Professional Documents
Culture Documents
2 UNDERSTANDING PROJECT CHARTER TEMPLATE & DEVELOPING PROJECT CHARTER OF FYDP .................... 6
4 CREATING NEW PROJECT ON MS PROJECT: GETTING FAMILIAR WITH THE SOFTWARE ENVIRONMENT ......10
5 INTRODUCTION TO DEVELOPING A GANTT CHART: LEARNING TASK MANAGEMENT; TASK FUNCTIONS; AND
TASKS LINKAGES ...............................................................................................................................................14
11 DEVELOPING NETWORK DIAGRAM FOR THE GIVEN PROJECT AND IDENTIFY CRITICAL ACTIVITIES ..............32
Step 1: File > Options > General tab > Project view > Default view.
Step 2: File > Options > Display tab > Show Indicators and Options Buttons For.
Step 3: File > Options > Schedule tab > Calendar options for this project.
Step 4: File > Options > Schedule tab > Calendar options for this project.
Set all options from “Week starts on” to “Days per month”.
Step 5: File > Options > Schedule tab > Schedule > Show Assignment Units.
Step 6: File > Options > Schedule tab > Calculation > Calculate Project after Each Edit.
Step 7: File > Options > Save tab > Save projects > Save Files In this format.
Step 9: File > Options > Advanced tab > Display > Show Status Bar > Show Scroll Bar.
Note: When the template is complete, the Project Charter document can be printed and approved. Prior to
printing, delete all [....] prompt text.
1. Is the level of authority of the Project Sponsor commensurate with the anticipated size, risk and
cost of the project?
2. Is there sufficient detail to allow the appointment of an appropriate Project Manager?
3. Have the project budgets received preliminary review and approval from the executive
management team?
4. Are all the known stakeholders identified?
5. Does the Project Charter describe the “project success criteria”?
2.2 Exercise
After the detailed explanation on creating Project Charter is delivered, the students shall now develop
project charters of their FYDPs, get them approved from their supervisors, either internal(s) or external or
both, and submit it to the course instructor. Upon any significant changes or revisions, they are also directed
to update the document and mention the version (or revision number).
Step 2: In entry table rows, enter all the tasks and sub activities in the task name column.
Step 3: Leave the main tasks as they are. Select the sub-activity and press the indent task button to convert
them into the sub-activity of respective task.
Step 5: In the Column Definition dialogue box, choose either “Outline Number” or “WBS” from the
dropdown list in the Field Name field. Click “OK” to close the Column Definition dialogue box and insert
the column.
• What tasks need to be performed to create the deliverables of the project and in what order? This
relates to the scope of the project.
• What are the time constraints and deadlines if any, for different tasks and for the project as a whole?
This relates to the schedule of the project.
• What kind of resources (man/machine/material) are needed to perform each task?
• How much will each task cost to accomplish? This would relate to the cost of the project.
• What kind of risk do we have associated with a particular schedule for the project? This might
affect the scope, cost and time constraints of the project.
Strictly speaking, from the perspective of Project Management Methodology, a Plan and Schedule are not
the same. A plan is a detailed action-oriented, experience and knowledge-based exercise which considers
all elements of strategy, scope, cost, time, resources, quality and risk for the project.
Scheduling is the science of using mathematical calculations and logic to generate time-effective sequence
of task considering any resource and cost constraints. Schedule is part of the Plan. In Project Management
Methodology, schedule would only mean listing of a project's milestones, tasks/activities, and deliverables,
with start and finish dates. Of course, the schedule is linked with resources, budgets and dependencies.
Click the Blank Project Tab. The following screen pops up.:
• Quick Access Toolbar: A customizable area where user can add the frequently used commands.
• Tabs on the Ribbon, Groups: With the release of Microsoft Office 2007 came the "Fluent User
Interface" or "Fluent UI", which replaced menus and customizable toolbars with a single "Office
menu", a miniature toolbar known as "quick-access toolbar" and what came to be known as the
ribbon having multiple tabs, each holding a toolbar bearing buttons and occasionally other controls.
Toolbar controls have heterogeneous sizes and are classified in visually distinguishable Groups.
Groups are collections of related commands. Each tab is divided into multiple groups.
• Commands: The specific features to perform actions in Project. Each tab contains several
commands. If the user points at a command, a description in a tooltip is seen.
• View Label: This appears along the left edge of the active view. Active view is the one the user
can see in the main window at a given point in time. Project includes lots of views like Gantt Chart
view, Network Diagram view, Task Usage view, etc. The View label just tells about the view one
is using currently. Project can display a single view or multiple views in separate panes.
• View Shortcuts: This lets the user switch between frequently used views in Project.
• Zoom Slider: Simply zooms the active view in or out.
• Status Bar: Displays details like the scheduling mode of new tasks (manual or automatic) and
details of filter applied to the active view.
A dialogue box appears. In the start date box, type the desired date format or click the down arrow to display
the calendar and select any date format of choice.
Click the arrow on the Current Date dropdown box. A list appears containing three base calendars.
Note: For MS Project, a task is the effort and action required to produce a particular project deliverable.
MS Project does not use the term “activity”.
2 hours 2h 2 hrs
3 days 3d 3 days
6 weeks 6w 6 weeks
Note: It is to remember that Project default values depend on user-defined work hours. So 1 day is not
equivalent to 24 hours, but has 8 hours of work for the day. Of course, user may change these defaults
anytime.
Start and Finish dates can also be entered and MS Project will calculate the duration on its own.
Text can also be entered when the user doesn’t have a duration metric currently (Task 3 and Task 4 in the
following screenshot).
Note: In the above screenshot, Task 6 is scheduled to start on Sunday, which is a non-working day and ends
on Wednesday. So essentially, one would believe that with these 3 days Monday, Tuesday, Wednesday, the
duration calculated would be 3 days. But MS Project calculates it as 4 days. So, one needs to be careful
when choosing the start date of the task. Because for any successive operation, MS Project considers that
Task 6 will take 4 days. The next time, when the start date is changed, the Finish date changes to reflect
this 4-day duration.
MS Project names the new task as <New Milestone> with zero-day duration.
Milestone will appear with a rhombus symbol in the Gantt Chart View.
Gantt Chart View > Format Tab > Show/Hide > click to check Project Summary Task on.
• Finish to Start (FS): Finish the first floor before starting to build the second floor. Most used.
• Finish to Finish (FF): Cooking all dishes for dinner to finish on time.
• Start to Start (SS): When doing a survey, we would seek survey responses but will also start
tabulating the responses. One does not have to finish collecting survey response before starting the
tabulation.
• Start to Finish (SF): Exam preparation will end when exam begins. Least used.
• Gantt Chart: In Gantt Chart and Network Diagram views, task relationships appear as the links
connecting tasks.
• Tables: In Tables, task ID numbers of predecessor task appear in the predecessor fields of successor
tasks.
5.6.1 Method 1
Select the two tasks to link.
Task tab > Schedule group > Link the Selected Tasks.
Task 1 and Task 2 can now be linked with any defined dependency.
5.6.2 Method 2
Double click a successor task to link. The Task information dialogue box opens.
Manual Scheduling: This is done to quickly capture some details without actually scheduling the tasks.
Automatic Scheduling: This uses the Scheduling engine in MS Project. It calculates values such as task
durations, start dates, and finish dates automatically. It takes into accounts all constraints, links and
calendars.
5.7.1.2 Method 2
Click Task > Tasks group > Auto Schedule.
Under scheduling options for this project select “All New Projects” from the dropdown box. Under new
tasks created, select “Auto Scheduled” from the dropdown box.
Aforementioned are some task management functions. Further discussions and more explanation shall be
given in class.
6.1 Settings
Resources > Level > Levelling Options > Levelling Calculations.
Set to manual.
Click the cell directly below the Resource Name heading column. Enter Resources as an individual person
(Zaid, Laiba, etc.), job function or group (engineer, coordinator, typist, etc.) or as an equipment (lathe
machine, earth mover, etc.).
Note: Max. Units field represents the maximum capacity of a resource to work on assigned tasks. 100%
stands for 100 percent of resource’s working time is available for work on task assigned. The resource is
available full-time on each workday. If the resource gets allocated to task or tasks that would require more
than his/its work hours, the resource is over allocated and MS Project will indicate this in red formatting.
Note: There is a clear difference between People and Equipment resources. People resources will have
limited work hours say 6, 8 or 12 hours. Equipment resources can have different working capacities of 2, 8
or 24 hours and could have maintenance breaks as well. Also note that it is possible multiple people
resources might be using one equipment resource, or one equipment might be accomplishing multiple tasks.
Cost of Task = Work Value (in number of hours) X Resource’s Pay Rate
Click View tab > Resource Views group > Resource Sheet.
Click the cell directly below Resource Name heading column to create Resources.
Click the Std. Rate field for each resource to costs in hourly (default), daily, weekly, monthly and yearly
rates. Click the Ovt. Rate field to enter overtime rates.
Click on Notes tab. Here let’s enter a note for Zaid “Zaid will work part-time”.
Click the box below the Resource Name column for the task to assign the resource.
From the dropdown, choose the resource name. For Task 1 “PT1”, the resource “Celic” has been assigned.
Click the Resources tab and click the cell below the Resource Name column. Select the resource from the
dropdown list.
In the following example below, let’s choose “Travel” as cost resource and enter the cost at $800. Other
material resources can also be assigned to the same task.
User will be able to see the plan’s start and finish dates.
In the Gantt Chart view, user can also look at the project summary task, to note the duration, start and finish
dates of the plan.
Gantt Chart View > Format Tab > Show/Hide > To check Project Summary Task on.
Cost for each task gets rolled up into summary tasks, and then ultimately to project summary task.
This will show the user the amount of usage of every resource.
When it is levelling, MS Project does not change who is assigned to each task. It only levels the work
resources, generic resources and committed resources. It does not level the material resources, cost
resources, or proposed resources.
Note: Because of these changes to the tasks, levelling can delay the finish date of some tasks and
consequently also the project's finish date.
For more control over levelling, user can level selected assignments or specific individuals.
Check the Indicator column to see which tasks have overallocated resources.
To level the workload for a specific individual and not everyone, click “Level Resource”.
• Every time the user level a project, the previous effects of levelling are cleared. To change this,
Resource > Levelling Options.
• To see the changes made to tasks by levelling, use the Levelling Gantt view.
Views > Task Views> Other Views > More Views > Levelling Gantt.
• To level within a specific time period,
Resource > Levelling Options, and then enter a From and To date.
In the “Schedule” group click “100% Complete” (or 25%, 50%, 75% as desired).
The Update Project dialogue box appears. Click “Update work as complete through” and then type or select
the date through which the user wants progress updated.
Note: If the user doesn't specify a date, MS Project uses the current or status date.
If user is updating specific tasks, click “Selected Tasks”. For updating all tasks in the project, click “Entire
Project”.
Note: It makes sense to save the baseline before entering any actual values such as percentage of task
completion.
Format tab > Bars and Styles group > Baseline (desired).
The user will see Baseline Gantt bars displayed together with the current Gantt bars.
Now for the required Task, click the corresponding “% Comp” column and enter the required % complete.
• Actual Start and finish dates - Project moves the schedule accordingly.
• Task’s Actual duration - If equal or greater than schedule duration: task = 100% complete.
The user will see the % W. Comp. (% work complete) column. This table includes Work (Scheduled work),
Actual, and Remaining columns. Click on Task to update.
Task tab > Schedule group > dropdown menu for Mark on Track > Update Tasks.
Change Start or Finish field in Actual group. Actual duration field can also be filled in.
Report Explanation
How much work, how many tasks are completed, and what’s left to be
Burndown
done.
The current cost status of the project and its top-level tasks, showing all
Cost Overview costs and percentage of completion to help determine if the project will
stay within budget.
How much of the project is complete, upcoming milestones and tasks that
Project Overview
are past due (late tasks).
The work that has been done in the current week, the status of any
Upcoming Tasks remaining tasks that were due, and what tasks are starting in the next
week.
A work burndown for the project and the work stats. for all top-level tasks
Work Overview
to know the percentage of completion and what’s left to be done.
Report Explanation
Overallocated Resources The work status for all overallocated resources, showing their actual work
and remaining work.
Resource Overview The work status of all people (work resources) who are working on the
project showing how much work is complete and what’s left to be done.
Report Explanation
Cash Flow The costs and cumulative costs per quarter for all top-level tasks.
Cost Overruns The cost variance for all top-level tasks and work resources. Also indicates
where actual costs exceed the baseline costs.
Earned Value Report Earned value, variance, and performance indices over time, comparing costs
and schedules to a baseline to determine if the project is on track.
Resource Cost Overview The cost status of work resources (people and material), showing cost details
in a table and cost distribution data in a chart.
Task Cost Overview The cost status of top-level tasks, showing cost details in a table and cost
distribution data in a chart.
Report Explanation
Critical Tasks All tightly scheduled tasks that are listed as critical on the project’s critical
path, meaning that any delay in such tasks will cause the schedule to slip.
Late Tasks All tasks that started or finished later than their scheduled start and finish
dates and that aren’t progressing as planned.
Milestone Report All tasks in the project that have milestones, showing which of them are
late, due, or completed.
Slipping Tasks All tasks in the project that are taking longer to complete than expected and
have a finish date that’s later than their baseline finish date.
If a predefined report doesn’t meet user’s needs, the user can use one of the following new report templates
to create his own project reports.
Select the Legend tab and then decide how the legend must look, which pages it should show up on, and
then the desired labels.
Under “Box Layout”, choose the box arrangement, alignment, spacing, height and width that work best for
the project. To space boxes evenly, select “Fixed” in the Height and Width boxes.
Under “Border”, choose the shape, colour, width and gridline options to create the desired look.
Click a name under “Data template” to apply the changes to an existing template. To create a new template
that will use the changes, click More Templates, and then click New (to create a new template), Copy (to
base the new template on an existing one), Edit (to change a template), or Import (to import a template from
another project).
Students must develop the chart and get it approved from their project advisers, either internal(s) or external
or both. After examination of the document, it must be attached to this workbook.