Nucleus Networks Sierra Metals - Global WAN/VSAT Project

WBS Title Given Work Given Earliest Traits WK 22, May 28 WK 23, June 4 WK 24, June 11 WK 25, June 18
Code Start 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
0 VSAT-MX-implementation-rev2 June 2, 2017 VSAT-MX-implementation-rev2

1 International Travel International Travel

1.1 Jeff and Pablo to Lima June 5, 2017 Jeff and Pablo to Lima

Jeff Nantais 1 day Jeff Nantais

1.2 Peru to Mexico Jun 18, 2017 Peru to Mexico

Jeff Nantais 1 day Jeff Nantais

Pablo Reyes 1 day Pablo Reyes

2 Peru Peru

2.1 Lima Implementation Lima Implementation

2.1.1 Meraki MX Implementation June 6, 2017 Meraki MX Implementation

Jeff Nantais 3 days Jeff Nantais

Marco Veliz Gómez 3 days Marco Veliz Gómez

Pablo Reyes 3 days Pablo Reyes

Victor Yparraguirre 3 days Victor Yparraguirre

2.2 Preparation for Yauricocha Preparation for Yauricocha

2.2.1 Health Tests for Marlink Jun 12, 2017


Health Tests for Marlink Engineers
Engineers
Marlink Engineers 5 hours Marlink Engineers

2.2.2 Altitude Acclimatization Altitude Acclimatization

Jeff Nantais 1 day Jeff Nantais

Marlink Engineers 1 day Marlink Engineers

Pablo Reyes 1 day Pablo Reyes

Victor Yparraguirre 1 day Victor Yparraguirre

2.3 Lima to Yauricocha Jun 13, 2017 Lima to Yauricocha

Jeff Nantais 1 day Jeff Nantais

Victor Yparraguirre 1 day Victor Yparraguirre

Marlink Engineers 1 day Marlink Engineers

Pablo Reyes 1 day Pablo Reyes

2.4 Yauricocha Implementation Yauricocha Implementation

2.4.1 VSAT Installation & Turn-up VSAT Installation & Turn-up

Jeff Nantais 1 day Jeff Nantais

Marlink Engineers 3 days Marlink Engineers

Emilio Apaza 1 day Emilio Apaza

2.4.2 Meraki MX Implementation Meraki MX Implementation

Jeff Nantais 3 days Jeff Nantais

Emilio Apaza 3 days Emilio Apaza

Pablo Reyes 3 days Pablo Reyes

Victor Yparraguirre 3 days Victor Yparraguirre

2.5 Travel Yauricocha to Lima Travel Yauricocha to Lima

Jeff Nantais 1 day Jeff Nantais

Marlink Engineers 1 day Marlink Engineers

Pablo Reyes 1 day Pablo Reyes

Victor Yparraguirre 1 day Victor Yparraguirre

3 Mexico Mexico

3.1 Travel to Bolivar (Flight) Travel to Bolivar (Flight)

Jeff Nantais 3 hours Jeff Nantais

Hector Moreno 3 hours Hector Moreno

Marlink Engineers 3 hours Marlink Engineers

Pablo Reyes 3 hours Pablo Reyes

3.2 Bolivar Implementation Bolivar Implementation

3.2.1 VSAT Installation & Turn-up VSAT Installation & Turn-up

Marlink Engineers 3 days Marlink Engineers

Pablo Reyes 1 day Pablo Reyes

Jeff Nantais 1 day Jeff Nantais

3.2.2 Meraki Implementation Meraki Implementation

Jeff Nantais 3 days Jeff Nantais

Hector Moreno 3 days Hector Moreno

Pablo Reyes 3 days Pablo Reyes

3.3 Cusi Implementation Cusi Implementation

3.3.1 Travel to Cusi Travel to Cusi

Hector Moreno 1 day Hector Moreno

Jeff Nantais 1 day Jeff Nantais

Pablo Reyes 1 day Pablo Reyes

3.3.2 Meraki MX Implementation Meraki MX Implementation

Hector Moreno 1 day Hector Moreno

Jeff Nantais 1 day Jeff Nantais

Pablo Reyes 1 day Pablo Reyes

3.4 Chihuahua Implementation Chihuahua Implementation

3.4.1 Chihuahua Meraki


Implementation - Initial Chihuahua Meraki Implementation - Initial Setup
Setup
Hector Moreno 1 day Hector Moreno

Jeff Nantais 1 day Jeff Nantais

Pablo Reyes 1 day Pablo Reyes

3.4.2 Cusi to Chihuahua Cusi to Chihuahua

Hector Moreno 3 hours Hector Moreno

Pablo Reyes 3 hours Pablo Reyes

Jeff Nantais 3 hours Jeff Nantais

3.4.3 Mexico Meraki


Implementation - Post Mexico Meraki Implementation - Post Setup
Setup
Hector Moreno 1 day Hector Moreno

Jeff Nantais 1 day Jeff Nantais

Pablo Reyes 1 day Pablo Reyes