Process Activity Name: REL-2.3.2 Upload Sustainment Transition
Acceptance Plan ................................................................................................. 39
Process Activity Name: REL-2.3.3 Conduct Sustainment Transition
Acceptance Planning .......................................................................................... 40
Process Activity Name: REL-2.3.4 Conduct Sustainment Transition
Acceptance Planning .......................................................................................... 41
Process Activity Name: REL-2.3.5 Review Sustainment Transition
Acceptance Plan ................................................................................................. 43
Process Activity Name: REL-2.3.6 Review Sustainment Transition
Acceptance Plan ................................................................................................. 44
Process Activity Name: REL-2.3.7 Create Sustainment Transition Acceptance
Plan Findings Report Package........................................................................... 45
Process Activity Name: REL-2.3.8 Evaluate Sustainment Transition
Acceptance Plan Findings Report Package ..................................................... 46
Process Activity Name: REL-2.3.8-DEC01 Ready for HPS Director?.............. 47
Process Activity Name: REL-2.3.8-DEC02 Return to PM ................................. 47
Process Activity Name: REL-2.3.9 Accept Sustainment Transition
Acceptance Plan ................................................................................................. 48
Process Activity Name: REL-2.3.9-DEC01 Ready for PM? .............................. 49
Process Activity Name: REL-2.3.10 Receive Sustainment Transition
Acceptance Plan Findings Report ..................................................................... 49
Process Activity Name: REL-2.3.11 Post HPS Accepted Sustainment
Transition Acceptance Plan ............................................................................... 50
Process Activity Name: REL-2.3.12 Return to PM ............................................ 51
Process Activity Name: REL-2.4 Prepare Product for Release ....................... 51
Process Activity Name: REL-2.5 Request Site Readiness Assessment ........ 53
Process Activity Name: REL-2.6 Accept Increment ......................................... 54
Process Activity Name: REL-2.6.1 Prepare Customer Acceptance Form ...... 54
Process Activity Name: REL-2.6.2 Validate Infrastructure in Place or Funded
.............................................................................................................................. 55
Process Activity Name: REL-2.6.3 Obtain Acceptance by Customer ............. 56
Process Activity Name: REL-2.6.4 Notify Stakeholder of Increment
Acceptance .......................................................................................................... 57
Process Activity Name: REL-2.6.4-DEC01 Accepted? ..................................... 58
Process Activity Name: REL-2.7 Obtain Finished Operational Acceptance
Plan ...................................................................................................................... 58
Process Activity Name: REL-2.8 Request ESE Release Readiness Office
Approval .............................................................................................................. 59
Process Activity Name: REL-2.9 Provide ESE Release Readiness Office
Approval .............................................................................................................. 60
Process Activity Name: REL-2.9-DEC01 Approved.......................................... 61
Release Management ii
Process Activity Name: REL-2.9-DEC02 VHA Impact? .................................... 61
Process Activity Name: REL-2.10 Obtain Finished Sustainment Transition
Acceptance Plan ................................................................................................. 62
Process Activity Name: REL-2.11 Request VHA Release Management
Approval .............................................................................................................. 63
Process Activity Name: REL-2.12 Provide VHA Release Management
Approval for IOC Exit .......................................................................................... 64
Process Activity Name: REL-PR1 Conduct Peer Review of Deployment,
Training and Sustainment Transition Acceptance Plans ................................ 65
Process Activity Name: REL-FR1 Conduct Formal Review of Deployment,
Training, and Sustainment Transition Acceptance Plans ............................... 66
Process Activity Name: REL-FR1-DEC01 Approved? ...................................... 67
Process Activity Name: REL-MS2 Conduct Milestone 2 Review .................... 68
Process Activity Name: REL-3 Distribute Release ........................................... 69
Process Activity Name: REL-3.0-DEC01 VHA Health Product? ...................... 70
Process Activity Name: REL-3.1 Release Product ........................................... 70
Process Activity Name: REL-3.2 Initiate Change ............................................. 71
Process Activity Name: REL-3.3 Verify Final Configuration ........................... 72
Process Activity Name: REL-3.4 Distribute Release ........................................ 73
Process Activity Name: REL-3.4-DEC01 Install Successful? .......................... 74
Process Activity Name: REL-3.4-DEC02 VBA Impact? .................................... 74
Process Activity Name: REL-3.5 Execute Backout/Roll Back/Rework
Procedures .......................................................................................................... 75
Process Activity Name: REL-3.5-DEC01 Rollback Successful? ..................... 76
Process Activity Name: REL-3.6 Update VBA Transformational Deployment
Calendar ............................................................................................................... 76
Process Activity Name: REL-3.7 Send Notification of Release Status ........... 77
Process Activity Name: REL-3.8 Close Request for Change .......................... 78
MS2
REL-1
Project Manager
REL-2 REL-3
Conduct Plan Distribute
Initial Operating
Release Deployment Release
Capability Activities
The links in this process map are inactive. Please scroll to view activity data. 1
Release Management: REL-1 Conduct Initial Operating Capability Activities
Release Officer
home proce ss ove rvie w raci he lp
Engineering
Enterprise
Systems REL-1.1
Commence
ESE Release Office
Review
VHA Release
Management
No
M Approve d?
Yes
Health Product
Coordinator
REL-1.8
Support
Release
Conduct
Health Product
Support Review
Implementation
REL-1.6
Operating
Capability
REL-1.5
Manager
Collect
Perform
Initial
Yes
REL-1.3 REL-1.4
REL-1.2 REL-1.7 REL-1.9
Request Conduct No
Conduct Update VHA
Project Manager
Yes
VHA No MS1 M
Impact? IOC
The links in this process map are inactive. Please scroll to view activity data. 2
Release Management: REL-2 Plan Release Deployment
home proce ss ove rvie w raci he lp
No
REL-2.9
Provide Approve d?
ESE Release Officer
Approval
Yes
VHA Release
Management
No
REL-2.12
Yes Provide
Approve d? VHA Release
Management
Approval for IOC
Exit
REL-2.3 REL-2.11
Finalize REL-2.6 Request
Sustainment Accept VHA Release
Transition Increment Management
Acceptance Plan Approval
REL-2.10
REL-2.7 Obtain
REL-2.1 No Yes Finished
Obtain
Create Acce pte d? Sustainment
Finished Operational
Deployment Plan Transition
Acceptance Plan Acceptance Plan
Training Manager
REL-2.2
Define
Training Plan
The links in this process map are inactive. Please scroll to view activity data. 3
Release Management: REL-2.3 Finalize Sustainment Transition Acceptance Plan
home process back overview raci help
Sustainment
Transition
Acceptance Plan
No
Ready for PM?
Yes
No
REL-2.3.11
REL-2.3.1
Post
Create/Update HPS HPS Accepted
Final Sustainment Involvement?
Sustainment
Transition
Transition
Project Manager
Acceptance Plan
Yes Acceptance Plan
REL-2.3.2 REL-2.3.10
Upload Receive
Sustainment Sustainment
Transition Transition
Acceptance Plan Acceptance Plan
Findings Report
Tier 3 (T3) Sustainment
REL-2.3.7 REL-2.3.12
REL-2.3.3 REL-2.3.5
Create Return
Manager
Conduct Review
Sustainment
Sustainment Sustainment to PM
Transition
Transition Transition
Acceptance Plan
Acceptance Planning Acceptance Plan
Findings Report
Package
Health Product Support
REL-2.3.8 Yes
REL-2.3.4 REL-2.3.6 Evaluate
Conduct Review Sustainment Ready
Sustainment Sustainment
Tier 2 (T2)
No Return Yes
to
PM?
The links in this process map are inactive. Please scroll to view activity data. 4
Release Management: REL-2.6 Accept Increment
home proc ess bac k overview rac i help
Project Manager
REL-2.6.1 REL-2.6.4
Prepare Notify
Stakeholder of
Customer
Increment
Acceptance Form Acceptance
Engineering Implementation
Service Delivery and
Manager
REL-2.6.2
Validate
Infrastructure in
Place or Funded
REL-2.6.3
Customer
Obtain
Acceptance by
Customer
The links in this process map are inactive. Please scroll to view activity data. 5
Release Management: REL-3 Distribute Release
Configuration
home proc ess overview rac i help
Manager
REL-3.3
Verify
Final Configuration
REL-3.4
Install Yes
Distribute S uc c essful?
Release
No No
VBA
Impac t?
Project Manager
Yes
REL-3.6
REL-3.5
Update
Execute
VBA
Backout/Roll Back/
Rework Transformational
Deployment
Procedures
Calendar
REL-3.7
No Rollbac k Yes Send
S uc c essful?
Notification of
Release Status
Coordinator
REL-3.2 REL-3.8
Change
Initiate Close
Change Request For Change
Health Product
No
Coordinator
REL-3.1
Support
Release
VHA
Yes
Health Release
Produc t?
Product
The links in this process map are inactive. Please scroll to view activity data. 6
Process: Release Management
Overview: The process map for Release Management cycles through the following process and
review activities:
REL-1 Conduct Initial Operating Capability Activities
REL-1.1 Commence ESE Release Office Review
REL-1.2 Conduct Initial Operating Capability Entry Meeting
REL-1.2-DEC01 VHA Impact?
REL-1.3 Request VHA Release Management Approval for IOC Entry
REL-MR1 VHA Stakeholder Approval Review
REL-MR1-DEC01 Approved?
REL-MS1-IOC Conduct Milestone 1 IOC Review
REL-1.4 Conduct Initial Operating Capability Planning Meeting
REL-1.5 Perform Initial Operating Capability Evaluation
REL-1.6 Collect Concurrences and Initial Operating Capability Evaluation Data
REL-1.7 Update Issues, Anomalies, Exceptions and Risks
REL-1.7-DEC01 VHA Impact?
REL-1.8 Conduct Health Product Support Review
REL-1.9 Consolidate Results
REL-MR2 Initial Operating Capability Exit Review
REL-2 Plan Release Deployment
REL-2.1 Create Deployment Plan
REL-2.2 Define Training Plan
REL-2.3 Finalize Sustainment Transition Acceptance Plan
REL-2.3.1 Create/Update Final Sustainment Transition Acceptance Plan
REL-2.3.1-DEC01 HPS Involvement?
REL-2.3.2 Upload Sustainment Transition Acceptance Plan
REL-2.3.3 Conduct Sustainment Transition Acceptance Planning
REL-2.3.4 Conduct Sustainment Transition Acceptance Planning
REL-2.3.5 Review Sustainment Transition Acceptance Plan
REL-2.3.6 Review Sustainment Transition Acceptance Plan
REL-2.3.7 Create Sustainment Transition Acceptance Plan Findings Report Package
REL-2.3.8 Evaluate Sustainment Transition Acceptance Plan Findings Report Package
REL-2.3.8-DEC01 Ready for HPS Director?
REL-2.3.8-DEC02 Return to PM
REL-2.3.9 Accept Sustainment Transition Acceptance Plan
REL-2.3.9-DEC01 Ready for PM?
REL-2.3.10 Receive Sustainment Transition Acceptance Plan Findings Report
REL-2.3.11 Post HPS Accepted Sustainment Transition Acceptance Plan
REL-2.3.12 Return to PM
REL-2.4 Prepare Product for Release
REL-2.5 Request Site Readiness Assessment
REL-2.6 Accept Increment
REL-2.6.1 Prepare Customer Acceptance Form
REL-2.6.2 Validate Infrastructure in Place or Funded
REL-2.6.3 Obtain Acceptance by Customer
Release Management 7
REL-2.6.4 Notify Stakeholder of Increment Acceptance
REL-2.6.4-DEC01 Accepted?
REL-2.7 Obtain Finished Operational Acceptance Plan
REL-2.8 Request ESE Release Readiness Office Approval
REL-2.9 Provide ESE Release Readiness Office Approval
REL-2.9-DEC01 Approved
REL-2.9-DEC02 VHA Impact?
REL-2.10 Obtain Finished Sustainment Transition Acceptance Plan
REL-2.11 Request VHA Release Management Approval
REL-2.12 Provide VHA Release Management Approval for IOC Exit
REL-PR1 Conduct Peer Review of Deployment, Training and Sustainment Transition
Acceptance Plans
REL-FR1 Conduct Formal Review of Deployment, Training, and Sustainment Transition
Acceptance Plans
REL-FR1-DEC01 Approved?
REL-MS2 Conduct Milestone 2 Review
REL-3 Distribute Release
REL-3.0-DEC01 VHA Health Product?
REL-3.1 Release Product
REL-3.2 Initiate Change
REL-3.3 Verify Final Configuration
REL-3.4 Distribute Release
REL-3.4-DEC01 Install Successful?
REL-3.4-DEC02 VBA Impact?
REL-3.5 Execute Backout/Roll Back/Rework Procedures
REL-3.5-DEC01 Rollback Successful?
REL-3.6 Update VBA Transformational Deployment Calendar
REL-3.7 Send Notification of Release Status
REL-3.8 Close Request for Change
Release Management 8
Release Management Description and Goals
Description
The Release Management Process provides protection of the live production environment and its
services through establishment of formal procedures and checks to govern the scheduling and
deployment of changes by controlling when changes will occur, what is approved and authorized
to be changed, and where those approved changes will be implemented.
Goals
This process uses tactical objectives that support realization of Enterprise Release Management’s
strategic goal by providing information in three general categories:
1. When will the change occur?
- Collect planned implementation dates for all Release packages as early as possible.
- Collaborate with Change Management to maintain an up-to-date “forward schedule of
changes” that reflects planned deployment dates for each activity.
- Collect updates at key points to continuously renew the Calendar and optimize deployment
planning.
2. What will change?
- Ensure that all Release packages are tested, authorized, and approved by appropriate
stakeholders.
- Ensure that all Release packages meet Project Management Accountability System Milestone
and production operational requirements prior to advancing to an Active Implementation State.
- Ensure that master copies of all software and required artifacts (supporting documentation) are
secured and indexed in the Definitive Media Library.
- Ensure that details about Release-related Configuration Items are made available to
Configuration Management services in order to update product and infrastructure baselines in the
Configuration Management Database.
3. Where will the change be implemented?
- Ensure collaboration and coordination among Product Development, Testing Services, Change
Management, Operations, Release Management, and Executive Management at the
implementation site(s) concerning the content and rollout of the Release and the readiness of the
host(s).
- Ensure that the implementation of software or hardware into the operational environment
adheres to the Office of Information and Technology (OI&T) framework of established standards
for Configuration Management, Change Management and Pre-Production testing and
verification, and meets local site requirements.
- Ensure that all implementers are prepared, trained, and ready to receive the Release.
Release Management 9
Release Management RACI Information
The following describes the RACI information for this process:
Release Management 10
REL-1.4 Conduct Initial Operating Capability Planning Meeting
Release Management 11
REL-MR2 Initial Operating Capability Exit Review
Release Management 12
REL-2.3.4 Conduct Sustainment Transition Acceptance Planning
Release Management 13
REL-2.3.10 Receive Sustainment Transition Acceptance Plan Findings Report
REL-2.3.12 Return to PM
Release Management 14
Accountable Role: Project Manager
Release Management 15
Responsible Role: Project Manager
Accountable Role: Office of Responsibility
Consulted Role: Integrated Project Team Member
Release Management 16
REL-3.1 Release Product
Release Management 17
Accountable Role: Office of Responsibility
Release Management 18
Release Management Process
Process Activity Name: REL-1 Conduct Initial Operating Capability
Activities
REL-2 Plan Release DeploymentPrevious Process Activity
None
Next Process Activity
REL-MS2 Conduct Milestone 2 Review
Description
The set of Conduct Initial Operating Capability Activities process and review activities is
selected from the Release Management Main Map via the REL-1 link:
Release Management 19
Artifacts Used
Tailored List of ESE Requirements
Artifacts Created
Email concerning Artifact Status and Deficiencies
Responsible Role
Enterprise Systems Engineering Release Readiness Officer
Release Management 20
Artifacts Used
Capacity and Performance Engineering ORR Analysis Report Conformance Validation Package
Data Transfer Agreements (if needed)
Enterprise Testing Services Analysis Report
Final ESE Testing Plan
Master Test Plan
Product Assessment Findings Reports
Project Management Plan (Risk Management Plan sections)
Release Notes
Test Case/Test Scripts
Test Site Memorandums of Understanding (Signed)
Updated Patch or New Patch
Artifacts Created
Artifact Review Agenda and Minutes
Initial Operating Capability Entry Request and Exit Summary (Entry Request portion)
Updated Project Management Plan (Risk Management Plan sections)
Responsible Role
Project Manager
Release Management 21
If Yes, REL-1.3 Request VHA Release Management Approval for IOC Entry
If No, REL-MS1 IOC Conduct Milestone 1 IOC Review
Description
The Project Manager in conjunction with VHA Release Management determines if there is VHA
impact. If there is impact, the next activity is REL-1.3 Request VHA Release Management
Approval for IOC Entry. If there is no VHA impact, the next activity is REL-MS1 IOC Conduct
Milestone 1 IOC Review.
Responsible Role
Project Manager
Artifacts Used
IOC Entry Request and Exit Summary (See Section 2.8 for required documents)
Artifacts Created
Updated Initial Operating Capability Entry Request and Exit Summary (Entry Request portion)
VHA Release Management Approval Request Email
Release Management 22
Responsible Role
Project Manager
Artifacts Used
Deployment Plan
IOC Entry Request and Exit Summary
IOC Site Memorandum of Understanding
IOC Testing Waiver
Installation Back-out Rollback Plan
Master Test Plan
Operational Acceptance Plan
Release Management 23
Production Operations Manual
Project Management Plan
Requirements Specification Document
Sustainment Transition Acceptance Plan
System Design Document
User Guide
Version Description Document
Artifacts Created
Artifact Review Agenda and Minutes
Email Notification
Responsible Role
VHA Release Management Team
Release Management 24
Responsible Role
VHA Release Management Team
The ProPath Required Artifacts page contains the specific listing of required artifacts needed to
enter the Milestone 1 IOC Review.
The draft Transition Plan is required for use during Milestone 1 IOC Reviews and the final
document during Milestone 2 Reviews.
Artifacts Used
Acceptance Criteria Plan
Initial Operating Capability Entry Request and Exit Summary
MS1-IOC Review Template
Artifacts Created
Milestone 1 - IOC Action Items & Observations
Updated PMAS Dashboard
Release Management 25
Responsible Role
Project Manager
The PMAS Dashboard landing page is open to all users in the VA network. For technical support
regarding the PMAS Dashboard, select the link in the area titled “I’m Looking for Site Help” and
select the link “Submit Help Desk Support Ticket”. For general questions or inquiries regarding
the PMAS Dashboard, submit an email to VA PMAS Business Office. The PMAS Dashboard is
updated when reportable information or conditions change. Each project/increment is updated at
least monthly until closed.
Process Activity Name: REL-1.4 Conduct Initial Operating Capability
Planning Meeting
Previous Process Activity
REL-MS1-IOC Conduct Milestone 1 IOC Review
Next Process Activity
REL-1.5 Perform Initial Operating Capability Evaluation
Description
The Project Manager, in coordination with the Product Development (PD) and/or Service
Delivery and Engineering (SDE) Implementation Managers, conducts a planning meeting with
IOC participants appropriate to the product release (i.e., Enterprise Operations, Field
Operations, Development Team, Site Representatives, Business Owners, Business Office
Release Management 26
Representatives, Veterans Administration/Veterans Health Administration/Veterans Benefits
Administration and Patient Safety Representatives, as necessary) to plan and coordinate
evaluation activities.
Artifacts Used
Initial Operating Capability Site Memorandum of Understanding
Master Test Plan
VHA Approval for IOC Entry (if product release impacts VHA)
Artifacts Created
Artifact Review Agenda and Minutes
Responsible Role
Project Manager
Activities include:
Release Management 27
- Distribute the product and product documentation to the Evaluation Sites (see More Info)
- Facilitate the timely installations at the Evaluation Sites
- Conduct formal or bi-weekly Evaluation Site calls
- Track defects identified during Initial Operating Capability Evaluation
- Address issues and questions identified during evaluation
- Obtain Site Concurrence Statements
Artifacts Used
IOC Site Evaluation Defect Log and Concurrence Statement
Master Test Plan
Registered Request for Change
Test Case/Test Scripts
Test Site Memorandum of Understanding (signed)
Artifacts Created
Updated IOC Site Evaluation Defect Log and Concurrence Statement
Responsible Role
Initial Operating Capability Implementation Manager
More Info
Navigate to either the ProPath Change Management Process Map and/or the ProPath
Configuration Management Process Map for more guidance.
Process Activity Name: REL-1.6 Collect Concurrences and Initial
Operating Capability Evaluation Data
Previous Process Activity
REL-1.5 Perform Initial Operating Capability Evaluation
Release Management 28
Next Process Activity
REL-1.7 Update Issues, Anomalies. Exceptions and Risks
Description
The Initial Operating Capability Implementation Manager obtains the IOC Site Evaluation
Defect Log and Concurrence Statement.
Artifacts Used
IOC Site Evaluation Defect Log and Concurrence Statement
Initial Operating Capability Entry Request and Exit Summary
Registered Request for Change
Test Site Memorandum of Understanding (signed)
Artifacts Created
Updated IOC Site Evaluation Defect Log and Concurrence Statement
Updated Initial Operating Capability Entry Request and Exit Summary
Responsible Role
Initial Operating Capability Implementation Manager
More Info
See ProPath Change Management Process Map for more guidance. The Initial Operating
Capability Entry Request and Exit Summary has been updated to include the information from
the Package-Patch Completion Transition Document.
Process Activity Name: REL-1.7 Update Issues, Anomalies,
Exceptions and Risks
Previous Process Activity
REL-1.6 Collect Concurrences and Initial Operating Capability Evaluation Data
Next Process Activity
REL-1.7-DEC01 VHA Impact?
Description
The Project Manager reviews the findings and updates the Initial Operating Capability (IOC)
Entry and Exit Summary document, IOC Exit Summary sections:
Release Management 29
- Issues, Anomalies, and Exceptions
- Risks and Mitigation Strategy
If a health product is being evaluated, the Project Manager should ensure that Health Product
Support Release Coordinator has completed their review and given approval to proceed prior to
completing the IOC Exit Summary.
Artifacts Used
Initial Operating Capability Entry Request and Exit Summary
Initial Operating Capability Site Evaluation Defect Log and Concurrence Statement
Registered Request for Change
Artifacts Created
Updated Initial Operating Capability Entry Request and Exit Summary (IOC Exit Summary
Section)
Responsible Role
Project Manager
More Info
See ProPath Change Management Process Map for more guidance.
Process Activity Name: REL-1.7-DEC01 VHA Impact?
Previous Process Activity
REL-1.7 Update Issues, Anomalies, Exceptions and Risks
Next Process Activity
Note: There is a decision dependency that determines the next activity to be performed.
Release Management 30
Description
The Project Manager determines if VHA is impacted.
If Yes, the next activity is REL-1.8 Conduct Health Product Support Review.
If No, the next activity is REL-1.9 Consolidate Results.
Responsible Role
Project Manager
Artifacts Created
Updated Initial Operating Capability Entry Request and Exit Summary
Responsible Role
Health Product Support Release Coordinator
Release Management 31
Health Product Support VA Primavera Guide
Health Product Support Release Coordinator IPT Membership Guide
Health Product Support Release of Products and Patches Guide
Health Product Support Software Distribution Directories Guide
More Info
None Listed
Artifacts Created
MS2 Review Template
Updated Initial Operating Capability Entry Request and Exit Summary
Responsible Role
Project Manager
Release Management 32
Technical Services Project Repository (TSPR)
Standards
Change to Project Management Accountability System (PMAS) Guide V5.0 (VAIQ 7606746)
Project Management Accountability System (PMAS) Guide
More Info
None Listed
The completion of the Authorizations section and submission of the document results in the MR2
milestone alert. The Project Manager updates the MS2 Review Template and informs the
Program Manager when the project is ready for PMAS approval.
Release Management 33
Artifacts Used
Acceptance Criteria Plan
Initial Operating Capability Entry Request and Exit Summary
MS2 Review Template
Artifacts Created
Artifact Review Agenda and Minutes
Updated Initial Operating Capability Entry Request and Exit Summary
Updated MS2 Review Template
Responsible Role
Project Manager
Release Management 34
REL-2.4 Prepare Product for Release
REL-2.5 Request Site Readiness Assessment
REL-2.6 Accept Increment
REL-2.7 Obtain Finished Operational Acceptance Plan
REL-2.8 Request ESE Release Readiness Office Approval
REL-2.9 Provide ESE Release Readiness Office Approval
REL-2.10 Obtain Finished Sustainment Transition Acceptance Plan
REL-2.11 Request VHA Release Management Approval
REL-2.12 Provide VHA Release Management Approval for IOC Exit
REL-PR1 Conduct Peer Review of Deployment, Training, and Sustainment Transition
Acceptance Plans
REL-FR1 Conduct Formal Review of Deployment, Training and Sustainment Transition
Acceptance Plans
Process Activity Name: REL-2.1 Create Deployment Plan
Note: This activity is performed concurrently with:
REL-2.2 Define Training Plan
And
REL-2.3 Finalize Sustainment Transition Acceptance Plan
Previous Process Activity
REL-1 Conduct Initial Operating Capability Activities
Next Process Activity
REL-2.4 Prepare Product for Release
Description
The Project Manager creates the Deployment Plan which is developed based on a thorough
analysis of the steps necessary to achieve the deployment and implementation goals of the
release - specifically to deploy configuration items in the release to a production environment.
Recommended sections to be included in the Deployment Plan are:
Release Management 35
- Operational readiness requirements prior to deployment
- Deployment and Implementation success criteria
Artifacts Used
Architecture and Design Documents
Project Management Plan
Artifacts Created
Deployment Plan
Responsible Role
Project Manager
Standards
Software Configuration Management Plan Standard
More Info
None Listed
Release Management 36
Artifacts Used
Deployment Plan
Project Management Plan
Release Notes
Version Description Document
Artifacts Created
Updated Project Management Plan
Responsible Role
Training Manager
Standards
None Listed
More Info
Contact the VALU IT National Training and Education Office at the mail group VA IT Training
Requests.
Process Activity Name: REL-2.3 Finalize Sustainment Transition
Acceptance Plan
Note: This activity is performed concurrently with:
REL-2.1 Create Deployment Plan
And
REL-2.2 Define Training PlanPrevious Process Activity
REL-1 Conduct Initial Operating Capability Activities
Next Process Activity
REL-2.4 Prepare Product for Release
Description
The set of Finalize Transition Plan process and review activities is selected from the REL-2 map
via the REL-2.3 link:
Release Management 37
REL-2.3.3 Conduct Sustainment Transition Acceptance Planning
REL-2.3.4 Conduct Sustainment Transition Acceptance Planning
REL-2.3.5 Review Sustainment Transition Acceptance Plan
REL-2.3.6 Review Sustainment Transition Acceptance Plan
REL-2.3.7 Create Sustainment Transition Acceptance Plan Findings Report Package
REL-2.3.8 Evaluate Sustainment Transition Acceptance Plan Findings Report Package
REL-2.3.9 Accept Sustainment Transition Acceptance Plan
REL-2.3.10 Receive Sustainment Transition Acceptance Plan Findings Report Package
REL-2.3.11 Post HPS Accepted Sustainment Transition Acceptance Plan
Process Activity Name: REL-2.3.1 Create/Update Final Sustainment
Transition Acceptance Plan
Previous Process Activity
REL-2.1 Create Deployment Plan
And
REL-2.2 Define Training Plan
Next Process Activity
REL-2.3.1-DEC01 HPS Involvement?
Description
The Project Manager creates the Sustainment Transition Acceptance Plan if an approved draft is
not available. The Product Support Integrated Project Team members participate in the review
and update of the Sustainment Transition Acceptance Plan, which provides a knowledge transfer
to the sustainment Product Support team about the product and its artifacts, code bases,
architecture, design, technology, budget, required resources and other pertinent information.
Artifacts Used
Project Quad Chart
Requirements Specification Document
Sustainment Transition Acceptance Plan (Draft)
Sustainment Transition Acceptance Plan Findings Report Package
System Design Document
Artifacts Created
Sustainment Transition Acceptance Plan
Updated Sustainment Transition Acceptance Plan
Release Management 38
Responsible Role
Project Manager
Release Management 39
Next Process Activity
Note: The next activities are performed concurrently
REL-2.3.5 Review Sustainment Transition Acceptance Plan
REL-2.3.6 Review Sustainment Transition Acceptance Plan
Description
The Project Manager uploads the Sustainment Transition Acceptance Plan to the Technical
Services Project Repository (TSPR) for records management and then to the Health Product
Support SharePoint Site to initiate the HPS Review process.
Artifacts Used
Sustainment Transition Acceptance Plan
Artifacts Created
Updated Health Product Support (HPS) SharePoint Site
Responsible Role
Project Manager
Release Management 40
And
REL-2.2 Define Training Plan
Next Process Activity
REL-2.4 Prepare Product for Release
Description
The Tier 3 (T3) Sustainment Manager conducts Sustainment Transition Acceptance Planning,
leveraging information from available project documents.
Artifacts Used
Business Requirements Document
Integrated Project Team Charter
Operational Acceptance Plan
Project Charter
Sustainment Transition Acceptance Plan
Artifacts Created
Updated Action Item Tracker
Updated HPS SharePoint Site Project Folder Contents
Responsible Role
Tier 3 (T3) Sustainment Manager
Release Management 41
REL-2.3.3 Conduct Sustainment Transition Acceptance PlanningPrevious
Process Activity
REL-2.3.2 Upload Sustainment Transition Acceptance Plan
Next Process Activity
Note: The next activities are performed concurrently
REL-2.3.5 Review Sustainment Transition Acceptance
And
REL-2.3.6 Review Sustainment Transition Acceptance
Description
Tier 2 (T2) Health Product Support Specialist conducts Sustainment Transition Acceptance
Planning, leveraging information from available project documents.
Artifacts Used
Business Requirements Document
Integrated Project Team Charter
Operational Acceptance Plan
Project Charter
Sustainment Transition Acceptance Plan
Artifacts Created
Updated Action Item Tracker
Updated HPS SharePoint Site Project Folder Contents
Responsible Role
Tier 2 (T2) Health Product Support Specialist
Release Management 42
Process Activity Name: REL-2.3.5 Review Sustainment Transition
Acceptance Plan
Note: This activity is performed concurrently with:
REL-2.3.6 Review Sustainment Transition Acceptance PlanPrevious Process
Activity
REL-2.3.2 Upload Sustainment Transition Acceptance Plan
Next Process Activity
REL-2.3.7 Create Sustainment Transition Acceptance Plan Findings Report Package
Description
The Tier 3 (T3) Sustainment Manager conducts a review of the Draft Sustainment Transition
Acceptance Plan noting any areas of concern, omission, or inconsistencies and documents those
notes in the Artifact Review Agenda and Minutes. The documented results are posted to the
Health Product Support SharePoint Site.
Artifacts Used
Business Requirements Document
Integrated Project Team Charter
Operational Acceptance Plan
Project Charter
Sustainment Transition Acceptance Plan (Draft)
Sustainment Transition Acceptance Plan Findings Report Package
Artifacts Created
Artifact Review Agenda and Minutes
Updated Sustainment Transition Acceptance Plan
Responsible Role
Tier 3 (T3) Sustainment Manager
Release Management 43
More Info
None Listed
Artifacts Created
Artifact Review Agenda and Minutes
Updated Sustainment Transition Acceptance Plan
Responsible Role
Tier 2 (T2) Health Product Support Specialist
Release Management 44
VA Cost Estimating Guide
More Info
None Listed
Artifacts Created
Sustainment Transition Acceptance Plan Findings Report Package
Responsible Role
Tier 3 (T3) Sustainment Manager
Release Management 45
VA Cost Estimating Guide
More Info
None Listed
Artifacts Created
Sustainment Transition Acceptance Plan Findings Report Package Evaluation Email (approved)
or (rejected)
Responsible Role
Tier 2 (T2) Health Product Support Specialist
Release Management 46
More Info
None Listed
If No, REL-2.3.7 'Create Sustainment Transition Acceptance Plan Findings Report Package'
Description
The Tier 2 (T2) Health Product Support Specialist determines if the Sustainment Transition
Acceptance Plan should be returned to the Project Manager. If yes, the next activity is REL-
2.3.12 Return to PM. If no, the next activity is REL-2.3.7 Create Sustainment Transition
Acceptance Plan Findings Report Package.
Responsible Role
Tier 2 (T2) Health Product Support Specialist
Release Management 47
Process Activity Name: REL-2.3.9 Accept Sustainment Transition
Acceptance Plan
Previous Process Activity
REL-2.3.8-DEC01 Ready for HPS Director?
Next Process Activity
REL-2.3.9-DEC01 Ready for PM?
Description
The Health Product Support Director receives the Sustainment Transition Acceptance Plan
Findings Report Package for final internal review and acceptance.
If accepted, the Sustainment Transition Acceptance Plan Findings Package is returned to the Tier
3 (T3) Sustainment Manager to provide to the Project Manager.
If the Package is not accepted, it is returned to the Tier 3 (T3) Sustainment Manager for
corrective actions.
Artifacts Used
Sustainment Transition Acceptance Plan Findings Report Package
Artifacts Created
Sustainment Transition Acceptance Plan Findings Report Package (Approved)
Responsible Role
Director, Health Product Support
Release Management 48
Process Activity Name: REL-2.3.9-DEC01 Ready for PM?
Previous Process Activity
REL-2.3.9 Accept Sustainment Transition Acceptance Plan
Next Process Activity
If Yes, REL-2.3.10 Receive Sustainment Transition Acceptance Plan Findings Report
If No, REL-2.3.7 Create Sustainment Transition Acceptance Plan Findings Report Package'
Description
The Director Health Product Support determines if the Sustainment Transition Acceptance Plan
is ready for return to the Project Manager.
If Yes, the next activity is REL-2.3.10 Receive Sustainment Transition Acceptance Plan Finding
Report.
If No, the next activity is REL-2.3.7 Create Sustainment Transition Acceptance Plan Findings
Report Package.
Responsible Role
Director, Health Product Support
Release Management 49
Artifacts Created
Updated Sustainment Transition Acceptance Plan
Responsible Role
Project Manager
More Info
None Listed
Artifacts Created
Sustainment Transition Acceptance Plan (Accepted)
Responsible Role
Project Manager
Release Management 50
Standards
None Listed
More Info
None Listed
Artifacts Created
Sustainment Transition Acceptance Plan Findings Report Package Email
Responsible Role
Tier 3 (T3) Sustainment Manager
More Info
None Listed
Release Management 51
And
REL-2.2 Define Training Plan
And
REL-2.3 Finalize Sustainment Transition Acceptance Plan
Next Process Activity
REL-2.5 Request Site Readiness Assessment
Description
The Project Manager communicates key information about the upcoming release to stakeholders.
This communication should include information regarding:
The Project Manager must plan for introductory orientation and training for all support teams.
Artifacts Used
Deployment Plan
Initial Operating Capability Entry Request and Exit Summary
Project Management Plan
Sustainment Transition Acceptance Plan
Artifacts Created
Release Announcement
Updated Project Management Plan
Updated Sustainment Transition Acceptance Plan
Responsible Role
Project Manager
Release Management 52
Standards
Initial Operating Capability Entry Request and Exit Summary Guide
More Info
None Listed
- Field liaison works with the Tasks, Resources, Administrations, and Communications (TRAC)
office to create an action item to the field to solicit responses regarding site readiness.
- TRAC creates a share portal to collect the information, and send a formal request to the field
with suspense dates.
- TRAC monitors the responses from the field and notifies the field liaison when the action is
complete.
Note: This action is typically only applicable in situations where physical hardware is involved.
Artifacts Used
Deployment Plan
Release Announcement
Artifacts Created
Notification of Site Readiness
Responsible Role
Project Manager
Release Management 53
Tools and Websites
None Listed
Standards
None Listed
More Info
Release Management 54
Artifacts Created
Customer Acceptance Form (Acceptance Criteria Plan - Attachment A)
Responsible Role
Project Manager
Standards
Change to Project Management Accountability System (PMAS) Guide V5.0 (VAIQ 7606746)
Project Management Accountability System (PMAS) Guide
More Info
None Listed
Artifacts Created
Updated Customer Acceptance Form (Acceptance Criteria Plan - Attachment A)
Responsible Role
Service Delivery and Engineering Implementation Manager
Release Management 55
Tools and Websites
None Listed
Standards
Change to Project Management Accountability System (PMAS) Guide V5.0 (VAIQ 7606746)
Project Management Accountability System (PMAS) Guide
More Info
None Listed
Artifacts Created
Signed Customer Acceptance Form
Responsible Role
Customer
Standards
Change to Project Management Accountability System (PMAS) Guide V5.0 (VAIQ 7606746)
Project Management Accountability System (PMAS) Guide
Release Management 56
More Info
None Listed
Artifacts Created
Email of Acceptance/Rejection
Responsible Role
Project Manager
Standards
Change to Project Management Accountability System (PMAS) Guide V5.0 (VAIQ 7606746)
Project Management Accountability System (PMAS) Guide
More Info
None Listed
Release Management 57
Process Activity Name: REL-2.6.4-DEC01 Accepted?
Previous Process Activity
REL-2.6.4 Notify Stakeholder of Increment Acceptance
Next Process Activity
Note: There is a decision dependency that determines the next activity to be performed.
Artifacts Created
Updated Operational Acceptance Plan
Release Management 58
Responsible Role
Project Manager
Artifacts Created
Email Review Request
Responsible Role
Project Manager
Release Management 59
Standards
NIST Special Publication 800-37, Guide for Applying the Risk Management Framework to
Federal Information Systems
NIST Special Publication 800-40, Guide to Enterprise Patch Management Technologies
More Info
None Listed
Artifacts Created
Complete/Incomplete Notification to VA OIT ESE Release Weekly Report PMAS Milestone
Review Status (Daily Email Message to SDE Voting Members)
Responsible Role
Enterprise Systems Engineering Release Officer
Release Management 60
More Info
Release Management 61
Process Activity Name: REL-2.10 Obtain Finished Sustainment
Transition Acceptance Plan
Previous Process Activity
REL-2.9-DEC02 VHA Impact?
Next Process Activity
REL-2.11 Request VHA Release Management Approval
Description
The Project Manager must ensure that the Product Support (PS) Transition Plan is finalized and
approved (including signatures) at Milestone 2. This can be accomplished by working with the
PS Integrated Project Team Member and PS Transition Team to review the Sustainment
Transition Acceptance Plan which describes knowledge transfer to the sustainment Product
Support team about the product, its artifacts, code bases, architecture, design, technology,
budget, required resources and other pertinent information to ensure complete understanding by
all parties.
Artifacts Used
Sustainment Transition Acceptance Plan
Artifacts Created
Updated Sustainment Transition Acceptance Plan
Responsible Role
Project Manager
Release Management 62
Process Activity Name: REL-2.11 Request VHA Release Management
Approval
Previous Process Activity
REL-2.10 Obtain Finished Sustainment Transition Acceptance Plan
Next Process Activity
REL-2.12 Provide VHA Release Management Approval for IOC Exit
Description
The Project Manager updates the Initial Operating Capability (IOC) Entry Request and Exit
Summary template (Section 2) and submits the document to the following mail group to request
approval for IOC Exit (i.e., National Deployment): VAOITOEDVHAReleaseApproval for
Veterans Health Administration (VHA) related applications/patches (refer to REL-1.3
Description for guidance) that require VHA approval for IOC Exit.
For those applications/patches that do not submit for IOC Entry but need to submit for IOC Exit
(e.g., applications/patches that do not field test at health care facilities such as web-based, cloud-
based, registries, and national databases), complete the IOC Entry Request and Exit Summary
template in full (both Sections 1 and 2) and submit to: VAOITOEDVHAReleaseApproval.
Required artifacts that should accompany the submission are identified on the ProPath Required
Artifacts Page.
Artifacts Used
Initial Operating Capability Entry Request and Exit Summary (see Section 2.8 for required
documents)
Artifacts Created
Updated Initial Operating Capability Entry Request and Exit Summary
VHA Release Management Approval Request
Responsible Role
Project Manager
Release Management 63
More Info
The VHA Release Approval Process is in addition to the involvement of VHA members on the
project's IPT due to the level of approvals required. It is recommended that the project team
allow at least ten (10) business days to secure approval for established projects; allow more than
ten business days if the project is new or includes multiple enhancements or patches/namespaces.
Ensure both Sections 1 and 2 of the IOC Entry Request and Exit Summary template are
complete.
Process Activity Name: REL-2.12 Provide VHA Release Management
Approval for IOC Exit
Previous Process Activity
REL-2.11 Request VHA Release Management Approval
Next Process Activity
REL-PR1 Conduct Peer Review of Deployment, Training, and Sustainment Transition
Acceptance Plans
Description
The VHA Release Management Team facilitates the Release Management Approval Process to
obtain VHA Stakeholder approvals for Initial Operating Capability (IOC) exit submissions
regarding VHA-related applications/patches. The list of approving Stakeholders depends on the
nature of the application/patch as submitted; appropriate Stakeholders are notified by email. The
VHA Release Management Team does not release software.
Artifacts Used
Deployment Plan
Initial Operating Capability Entry Request and Exit Summary
Initial Operating Capability Site Concurrence Statements
Initial Operating Capability Site Evaluation Log
Production Operations Manual (including the Installation Guide)
Software Quality Assurance Review Checklist
Training Plan
VHA Release Management Approval Request
Artifacts Created
Email Notification
Updated Initial Operating Capability Entry Request and Exit Summary
VHA Approval for IOC Exit
Responsible Role
VHA Release Management Team
Release Management 64
Tools and Websites
Release Request Process Site
Technical Services Project Repository (TSPR)
Standards
Initial Operating Capability Entry Request and Exit Summary Guide
More Info
The project cannot proceed with IOC Exit until the VHA Release Management Team sends the
VHA approval notice via email.
Process Activity Name: REL-PR1 Conduct Peer Review of
Deployment, Training and Sustainment Transition Acceptance Plans
Previous Process Activity
REL-2.12 Provide VHA Release Management Approval for IOC Exit
Next Process Activity
REL-FR1 Conduct Formal Review of Deployment, Training and Sustainment Transition
Acceptance Plans
Description
The Project Manager conducts the Peer Review of the Deployment, Training, and Sustainment
Transition Acceptance Plans in accordance with the Quality Assurance Standard (appropriate
sections pertaining to Peer Reviews) performing the following general steps:
The goal of the peer review of the Deployment, Training, and Sustainment Transition
Acceptance Plans is to resolve any questions the project team may have and to ensure quality of
the deliverable.
Artifacts Used
Deployment Plan
Project Management Plan
Sustainment Transition Acceptance Plan
Release Management 65
Artifacts Created
Deployment, Training, and Sustainment Transition Acceptance Plans Review Findings Summary
Record of Notification
Updated Deployment Plan
Updated Project Management Plan
Updated Sustainment Transition Acceptance Plan
Responsible Role
Project Manager
Standards
Quality Assurance Standard
More Info
None Listed
The goal of the formal review is to obtain stakeholder concurrence of the Deployment, Training,
and Transition Plans and appropriate approval signatures. To this end, the Deployment, Training,
and
Release Management 66
Sustainment Transition Acceptance Plans Review Findings Summary, the Deployment Plan,
Training Plan, and Sustainment Transition Acceptance Plan from the Peer Review are reviewed
and new findings are captured in a new Deployment, Training, and Sustainment Transition
Acceptance Plans Review Findings Summary.
Artifacts Used
Deployment Plan
Project Management Plan
Sustainment Transition Acceptance Plan
Training Plan
Artifacts Created
Artifact Review Agenda and Minutes
Deployment, Training, and Transition Plans Review Findings Summary
Updated Deployment Plan (Approval Signatures Included)
Updated Project Management Plan (Approval Signatures Included)
Updated Sustainment Transition Acceptance Plan (Approval Signatures Included)
Responsible Role
Project Manager
Standards
Digital Signature Guide
Quality Assurance Standard
More Info
None Listed
Release Management 67
If No, REL-2.4 Prepare Product for Release
Description
VHA Release Management determines if the Transition Plan is approved. If yes the next activity
is REL-MS2 Conduct Milestone 2 Review. If no the next activity is REL-2.4 Prepare Product for
Release.
Responsible Role
VHA Release Management Team
If the project is determined to not be ready for PMAS Milestone 2, the OOR informs the Project
Manager on areas needing project enhancements.
The ProPath Required Artifacts Page contains the specific listing of required artifacts for
Milestone Review 2 needed to exit the Active Development state.
Artifacts Used
ESE Release Office Approval
MS2 Template
Signed Customer Acceptance Form
Sustainment Transition Acceptance Plan (final) (VHA Impact)
Release Management 68
VHA Approval for IOC Exit (VHA Impact)
Artifacts Created
Milestone 2 Action Items and Observations
Updated PMAS Dashboard
Responsible Role
Office of Responsibility
Release Management 69
REL-3.1 Release Product
REL-3.2 Initiate Change
REL-3.3 Verify Final Configuration
REL-3.4 Distribute Release
REL-3.5 Execute Backout/Roll Back/Rework Procedures
REL-3.6 Update VBA Transformational Deployment Calendar
REL-3.7 Send Notification of Release Status
REL-3.8 Close Request for Change
Process Activity Name: REL-3.0-DEC01 VHA Health Product?
Previous Process Activity
REL-MS2 Conduct Milestone 2 Review
Next Process Activity
Note: There is a decision dependency that determines the next activity to be performed.
Release Management 70
Artifacts Created
Automatic Generated Email
Responsible Role
Health Product Support Release Coordinator
Standards
Health Product Support Release of Products and Patches Guide
Health Product Support Release Coordinator IPT Membership Guide
More Info
None Listed
Release Management 71
Artifacts Created
Notifications to Affected and Responsible Entities
Registered Request for Change
Responsible Role
Change Coordinator
Artifacts Created
Final Configuration Approval Document
Responsible Role
Configuration Manager
Release Management 72
Tools and Websites
None Listed
Standards
None Listed
More Info
See Configuration Management Process Map for additional guidance.
Process Activity Name: REL-3.4 Distribute Release
Previous Process Activity
REL-3.3 Verify Final Configuration
Next Process Activity
REL-3.4-DEC01 Install Successful?
Description
The Project Manager approves distribution of the release. All configuration items are distributed
in a release package using proper methods of distribution detailed in the Deployment Plan. The
Project Manager consults with the ESE Release Readiness Officer to ensure all required artifacts
are included in the Release Package.
Artifacts Used
Deployment Plan
Final Configuration Approval Document
Notifications to Affected and Responsible Entities
Registered Request for Change
Version Description Document
Artifacts Created
Release Package
Responsible Role
Project Manager
Standards
None Listed
Release Management 73
More Info
See Configuration Management Process Map for additional guidance.
Process Activity Name: REL-3.4-DEC01 Install Successful?
Previous Process Activity
REL-3.4 Distribute Release
Next Process Activity
Note: There is a decision dependency that determines the next activity to be performed.
Release Management 74
Process Activity Name: REL-3.5 Execute Backout/Roll Back/Rework
Procedures
Previous Process Activity
REL-3.4-DEC01 Install Successful?
Next Process Activity
REL-3.5-DEC01 Rollback Successful?
Description
The Implementation Manager, working with members of the release team, executes back-out/roll
back as described in the Installation Back-out Rollback Plan, and/or performs rework procedures
as needed to resolve issues with the deployment and to provide issue resolution information to
the Project Manager.
The Project Manager analyzes the issue and determines the point in the lifecycle that should be
readdressed and updates the Deployment Plan. The Project Manager updates the Incident
Response Plan as necessary based upon the findings in the incident report and corrective actions
taken to resolve the issue.
Artifacts Used
Deployment Plan
Incident Report
Incident Response Plan
Installation Back-out Rollback Plan
Release Package
Artifacts Created
Updated Deployment Plan
Updated Incident Report
Updated Incident Response Plan
Updated Registered Request for Change
Responsible Role
Project Manager
Standards
None Listed
Release Management 75
More Info
See Change Management Process Map for additional guidance.
Process Activity Name: REL-3.5-DEC01 Rollback Successful?
Previous Process Activity
REL-3.5-DEC01 VBA Impact?
Next Process Activity
Note: There is a decision dependency that determines the next activity to be performed.
Artifacts Created
Deployment Calendar Weekend Report
Updated VBA Transformational Deployment Calendar
Release Management 76
Responsible Role
Project Manager
Release Management 77
Artifacts Created
Release Notification
Responsible Role
Project Manager
Standards
None Listed
More Info
None Listed
Artifacts Created
Completed (Successfully or Unsuccessfully) Registered Request for Change
Responsible Role
Change Coordinator
Release Management 78
Standards
None Listed
More Info
None Listed
END OF PROCESS.