You are on page 1of 4

RT Film interpretation meeting by NSRP and JGCS

REPORT No. 13
NSRP 3rd RT

UPDATED: 1-Jan-2018

Unit Area JGCS NSRP Size Thick.


No. Date Spool drawing No. Line No. (inch) (mm) Welder No. Mat'l RT%
No. Joint No. Joint No.

870 1-Jan 061 AA05 AA05-LN-061-9602-02 013 1 4.55 3632 SS 10


871 1-Jan 061 AA05 AA05-LN-061-9603-01 010 0.5 3.73 3632 SS 10
872 1-Jan 084 A311 A311-AM-084-0351-01 012 8 3.76 3306 SS 10
873 1-Jan 084 A311 A311-AM-084-0351-01 006 8 3.76 3306 SS 10
874 1-Jan 084 A311 A311-AM-084-0351-01 054 8 3.76 3295 SS 10
875 1-Jan 084 A311 A311-AM-084-0351-01 042 8 3.76 3295 SS 10
876 1-Jan 084 A311 A311-AM-084-0351-01 048 8 3.76 3295 SS 10
877 1-Jan 084 A311 A311-AM-084-0351-01 036 8 3.76 3295 SS 10
878 1-Jan 084 A311 A311-AM-084-0351-01 030 8 3.76 3916 SS 10
879 1-Jan 084 A311 A331-AM-084-0101-01 098 12 4.57 3917 SS 10
880 1-Jan 084 A331 A331-AM-084-0101-01 003 12 4.57 3917 SS 10
881 1-Jan 084 A331 A331-AM-084-0101-01 009 3 3.05 3295 SS 10
882 1-Jan 084 A331 A331-AM-084-0402-01 028 3 3.05 3295 SS 10
883 1-Jan 140 AG1R AG1R-P-140-3002-27 001 2 5.54 3930 CS 10
884 1-Jan 140 AG1R AG1R-P-140-3002-29 001 2 5.54 3064 CS 10
885 1-Jan 140 AG1R AG1R-P-140-3005-27 001 2 5.54 3509 CS 10
886 1-Jan 140 AG1R AG1R-P-140-3005-28 008 2 5.54 3919 CS 10
887 1-Jan 140 AG1R AG1R-P-140-3135-07 007 3 5.54 3343 CS 10
888 1-Jan 140 AG1R AG1R-P-140-3144-03 001 4 6.02 3047 CS 10
889 1-Jan 140 AG1R AG1R-P-140-3144-08 001 4 6.02 3130 CS 10
Page 1 of 4
Unit Area JGCS NSRP Size Thick.
No. Date Spool drawing No. Line No. (inch) (mm) Welder No. Mat'l RT%
No. Joint No. Joint No.

890 1-Jan 061 AA05 AA05-LN-061-8511-02 004 0.5 3.73 3632 SS 10


891 1-Jan 061 AA05 AA05-LN-061-8132-01 018 0.5 3.73 3632 SS 10
892 1-Jan 061 AA05 AA05-LN-061-8132-01 002 0.5 3.73 3632 SS 10
893 1-Jan 044 A54A A54A-FG-044-0131-01 018 2 3.91 3330 SS 10
894 1-Jan 044 A54A A54A-FG-044-0114-01 007 2 3.91 3330 SS 10
895 1-Jan 044 A54A A54A-FG-044-0111-01 021 2 3.91 3330 SS 10
896 1-Jan 020 AC23 AC23-FLG-020-0105-01 009 2 5.54 9241 CS 10
897 1-Jan 084 A311 A311-AM-084-0351-01 018 8 3.76 3306 SS 10
898 1-Jan 022 AF22 AF22-P-022-6407-01 027 18 7.92 CS 10
899 1-Jan 022 AF25 AF25-LPS-022-7511-01 004 1 4.55 CS 10
900 1-Jan 022 AF25 AF25-LPS-022-7511-01 055 1 4.55 CS 10
901 1-Jan 022 AF25 AF25-P-022-5006-01 001 6 10.97 CS 10
902 1-Jan 022 AF33 AF33-P-022-0304-02 008 12 9.53 CS 10
903 1-Jan 022 AF33 AF33-P-022-5909-01 031 3 5.49 CS 10
904 1-Jan 023 AF33 AF33-CBD-023-7002-01 004 10 12.7 CS 10
905 1-Jan 023 AF43 AF43-AM-023-2908-01 013 3 5.49 CS 10
906 1-Jan 023 AF43 AF43-P-023-1306-01 017 30 9.53 CS 10

Page 2 of 4
by NSRP and JGCS

Summary
Accept 19 Severe repair total 487
100% line: Severe defect 29 Severe repaired 5 (RT done)
100% line: Minor defect 16 Minor repair total 16
10% line: Severe defect 458 Minor repaired 0
10% line: Minor defect 384
Reviewed total 906

NSRP JGCS Final Interpretation Inspection type Severe Defect Criteria Repair status Piping component PWHT
Interpretation Interpretation by NSRP and JGCS

Reject/IP Reject/IP Reject/IP NSRP 3rd RT Severe Defect


Reject/IP Reject/IP Reject/IP NSRP 3rd RT Severe Defect
Reject/LOF Reject/LOF Reject/LOF NSRP 3rd RT Severe Defect
Reject/IP Reject/IP Reject/IP NSRP 3rd RT Severe Defect
Reject/IP Reject/IP Reject/IP NSRP 3rd RT Severe Defect
Reject/IP Reject/IP Reject/IP NSRP 3rd RT Severe Defect
Reject/IP Reject/IP Reject/IP NSRP 3rd RT Severe Defect
Reject/LOF Reject/LOF Reject/LOF NSRP 3rd RT Severe Defect
Reject/LOF Reject/LOF Reject/LOF NSRP 3rd RT Severe Defect
Reject/LOF/IP Reject/LOF/IP Reject/LOF/IP NSRP 3rd RT Severe Defect
Reject/IP Reject/IP Reject/IP NSRP 3rd RT Severe Defect
Reject/Poor Profile Reject/Poor Profile Reject/Poor Profile NSRP 3rd RT Severe Defect
Reject/Poor Profile Reject/Poor Profile Reject/Poor Profile NSRP 3rd RT Severe Defect
Reject/LOF Reject/LOF Reject/LOF NSRP 3rd RT Minor Defect
Reject/LOF Reject/LOF Reject/LOF NSRP 3rd RT Minor Defect
Reject/LOF Reject/LOF Reject/LOF NSRP 3rd RT Minor Defect
Reject/Po Reject/Po Reject/Po NSRP 3rd RT Minor Defect
Reject/IP Reject/IP Reject/IP NSRP 3rd RT Severe Defect
Reject/LOF Reject/LOF Reject/LOF NSRP 3rd RT Minor Defect
Reject/Po Reject/Po Reject/Po NSRP 3rd RT Minor Defect
Page 3 of 4
NSRP JGCS Final Interpretation Inspection type Severe Defect Criteria Repair status Piping component PWHT
Interpretation Interpretation by NSRP and JGCS

Reject/IP Reject/IP Reject/IP NSRP 3rd RT Severe Defect


Reject/IP Reject/IP Reject/IP NSRP 3rd RT Severe Defect
Reject/IP Reject/IP Reject/IP NSRP 3rd RT Severe Defect
Reject/IP Reject/IP Reject/IP NSRP 3rd RT Severe Defect
Reject/IP Reject/IP Reject/IP NSRP 3rd RT Severe Defect
Reject/IP Reject/IP Reject/IP NSRP 3rd RT Severe Defect
Reject/Po Reject/Po Reject/Po NSRP 3rd RT Minor Defect
Reject/IP Reject/IP Reject/IP NSRP 3rd RT Minor Defect
Reject/LOF Reject/LOF Reject/LOF NSRP 3rd RT Minor Defect
Reject/LOF Accept Accept NSRP 3rd RT Accept
Reject/Poor Profile Reject/Poor Profile Reject/Poor Profile NSRP 3rd RT Severe Defect
Reject/Po Accept Accept NSRP 3rd RT Accept
Reject/LP Reject/IP Reject/IP NSRP 3rd RT Minor Defect
Reject/Po Reject/Po Reject/Po NSRP 3rd RT Minor Defect
Reject/LP/LF Reject/IP/LF Reject/IP?LF NSRP 3rd RT Minor Defect
Reject/LF/Po Reject/LF/Po Reject/LF/Po NSRP 3rd RT Minor Defect
Reject/Po Accept Accept NSRP 3rd RT Accept

Page 4 of 4