 25, 2014) Record: Journal of the Transportation Research
Board.
Sutter, l., K. Peterson, G. Julio-Betancourt, Thomas, M. D. A., B. Fournier, K. J. Folliard,
D. Hooton, T. Van Dam, and K. Smith. and Y. A. Resendez. 2011. Alkali-Silica Vandenbossche, J., N. Dufalla, and Z. Li.
2008. The Deleterious Chemical Effects of Reactivity Field Identification Handbook. 2012. A Revised Thin and Ultra-Thin Bonded
Concentrated Deicing Solutions on Portland FHWA HIF-12-022. Washington, D.C.: Whitetopping Design Procedure. Presented at
Cement Concrete, Final Report. Publication Federal Highway Administration. 2013 TRB Annual Meeting.
SD2002-01-F. Pierre, SD: South Dakota
Torres, H. N., J. Roesler, R. O. Rasmussen, Vandenbossche, J. 2013. BCOA ME.
Department of Transportation.
and D. Harrington. 2012. Guide to the Swanson School of Engineering, University
Tayabji, S., J. Anderson, H. Barzegar, G. Design of Concrete Overlays Using Existing of Pittsburgh. (www.engineering.pitt.edu/
Fick, E. Gowder, J. Shilstone, P. C. Taylor, Methodologies. FHWA Project DTFH61- Vandenbossche/BCOA-ME_DesignGuide/,
and M. Torres. 2007. Supplemental Report 06-H-00011 (Work Plan 13). Ames, IA: accessed March 10, 2014)
for Proposed Specification for Construction of National Concrete Pavement Technology
Concrete Airfield Pavement. Report IPRF-01- Center, Iowa State University. Wade, M. J., G. D. Cuttell, J. M.
G-002-04-1A. Washington, DC: Innovative Vandenbossche, K. D. Smith, M. B. Snyder,
Trevino, M., B. F. McCullough, and D. W. and H. T. Yu. 1995. Performance of Concrete
Pavement Research Foundation.
Fowler. 2004. Techniques and Procedures Pavements Containing Recycled Concrete
Taylor, P. C., ed. 2006. Integrated Materials for Bonded Concrete Overlays. FHWA/ Aggregate. Report No. DTFH61-93-C-
and Construction Practices for Concrete TX-05/0-4398-2. Austin, TX: Center for 000133-Task B. Interim Report. Washington,
Pavement: A State-of-the-Practice Manual. Transportation Research, University of Texas DC: Federal Highway Administration.
Publication FHWA HIF-07-004. Ames, at Austin.
IA: Center for Transportation Research and Walker, W. W. and J. A. Holland. 2007.
Van Dam, T., P. Taylor, G. Fick, D. Gress, M. Performance-Based Dowel Design: Lift-truck
Education, Iowa State University.
Van Geem, and E. Lorenz. 2012. Sustainable design changes require a new look at joint
Taylor, P., R. O. Rasmussen, H. Torres, G. Concrete Pavements: A Manual of Practice. durability. In Concrete Construction Jan. 2007.
Fick, D. Harrington, and T. Cackler. 2012. Ames, IA: National Concrete Pavement
Guide for Optimum Joint Performance of Technology Center, Iowa State University. Yurdakul, E. 2010. Optimizing concrete
Concrete Pavements. Ames, IA: National (www.cptechcenter.org/technical-library/ mixtures with minimum cement content for per-
Concrete Pavement Technology Center, Iowa documents/Sustainable_Concrete_ formance and sustainability. MS Thesis. Ames,
State University. Pavement_508.pdf, accessed March 10, 2014) IA: Iowa State University.

TCPavements. 2010. Optipave V2.0. (www.


tcpavements.com/index.php?op=0&lang=en,
accessed March 10, 2014)

Guide to Concrete Overlays 143


SOURCES

SOURCES

BIBLIOGRAPHY

AASHTO. 1993. Guide Specifications for Cable, J. K., F. S. Fanous, H. Ceylan, D. . 2012. Alkali-Silica Reactivity Field
Highway Construction. Washington, DC: Wood, D. Frentress, T. Tabbert, S.-Y. Oh, Identification Handbook. FHWA-HIF-12-022.
American Association of State Highway and and K. Gopalakrishnan. 2005. Design and Washington, DC: Federal Highway
Transportation Officials. Construction Procedures for Concrete Overlay Administration.
and Widening of Existing Pavements. IHRB
. 2002. Guide for Design of New and Mack, J. W., L. D. Hawbaker, and L. W.
Project TR-511. Ames, IA: Iowa State
Established Pavement Structures. Washington, Cole. 1998. Ultrathin Whitetopping: State-
University.
DC: Transportation Research Board. of-the-Practice for Thin Concrete Overlays
Cable, J. K., J. M. Hart, and T. J. Ciha. of Asphalt. Transportation Research Record
American Concrete Pavement Association
2001. Thin Bonded Overlay Evaluation. 1610:3943.
(ACPA). 2000. Repair of Ultra-Thin
IHRB Project HR-559. Ames, IA: Iowa State
Whitetopping: Roadways and Airfields. Mathis, D. M. 1990. Pavement Drainage
University.
Publication PA397P. Skokie, IL: American Rehabilitation. Proceedings, Virginia Pavement
Concrete Pavement Association. Delatte, N., S. Chen, J. Davidson, A. Drainage Workshop. Williamsburg, VA:
Sehdev, N. Amer, and M. Endfinger. 2001. Virginia Department of Transportation.
. 2006. Concrete Pavement Field
Design and Quality Control of Concrete
Reference: Preservation and Repair. Publication McGhee, K. H. 1994. Portland Cement
Overlays. UTCA Report 01220. Tuscaloosa,
EB 239 P. Skokie, IL: American Concrete Concrete Resurfacing. NCHRP Synthesis of
AL: University Transportation Center for
Pavement Association. Highway Practice 204. Washington, DC:
Alabama.
Transportation Research Board.
. 2007. Subgrades and Subbases for
ERES Consultants. 1999. Evaluation of
Concrete Pavements. EB204P. Skokie, IL: National Cooperative Highway Research
Unbonded Portland Cement Concrete Overlays.
American Concrete Pavement Association. Program (NCHRP). 2005. Versions
NCHRP Report 415. Washington, DC:
0.900 and 1.0 of the M-E Pavement
. 1999. Ultra-Thin Whitetopping. Transportation Research Board.
Design Software. NCHRP Project 1-40A.
Information Series IS100.02P. Skokie, IL:
Federal Highway Administration (FHWA). Washington, DC: Transportation Research
American Concrete Pavement Association.
1992. Drainable Pavement Systems, Participant Board.
. 2007. Concrete Intersections: A Guide Notebook. FHWA-SA-92-008. Washington,
. 2006. Technical Assistance to
for Design and Construction. TB019P. Skokie, DC: Federal Highway Administration.
NCHRP and NCHRP Project 1-40a.
IL: American Concrete Pavement Association.
. 1999. Pavement Preventive NCHRP Project 1-40d. Washington, DC:
. 2008. Concrete Pavement Field Maintenance Reference Manual. Washington, Transportation Research Board.
Reference: Pre-Paving. EB237P. Skokie, IL: DC: Federal Highway Administration.
. 2007. AASHTO Mechanistic-
American Concrete Pavement Association.
. 2000. Insights into Pavement Empirical Design Guide. Version 1.0.
Altoubat, S. A., J. R. Roesler, D. A. Lange, Preservation: A Compendium. Washington, NCHRP Project 1-37a. Washington, DC:
and K.-A. Rieder. 2008. Simplified Method DC: Federal Highway Administration. Transportation Research Board.
for Concrete Pavement Design with Discrete
. 2001a. Pavement Preservation: Rasmussen, R. O. 2008. Geotextile Interlayers
Structural Fibers. Construction and Building
Selecting Pavements for Preventive Maintenance. for Separating Cementitious Pavement
Materials 22 (3): 384393.
NHI Course 131058. Washington, DC: Layers: European Practice and U.S. Field
Anderson, S. D., G. L. Ullman, and B. Federal Highway Administration. Trials. Washington, DC: Federal Highway
C. Blaschke. 2002. A Process for Selecting Administration and Transtec Group, Inc.
. 2001b. PCC Pavement Evaluation
Strategies for Rehabilitation of Rigid Pavements.
and Rehabilitation. NHI Course 131062. Riley, R. C., A. Gotlif, and J. Mallela. 2005a.
NCHRP Project 10-50A. Washington, DC:
Washington, DC: Federal Highway Whitetopping: Atypical is Typical. Proceedings
Transportation Research Board.
Administration. of the International Conference on Best Practices
Cable, J. K., M. L. Anthony, F. S. Fanous, and for Ultrathin and Thin Whitetoppings. Denver,
. 2004. Pavement Preservation:
B. M. Phares. 2006. Evaluation of Composite CO, April 1215.
Integrating Pavement Preservation Practices
Pavement Unbonded Overlays. IHRB Project
and Pavement Management. NHI Course Riley, R. C., L. Titus-Glover, J. Mallela,
TR-478. Ames, IA: Iowa State University.
131104. Washington, DC: Federal Highway S. Waalkes, and M. Darter. 2005b.
Cable, J. K., L. E. Edgar, and D. R. Administration. Incorporation of Probabilistic Concepts into
Anderson. 2005. Ultra-Thin Portland Cement Fatigue Analysis of Ultrathin Whitetopping
. 2007. Thin WhitetoppingThe
Concrete Overlay Extended Evaluation. IHRB as Developed for the American Concrete
Colorado Experience. FHWA-HIF-07-025.
Project TR-432. Ames, IA: Iowa State Pavement Association. Proceedings of the
Washington, DC: Federal Highway
University. International Conference on Best Practices for
Administration.
Ultrathin and Thin Whitetoppings. Denver,
CO, April 1215.

144 Guide to Concrete Overlays


SOURCES

Roesler, J. R. 2004. Fracture of Plain and Titus-Glover, L., J. Mallela, M. I. Darter, Wu, C.-L., S. M. Tarr, T. M. Refai, M. A.
Fiber-reinforced Concrete Slabs under G. Voigt, and S. Waalkes. 2005. Enhanced Nagi, and M. J. Sheehan. 1999. Development
Monotonic Loading. Journal of Materials in Portland Cement Concrete Fatigue Model of Ultra-Thin Whitetopping Design Procedure.
Civil Engineering 16 (5): 452460. for StreetPave: Rigid and Flexible Pavement PCA R&D Serial 2124. Skokie, IL: Portland
Design 2005. Transportation Research Record Cement Association.
Roesler, J. R. 2007. Design and Specification
1919:2937.
of Concrete Pavements with Structural Wells, G. K., and S. M. Wiley. 1987. The
Fibers. Paper presented at the International Vandenbossche, J. M., and A. J. Fagerness. Effectiveness of Portland Cement Concrete
Workshop on Best Practices for Concrete 2002. Performance, Analysis, and Repair Pavement Rehabilitation Techniques. FHWA/
Pavements, Recife, Brazil. of Ultrathin and Thin Whitetopping CA/TL-87/10. Washington, DC: Federal
at Minnesota Road Research Facility. Highway Administration.
Sheehan, M. J., S. M. Tarr, and S. D. Tayabji.
Transportation Research Record 1809:191198.
2004. Instrumentation and Field Testing of Young, B. 1990. Evaluation of the
Thin Whitetopping Pavements in Colorado VDOT. 1990. Guidelines for Providing Performance of Fin Drains in Georgia.
and Revision of the Existing Colorado Thin Improved Drainage Systems for VDOT FHWA-GA-90-8709. Atlanta, GA: Georgia
Whitetopping Procedure. Report CDOT- Pavement Structures. Charlottesville, VA: Department of Transportation.
DTD-R-2004-12. Denver, CO: Colorado Virginia Department of Transportation.
Department of Transportation.
Winkelman, T. J. 2002. Bonded Concrete
Tarr, S. M., M. J. Sheehan, and P. A. Overlay Performance in Illinois. Report
Okamoto. 1998. Guidelines for the Thickness FHWA/IL/PRR 143. Springfield, IL: Illinois
Design of Bonded Whitetopping Pavements Department of Transportation.
in the State of Colorado. Report CDOT-
DTD-R-98-10. Denver, CO: Colorado
Department of Transportation.

Guide to Concrete Overlays 145


MEMO
MEMO
2711 South Loop Drive, Suite 4700
Ames, IA 50010-8664
515-294-5798
www.cptechcenter.org

You might also like