OBJECTIVE OF PROJECT
To increase the production of sewing line.
To minimize the rework in quality.
To identify the factors that lead to increase in rejections and reworks.
To determine the critical operations and factors that leads to increased level of
rejections and rework.
To search for possible solutions or alternatives for critical and semi-critical operations.
To bring down and sustain rejections to a minimum level.
SCOPE OF PROJECT
Decrease in level of rejections and reworks and reduced fabric usage.
Increased productivity
Reduction in lead time
Cost reduction and increased profit.
PROBLEM IDENTIFICATION
The sewing line was producing number of different type of defects- minor defects,
major defects.
Alteration frequency was more than 22.7%.
Overall productivity loss 2 day.
Rejection per day was 40-42 garments.
PROJECT METHODOLOGY
Review of the existing quality inspection system in sewing department.
Identification of defects in the sewing line by collecting data from old records
Analysis of data collected in order to identify majorly occurring defects and alterations.
Categorization of defects
Assessing root cause analysis of defects.
Development of a model Quality Inspection System as traffic light system.
Implementation of check sheets at work station to capture operator’s performance
quality level.
Analysis the data of operator’s quality performance after suggestion implementation.
There are two quality inspection check point: Inline & end line check point.
After passing of pieces from two check points, the end line inspection checker checks all
the measurement and all type of defects in garment.
Every hour the end line checker checks all 30-42 pieces and point out no. of defective
pieces and note down in inspection report.
The lot of 30-42 pieces is checked by Q. A. audit as 10% of the lot is inspected by Q.A.
2.2 Identification of defects in the sewing line by collecting data from old records
2.3 Analysis of data collected in order to identify majorly occurring defects and alterations
35
30
30
25
21
19 18 19
20
15 13
10
0
Tuesday Wednesday Thursday Friday Saturday Monday Tuesday
Defect %
60
50
40
30
20
10
0
Tuesday Wednesday Thursday Friday Saturday Monday Tuesday
20
15
10
0
Tuesday Wednesday Thursday Friday Saturday Monday Tuesday
DHU %
2.5 Cause & Effect diagram for major occurring defects as alteration and rejections and their
implemented solutions
MATERIAL METHOD
Uneven width
at collar end
Improper handling
Material handling
MATERIAL METHOD
3. Sleeve pinching
Sleeve pinching
MATERIAL METHOD
Root Cause Solution
Careless of operator Self-assessment and handling
Improper
placement of
lace
MATERIAL METHOD
Improper
placement of lace
5. Uneven loops
Uneven loops
MATERIAL METHOD
Uneven loops
Root Cause Solution
Cutting of thin lace not equal Proper instructions given to cut the
elastic
Placement of
Lace from neck
not proper
Marking not visible Material handling-spacing
MATERIAL METHOD
Placement of lace from
neck not proper
Attachment of
front lace not
proper
MATERIAL METHOD
Attachment of front
lace not proper
Root Cause Solution
Instruction not followed Again instructions are given and keep
on checking time to time
Ticket number is
not matching
MATERIAL METHOD
Ticket number is not
Root Cause matching Solution
Instruction not followed Again instructions are given and keep
on checking time to time
2.7 Implementation of check sheets at work station to capture operator’s performance quality
level
Date Daily Total Daily Total Number Number Defective Defect WIP
input input output output of of pass pcs %
checked pcs
pcs
11/7/17 550 550 15 15 40 23 17 42.5 535
12/7/17 550 1100 104 119 137 96 41 30 981
13/7/17 300 1400 160 279 205 160 45 21 1121
14/7/17 200 1600 205 484 236 190 46 19 1116
15/7/17 50 1650 247 731 255 220 35 13 919
16/7/17 Sunday - - - - - - - -
17/7/17 150 1800 230 961 264 215 49 18 839
18/7/17 272 2072 250 1211 303 245 58 19 861
19/7/17 228 2300 270 1481 300 258 42 14 826
20/7/17 350 2650 238 1719 263 227 36 13.6 938
21/7/17 250 2900 254 1973 287 242 45 15.6 934
22/7/17 184 3084 240 2213 225 202 23 10.2 878
23/7/17 Sunday - - - - - - - -
24/7/17 closed 3084 290 2503 300 279 30 10.5 588
25/7/17 closed 3084 284 2787 290 254 36 12.5 304
26/7/17 closed 3084 304 3091 312 242 42 13.4 0
Before
Implementation
Days Tuesday Wednesday Thursday Friday Saturday Monday Tuesday Average
Percentage
Alteration% 42.5 30 21 19 13 18 19 23.2
After
Implementation
Alteration% 14 13.6 15.6 10.2 10.5 12.5 13.4 12.82
Before
implementation
Days Tues Wednes Thurs Fri Satur Mon Tues Average
day day day day day day day
Alteration
17 41 45 46 35 49 58 41.57
After
implementation
Alteration
42 36 45 23 30 36 42 36.28
Before
implementation
Days Tues Wednes Thurs Fri Satur Mon Tues Average
day day day day day day day
Alteration
17 41 45 46 35 49 58 41.57
After
implementation
Alteration
42 36 45 23 30 36 42 36.28
Before
implementation
Days Tues Wednes Thurs Fri Satur Mon Tues Average
day day day day day day day Productivity
Productivity
23 96 160 190 220 215 245 164
After
implementation
Productivity
258 227 242 202 279 254 242 267
D. Productivity improvement
Conclusion
Traffic light system is a system that can be implemented in any garment manufacturing
company and help to improve the quality status, improve the lead time and thus
strengthen the supply chain performance without increasing the resource.
We know save of days is nothing but decreasing the lead time and the more the lead
time the better the supply chain performance is.
Implementation of the traffic light system for the global change is also proposed to the
factory management to get the ultimate benefit.
After implementing the lean traffic light system the quality status is improved.