Physical and Financial Progress of Work in SIS 2011-12upto 28.2.

2015

Date of Expected Stage of work


Sl. Out lay of Executing Name of the Expenditure Bills pending
Name of the work Funds released Commencement date of & % of
No. work Agency Contractor incurred at PAO/APAO
of work Completion completion

1 2 3 4 5 6 7 8 9 10 11
1 Construction of Command 45.00 45.00 lakhs on R&B M/S Satya 22.9.2014 5.2.2015 2,068,492.00 - plasterings,
and Control Centre, lakhs 03.3.2014 & Department, Constructions, E.O.T plumbing, POP
Kakinada revalidated Kakinada Kakinada 30.3.2015 ceiling
on09.9.2014 completed &
85% completed

Asst. Executive Engineer (R&B), Dy. Executive Engineer (R&B),


East Buildings Section, Kakianda. Buildings Sub Division, Kakinada

Executive Engineer (R&B),


(R&B) Division., Kakinada.