ID Task Task Name Duration

1 IN-BUILDING AT PIA 42 days


2 LOA AWARD (APPROVED) 2 days
3 TP REVISED APPROVAL (BY DNB) 5 days
4 MATERIAL PREPARATION 3 days
5 RF COMPONENTS 3 days
6 CIVIL, MECHANICAL & ELECTRICAL (CME) 3 days
7 SAQ 5 days
8 KICK-OFF MEETING 1 day APM,PM
9 SITE ACCESS (PTW) 3 days APM
10 SAFETY BRIEFING 1 day ALL
11 MATERIAL DELIVERY 4 days
12 MATERIAL ARRIVAL (CME) 3 days
13 MATERIAL ARRIVAL (RF COMPONENTS) 4 days
14 SITE IMPLEMENTATION 32 days
15 SITE VERIFICATION 2 days ALL
16 DRILLING, HACKING & CORING (RISER & EQUIPMENT) 4 days TEAM 1,TEAM 2
17 CME (CABLE TRAY WITH ACCESSORIES, THREADED ROD & HACKING WALL) 14 days
18 SECTOR 1 7 days TEAM 1
19 SECTOR 2 7 days TEAM 2
20 SECTOR 3 7 days TEAM 1
21 EQUIPMENT ROOM 10 days
22 INSTALLATION OF CABLE LADDER, TRUNKING, MGB 3 days TEAM 1
23 POWER SOURCES 1 day TEAM 2
24 ANTENNA, CABLING & TESTING, CLAMPING & COMPONENTS INSTALLATION 18 days
25 SECTOR 1 9 days
26 ARRIVAL HALL/DEPARTURE HALL 9 days TEAM 2
27 SECTOR 2 9 days
28 ARRIVAL HALL/DEPARTURE HALL 9 days TEAM 1
29 SECTOR 3 9 days
30 ARRIVAL HALL/DEPARTURE HALL 9 days TEAM 1
31 COMBINING & MAIN TRUNK 1 day
32 SECTOR 1 1 day TEAM 2
33 SECTOR 2 1 day TEAM 1
34 SECTOR 3 1 day TEAM 1
35 SITE CLEARANCE & MAKE GOOD 2 days
36 WALKTEST 2 days
37 WALKLTEST (TO BE PERFORMED ONCE ON AIR) 2 days ALL

Task Project Summary Manual Task Start-only Deadline

Project: PIA PROJECT TIMELINE Split Inactive Task Duration-only Finish-only Progress
Date: 18 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone

Page 1