4. In a CPM network
a. Arrow head represents start of an activity
b. The activity arrows are drawn to a sale
c. The tail of an arrow represents start of an activity
d. The tail of an arrow represents finish of an activity
5. In PERT the time estimates of activities and probability of their occurrence follow
a. Poisson’s distribution b. Normal distribution c. Beta distribution
d. Binomial distribution
7. The area under the Beta distribution curve is divided into two halves by a vertical
ordinate through
a. Expected time b. Optimistic time c. Most likely time d.Pessimistic time