Professional Documents
Culture Documents
Specification Template For BMS Guide
Specification Template For BMS Guide
BMS Guide
Addendum
The user can copy relevant sections relating to their project and requirements
taking guidance from the BMSPG and insert relevant sections from this
document into their draft tender.
Sections 1 is purely acts as a prompt that may have to be included into the
‘Preliminaries/Conditions of Contract’ of any tender but will not replace or
dictate an alternative to your organisations own procurement governance.
Where the text is coloured, the user will insert their own text or prompt to the
user to confirm the validity and update to the latest version of any
recommended legislation or regulations.
Resource Efficient Scotland has published this document to assist the user in
compiling a tender specification but the user is ultimately responsible for the
final tender documentation which may include or not any content from this
document.
3 | Page
Contents
1.0 INTRODUCTION 5
1.0 INTRODUCTION
The objective of the BMS Upgrade is to enhance the system design to ensure that
the HVAC system operates to its greatest energy efficiency whilst maintaining
satisfactory conditions for the occupants.
Provide a General Specification for all works associated with the BMS
upgrade and to obtain Schedules of Rates and Performance Contracting
Proposals which will form the basis of a Framework agreement.
Provide a Standard specification for all future capital projects which have
any HVAC controls elements both those implemented directly by the
[INSERT ORGANISATION’S DETAILS] and on their behalf through their
partners.
In some instances the BMS Contractor will be the Lead Contractor (employing other
sub-contractors as necessary) and will be responsible for managing the works under
the CDM regulations. In this circumstance, the full specification should be used.
Where the controls and BMS is being carried out as a sub-contract to a main
contractor or M&E contractor the Mechanical and Electrical sections of this
specification should be omitted.
2.8 Security/Safety/Protection
Insert your organisations security and Health & Safety policy documents.
2.12 Arbitration
Insert your organisation arbitration process
3.1 Introduction
The General Specification details the requirements for the Upgrade of the
[INSERT ORGANISATION’S DETAILS]’s controls system.
3.2.3.2 The Contractor shall produce control schematic drawings for all items
of plant. These schematics shall form the basis of the BMS Supervisor screen
graphics. For each [INSERT ORGANISATION’S DETAILS] site the graphics
should incorporate floor-plans of the site plan from which to navigate the
buildings and plantrooms.
3.2.3.4 The Contractor shall provide drawings showing precise locations of all
BMS outstations, other control panels, field sensors and control devices, cable
containment and cable routes for all network cables, control and power
wiring. Additionally the Contractor shall provide Descriptions of Operation for
each system. As the design is developed, issue all drawings, schedules and
documents for comment prior to construction.
3.2.4.3 Develop software alarm strategy in discussion with the CA and the
Client.
3.2.4.4 Seasonal Fine Tuning of control strategies and minor changes to the
alarm strategy shall be provided during the first year of operation.
The Contractor shall provide control panel schematics and layouts for
approval by the CA before commencing manufacture of control panel. XX days
shall be allowed for approval / comment on drawings.
3.2.6.1 The location of all sensors etc shall be agreed with the CA prior to
installation.
The Contractor shall install and be responsible for carrying out all associated
electrical installation works.
3.2.8.1 The Contractor shall include for commissioning of the new installations
to suit the requirements of the project.
3.2.8.2 Check control loops for correct and stable control and make
adjustments as necessary during the first year of operation.
3.2.8.4 Full schedules of all control settings shall be recorded and included
within the O&M documentation.
9 | Page
The contractor shall supply all drawings for all parts of the installation as are
required by the Construction Design and Management (CDM) Regulations
2007, including three hard copy sets of “as installed” drawings and on CD.
3.2.10.2 The manuals shall be plastic covered, ring binders and all paper will
be of good quality. They shall also be provided in PDF electronic format and
shall comprise (delete as applicable):
Detailed on-site training (XX day minimum) in the operation and maintenance
of the system for up to XX members of the Client's organisational /
management staff will be provided after each significant work package.
3.2.12.1 Construction
Access shall be from the front via doubled hinged doors with dished edges;
gasket sealed onto the complementary dished return edges of the case.
The panel wiring shall be in accordance with the approved drawings and
current edition of the I.E.E. Wiring Regulations. Cables shall be sized to take
account of the de-rating required for areas with limited or zero ventilation and
for bunching of conductors.
Any external supplies to the panel shall have isolating links provided on the
terminal rail.
Wiring from panel to panel doors shall be subdivided into reasonable sized
bunches and run through proprietary flexible plastic tubing. The tubing shall
be supported at both ends and have sufficient loop to allow unrestricted
opening of the panel door.
4.1 Introduction
The General Specification details the requirements for the Upgrade of the
[INSERT ORGANISATION’S DETAILS]’s BMS and controls.
4.1.2 The equipment and installations are to comply with all statutory
regulations current at the time of tender and in particular regard to
following should be made:
Note: The list below may not be the latest versions of the regulations and
legislation
4.1.4 The Contractor is to allow for all mechanical, electrical and builder’s
works associated with this project.
4.1.6 The works shall include the responsibility for defects liability and the
maintenance (both planned preventative and breakdown), of all plant and
equipment for a period of xx months from the Certificate of Take-Over.
4.1.7 The Contractor shall allow for all maintenance items that will be
required during the period of responsibility for operation and maintenance.
4.2.1 The Contractor shall provide a full and complete set of working
drawings prior to any work commencing on site.
4.3.1 Any related builders works shall be carried out by the Contractor unless
otherwise specified in the contract.
4.3.2 Where services breach fire barriers, then the Contractor shall ensure
proper re-instatement is carried out to maintain adequate fire and smoke
protection.
4.4.1 The Contractor shall provide a set of Builders Works Drawings to allow
the correct installation of the new services.
4.5.3 Allowance for thermal expansion will be made by the use of bends and
anchors in the pipework run. The pipework will be arranged to prevent strain
on equipment and will be adequately supported. Supports will allow for the
thermal expansion of the pipework.
14 | P a g e
4.5.4 The Contractor shall allow for the supply, installation and commissioning
of the valves shown in Tender drawings plus any additional areas called for in
the General Specification or statutory regulations.
4.5.6 Isolation valves shall be cast iron wedge gate valves to BS 5150.
4.5.7 Where commissioning sets are required, these shall incorporate flow
measuring facilities and shall be installed in accordance with the
manufacturer’s recommendations.
4.5.8 Lockshield valves shall be used where called for in the General
Specification or Statutory Regulations.
4.5.9 Manual air vents and drain valves are to be located at all high and low
points respectively.
4.5.11 The Contractor shall ensure adequate isolating valves are incorporated
into the new systems to allow local isolation of services for maintenance
purposes.
4.6 Ductwork
4.6.1 The contractor shall allow for the supply and installation of all
ventilation equipment as detailed on the tender drawings and equipment
schedule.
4.6.5 The contractor shall provide fire dampers where ductwork penetrates
through fire barrier. Fire dampers will be of the fusible link out of air stream
drop curtain type. Contractor is to ensure access hatch to the dampers is
provided.
4.6.7 The Contractor shall allow for the provision of an engraved label
adjacent to each fan controller stating “Extract Fan” or “Supply Fan”
whichever is appropriate.
4.7.1 All LTHW pipework will be hydraulically tested to 1.5 times the pipeline
working pressure or 4 bar gauge for one hour whichever is higher.
4.7.2 The complete installation shall be dynamically flushed and filled with an
approved corrosion inhibitor.
4.8.1 All steel pipework shall be painted in accordance with BS1710 (British
Pipe Marking Standard) in accordance with the General Specification prior to
the application of any insulation. The Contractor shall ensure that all
uninsulated pipework is painted to match the local décor with 2 coats of paint.
16 | P a g e
The fibre-glass insulation should have a foil backed finish and have a grey
‘Isogenopak’ within the plantroom. All insulated pipework should be labelled
to indicate service and direction of flow.
4.8.3 Insulation shall be taken over all new valves and shall be cut for ease of
access to valves. Control valves (over 50mm dia) and flanges shall be
insulated using flexible, waterproof muffs, incorporating ‘velcro’ quick release
fasteners.
4.9.1 Some parts of the site may been subject to an Asbestos Survey and an
Asbestos Register may be available (a copy of which is to be provided on
request from the client), however, arrangements will made to carry out a
comprehensive asbestos survey (by others) as required within the areas of
work and other related areas, in order to identify any instances of materials
that might contain asbestos i.e. pipework insulation, walls etc, prior to the
commencement of contract.
The Contractor shall provide drawings detailing cable, pipe and duct routes to
cross check with asbestos records.
4.9.2 Should the Contractor find any suspicious material during the
installation, then he shall stop work IMMEDIATELY and seek advice from the
CA. Should the suspicious material prove to be Asbestos, then its removal
shall be funded outside of the Contract.
17 | P a g e
5.1 Introduction
The General Specification details the requirements for the Upgrade of the
[INSERT ORGANISATION’S DETAILS] controls system. This specification shall
be read in conjunction with relevant documents detailed in Section 4.1.2.
5.1.2 The Contractor is to allow for all mechanical, electrical and builder’s
works associated with this project.
5.1.3 The works shall include the responsibility for defects liability and the
maintenance (both planned preventative and breakdown), of all plant and
equipment for a period of xx months from the Certificate of Take-Over.
5.1.4 The Contractor shall allow for all maintenance items that will be
required during the period of responsibility for operation and maintenance.
5.1.6 All materials shall be new, unless otherwise specified, and of a type and
rating matched to the duty for which they are specified. All materials and
items of equipment performing the same function shall be of one manufacture
and type, unless otherwise stated in the Specification.
5.1.7 The works shall be set out with all measurements and dimensions
required for the supply and erection of materials on site, making any
modifications in detail as may be found necessary during the progress of the
works. Any such modifications or alterations shall be submitted to the CA
before proceeding.
5.1.13 Mounting heights given are for general tendering purposes, and will
apply unless otherwise detailed in this Section of the Specification.
5.1.14 The heights given apply to the centre of the box, unless otherwise
stated, but due allowance shall be given for any building feature, i.e. wall
tiling etc. where adjustment shall be made to coincide with the underside of
the tile.
(To Underside)
5.1.15 All heights shall be checked with the CA before actual installation
commences.
19 | P a g e
5.1.16 The installations shall include provision for the integrity of the fire
barriers through which cables, conduits, trunking, bus-bar systems etc. are
being installed, by making good around the installations with appropriate fire
stopping materials. This work shall be carried out to the requirements of the
Building Regulations and those of the 17th Edition of the I.E.E Wiring
Regulations including all current amendments.
5.1.17 All steel screws, nuts, bolts and washers used for fixing ferrous
materials to the building structure shall be sheradised (vapour galvanised).
Non-ferrous fixings shall be employed when fixing non-ferrous materials.
5.1.21 Fixings inside dry partitions shall be by wood screws to timber blocks
fixed to the partition support frame. The timber noggins shall be notched to
accept the accessory back box. Instruct the builder on size and location of
these timber blocks. Where necessary, provide extension rings for accessory
boxes so that the edge of the box is just recessed. Where cabling through
metal partitioning, jumbo stud, PVC conduits or flexible conduits shall be
employed.
5.1.22 All steelwork fabrications prepared shall be wire brushed and rust
treated with zinc chromate and painted with two coats of a rust inhibiting lead
free primer.
5.1.23 All steelwork fabrications, cut outs etc. shall be smoothed free from all
burrs or rough edges, and protection against abrasion to cables added where
appropriate.
5.1.26 Low voltage power cable shall generally be wire armoured to BS 6346,
BS 5467, BS 6724 or BS 6360 with XLPE compound insulation and/or LSF
bedding, as detailed further in this Specification.
5.1.27 Cables shall be fixed to tray, or direct to a surface using cable cleats.
The intervals for fixing shall be as stated in the IEE Regulations, or as stated
by the cable manufacturer where no regulation applies. Where fixed to cable
trays, power cables having an overall diameter of 10mm or less may be
strapped to the tray using PVC covered metal strip of appropriate colour, fixed
using brass pins and nuts Cable routes shall be so arranged that cables,
hangers, cleats etc. do not come into contact with or in close proximity to
piped services.
5.1.28 At all terminations, the sheath and armour shall be secured by brass
compression glands, of a type suitable for both cable and location. The glands
shall be complete with both earthing tag and plastic shroud.
5.1.29 Connections to the earthing tag shall be by brass nuts and bolts. At the
point of termination for SWA cables feeding any equipotential zone, the cable
shall terminate in a BICC type BW gland with integral earth and 481AA
insulated adapter.
5.1.31 Copper bonds shall be provided within the joint to maintain full earth
continuity. The resistance shall be no greater than that of the live conductors
and the insulation resistance between cores and between cores and earth
shall be no less than that of the original cable.
5.1.32 Cores shall be phased out. Either coloured core insulation or coloured
sleeve markers shall identify the phases.
5.1.33 Cables buried in the ground shall be in a trench 500mm deep, with
100mm of sand laid in the bottom, the cable laid on the sand then covered
with 100mm of sand. Propriety 100mm wide cable marker tape marked
“Electric Cables” shall be placed over the full length of the route, then back
filled with sifted earth, free from rocks and stones, well rammed and 200mm
below finished ground level and the ground then reinstated to existing ground
level.
21 | P a g e
5.1.34 Cables which follow the same route, and are laid in the ground, shall
be in horizontal formation with spacing between cables, where possible, of
not less than 150mm, with the exception of single core cables, which shall be
laid in trefoil formation and touching along their entire length. Each group of
cables shall be indicated by separate marker tapes.
5.1.35 Cable ducts shall be installed under roadways, crossing roadways and
for building access.
5.1.36 Cable ducts shall be smooth bore vitrified clay, or heavy duty plastic
socket and spigot type. All ends of conduit shall be sealed around the cable
with a waterproof and gas proof seal of the self-extinguishing plastic foam
type.
5.1.37 Any spare cable ducts shall have suitable end caps.
5.1.38 Cable markers, concrete block type shall be placed in the route at a
maximum of 50 metres apart and at each change of direction with a minimum
of two markers per route, and at each entry to a building.
5.1.40 Prior to the cable(s) being laid, the CA shall be informed and
arrangements made for an inspection to be made at each stage.
5.1.42 Where multi-core cables are employed, each core shall be numbered
and numbered markers at each end shall identify the terminal number of the
equipment to which the core is to be connected.
5.1.44 Where power cables pass through walls or floors, they shall pass
through properly formed openings, which shall be fire stopped after
installation using a proprietary foam.
22 | P a g e
5.1.45 Where power cables are laid in a common trench with other services,
particularly communication cables, there shall be a minimum separation of at
least 300mm between these services.
5.2.1 All drawings are diagrammatic only, and shall be used as a guide only to
assist in the compilation of the Tender.
5.2.2 The Contractor shall provide a full and complete set of working
drawings prior to any work commencing on site. These shall furnish the
dimensioned builders work drawings for all cable trenches, ducts, concrete
pads etc.
5.2.3 All final routings of MV/LV sub-main cabling, conduits, trunkings, cable
trays etc. and locations of accessories, items of equipment and plant shall be
fully agreed with the CA prior to the commencement of the installation.
5.3.1 Where services breach fire barriers, then the Contractor shall ensure
proper re-instatement is carried out to maintain adequate fire and smoke
protection.
5.4.1 The Contractor shall provide a set of Builders Works Drawings to allow
the correct installation of the new services for all holes, chases, cable
trenches, ducts, concrete pads, etc. to allow the correct installation of the
new services.
5.5.1 The whole of the earthing and bonding installations shall be installed
and tested in accordance with the requirements of the 17th Edition of the IEE
Wiring Regulations, Local Supply Authority, this Specification and in
compliance with BS 7430 (earthing protection).
23 | P a g e
5.6 Testing
5.6.1 Conduits and cables shall be tested during the progress of the work
before their concealment, as follows:
5.6.2 Immediately prior to completion, and in the presence of the CA, carry
out the initial inspection and testing as per 17th Edition of the IEE Wiring
Regulations.
5.6.6 Note that the CA will not accept the installation as practically complete
until a test/completion certificate is presented.
24 | P a g e
5.7.2 Distribution board schedules and ‘As Fitted’ drawings shall contain such
information as is required to satisfy clause 514-09 of the regulations. In
addition, ‘As Fitted’ drawings shall detail conduit runs, giving sizes.
5.7.3 Supply and fit such notices as may be required by regulation 515-08 to
514-13 inclusive.
5.8.1 Any tools that are required of a special nature for any equipment etc.
installed by the Electrical Sub-Contractor, shall be handed to the CA at the
hand over meeting, in a purpose designed box or receptacle.
6.2 Introduction
6.2.4 The works will follow an agreed Programme (add specific project
requirements). Installation of new BMS upgrade and enhancement will include
the following: [ADD/OMIT AS APPROPRIATE].
Installation of additional controls for heating system
Associated control wiring
Associated electrical wiring
Strip out works
Commissioning, testing and setting to work.
Provision of O&M documentation and “as fitted” drawings.
XX months defects liability and maintenance.
The BMS control system should be designed to maximise the efficiency of the
heating, ventilation and air-conditioning plant serving each building. The
description of operations below and the points schedule should be considered
indicative and should be further developed by the BMS Contractor based on
detailed site surveys and any further information obtained from site O&M
Manuals and by interrogation of the existing control system.
Plant Description
Add specific project details
Plant operation
The boilers are to operate in sequence with the duty boiler being rotated on a
weekly basis. Fault status for each boiler is to be monitored on the BMS
raising an alarm and activating the next boiler in sequence.
installed across the pump set is to provide a flow status on the BMS and
facilitates auto-changeover in the event of the duty pump failing.
The use of Inverter closed loop controls is encouraged for heating circulation
pump-sets and the contractor shall evaluate the efficiencies associated with
the deployment of inverter controls
Where applicable the flue dilution fan operates when there is demand from
the heating plant and/or HWS heater. A differential pressure switch placed
across the fan is to provide an air flow status on the BMS, providing a critical
alarm in the event of air flow failure.
Fire alarm – in the event of the fire alarm being activated the gas valve and
mechanical plant will be shutdown by hardwire interlock; fault status will be
monitored by the BMS and a high-level alarm raised.
Control
iii) High outside air temperature interlock (eco setting) – When the
external temperature reaches or exceeds 14 to 16°C (operator
adjustable) or the zone temperature is above approximately 23°C
(operator adjustable) the associated zone heating plant is to shut
down.
v) Boiler sequencing
Condensing boilers - sequence the boilers to maintain a compensated
common boiler flow temperature initially set up as shown in the table
below. In addition the BMS also monitors the boiler return
temperature. Facility should also be provided for space temperature
influence of the compensated temperature set point.
*Where boilers serve HWS calorifiers the minimum flow temperature should
be 65°C
Negative room trim: For every 1ºC that the minimum space
temperature falls below the space temperature setpoint the VT
flow setpoint will be increased by 3ºC. This is subject to a
maximum setpoint of 80ºC.
Positive room trim: For every 1ºC that the minimum space
temperature rises above the space temperature setpoint the VT
flow setpoint will be reduced by 3ºC. This is subject to a
minimum setpoint of 20ºC.
Plant Description
Plant Operation
HWS Heater
The HWS hot water heater is to operate by a dedicated BMS time-schedule.
Fault status is to be monitored on the BMS raising an alarm. A differential
pressure switch is to be installed across the HWS secondary pump provides a
flow status on the BMS (alternatively a current transformer may be used to
prove pump status).
The time-schedule will be set to meet the requirements of the site and should
be set such that the hot water is utilised during the day so that there is
minimal overnight HWS storage. Residential sites will require 24/7 provision.
For schools sites with HWS calorifiers it may be appropriate to heat the
system up for two or 3 discrete periods of the day to match consumption
requirements. This will avoid the heating plant running continuously.
HWS Calorifier
Operation as above. Primary HWS pumps are to operate in sequence on a
duty standby basis with the duty pump rotated on a weekly basis. A
differential pressure switch installed across the pump set to provide a flow
status on the BMS and facilitates auto-changeover in the event of the duty
pump failing. The de-strat pump is enabled independently.
Control
HWS Heaters - operate under its integral controls and is set to maintain a
HWS flow temperature setpoint of 60°C. The BMS is to monitor the flow
temperatures and raise alarms should the flow temperature exceed 65°C or
fall below 55°C (after a predetermined period, initially set to 30 minutes).
The BMS is to monitor and logs the HWS return temperature.
HWS calorifiers – the BMS is to modulate the HWS diverting valve to maintain
the HWS setpoint of 60°C. A hi-limit thermostat fitted to the calorifier de-
energise the HWS valve actuator activate spring safe function and close the
valve in the event of detecting a HWS temperature of 70°C.
Plate heat exchange – such units will operate under integral controls.
Plant Description
Plant Operation
All fans motors should normally be fitted with and VSD which is to be
controlled by either temperature and/or CO2 control. (This is optional)
Differential pressure switches are to be installed across the supply and extract
fans to provide air flow status’s on the BMS. A differential pressure switch is
to be installed across the fresh air filters to provide a filter dirty status on the
BMS.
Control
Temperature control
Frost control – the BMS will modulate the frost coil valve to maintain an off-
frost coil temperature monitored by a duct sensor downstream. A capillary
31 | P a g e
thermostat clipped to the downstream face of the frost coil is to shut down
the AHU supply fan by hardwired interlock. The frost coil should be fitted with
a spring-open actuator such that in the event of the frost thermostat being
activated a hardwire interlock de-energises the actuator, with the spring
mechanism opening the valve to allow flow through the coil. Activation of the
frost coil stat is monitored on the BMS raising an alarm.
The heat reclaim unit, heating coil and cooling coil (where applicable) are to
be modulated to maintain a compensated supply air temperature initial set as
detailed below (note these can be changed after initials set dependant on
client requirements):
The heat reclaim unit, heating coil and cooling coil (where applicable) are to
modulate to maintain a space or return air temperature of 22 +/- 2°C. Heat
reclaim control as detailed in paragraph above.
AHUs serving dedicated areas such as theatres, meeting room etc should
deploy CO2 Control and Occupancy Control
Where VSDs are fitted, room or duct mounted CO2 sensors are to be installed
and monitored by the BMS to modulate the supply and extract fan VSDs to
maintain satisfactory air quality initial as detailed below by the following
typical values: (user adjustable)
AHU serving Variable Air Volume (VAV) system fan speed control
The supply fan variable speed drive (VSD) is modulated to maintain a static
pressure setpoint (to be determined during commissioning). Velocity sensors
are to be installed and located in the supply and extract ductwork monitor the
air flow rates (m³/s). The extract fan VSD is to be modulated to maintain an
air flow rate of a minimum of 80% of the supply fan.
Plant Description
Add specific project details
Plant operation
The chillers are to operate in sequence, with the duty chiller being rotated on
a weekly basis. Fault status for each chiller is to be monitored on the BMS
raising an alarm and activating the next chiller in sequence.
The use of Inverter closed loop controls is encouraged for chilled water
circulation and the contractor shall evaluate the efficiencies associated with
the deployment of inverter controls
33 | P a g e
Control
The BMS is to operate the heat pump and air conditioning units under
individual time-schedules.
Presence detection sensors (microwave) within each room shall switch off the
units should no occupancy be detected for a period of 10 minutes (user
adjustable). The BMS Contractor will be responsible for the provision of any
necessary interface to achieve remote enable of the units.
A temperature sensor within each room will provided an alarm should the
temperature fall below approximately 18°C or exceed approximately 25°C
(when the unit has been enabled to operate).
34 | P a g e
Storage heaters are to be enabled by the BMS under demand from individual
optimised zone time-schedules.
The optimiser will determine the required charging period to meet the
requirements of the zone. The optimiser will be self-learning so that it can
adapt to the requirements of the heating zone.
Time extension switches should be provided for the HWS plant and ventilation
plant.
7.1 Introduction
Standard service
Fully comprehensive service
Enhanced energy performance service
7.1.2 The requirements for each level of service are defined in the following
sections.
7.2.1 The contractor shall have a 24 hour bureau facility to provide Remote
Response, Alarm Management, Call-out Response and Energy Management
Services. An Early Warning monitoring system will be provided for the site to
identify any related heating problems prior to the commencement of the
school day.
7.2.2 The contractor shall be able to stay connected to all sites 24/7, 365
days, which have remote connectivity for the purposes of supporting the
engineers, testing remote connectivity and to make ‘Change-Control’
alterations which are to be remotely logged.
7.2.4 All critical alarms shall be logged in a secure, managed database. Alarm
logs shall be automatically generated and posted online for the [INSERT
ORGANISATION’S DETAILS]’s use.
7.2.5 The contractor shall interrogate the site in response to a call-out prior to
attending site to establish more accurately the nature of the fault and the
best course of action, including:
36 | P a g e
7.2.6 The contractor shall log and report on all call-outs. The reports shall
include the following:
List of all Calls
Outstanding Calls
Completed Calls
Cancelled calls
Rejected Calls
Call be number
Calls total
Calls by site
Electrical
Check panel exterior for signs of damage. Ensure main door electrical
isolator is engaged and operational.
Check tightness of all electrical terminations. Check and re-torque
busbar nuts and bolts (in accordance with IEE Regulations).
Check integrity of power cabling insulation at frequency given in IEE
Guidance Note 3 Inspection and testing.
37 | P a g e
IT
Hardware
occur to these protective devices that fail safe and thus the failure is
often undetectable until the safety device is required to operate (at
least every six months).
Check operation of variable speed drives according to manufacturers’
recommendations (every 12 months).
Check operation of valves and damper actuators is correct; drive
actuators open and closed and to intermediate positions. Check for
hysteresis and that any position feedback devices/auxiliary switches
operate correctly. Check spring-return if applicable. Inspect for valves
and dampers letting by. Check tightness of the shaft connection. This
may be undertaken in conjunction with related ‘software’ maintenance
tasks (at least every six months).
Replace outstation battery (in accordance with manufacturers’
recommendations).
Interrupt electrical supply to each outstation, reinstate and ensure
system restarts satisfactorily.
Confirm that all critical alarms are received by the central supervisor
(at least every six months).
Check spurious alarms and reported faults (as incurred).
Building Performance
Verify and review operation and settings for control loops, setpoints,
dead bands, overrides, offsets, time switching schedules, optimised
start/stop routines, rotational points, hours run meters, and energy
and water meters. Check that temperatures/relative humidities/CO 2
concentrations and so on are maintained within the design intentions
of the building/plant. Adjust settings in conjunction with the building
39 | P a g e
7.3.1 The fully comprehensive service will include all of the items included in
the Standard Service, plus the following additional services:
The contractor shall provide an Energy Software Portal where the [INSERT
ORGANISATION’S DETAILS]’s automated monitored and targeted (aM&T)
electricity and heating fuel (gas, oil, biomass) data for each site can be
viewed by the client at any time. The data will be presented by automatically
generated charts and reports.
The contractor will establish energy performance baseline figures for each
building served by the BMS. Energy building profiles for each day of the
previous base line periods shall be developed based on historical data
40 | P a g e
On a daily basis, energy data will be collected for each site using File Transfer
Protocol (FTP), transferred in CSV format or obtain directly from sub-meters
or directly from energy provider secure websites. This data will automatically
be tabulated and compared against the building profiles for each site.
Variations in data above predetermined limits will generate an Energy Excess
alarm and “potential waste” reports etc.
In the event of an Energy Excess alarm the contractor will log the event, carry
out a thorough investigation to determine cause(s) of excessive energy usage
by remote BMS connection and provide a detailed report detailing remedial
actions taken and any appropriate recommendations.
Using the Building Profile as a benchmark the contractor shall log all HHD for
electricity and gas and use this data to produce appropriate reports and
charts for each site. Charts will be provided for consumption kWh, CO2 and
£.
The contractor will compare the baseline performance figures with relevant
benchmark figures (where these exist), depending upon the building type.
Energy / MM&T Software / Portal - The contractor will produce and host an
Energy Portal (web based) to allow the [INSERT ORGANISATION’S DETAILS]
to access the reports and charts, accessibility having a hierarchy control with
usernames and passwords.
The Portal shall have a Dashboard style layout which can be configured to
meet the requirements of the [INSERT ORGANISATION’S DETAILS].
Energy Tracker - The contractor shall forecast and track expected savings as
agreed by the [INSERT ORGANISATION’S DETAILS]. Forecasts shall be based
on measuring current consumption and against historical data after the data
has been ‘weather corrected’ using official heating and cooling degree day
data and any other relevant “driver” variable.
41 | P a g e
8.4.2 Review of BMS Set-Points. The contractor shall compile a log sheet, on
which they will record all BMS set-points with regard to operating times and
temperatures. The sheet will also include space for the corresponding
requirements of the [INSERT ORGANISATION’S DETAILS] to be recorded (this
to be determined in consultation with [INSERT ORGANISATION’S DETAILS]
estate or energy staff).
Ensure that the BMS is set in line with the [INSERT ORGANISATION’S
DETAILS]’s latest requirements.
Produce a concise report confirming the checks made and any issues
resulting.
The contractor shall present a business case for each proposal to the [INSERT
ORGANISATION’S DETAILS], defining installation costs and itemised savings
resulting from reduced energy use, maintenance etc. The methodology used
to estimate savings will be clearly defined.
STOR is one of National Grid’s most important tools for securing the national
electricity system in real time. Under the STOR arrangements, National Grid
pays a “rent” (termed availability) for STOR capacity, and pays a usage
charge (utilisation) when the reserve is needed, e.g., during demand peaks,
or when large power stations fail. STOR is a year-round service. There are a
number of companies who tender for the National Grid STOR contracts and
recruit generator sites owners to meet the agreed capacity requirement. The
value of the STOR contract is dependent on a tender negotiation and the
number of hours of utilisation. Savings can be achieved through load
shedding of non-essential equipment, e.g. HVAC chillers, pumps etc and by
the operation of standby generators, where applicable.
43 | P a g e
8.1 Introduction
8.2.1 The Contractor shall complete the Schedule of Rates proforma included
in the Tender documentation. This includes a comprehensive schedule of
rates for all materials and equipment applicable to the works, which apply to
this tender or are likely to apply to future phases. The schedule shall equate
to the tender/quotation sum.
8.2.3 The tendering company should also provide prices for the three
maintenance options as in 8.1.1 for:
a) new installations
b) existing BMS installations
We the undersigned, do hereby offer to carry out the whole of the work
described in this Specification, and associated drawings (listed in Table of
Contents contained within this Specification), in strict accordance with the
terms and conditions thereof, for the following sums of money:
6 Contingency (x%) £
TENDERER:
..................................................................................................................
ADDRESS:
...............................................................................................................
.................................................................................................................
SIGNED:.............................................................................................
DATED:..............................................................................................
47 | P a g e
Cost
Item Manufacturer Model Unit Size per Cost
(e.g.,single, unit
Length metre)
Supply, installation and commission
Space temperature sensor single -
Duct temperature sensor single -
Immersion temperature sensor single -
Outside air temperature sensor single -
Frost thermostat single -
Differential pressure switch single -
Current transducer single -
Wind sensor single -
Solar sensor single -
Valve & actuator (0 - 10V) single 20mm
Valve & actuator (0 - 10V) single 25mm
Valve & actuator (0 - 10V) single 40mm
Valve & actuator (0 - 10V) single 50mm
Damper actuator (15Nm, 0 - 10V) single -
Outstation [ADD DETAILS] [ADD single
DETAILS]
Input/output module [ADD DETAILS] [ADD single
DETAILS]
Input/output module [ADD DETAILS] [ADD single
48 | P a g e
DETAILS]
Input/output module [ADD DETAILS] [ADD single
DETAILS]
Input/output module [ADD DETAILS] [ADD single
DETAILS]
Other Control devices, list price less - - single - (% list
percentage less)
Control Panel modification for - - per point -
Outstation < 50 points
Control Panel modification for - - per point -
Outstation > 50 points
Control Panel manufacture % mark-up - - - -
Sub-contractor mark-up (e.g. - - - -
Mechanical or building contractor) %
mark-up
Engineering (including software - - per point -
design, graphics)
Project Management - - per point -
Commissioning - - per point -
Existing installation
Standard maintenance service - - per - -
point/annum
Fully comprehensive maint cover - - per - -
point/annum
Electrical Installation
Cabling Installation- Single Phase - - metres 1mm
(PVC/LSF Single circuit)
Cabling Installation- Single Phase - - metres 1.5mm
(PVC/LSF Single circuit)
Cabling Installation- Single Phase - - metres 2.5mm
(PVC/LSF Single circuit)
Cabling Installation- Single Phase - - metres 4mm
(PVC/LSF Single circuit)
Cabling Installation- Single Phase - - metres 6mm
(PVC/LSF Single circuit)
Cabling Installation- Single Phase - - metres 10mm
(PVC/LSF Single circuit)
Cabling Installation Single Phase - - metres 16mm
(PVC/LSF Single circuit)
Cabling Installation Single Phase - - metres 25mm
(PVC/LSF Single circuit)
Cabling Installation Single Phase - - metres 35mm
(PVC/LSF Single circuit)
Cabling Installation -3 Phase (PVC/LSF - - metres 1mm
Single circuit)
Cabling Installation 3 Phase (PVC/LSF - - metres 1.5mm
Single circuit)
50 | P a g e
Metal
Plastic
Containment Conduit Installation - - - metres 9mm
Plastic
Containment Trunking Installation – - - metres 50x50
Metal
Containment Trunking Installation - - metres 75x50
Containment Trunking Installation - - metres 100x50
Containment Trunking Installation - - metres 100x100
Containment Trunking Installation - - metres 150x100
Containment Trunking Installation - - metres 150x50
Containment Trunking Installation - - metres 150x75
Containment Trunking Installation - - metres 200x100
Containment Trunking Installation - - metres 200x150
Containment Trunking Installation - - metres 200x200
Containment Trunking Installation - - metres 300x100
Containment Trunking Installation - - metres 300x150
Containment Trunking Installation - - metres 300x200
Containment Trunking Installation - - metres 300x300
Containment Trunking Installation - - - metres 50x50
Plastic
Containment Trunking Installation - - metres 75x50
Containment Trunking Installation - - metres 100x50
Containment Trunking Installation - - metres 100x100
Containment Trunking Installation - - metres 150x100
Containment Trunking Installation - - metres 150x50
Containment Trunking Installation - - metres 150x75
Containment Trunking Installation - - metres 200x100
Containment Trunking Installation - - metres 200x150
53 | P a g e
TOTALS
57 | P a g e