PIP ELCGL01D
Data Sheet for Electrical Design Criteria
PURPOSE AND USE OF PROCESS INDUSTRY PRACTICES
In an effort to minimize the cost of process industry facilities, this Practice has
been prepared from the technical requirements in the existing standards of major
industrial users, contractors, or standards organizations. By harmonizing these
technical requirements into a single set of Practices, administrative, application, and
engineering costs to both the purchaser and the manufacturer should be reduced. While
this Practice is expected to incorporate the majority of requirements of most users,
individual applications may involve requirements that will be appended to and take
precedence over this Practice. Determinations concerning fitness for purpose and
particular matters or application of the Practice to particular project or engineering
situations should not be made solely on information contained in these materials. The
use of trade names from time to time should not be viewed as an expression of
preference but rather recognized as normal usage in the trade. Other brands having the
same specifications are equally correct and may be substituted for those named. All
Practices or guidelines are intended to be consistent with applicable laws and
regulations including OSHA requirements. To the extent these Practices or guidelines
should conflict with OSHA or other applicable laws or regulations, such laws or
regulations must be followed. Consult an appropriate professional before applying or
acting on any material contained in or suggested by the Practice.
This Practice is subject to revision at any time by the responsible Function Team and
will be reviewed every 5 years. This Practice will be revised, reaffirmed, or withdrawn.
Information on whether this Practice has been revised may be found at www.pip.org.
PIP will not consider requests for interpretations (inquiries) for this Practice.
PAGE 1 OF 8
November 2002
PAGE 2 OF 8
November 2002
4. Area Classification
4.1 " Per PIP ELEHA01 " Other_______________
4.2 " Division Method " Zone Method
ASSOC. PIP: DATA SHEET FOR ELECTRICAL
ELCGL01 DESIGN CRITERIA ELCGLO1D
PAGE 3 OF 8
November 2002
5. Power Distribution
5.1 System Configuration
System ! Simple Radial ! Expanded ! Primary ! Primary Loop ! Secondary
Configuration System Radial System Selective System Selective
Arrangements System System
! One Line Attached Document Number ________________________________
5.3 Transformers
5.3.1 Power Transformers
! Liquid Filled ! Indoor ! Outdoor
! Dry Type ! Indoor ! Outdoor
! Cast Coil ! Indoor ! Outdoor
5.3.2 Transformer Size Based On
! 650C Rise ! 550C Rise ! Other _________
5.3.4 ! Liquid Type: _________
5.3.5 Power Transformer Location ! Outdoor ! Other _________
5.3.5 Outdoor Transformer Spec ! PIP ELSTR01 ! PIP ELSTR04 ! Other __________
5.3.5 Indoor Transformer Spec ! PIP ELSTR03 ! Other _________
5.3.6 Control Power and Lighting Transformers ! 800C / 2200C ! Other __________
5.3.7 Outdoor Control Power and Lighting Transformers ! Epoxy-Encapsulated ! Other __________
PAGE 4 OF 8
November 2002
5.5 Switchgear
5.5.1 Low-Voltage Switchgear " Metal-Enclosed Drawout (PIP ELSSG01) " MCCB Panelboard
5.5.2 Medium-Voltage Switchgear " Metal-Clad " Metal-Enclosed " Metal-Enclosed (PIP ELSSG03) for
(PIP ELSSG02) (PIP ELSSG03) Transformer Main Only
5.5.3 Control Voltage LV Metal-Enclosed " 125 VDC Trip " Captrip Trip
" 125 VDC Close " AC Close
MV Metal-Clad " 125 VDC Trip " Captrip Trip
" 125 VDC Close " AC Close
MV Metal-Enclosed " 125 VDC Trip " Captrip Trip
" 125 VDC Close " AC Close
5.6 Switchgear / Substation Batteries " Flooded-Cell Lead-Acid per PIP ELSAP11 ! Other _______________
7. Motor Control
7.2 480-Volt Motor Control
7.2.1 MCC Type " Fused Disconnect Switch " Molded-Case Circuit " Motor Circuit Protector " Other _______
(PIP ELSMC12) Breaker (PIP ELSMC13) (PIP ELSMC13)
7.2.2 MCC Indoor Enclosure Type " NEMA 1 Gasketed " NEMA 12
7.2.4 MCC Outdoor Enclosure Type " NEMA 3R " NEMA 4X " Other _________________
7.2.5 MCC Enclosure Arrangement " Front Only " Back-to-Back
7.2.6 Indoor MCC Floor Space " 20% Growth " Other _________________
7.2.8 Outdoor Starters (Non-Classified) " NEMA 4X " NEMA 3R " Other _________________
7.2.9 Explosion-Proof Starter Enclosures " Bolted " Threaded " Other _________________
7.2.11 Minimum Starter Size " Size 1 " Other _________________
7.2.12 Overload Protection " Electronic
" Eutectic Alloy " Class 10 " Class 20 " Class 30
" Bi-Metallic " Class 10 " Class 20 " Class 30
7.3 Low-Voltage Adjustable Speed Drives " Per PIP ELSMC20 " Other_____________________________
PAGE 5 OF 8
November 2002
8. Grounding
8.1 Ground Grid Conductor " Bare " Covered
8.2 System Grounding (Also See 3.5)
8.2.2 " 480-Volt Wye per PIP ELSGS01 " 480-Volt Delta per PIP ELSGS02 " Other _______________
8.2.3 " Low Resistance - XFMR Wye Neutral Resistor per PIP ELSGS11 " Low Resistance Other ______________
High Resistance per the Following:
" 2400-Volt Wye per PIP ELSGS03 " 2400-Volt Delta per PIP ELSGS04
" 4160-Volt Wye per PIP ELSGS05 " 4160-Volt Delta per PIP ELSGS06
8.2.4 Distribution System Grounding " XFMR Wye Neutral Resistor per " Zig-Zag Transformer
Method PIP ELSGS11
" Other___________________
PAGE 6 OF 8
November 2002
9. Lighting
9.1 Illumination Level ! Per API RP540 ! Other __________
9.2 Luminaires and Circuits
9.2.1 Areas Luminaire Type Voltage Rating
General Building / Office ! Fluorescent ! 120
! Incandescent ! 208
! Metal Halide ! 277
Shops, Warehouse, etc. ! Fluorescent ! 120
! Metal Halide ! 208
! High-Pressure Sodium ! 277
! 480
Floodlights, Roadway ! Metal Halide ! 120
Lighting, Parking Lots, ! High-Pressure Sodium ! 208
etc. ! 277
! 480
Outdoor Process ! Metal Halide ! 120
! High-Pressure Sodium ! 208
! 277
! 480
Indoor Process ! Fluorescent ! 120
! Metal Halide ! 208
! High-Pressure Sodium ! 277
! 480
Control Room ! Fluorescent ! 120
! Incandescent ! 208
! Other __________________ ! 277
9.2.4 Emergency Lighting ! Per 9.2.4 ! Per 9.2.4 and Other __________
Locations
PAGE 7 OF 8
November 2002
11.4 Direct Burial " Not Allowed " Armored Cable " Non-Armored Cable
11.5 Overhead Pole Lines " Not Allowed " Open Wire " Messenger
11.6 Messenger Cable Support Method __________________
1/C " XLPE/PVC " XLPE/CPE " XLPE/CSPE " Other _______________
" EPR/PVC " EPR/CPE " EPR/CSPE
12.5 Multiconductor Minimum Size " No. 14 " No. 16 " Other _______________
PAGE 8 OF 8
November 2002
Other Requirements: