Jadwal Pelaksanaan Pekerjaan

No. Uraian Pekerjaan Bobot Awal Durasi Lanjutan Durasi 01-03 02-03 03-03

1 Pekerjaan A 25.64 01-03-2016 2 04-03-2016 3 5.13 5.13

2 Pekerjaan B 11.54 01-03-2016 4 2.88 2.88 2.88

3 Pekerjaan C 8.97 01-03-2016 7 1.28 1.28 1.28

4 Pekerjaan D 19.23 02-03-2016 2 07-03-2016 2 4.81 4.81

5 Pekerjaan E 19.23 03-03-2016 3 6.41

6 Pekerjaan F 12.82 03-03-2016 6 2.14

7 Pekerjaan G 2.56 05-03-2016 5


Total 100.00 Jumlah Bobot 9.29 14.10 17.52
Kumulatif Bobot 9.29 23.40 40.92
04-03 05-03 06-03 07-03 08-03 09-03 %tase

5.13 5.13 5.13 100.00


90.00
2.88 80.00
1.28 1.28 1.28 1.28 70.00
60.00
4.81 4.81 50.00
6.41 6.41 40.00
30.00
2.14 2.14 2.14 2.14 2.14 20.00
0.51 0.51 0.51 0.51 0.51 10.00
-
17.84 15.47 9.06 8.74 7.46 0.51
58.76 74.23 83.29 92.03 99.49 100.00