URAIAN KEGIATAN SATUAN VOLUME HARGA SATUAN TOTAL HARGA


I PEKERJAAN PERSIAPAN
1 Pengukuran dan Pasang Bouwplank m 3.00 2,000,000 6,000,000

II PEKERJAAN TANAH DAN PASIR


1 Galian tanah pondasi m3 2.1 41,750 87,675
2 Mengurug kembali galian pondasi m3 2.9 14,250 41,325
3 Urugan pasir bawah pondasi m3 2.11 121,900 257,209
4 Urugan tanah peninggian m3 2.15 93,550 201,133
5 Pemadatan tanah m3 2.1 29,500 61,950
649,292
III PEKERJAAN PASANGAN
1 Pasangan dinding 1/2 bata 1 pc : 5 ps m2 31.5 90,750 2,858,625
2,858,625
IV PEKERJAAN BETON
1 Kolom 13/20 m3 0.25 5,650,000 1,412,500
2 Balok 13/20 m3 0.78 4,750,000 3,705,000
3 Kolom struktur 15/15 (selasar) m3 0.78 4,850,000 3,783,000
4 Balok ring m3 2.85 7,450,000 21,232,500
30,133,000

V PEKERJAAN PLESTERAN DAN LANTAI


1 Pekerjaan lantai keramik (30 x 30) m2 210 165,450 34,744,500
2 Plesteran m2 54 46,450 2,508,300
3 Acian plesteran m2 54 26,350 1,422,900
38,675,700

VI PEKERJAAN KAYU DAN ALUMINIUM


1 Lisplank kayu m 39 67,550 2,634,450
2 Kusen kayu m3 1.25 125,000 156,250
3 Daun jendela m2 32 365,000 11,680,000
4 Daun pintu m2 5 475,000 2,375,000
5 Pek. Ventilasi m2 12 287,500 3,450,000
6 Kaca polos m2 24 145,000 3,480,000
23,775,700
6,000,000

2,858,625

30,133,000

38,675,700

23,775,700