You are on page 1of 3

Canal Crossing By John E. Christopher, Ph.D., P.E.

Erection challenges for a


bridge replacement over
the Erie Canal brought
about a buoyant solution.

E
recting a Warren truss bridge
over a relatively small water-
way like the Erie Canal might
seem routine at first. However,
construction constraints dur-
ing the $5.5 million replacement of the
Prospect Street crossing in Lockport, NY
introduced challenges that required an
out of the ordinary solution.
The new bridge is located just
northeast of Prospect Street, carry-
ing Stevens Street. The canal is less
than 120’ (36.5 m) wide at the original
Prospect Street crossing, but the re-
placement bridge is oriented approxi-
mately 45 degrees to the canal. In ad-
Floating the fully assembled bridge into place.
dition, abutments are perpendicular
to the axis of the bridge and set back
some distance from the canal edges.
This arrangement required a signifi- struction, many conditions had to be two possibilities:
cant increase in span length, from the considered: 1. Erect each of the two trusses separately
original 117’-8” (35.9 m) at the Pros- ➜ The center of the span was not to coin- but fully assembled, and then fill in the
pect Street crossing to 267’-8” (81.3 m) cide with the center of the canal. bracing, floor beams, and stringers.
at the new location. ➜ Sediment in the canal bottom contains 2. Erect as much of the bridge as possi-
The new bridge was fabricated with contaminated and hazardous mate- ble on pontoons, and then float it into
roughly 600 tons of ASTM A790M, Grade rials, which could not be disturbed. place.
345W structural steel. During new con- Considering this condition, the New
York Department of Transportation re- Land-based Erection Scheme
stricted the contractor from any con- In order to execute the first option
struction operation or technique that with any efficiency, each truss would
would disturb the canal bottom. This have had to be assembled on its side,
restriction clearly and specifically ex- with both chords temporarily supported
cluded the use of any erection bents on skids adjacent to one of the abutments.
within or upon the sediment. This operation would have then required
➜ The navigation season for the canal is the truss to be upended, lifted into posi-
May 1 through November 25, which tion, and placed onto the abutment seats.
includes recreational use. At other A number of problems associated
times, the canal is drained. with this approach emerged. First, the
➜ High voltage lines cross the canal ad- length, weight, and lack of lateral stiff-
jacent to the new bridge location. ness of the trusses indicated there was
➜ The new bridge would support a wa- insufficient resistance to lateral-torsion-
ter main and two gas lines located be- al buckling under their self-weight. As
low, through the outboard sidewalk a result, this approach would have re-
John E. Christopher is president of Struc- brackets. quired additional temporary stiffening
tural Engineering Concepts, Pittsburgh, These conditions presented several elements to stabilize each truss when
and Adjunct Assistant Professor of Civil challenges to the erector. Elimination subjected to conditions of erection and
and Environmental Engineering at the of temporary erection bents limited the handling. Estimates indicated the fabri-
University of Pittsburgh. means to erect the new bridge to only cation and assembly of these stiffening

June 2005 • Modern Steel Construction


elements would have been costly.
Second, the extra weight of these stiff-
ening elements would have increased the
lift weight close to the maximum hoist
capacity of the Manitowoc 2250 crawler
crane with the MAX-ER 2000 selected for
the project. The weight of one completed
truss assembly was about 300 kips with
an additional weight of about 60 kips for
the stiffening elements. Depending on
the weight of the rigging, the outreach
capacity of the crane with this load was
about 75’. A larger rig was not available.
In addition, the combined weight of the Flexifloat pontoon arrangement.
lifted load and the crane weight would
have placed a significant surcharge on Stage 1 — Assembly 1
the embankment at the edge of the canal.
10 @ 26'-8 = 268'-8
Also, the first truss would have had
to safely resist lateral storm wind loads 338.16 k

without the benefit of the second truss


Y = 11.92 ft

and the lateral bracing system in place. U1 U2 U3 U4 U5 U6 U7 U8 U9

Moreover, the bridge bearings were lo- CG

cated at the bottom chord. Without addi-


tional temporary supports, there would L0 L1 L2 L3 L4 L5 L6 L7 L8 L9 L10
Top of Barge Deck
be nothing to prevent overturning from
lateral wind load. This required the use of X = 103.41 ft Shoring

additional temporary structural elements ELEVATION


to resist superimposed lateral forces. Stage 2 — Assemblies 1 & 2
The associated problems and cost of
this approach indicated the need for an 611.26 k
Y = 12.71 ft

alternate scheme. As this approach was


being considered, an ironworker at one U1 U2 U3 U4 U5 U6 U7 U8 U9

of the planning meetings said, “This CG

looks like a float-in job to me!”


L0 L1 L2 L3 L4 L5 L6 L7 L8 L9 L10

Pontoon-based Erection Scheme Top of Barge Deck

Taking his suggestion, the erector con- X = 133.32 ft Shoring

tacted Robishaw Engineering in Hous- ELEVATION


ton to determine the feasibility of this Stage 3 — Assemblies 1, 2 & 3
approach using their Flexifloat sectional
barge equipment. They reported that 884.72 k

Flexifloat pontoon modules locked to-


Y = 12.36 ft

gether could form the working surface U1 U2 U3 U4 U5 U6 U7 U8 U9

required to carry the bridge. The inter- CG

locking arrangement of these modules


had the strength and stiffness to make L0 L1 L2 L3 L4 L5 L6 L7 L8 L9 L10
Top of Barge Deck
the pontoon assembly behave as a single
unit. This characteristic provided the X = 163.80 ft Shoring
necessary floating capacity and stability ELEVATION
to support the whole bridge, mounted on
shoring about 30’ above the canal, when Stage 4 — Entire Bridge
subjected to storm-level winds. It quickly 1156.84 k
became apparent that this approach was
Y = 12.23 ft

safer and more economical than the first. U1 U2 U3 U4 U5 U6 U7 U8 U9

Once the decision was made to float CG


the bridge into place, execution of the
plan was started with the necessary en- L0 L1 L2 L3 L4 L5 L6 L7 L8 L9 L10

gineering. The erector selected Structural Top of Barge Deck

Engineering Concepts of Pittsburgh to X = 133.62 ft Shoring


identify the major lifts, design the rig- ELEVATION
ging, design the temporary shoring that
supported the bridge above the pontoons, The stages of loading on the pontoons, starting at the center of the bridge and working outward.

June 2005 • Modern Steel Construction


and design the jacking arrangement nec- loading stages, the list and trim limits, the pontoon shoring and everything was
essary to lower the bridge onto its abut- and the possibility of storm wind loads. ready, it took about eight hours to float it
ment seats. This design kept the pontoon deck forces into place and remove the pontoons and
Robishaw developed a preliminary within the 5,000 psf deck load-bearing shoring. The jacking operation took place
plan for the pontoon arrangement based limit specified by Robishaw Engineering. during the following week.
on the loads calculated by Structural En- The shoring design also included means The use of high-strength steel made
gineering Concepts. The plan required the to jack the assembly support points to fa- the float-in erection method possible. The
use of a group of pontoons that formed cilitate making the connections between steel frame was light enough to temporar-
a rectangular surface area 120’ long by assemblies. ily support the fully assembled bridge on
70’ wide. Although this defined the pon- In addition to the shoring design, pontoons and shoring. The heavier load
toon system needed to safely support the Structural Engineering Concepts planned of an alternative reinforced concrete struc-
bridge, an accurate survey of the canal in- the procedure to move the bridge into ture would have made it impractical, or
dicated the corners of the pontoon group place. Because the bridge is skewed with even impossible, to implement this meth-
in this preliminary arrangement would respect to the canal, it could not be moved od. As it was, there was no extra space in
interfere with the canal edges. This prob- into place laterally without interference the canal for the additional pontoons that
lem was exacerbated by the fact that the with the abutment backwalls. As a result, would have been necessary to resist the
center of the bridge span and the center the shoring had to be high enough to al- added weight of a concrete design.
of the canal did not coincide. In addi- low the bearing points at the end of the Also, the restriction imposed by NY
tion, the bridge could only be mounted bridge to swing over the high point of the DOT to specifically exclude the use of
eccentrically to the pontoons by no more abutment backwalls. The shoring height any erection bents within or upon the ca-
than about 1.5’. Therefore, the pontoon was determined using this consideration, nal sediments made a poured-in-place or
arrangement required a modification. the normal canal water elevation, and the pre-cast structure of this span impossible
Based on survey information, Struc- pontoon freeboard and trim estimated by to erect. Aside from being specified by
tural Engineering Concepts suggested Robishaw Engineering. the Erie Canal Authority, structural steel
a revised pontoon arrangement that ap- The final item of consideration for the was the optimum choice for this project
proximated a parallelogram. Robishaw procedure was to determine how to ex- in light of the construction conditions
Engineering used this suggestion to tract the pontoons from under the bridge and limitations. 
produce the arrangement shown in the after it was floated into place. The depth
figure on the previous page. With this ar- of the canal water, plus the reserve pon- Owner
rangement, the pontoons supported the toon freeboard, allowed the operation to New York State Dept. of Transportation
bridge at each stage of the erection. use ballast in the pontoons to lower the
Engineers
In an area to the north and east of the bridge by about 2’. The erector also con-
Hatch Mott MacDonald, Buffalo, NY
construction site at the edge of the canal, tacted the Erie Canal Authority to request
(bridge design)
the erector made four main assemblies of a reduction in the canal water level dur-
the bridge. Each assembly included the ing the final placement operation. Initial- Structural Engineering Concepts,
main truss members, floor beams, deck ly, the Authority indicated the possibility Pittsburgh (erection)
stringers, top chord and bottom chord of reducing the water level by about 2’ Robishaw Engineering, Inc., Houston
lateral bracing, sidewalk brackets, side- after the bridge was moved into place. (pontoon)
walk stringers, and utility piping. Struc- Structural Engineering Concepts speci-
tural Engineering Concepts compiled the fied a jacking procedure and designed
Engineering Software
STAAD 21.0 (bridge design)
weights and centers of gravity of these the temporary 5’-high timber blocking
STAAD Pro 2003 (erection)
units for the purpose of designing the at the abutments, considering that flood-
rigging and shoring. Using the Manito- ing the pontoons and draining the canal Detailer and Fabricator
woc 2250 crawler crane with the MAX- could lower the bridge by about 4’. American Bridge Manufacturing,
ER 2000, the heaviest lift was 356 kips In October of 2004, roughly five Coraopolis, PA, AISC member
at an outreach of 65’. The capacity of the months after the steel erection process
crane allowed its position to be moved was initiated, the bridge was ready to be
Detailing Software
AutoCAD
far enough away from the canal wall to moved into place. However, the previous
avoid adding any significant lateral soil season produced rainfall far above aver- General Contractor
pressure on it. age, and the canal water level was about Holmes & Murphy, Inc., Orchard Park, NY
The stages of loading on the pontoons, 4’ higher than normal. In addition, the
starting at the center of the bridge and Erie Canal Authority did not reduce the
working outward, is shown in the figure canal water level during the operation.
on the previous page. Note that the cen- These conditions required the height
ter of gravity shifts considerably as each of the temporary blocking at the abut-
assembly is placed on the shoring. Rob- ments to increase to about 12’. This also
ishaw Engineering considered these con- increased the labor necessary to jack the
ditions and provided ballast instructions structure down onto the bearing seats.
that kept the pontoons within allowable In spite of the canal’s unexpectedly
list and trim limits. high water level, the operation went
The design of the shoring by Structural smoothly with no other apparent prob-
Engineering Concepts considered these lems. Once the bridge was erected on

June 2005 • Modern Steel Construction

You might also like