DEWATERING PUMP DAILY INSPECTION CHECKLIST

MARJAN INCREMENT PROJECT


Location: ______________ Inspection Month: ____year______

Dewatering Pump :
Modle# Manufacture:
S/N ITEM 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31

1 Pump is clean and in good condition

2 Are there any fuel leaks


3 Are tyres in good condition.
4 All engine hoses in good condition
5 Exhaust system functioning normally
6 Exhaust provided with spark arrestor
7 Are guards fitted to rotating/moving parts
8 Battery secured properly
9 No abnormal sounds noted in the equipment.
10 Relevant safety signs are provided & displayed.
11 Equipment properly grounded with Copper rod
12 Fire extinguisher (UL Listed) is available
13 Drip tray is provided.
14 Control & Switches are functional.
15 No evidence of spillage around the pump.
16 Monthly Inspection Sticker is available