IMPLEMENTATION DAYS PER SITE TYPE

21 days 32 days
NORMAL
NORMAL
2 Sites
3 Sites
Zero (0) Additional Hauling Days
Zero (0) Additional Hauling Days

39 days
28 days DIFFICULT
46 days (interisland)
DIFFICULT
5 Sites
2 Sites
Seven (7) Additional Hauling Days
seven (7) Additional Hauling Days NON-COASTAL COASTAL
(11 Sites) 14 Sites
PROJECT
25 Sites
21 Days (only 7 days curing ) 32 Days (only 7 days curing)

33 days 44 days
40 days (interisland) 49 days (interisland)
EXTREMELY DIFFICULT
EXTREMELY DIFFICULT
6 Sites
7 Sites
Twelve (12) Additional Hauling Days
Twelve (12) Additional Hauling Days
)

***Plus 3 days MOB-DEMOB: Time for the team to demobilize from one site and mobilize to the next site.