On-Site Equipment Inspection

Check Sheet
Mill
Equipment Title: Project:
System: P&ID:
Author: Date:
Step Item Yes No N/A Comments Sign &
Date
1 Check cleanliness
Clear of debris:
Dry:
Grease Free:
2 Hold down bolts installed & secure
3 Gearbox fitted
4 Guards fitted, complies to standards
5 Shaft correctly aligned
6 Lubrication and greasing completed
7 Stop start button installed and labeled
8 Can key parts be safely removed for
maintenance
9 Motor rotation correct
10 Motor fitted
11 Scalping receiver in position?
12 All instrumentation installed as per design
and installation manuals and P&ID
13 Inlet and outlet pipe work clean and ready
for operation
14 Has the equipment been suitably grounded
15 E-Stop easily accessible?