Professional Documents
Culture Documents
PLANNING
TECHNIQUES
EXAMPLES:
Data Conversion
Project
Parviz F. Rad
Vittal Anantatmula
Resource Breakdown Structure
The following represents the pool of resources available for assignment to the project. Note that
any project entry requirement costs (e.g., network infrastructure to support remote work) are
assumed by the client external to the project and are not enumerated below.
All internal rates identified are valid for and guaranteed through the calendar year of 2003,
and are valid for use of these resources in any geography in which the CoC operates. These
rates are based upon internally-published and fully-burdened, therefore these already include
many of the incidental ongoing expenses of the practice, such as home office support, cell
phones, laptop computer, general software, office supplies, etc. Note that, within a given
discipline, the band level or title reflects the relative skill level of the individual in that
discipline. The rates for each band level are identified in the final table.
Contractor rates, where used, also are fully burdened and apply to the same time period and
geography, and are the rates negotiated with vendors approved by the Purchasing
Organization.
As XYZ is so large, for all practical purposes, there is no limit to the availability of any of these
skills.
Objectives
This project provides data from an acquired bank converted to a format allowing merging of the
data into the client's applications. Project includes needs assessment, application and process
design, implementation, and creation of the converted files and reports for client testing.
This project provides data from an acquired bank converted to a format allowing merging of the
data into the client's applications. Project includes needs assessment, application and process
design, implementation, and creation of the converted files and reports for client testing and
integration.
Estimates
Notes regarding these estimates:
1. Nearly all lowest-level elements have three or more resources – for those few that do not, it
was determined to be inappropriate. However, many more than the required 35 do so.
2. Many activities begin with work products from the methodology and customize and elaborate
these for the specific project at hand; the client is not charged for the value of the pre-existing
work.
3. PM-related work products (status reports, labor tracking, invoicing, etc.) not listed are
included in the overhead applied to the rate structure of this project.
4. Client personnel resources are not listed on an element if their only involvement is approval;
if their involvement is a contributory evaluation, it is included.
5. Many of the resources in the RBS were not applicable to the scope and size of this particular
project.
6. No hardware or software is required for this project other than what is already installed at the
client (including the Gladstone software license) and installed on the workstations of the
assigned resources.
7. Most intensities are “1,” and should require no explanation. The most common multiple
intensity is “4” and relates to the Business Analyst (P.3.2) resource. As a separate BA will be
used for each Application File (e.g., Customer Information File, Account File, Account
History File, Pre-Authorized Transaction File), this refers to this set of analysts. The
intensities for traveling refer to the number of persons flying (T.1.2) or experiencing per-diem
onsite expenses (T.2.2) for that activity.
8. The effort abbreviation “WH” stands for “Worker-Hours” and is used regardless of the
particular role referred to, even though the rates of a WH vary by role and level. This will be
resolved (expanded) in the next assignment, which addresses cost.
WBS
WBS Element Name Resource Intensity Duration Effort
Num
0 Core Banking Data Conversion N/A
1.0 Needs Analysis Documentation N/A
1.1 Source System Analysis Report N/A
Source Application & Interfaces
1.1.1 P.5.1 Conversion Architect 1 40 40 WH
Report
P.3.1 BA Lead - Banking 1 10 10 WH
C.2.1 Client Architect 1 10 10 WH
C.3.1 Client BA 1 10 10 WH
1.1.2 Source Data Dictionary P.5.1 Conversion Architect 1 40 40 WH
P.3.1 BA Lead - Banking 1 40 40 WH
P.3.2 BA - Banking 4 40 160 WH
C.3.1 Client BA 1 40 40 WH
1.2 Source Data Analysis Report N/A
1.2.1 Source Product Report P.3.1 BA Lead - Banking 1 16 16 WH
P.5.5 Programmer - Host Cobol 1 24 24 WH
C.3.1 Client BA 1 8 8 WH
Customer Information File
1.2.2 P.5.1 Conversion Architect 1 4 4 WH
Analysis Report
P.3.1 BA Lead - Banking 1 2 2 WH
P.3.2 BA - Banking 1 16 16 WH
P.5.5 Programmer - Host Cobol 1 32 32 WH
C.3.1 Client BA 1 10 10 WH
Name & Address Scrubbing
1.2.3 P.5.1 Conversion Architect 1 2 2 WH
Analysis Report
P.3.1 BA Lead - Banking 1 8 8 WH
P.5.5 Programmer - Host Cobol 1 16 16 WH
C.3.1 Client BA 1 4 4 WH
1.2.4 Account File Analysis Report P.5.1 Conversion Architect 1 4 4 WH
P.3.1 BA Lead - Banking 1 2 2 WH
P.3.2 BA - Banking 1 16 16 WH
P.5.5 Programmer - Host Cobol 1 32 32 WH
C.3.1 Client BA 1 10 10 WH
Account History File Analysis
1.2.5 P.5.1 Conversion Architect 1 4 4 WH
Report
P.3.1 BA Lead - Banking 1 2 2 WH
P.3.2 BA - Banking 1 16 16 WH
P.5.5 Programmer - Host Cobol 1 32 32 WH
C.3.1 Client BA 1 10 10 WH
Pre-Authorized Transaction File
1.2.6 P.5.1 Conversion Architect 1 2 2 WH
Analysis Report
P.3.1 BA Lead - Banking 1 2 2 WH
P.3.2 BA - Banking 1 8 8 WH
P.5.5 Programmer - Host Cobol 1 16 16 WH
C.3.1 Client BA 1 5 5 WH
1.3 Target System Analysis Report N/A
Target Application & Interfaces
1.3.1 P.5.1 Conversion Architect 1 40 40 WH
Report
P.3.1 BA Lead - Banking 1 10 10 WH
P.3.2 BA - Banking 4 2 8 WH
C.2.1 Client Architect 1 10 10 WH
C.3.1 Client BA 1 10 10 WH
1.3.2 Target Data Dictionary P.5.1 Conversion Architect 1 40 40 WH
P.3.1 BA Lead - Banking 1 40 40 WH
P.3.2 BA - Banking 4 40 160 WH
C.3.1 Client BA 1 40 40 WH
2.0 Design Documentation N/A
Overall Solution Architecture
2.1 N/A
Document
Conversion Dependency (Intra-
2.1.1 P.5.1 Conversion Architect 1 20 20 WH
Appl & External) Report
P.3.1 BA Lead - Banking 1 8 8 WH
P.3.2 BA - Banking 4 4 16 WH
C.2.1 Client Architect 1 4 4 WH
C.3.1 Client BA 1 4 4 WH
2.1.2 Target Record Layout Definition P.5.1 Conversion Architect 1 4 4 WH
P.3.1 BA Lead - Banking 1 4 4 WH
P.3.2 BA - Banking 4 4 16 WH
P.5.5 Programmer - Host Cobol 4 16 64 WH
C.2.1 Client Architect 1 2 2 WH
C.3.1 Client BA 1 2 2 WH
2.1.3 Exception Condition Definition P.5.1 Conversion Architect 1 8 8 WH
P.3.1 BA Lead - Banking 1 4 4 WH
P.3.2 BA - Banking 4 8 32 WH
C.2.1 Client Architect 1 4 4 WH
C.3.1 Client BA 1 4 4 WH
2.1.4 Job List Definition P.5.1 Conversion Architect 1 8 8 WH
P.3.1 BA Lead - Banking 1 2 2 WH
P.5.5 Programmer - Host Cobol 4 2 8 WH
2.1.5 Conversion Sequencing Report P.5.1 Conversion Architect 1 8 8 WH
P.3.1 BA Lead - Banking 1 4 4 WH
P.1.4 Conversion PM 1 2 2 WH
C.2.1 Client Architect 1 4 4 WH
C.3.1 Client BA 1 2 2 WH
2.1.6 Execution Checklist Definition P.5.1 Conversion Architect 1 4 4 WH
P.3.1 BA Lead - Banking 1 2 2 WH
P.1.4 Conversion PM 1 2 2 WH
Detailed Schedule of Mapping
2.2 P.5.1 Conversion Architect 1 2 2 WH
Sessions
P.3.1 BA Lead - Banking 1 8 8 WH
P.3.2 BA - Banking 4 2 8 WH
P.1.4 Conversion PM 1 2 2 WH
2.3 Mapping Specifications N/A
2.3.1 Customer Information File Specs P.3.2 BA - Banking 1 60 60 WH
P.3.1 BA Lead - Banking 1 8 8 WH
P.1.4 Conversion PM 1 16 16 WH
P.5.1 Conversion Architect 1 6 6 WH
P.5.5 Programmer - Host Cobol 1 40 40 WH
C.3.1 Client BA 1 60 60 WH
C.1.1 Client PM 1 8 8 WH
C.2.1 Client Architect 1 16 16 WH
C.4.1 Client Programmer - Source 1 40 40 WH
C.4.2 Client Programmer - Target 1 40 40 WH
4 Person-
T.1.2 Remote Flight 4 1
Flights
12 Per-
T.2.2 Remote Resource Onsite A 4 3
Diem Days
16 Room
F.2.3 Conf Room M 1 16
Hours
24 Person
F.3.1 Deli Lunch 2 12
Lunches
2.3.2 Account File Specs P.3.2 BA - Banking 1 60 60 WH
P.3.1 BA Lead - Banking 1 8 8 WH
P.1.4 Conversion PM 1 16 16 WH
P.5.1 Conversion Architect 1 6 6 WH
P.5.5 Programmer - Host Cobol 1 40 40 WH
C.3.1 Client BA 1 60 60 WH
C.1.1 Client PM 1 8 8 WH
C.2.1 Client Architect 1 16 16 WH
C.4.1 Client Programmer - Source 1 40 40 WH
C.4.2 Client Programmer - Target 1 40 40 WH
4 Person-
T.1.2 Remote Flight 4 1
Flights
12 Per-
T.2.2 Remote Resource Onsite A 4 3
Diem Days
16 Room
F.2.3 Conf Room M 1 16
Hours
24 Person
F.3.1 Deli Lunch 2 12
Lunches
2.3.3 Account History File Specs P.3.2 BA - Banking 1 60 60 WH
P.3.1 BA Lead - Banking 1 8 8 WH
P.1.4 Conversion PM 1 16 16 WH
P.5.1 Conversion Architect 1 6 6 WH
P.5.5 Programmer - Host Cobol 1 40 40 WH
C.3.1 Client BA 1 60 60 WH
C.1.1 Client PM 1 8 8 WH
C.2.1 Client Architect 1 16 16 WH
C.4.1 Client Programmer - Source 1 40 40 WH
C.4.2 Client Programmer - Target 1 40 40 WH
4 Person-
T.1.2 Remote Flight 4 1
Flights
12 Per-
T.2.2 Remote Resource Onsite A 4 3
Diem Days
16 Room
F.2.3 Conf Room M 1 16
Hours
24 Person
F.3.1 Deli Lunch 2 12
Lunches
Pre-Authorized Transaction File
2.3.4 P.3.2 BA - Banking 1 40 40 WH
Specs
P.3.1 BA Lead - Banking 1 6 6 WH
P.1.4 Conversion PM 1 12 12 WH
P.5.1 Conversion Architect 1 4 4 WH
P.5.5 Programmer - Host Cobol 1 30 30 WH
C.3.1 Client BA 1 40 40 WH
C.1.1 Client PM 1 6 6 WH
C.2.1 Client Architect 1 12 12 WH
C.4.1 Client Programmer - Source 1 30 30 WH
C.4.2 Client Programmer - Target 1 30 30 WH
4 Person-
T.1.2 Remote Flight 4 1
Flights
12 Per-
T.2.2 Remote Resource Onsite A 4 3
Diem Days
16 Room
F.2.3 Conf Room M 1 16
Hours
24 Person
F.3.1 Deli Lunch 2 12
Lunches
2.3.5 Used/Unused Source Field Report P.3.2 BA - Banking 4 8 32 WH
P.3.1 BA Lead - Banking 1 8 8 WH
P.1.4 Conversion PM 1 8 8 WH
P.5.1 Conversion Architect 1 16 16 WH
P.5.5 Programmer - Host Cobol 4 2 8 WH
C.3.1 Client BA 1 24 24 WH
C.1.1 Client PM 1 4 4 WH
C.2.1 Client Architect 1 8 8 WH
C.4.1 Client Programmer - Source 1 8 8 WH
C.4.2 Client Programmer - Target 1 8 8 WH
2.4 Balancing Design Document N/A
Customer Information File
2.4.1 P.3.2 BA - Banking 1 16 16 WH
Balancing Design
P.3.1 BA Lead - Banking 1 4 4 WH
P.5.1 Conversion Architect 1 4 4 WH
P.5.5 Programmer - Host Cobol 1 4 4 WH
C.3.1 Client BA 1 8 8 WH
C.2.1 Client Architect 1 4 4 WH
C.4.1 Client Programmer - Source 1 4 4 WH
C.4.2 Client Programmer - Target 1 4 4 WH
2.4.2 Account File Balancing Design P.3.2 BA - Banking 1 16 16 WH
P.3.1 BA Lead - Banking 1 4 4 WH
P.5.1 Conversion Architect 1 4 4 WH
P.5.5 Programmer - Host Cobol 1 4 4 WH
C.3.1 Client BA 1 8 8 WH
C.2.1 Client Architect 1 4 4 WH
C.4.1 Client Programmer - Source 1 4 4 WH
C.4.2 Client Programmer - Target 1 4 4 WH
Account History File Balancing
2.4.3 P.3.2 BA - Banking 1 16 16 WH
Design
P.3.1 BA Lead - Banking 1 4 4 WH
P.5.1 Conversion Architect 1 4 4 WH
P.5.5 Programmer - Host Cobol 1 4 4 WH
C.3.1 Client BA 1 8 8 WH
C.2.1 Client Architect 1 4 4 WH
C.4.1 Client Programmer - Source 1 4 4 WH
C.4.2 Client Programmer - Target 1 4 4 WH
Pre-Authorized Transaction File
2.4.4 P.3.2 BA - Banking 1 8 8 WH
Balancing Design
P.3.1 BA Lead - Banking 1 2 2 WH
P.5.1 Conversion Architect 1 2 2 WH
P.5.5 Programmer - Host Cobol 1 2 2 WH
C.3.1 Client BA 1 4 4 WH
C.2.1 Client Architect 1 2 2 WH
C.4.1 Client Programmer - Source 1 2 2 WH
C.4.2 Client Programmer - Target 1 2 2 WH
3.0 Software and Execution Forms N/A
3.1 Data Conversion Applications N/A
Customer Information File
3.1.1 P.3.2 BA - Banking 1 24 24 WH
Application
P.3.1 BA Lead - Banking 1 4 4 WH
P.5.5 Programmer - Host Cobol 1 32 32 WH
C.3.1 Client BA 1 8 8 WH
C.4.1 Client Programmer - Source 1 2 2 WH
3.1.2 Account File Application P.3.2 BA - Banking 1 24 24 WH
P.3.1 BA Lead - Banking 1 4 4 WH
P.5.5 Programmer - Host Cobol 1 32 32 WH
C.3.1 Client BA 1 8 8 WH
C.4.1 Client Programmer - Source 1 2 2 WH
3.1.3 Account History File Application P.3.2 BA - Banking 1 24 24 WH
P.3.1 BA Lead - Banking 1 4 4 WH
P.5.5 Programmer - Host Cobol 1 32 32 WH
C.3.1 Client BA 1 8 8 WH
C.4.1 Client Programmer - Source 1 2 2 WH
Pre-Authorized Transaction File
3.1.4 P.3.2 BA - Banking 1 12 12 WH
Application
P.3.1 BA Lead - Banking 1 2 2 WH
P.5.5 Programmer - Host Cobol 1 16 16 WH
C.3.1 Client BA 1 4 4 WH
C.4.1 Client Programmer - Source 1 2 2 WH
3.2 Prove Reports N/A
Customer Information File
3.2.1 P.3.2 BA - Banking 1 12 12 WH
Application
P.5.5 Programmer - Host Cobol 1 8 8 WH
C.3.1 Client BA 1 4 4 WH
3.2.2 Account File Application P.3.2 BA - Banking 1 12 12 WH
P.5.5 Programmer - Host Cobol 1 8 8 WH
C.3.1 Client BA 1 4 4 WH
3.2.3 Account History File Application P.3.2 BA - Banking 1 12 12 WH
P.5.5 Programmer - Host Cobol 1 8 8 WH
C.3.1 Client BA 1 4 4 WH
Pre-Authorized Transaction File
3.2.4 P.3.2 BA - Banking 1 8 8 WH
Application
P.5.5 Programmer - Host Cobol 1 6 6 WH
C.3.1 Client BA 1 2 2 WH
3.3 Exception Reports N/A
Customer Information File
3.3.1 P.3.2 BA - Banking 1 2 2 WH
Application
P.5.5 Programmer - Host Cobol 1 10 10 WH
C.3.1 Client BA 1 2 2 WH
3.3.2 Account File Application P.3.2 BA - Banking 1 2 2 WH
P.5.5 Programmer - Host Cobol 1 10 10 WH
C.3.1 Client BA 1 2 2 WH
3.3.3 Account History File Application P.3.2 BA - Banking 1 2 2 WH
P.5.5 Programmer - Host Cobol 1 10 10 WH
C.3.1 Client BA 1 2 2 WH
Pre-Authorized Transaction File
3.3.4 P.3.2 BA - Banking 1 2 2 WH
Application
P.5.5 Programmer - Host Cobol 1 6 6 WH
C.3.1 Client BA 1 2 2 WH
3.4 Audit Reports N/A
Customer Information File
3.4.1 P.3.2 BA - Banking 1 2 2 WH
Application
P.5.5 Programmer - Host Cobol 1 8 8 WH
C.3.1 Client BA 1 2 2 WH
3.4.2 Account File Application P.3.2 BA - Banking 1 2 2 WH
P.5.5 Programmer - Host Cobol 1 8 8 WH
C.3.1 Client BA 1 2 2 WH
3.4.3 Account History File Application P.3.2 BA - Banking 1 2 2 WH
P.5.5 Programmer - Host Cobol 1 8 8 WH
C.3.1 Client BA 1 2 2 WH
Pre-Authorized Transaction File
3.4.4 P.3.2 BA - Banking 1 2 2 WH
Application
P.5.5 Programmer - Host Cobol 1 8 8 WH
C.3.1 Client BA 1 2 2 WH
3.5 Conversion Supporting Forms N/A
3.5.1 Balancing Spreadsheet P.3.2 BA - Banking 4 8 32 WH
P.3.1 BA Lead - Banking 1 8 8 WH
P.5.1 Conversion Architect 1 8 8 WH
C.3.1 Client BA 1 2 2 WH
C.2.1 Client Architect 1 2 2 WH
3.5.2 Conversion Activity Checklist P.1.4 Conversion PM 1 8 8 WH
P.3.1 BA Lead - Banking 1 8 8 WH
P.5.1 Conversion Architect 1 8 8 WH
Conversion Extracts (Note: each
extract consists of code library,
checklist, converted files,
4.0 N/A
balancing sheets, load data
analysis report, exception report,
audit trail file)
4.1 System Test Extract C.4.1 Client Programmer - Source 1 4 4 WH
P.1.4 Conversion PM 1 16 16 WH
P.5.5 Programmer - Host Cobol 4 12 48 WH
P.3.2 BA - Banking 4 12 48 WH
D.1.1 Local Media Delivery 1 1 1 Delivery
4.2 Dry Run Test Extract C.4.1 Client Programmer - Source 1 4 4 WH
P.1.4 Conversion PM 1 16 16 WH
P.5.5 Programmer - Host Cobol 4 12 48 WH
P.3.2 BA - Banking 4 12 48 WH
D.1.1 Local Media Delivery 1 1 1 Delivery
4.3 Conversion Extract C.4.1 Client Programmer - Source 1 4 4 WH
P.1.4 Conversion PM 1 16 16 WH
P.5.5 Programmer - Host Cobol 4 12 48 WH
P.3.2 BA - Banking 4 12 48 WH
D.1.1 Local Media Delivery 1 1 1 Delivery
Project Completion Analysis
5.0 N/A
Report
5.1 Plan vs. Actuals Report P.1.4 Conversion PM 1 16 16 WH
P.5.1 Conversion Architect 1 8 8 WH
5.2 Lessons Learned P.1.2 Principal 1 4 4 WH
P.1.4 Conversion PM 1 8 8 WH
P.5.1 Conversion Architect 1 8 8 WH
P.3.1 BA Lead - Banking 1 4 4 WH
C.1.1 Client PM 1 4 4 WH
C.3.1 Client BA 1 4 4 WH
C.2.1 Client Architect 1 4 4 WH
Appendix A. Work Breakdown Structure
This WBS has been modified from the original version. Notes regarding this WBS include:
1. This WBS is complete to accomplish the project objectives.
2. The project execution environment (e.g., network infrastructure to support remote work,
host system, specialty software, etc.), testing, loader program, etc. are the responsibility of
the client. Therefore, these are considered external to the project and are not included in
this WBS, even though these resources are crucial to the creation of these elements.
3. Project standards have been established in advance of, and without cost to, this project.
4. Not all of these elements will require three resources but are included here to fully define
the project objectives and/or to clarify the parent element.
5. There are many more than the 35 required Level-3 elements that will use at least 3
resources.
This RBS has been modified from the original submission. Notes regarding this RBS include:
1. All cost rates for internal and contracted resources (negotiated through Purchasing) are
valid for and guaranteed through the calendar year of 2003, and are valid world-
wide.
2. Resources are XYZ internal, unless described as “contracted.”
3. All internal and contracted rates are fully burdened (i.e., include all overhead costs).
4. As XYZ is so large, for all practical purposes, there is no limit to the availability of any
of these skills.
5. Skill levels reflect, within a given discipline, the relative skill level of the individual in
that discipline. These levels are defined in internal XYZ documentation and are
commonly understood by XYZ resources and XYZ clients.
6. This RBS is probably still not what is expected per the course, but I have not yet
received answers to my questions from the RBS assignment (“A”), so I could not
fix/improve in those areas.
7. Client personnel are generally listed for planning purposes, but at zero cost, as these are
contracted as the responsibility of the client.
8. Even though tape media is used for the transport of data, this media is already client-
owned.
The following are the totals (cost and resource), as originally submitted in Assignment “D” and
slightly modified in subsequent assignments. Notes regarding these totals:
1. To keep this table less cluttered, the unit and extended costs for each resource at the
lowest levels of the WBS are shown in the WBS found in the Appendix (“Elemental
Estimates”).
2. The roll-up of cost at Level 1 also has been shown with that cost as a percentage of the
total project. This will be discussed further following the table. Note that this shows a
total of 101%, but this is due to rounding error. However, for purposes of determining
uniformity across the Level-1 elements, this rounding error is insignificant.
3. Costs are shown in whole dollars, which is consistent with all unit costs anyway.
As seen in the above table, the distribution of the Level-1 work packages is:
(27%) Needs Analysis
(36%) Design Documentation
(24%) Software & Execution Forms
(12%) Conversion Extracts
(2%) Project Completion Analysis Report
This represents a project heavily invested in pre-implementation in the Needs Analysis and
Design work packages. Keeping in mind that a conversion project has a one-shot execution (the
actual conversion weekend when the old application is removed and the new one enabled), there
is little room for error – the requirements and design must be perfect (hence the more significant
relative investment in the first two packages).
While it is common in many traditional software development projects for a higher relative
investment in the implementation and unit testing (Package 3, “Software & Execution Forms”),
the conversion methodology employed by this practice uses software tools that reduce the
development effort and validation, given thorough requirements and design (hence the more
significant investment in the first two packages). By the time that actual extracts (Package 4,
“Conversion Extracts”) are required, the process is well defined and “rote” – it only hits as high
as 12% because of the number of extract sets that must be created. The final work package
(Package 5, “Project Completion Analysis Report”) is a small wrap-up, so it only amounts to 2%.
I checked this distribution against that of similarly-scoped projects we have completed in the past
18 months, and it is within the percentage point ranges (about a 4-point range for each of these
major areas, when adjusting to the parameters of this course criteria and ignoring impact of
changes resulting from subsequent change control) of our actual experience.
In addition, the total project cost, just short of $500K, is within 10 percent of our completed
projects of similar scope (four major files to convert), when adjusted consistently with the course
requirements.
Cost by Resource Totals
The following table represents the total project effort and cost by resource. Also shown is the
cost of each resource as a percentage of total project cost. This shows that the heaviest charged
role is that of the Business Analysts, with Cobol Programmer in next place. This is also fairly
consistent with similar projects we have completed and explained by the established
methodology and the reusable components used in these projects.
The following are the elemental estimates, as originally submitted in Assignment “C” and
slightly modified in subsequent assignments. Assignment “D” also introduced the unit cost and
extended cost columns.
Total Effort
WBS Unit Extended
WBS Element Name Resource
Num Cost Cost
Qty Units
Core Banking Data
0
Conversion
Needs Analysis
1.0
Documentation
Source System Analysis
1.1
Report
Source Application & P.5.1 Conversion
1.1.1 1 40 40 P.5.1 Architect Hours $185 $7,400
Interfaces Report Architect
P.3.1 BA Lead -
1 10 10 P.3.1 BA Lead Hours $185 $1,850
Banking
C.2.1 Client Architect
C.2.1 Client Architect 1 10 10 $0 $0
Hours
C.3.1 Client BA 1 10 10 C.3.1 Client BA Hours $0 $0
P.5.1 Conversion
1.1.2 Source Data Dictionary 1 20 20 P.5.1 Architect Hours $185 $3,700
Architect
P.3.1 BA Lead -
1 40 40 P.3.1 BA Lead Hours $185 $7,400
Banking
P.3.2 BA - Banking 4 40 160 P.3.2 BA Hours $165 $26,400
C.3.1 Client BA 1 40 40 C.3.1 Client BA Hours $0 $0
Source Data Analysis
1.2
Report
P.3.1 BA Lead -
1.2.1 Source Product Report 1 12 12 P.3.1 BA Lead Hours $185 $2,220
Banking
P.5.5 Programmer - Host P.5.5 Programmer
1 16 16 $165 $2,640
Cobol Hours
C.3.1 Client BA 1 8 8 C.3.1 Client BA Hours $0 $0
Customer Information P.5.1 Conversion
1.2.2 1 4 4 P.5.1 Architect Hours $185 $740
File Analysis Report Architect
P.3.1 BA Lead -
1 2 2 P.3.1 BA Lead Hours $185 $370
Banking
P.3.2 BA - Banking 1 16 16 P.3.2 BA Hours $165 $2,640
P.5.5 Programmer - Host P.5.5 Programmer
1 24 24 $165 $3,960
Cobol Hours
C.3.1 Client BA 1 10 10 C.3.1 Client BA Hours $0 $0
Name & Address
P.5.1 Conversion
1.2.3 Scrubbing Analysis 1 2 2 P.5.1 Architect Hours $185 $370
Architect
Report
P.3.1 BA Lead -
1 8 8 P.3.1 BA Lead Hours $185 $1,480
Banking
P.5.5 Programmer - Host P.5.5 Programmer
1 16 16 $165 $2,640
Cobol Hours
C.3.1 Client BA 1 4 4 C.3.1 Client BA Hours $0 $0
Account File Analysis P.5.1 Conversion
1.2.4 1 4 4 P.5.1 Architect Hours $185 $740
Report Architect
P.3.1 BA Lead -
1 2 2 P.3.1 BA Lead Hours $185 $370
Banking
P.3.2 BA - Banking 1 16 16 P.3.2 BA Hours $165 $2,640
P.5.5 Programmer - Host P.5.5 Programmer
1 24 24 $165 $3,960
Cobol Hours
C.3.1 Client BA 1 10 10 C.3.1 Client BA Hours $0 $0
Account History File P.5.1 Conversion
1.2.5 1 4 4 P.5.1 Architect Hours $185 $740
Analysis Report Architect
P.3.1 BA Lead -
1 2 2 P.3.1 BA Lead Hours $185 $370
Banking
P.3.2 BA - Banking 1 16 16 P.3.2 BA Hours $165 $2,640
P.5.5 Programmer - Host P.5.5 Programmer
1 24 24 $165 $3,960
Cobol Hours
C.3.1 Client BA 1 10 10 C.3.1 Client BA Hours $0 $0
Pre-Authorized
P.5.1 Conversion
1.2.6 Transaction File Analysis 1 2 2 P.5.1 Architect Hours $185 $370
Architect
Report
P.3.1 BA Lead -
1 2 2 P.3.1 BA Lead Hours $185 $370
Banking
P.3.2 BA - Banking 1 8 8 P.3.2 BA Hours $165 $1,320
P.5.5 Programmer - Host P.5.5 Programmer
1 16 16 $165 $2,640
Cobol Hours
C.3.1 Client BA 1 5 5 C.3.1 Client BA Hours $0 $0
Target System Analysis
1.3
Report
Target Application & P.5.1 Conversion
1.3.1 1 40 40 P.5.1 Architect Hours $185 $7,400
Interfaces Report Architect
P.3.1 BA Lead - 1 10 10 P.3.1 BA Lead Hours $185 $1,850
Banking
P.3.2 BA - Banking 4 2 8 P.3.2 BA Hours $165 $1,320
C.2.1 Client Architect
C.2.1 Client Architect 1 10 10 $0 $0
Hours
C.3.1 Client BA 1 10 10 C.3.1 Client BA Hours $0 $0
P.5.1 Conversion
1.3.2 Target Data Dictionary 1 20 20 P.5.1 Architect Hours $185 $3,700
Architect
P.3.1 BA Lead -
1 40 40 P.3.1 BA Lead Hours $185 $7,400
Banking
P.3.2 BA - Banking 4 40 160 P.3.2 BA Hours $165 $26,400
C.3.1 Client BA 1 40 40 C.3.1 Client BA Hours $0 $0
2.0 Design Documentation
Overall Solution
2.1
Architecture Document
Conversion Dependency
P.5.1 Conversion
2.1.1 (Intra-Appl & External) 1 20 20 P.5.1 Architect Hours $185 $3,700
Architect
Report
P.3.1 BA Lead -
1 8 8 P.3.1 BA Lead Hours $185 $1,480
Banking
P.3.2 BA - Banking 4 4 16 P.3.2 BA Hours $165 $2,640
C.2.1 Client Architect
C.2.1 Client Architect 1 4 4 $0 $0
Hours
C.3.1 Client BA 1 4 4 C.3.1 Client BA Hours $0 $0
Target Record Layout P.5.1 Conversion
2.1.2 1 4 4 P.5.1 Architect Hours $185 $740
Definition Architect
P.3.1 BA Lead -
1 4 4 P.3.1 BA Lead Hours $185 $740
Banking
P.3.2 BA - Banking 4 4 16 P.3.2 BA Hours $165 $2,640
P.5.5 Programmer - Host P.5.5 Programmer
4 16 64 $165 $10,560
Cobol Hours
C.2.1 Client Architect
C.2.1 Client Architect 1 2 2 $0 $0
Hours
C.3.1 Client BA 1 2 2 C.3.1 Client BA Hours $0 $0
Exception Condition P.5.1 Conversion
2.1.3 1 8 8 P.5.1 Architect Hours $185 $1,480
Definition Architect
P.3.1 BA Lead -
1 4 4 P.3.1 BA Lead Hours $185 $740
Banking
P.3.2 BA - Banking 4 8 32 P.3.2 BA Hours $165 $5,280
C.2.1 Client Architect
C.2.1 Client Architect 1 4 4 $0 $0
Hours
C.3.1 Client BA 1 4 4 C.3.1 Client BA Hours $0 $0
P.5.1 Conversion
2.1.4 Job List Definition 1 8 8 P.5.1 Architect Hours $185 $1,480
Architect
P.3.1 BA Lead -
1 2 2 P.3.1 BA Lead Hours $185 $370
Banking
P.5.5 Programmer - Host P.5.5 Programmer
4 2 8 $165 $1,320
Cobol Hours
Conversion Sequencing P.5.1 Conversion
2.1.5 1 8 8 P.5.1 Architect Hours $185 $1,480
Report Architect
P.3.1 BA Lead -
1 4 4 P.3.1 BA Lead Hours $185 $740
Banking
P.1.4 Conversion PM 1 2 2 P.1.4 PM Hours $185 $370
C.2.1 Client Architect 1 4 4 C.2.1 Client Architect $0 $0
Hours
C.3.1 Client BA 1 2 2 C.3.1 Client BA Hours $0 $0
Detailed Schedule of P.5.1 Conversion
2.2 1 2 2 P.5.1 Architect Hours $185 $370
Mapping Sessions Architect
P.3.1 BA Lead -
1 8 8 P.3.1 BA Lead Hours $185 $1,480
Banking
P.3.2 BA - Banking 4 2 8 P.3.2 BA Hours $165 $1,320
P.1.4 Conversion PM 1 2 2 P.1.4 PM Hours $185 $370
2.3 Mapping Specifications
Customer Information
2.3.1 P.3.2 BA - Banking 1 60 60 P.3.2 BA Hours $165 $9,900
File Specs
P.3.1 BA Lead -
1 8 8 P.3.1 BA Lead Hours $185 $1,480
Banking
P.1.4 Conversion PM 1 16 16 P.1.4 PM Hours $185 $2,960
P.5.1 Conversion
1 6 6 P.5.1 Architect Hours $185 $1,110
Architect
P.5.5 Programmer - Host P.5.5 Programmer
1 40 40 $165 $6,600
Cobol Hours
C.3.1 Client BA 1 60 60 C.3.1 Client BA Hours $0 $0
C.1.1 Client PM 1 8 8 C.1.1 Client PM Hours $0 $0
C.2.1 Client Architect
C.2.1 Client Architect 1 16 16 $0 $0
Hours
C.4.1 Client C.4.1 Client
1 40 40 $0 $0
Programmer - Source Programmer Hours
C.4.2 Client C.4.2 Client
1 40 40 $0 $0
Programmer - Target Programmer Hours
T.1.2 Remote Flight 4 1 4 T.1.2 Person Flights $900 $3,600
T.2.2 Remote Resource
4 3 12 T.2.2 Per-Diem Days $100 $1,200
Onsite A
F.2.3 Conf Room M 1 16 16 F.2.3 Room Hours $100 $1,600
F.3.1 Deli Lunch 2 12 24 F.3.1 Person Lunches $8 $192
2.3.2 Account File Specs P.3.2 BA - Banking 1 60 60 P.3.2 BA Hours $165 $9,900
P.3.1 BA Lead -
1 8 8 P.3.1 BA Lead Hours $185 $1,480
Banking
P.1.4 Conversion PM 1 16 16 P.1.4 PM Hours $185 $2,960
P.5.1 Conversion
1 6 6 P.5.1 Architect Hours $185 $1,110
Architect
P.5.5 Programmer - Host P.5.5 Programmer
1 40 40 $165 $6,600
Cobol Hours
C.3.1 Client BA 1 60 60 C.3.1 Client BA Hours $0 $0
C.1.1 Client PM 1 8 8 C.1.1 Client PM Hours $0 $0
C.2.1 Client Architect
C.2.1 Client Architect 1 16 16 $0 $0
Hours
C.4.1 Client C.4.1 Client
1 40 40 $0 $0
Programmer - Source Programmer Hours
C.4.2 Client C.4.2 Client
1 40 40 $0 $0
Programmer - Target Programmer Hours
T.1.2 Remote Flight 4 1 4 T.1.2 Person Flights $900 $3,600
T.2.2 Remote Resource
4 3 12 T.2.2 Per-Diem Days $100 $1,200
Onsite A
F.2.3 Conf Room M 1 16 16 F.2.3 Room Hours $100 $1,600
F.3.1 Deli Lunch 2 12 24 F.3.1 Person Lunches $8 $192
Account History File
2.3.3 P.3.2 BA - Banking 1 60 60 P.3.2 BA Hours $165 $9,900
Specs
P.3.1 BA Lead -
1 8 8 P.3.1 BA Lead Hours $185 $1,480
Banking
P.1.4 Conversion PM 1 16 16 P.1.4 PM Hours $185 $2,960
P.5.1 Conversion
1 6 6 P.5.1 Architect Hours $185 $1,110
Architect
P.5.5 Programmer - Host P.5.5 Programmer
1 40 40 $165 $6,600
Cobol Hours
C.3.1 Client BA 1 60 60 C.3.1 Client BA Hours $0 $0
C.1.1 Client PM 1 8 8 C.1.1 Client PM Hours $0 $0
C.2.1 Client Architect
C.2.1 Client Architect 1 16 16 $0 $0
Hours
C.4.1 Client C.4.1 Client
1 40 40 $0 $0
Programmer - Source Programmer Hours
C.4.2 Client C.4.2 Client
1 40 40 $0 $0
Programmer - Target Programmer Hours
T.1.2 Remote Flight 4 1 4 T.1.2 Person Flights $900 $3,600
T.2.2 Remote Resource
4 3 12 T.2.2 Per-Diem Days $100 $1,200
Onsite A
F.2.3 Conf Room M 1 16 16 F.2.3 Room Hours $100 $1,600
F.3.1 Deli Lunch 2 12 24 F.3.1 Person Lunches $8 $192
Pre-Authorized
2.3.4 P.3.2 BA - Banking 1 40 40 P.3.2 BA Hours $165 $6,600
Transaction File Specs
P.3.1 BA Lead -
1 6 6 P.3.1 BA Lead Hours $185 $1,110
Banking
P.1.4 Conversion PM 1 12 12 P.1.4 PM Hours $185 $2,220
P.5.1 Conversion
1 4 4 P.5.1 Architect Hours $185 $740
Architect
P.5.5 Programmer - Host P.5.5 Programmer
1 30 30 $165 $4,950
Cobol Hours
C.3.1 Client BA 1 40 40 C.3.1 Client BA Hours $0 $0
C.1.1 Client PM 1 6 6 C.1.1 Client PM Hours $0 $0
C.2.1 Client Architect
C.2.1 Client Architect 1 12 12 $0 $0
Hours
C.4.1 Client C.4.1 Client
1 30 30 $0 $0
Programmer - Source Programmer Hours
C.4.2 Client C.4.2 Client
1 30 30 $0 $0
Programmer - Target Programmer Hours
T.1.2 Remote Flight 4 1 4 T.1.2 Person Flights $900 $3,600
T.2.2 Remote Resource
4 3 12 T.2.2 Per-Diem Days $100 $1,200
Onsite A
F.2.3 Conf Room M 1 16 16 F.2.3 Room Hours $100 $1,600
F.3.1 Deli Lunch 2 12 24 F.3.1 Person Lunches $8 $192
Used/Unused Source
2.3.5 P.3.2 BA - Banking 4 8 32 P.3.2 BA Hours $165 $5,280
Field Report
P.3.1 BA Lead -
1 8 8 P.3.1 BA Lead Hours $185 $1,480
Banking
P.1.4 Conversion PM 1 8 8 P.1.4 PM Hours $185 $1,480
P.5.1 Conversion
1 16 16 P.5.1 Architect Hours $185 $2,960
Architect
P.5.5 Programmer - Host P.5.5 Programmer
4 2 8 $165 $1,320
Cobol Hours
C.3.1 Client BA 1 24 24 C.3.1 Client BA Hours $0 $0
C.1.1 Client PM 1 4 4 C.1.1 Client PM Hours $0 $0
C.2.1 Client Architect
C.2.1 Client Architect 1 8 8 $0 $0
Hours
C.4.1 Client C.4.1 Client
1 8 8 $0 $0
Programmer - Source Programmer Hours
C.4.2 Client C.4.2 Client
1 8 8 $0 $0
Programmer - Target Programmer Hours
Balancing Design
2.4
Document
Customer Information
2.4.1 P.3.2 BA - Banking 1 16 16 P.3.2 BA Hours $165 $2,640
File Balancing Design
P.3.1 BA Lead -
1 4 4 P.3.1 BA Lead Hours $185 $740
Banking
P.5.1 Conversion
1 4 4 P.5.1 Architect Hours $185 $740
Architect
P.5.5 Programmer - Host P.5.5 Programmer
1 4 4 $165 $660
Cobol Hours
C.3.1 Client BA 1 8 8 C.3.1 Client BA Hours $0 $0
C.2.1 Client Architect
C.2.1 Client Architect 1 4 4 $0 $0
Hours
C.4.1 Client C.4.1 Client
1 4 4 $0 $0
Programmer - Source Programmer Hours
C.4.2 Client C.4.2 Client
1 4 4 $0 $0
Programmer - Target Programmer Hours
Account File Balancing
2.4.2 P.3.2 BA - Banking 1 16 16 P.3.2 BA Hours $165 $2,640
Design
P.3.1 BA Lead -
1 4 4 P.3.1 BA Lead Hours $185 $740
Banking
P.5.1 Conversion
1 4 4 P.5.1 Architect Hours $185 $740
Architect
P.5.5 Programmer - Host P.5.5 Programmer
1 4 4 $165 $660
Cobol Hours
C.3.1 Client BA 1 8 8 C.3.1 Client BA Hours $0 $0
C.2.1 Client Architect
C.2.1 Client Architect 1 4 4 $0 $0
Hours
C.4.1 Client C.4.1 Client
1 4 4 $0 $0
Programmer - Source Programmer Hours
C.4.2 Client C.4.2 Client
1 4 4 $0 $0
Programmer - Target Programmer Hours
Account History File
2.4.3 P.3.2 BA - Banking 1 16 16 P.3.2 BA Hours $165 $2,640
Balancing Design
P.3.1 BA Lead -
1 4 4 P.3.1 BA Lead Hours $185 $740
Banking
P.5.1 Conversion
1 4 4 P.5.1 Architect Hours $185 $740
Architect
P.5.5 Programmer - Host P.5.5 Programmer
1 4 4 $165 $660
Cobol Hours
C.3.1 Client BA 1 8 8 C.3.1 Client BA Hours $0 $0
C.2.1 Client Architect
C.2.1 Client Architect 1 4 4 $0 $0
Hours
C.4.1 Client C.4.1 Client
1 4 4 $0 $0
Programmer - Source Programmer Hours
C.4.2 Client C.4.2 Client
1 4 4 $0 $0
Programmer - Target Programmer Hours
Pre-Authorized
2.4.4 Transaction File P.3.2 BA - Banking 1 8 8 P.3.2 BA Hours $165 $1,320
Balancing Design
P.3.1 BA Lead -
1 2 2 P.3.1 BA Lead Hours $185 $370
Banking
P.5.1 Conversion
1 2 2 P.5.1 Architect Hours $185 $370
Architect
P.5.5 Programmer - Host P.5.5 Programmer
1 2 2 $165 $330
Cobol Hours
C.3.1 Client BA 1 4 4 C.3.1 Client BA Hours $0 $0
C.2.1 Client Architect
C.2.1 Client Architect 1 2 2 $0 $0
Hours
C.4.1 Client C.4.1 Client
1 2 2 $0 $0
Programmer - Source Programmer Hours
C.4.2 Client C.4.2 Client
1 2 2 $0 $0
Programmer - Target Programmer Hours
Software and Execution
3.0
Forms
Data Conversion
3.1
Applications
Customer Information
3.1.1 P.3.2 BA - Banking 1 40 40 P.3.2 BA Hours $165 $6,600
File Application
P.3.1 BA Lead -
1 6 6 P.3.1 BA Lead Hours $185 $1,110
Banking
P.5.5 Programmer - Host P.5.5 Programmer
1 60 60 $165 $9,900
Cobol Hours
C.3.1 Client BA 1 8 8 C.3.1 Client BA Hours $0 $0
C.4.1 Client C.4.1 Client
1 4 4 $0 $0
Programmer - Source Programmer Hours
3.1.2 Account File Application P.3.2 BA - Banking 1 40 40 P.3.2 BA Hours $165 $6,600
P.3.1 BA Lead -
1 6 6 P.3.1 BA Lead Hours $185 $1,110
Banking
P.5.5 Programmer - Host P.5.5 Programmer
1 60 60 $165 $9,900
Cobol Hours
C.3.1 Client BA 1 8 8 C.3.1 Client BA Hours $0 $0
C.4.1 Client C.4.1 Client
1 4 4 $0 $0
Programmer - Source Programmer Hours
Account History File
3.1.3 P.3.2 BA - Banking 1 40 40 P.3.2 BA Hours $165 $6,600
Application
P.3.1 BA Lead -
1 6 6 P.3.1 BA Lead Hours $185 $1,110
Banking
P.5.5 Programmer - Host P.5.5 Programmer
1 60 60 $165 $9,900
Cobol Hours
C.3.1 Client BA 1 8 8 C.3.1 Client BA Hours $0 $0
C.4.1 Client C.4.1 Client
1 4 4 $0 $0
Programmer - Source Programmer Hours
Pre-Authorized
3.1.4 Transaction File P.3.2 BA - Banking 1 25 25 P.3.2 BA Hours $165 $4,125
Application
P.3.1 BA Lead -
1 4 4 P.3.1 BA Lead Hours $185 $740
Banking
P.5.5 Programmer - Host 1 40 40 P.5.5 Programmer $165 $6,600
Cobol Hours
C.3.1 Client BA 1 6 6 C.3.1 Client BA Hours $0 $0
C.4.1 Client C.4.1 Client
1 3 3 $0 $0
Programmer - Source Programmer Hours
3.2 Prove Reports
Customer Information
3.2.1 P.3.2 BA - Banking 1 16 16 P.3.2 BA Hours $165 $2,640
File Application
P.5.5 Programmer - Host P.5.5 Programmer
1 10 10 $165 $1,650
Cobol Hours
C.3.1 Client BA 1 4 4 C.3.1 Client BA Hours $0 $0
3.2.2 Account File Application P.3.2 BA - Banking 1 16 16 P.3.2 BA Hours $165 $2,640
P.5.5 Programmer - Host P.5.5 Programmer
1 10 10 $165 $1,650
Cobol Hours
C.3.1 Client BA 1 4 4 C.3.1 Client BA Hours $0 $0
Account History File
3.2.3 P.3.2 BA - Banking 1 16 16 P.3.2 BA Hours $165 $2,640
Application
P.5.5 Programmer - Host P.5.5 Programmer
1 10 10 $165 $1,650
Cobol Hours
C.3.1 Client BA 1 4 4 C.3.1 Client BA Hours $0 $0
Pre-Authorized
3.2.4 Transaction File P.3.2 BA - Banking 1 12 12 P.3.2 BA Hours $165 $1,980
Application
P.5.5 Programmer - Host P.5.5 Programmer
1 8 8 $165 $1,320
Cobol Hours
C.3.1 Client BA 1 2 2 C.3.1 Client BA Hours $0 $0
3.3 Exception Reports
Customer Information
3.3.1 P.3.2 BA - Banking 1 4 4 P.3.2 BA Hours $165 $660
File Application
P.5.5 Programmer - Host P.5.5 Programmer
1 12 12 $165 $1,980
Cobol Hours
C.3.1 Client BA 1 2 2 C.3.1 Client BA Hours $0 $0
3.3.2 Account File Application P.3.2 BA - Banking 1 4 4 P.3.2 BA Hours $165 $660
P.5.5 Programmer - Host P.5.5 Programmer
1 12 12 $165 $1,980
Cobol Hours
C.3.1 Client BA 1 2 2 C.3.1 Client BA Hours $0 $0
Account History File
3.3.3 P.3.2 BA - Banking 1 4 4 P.3.2 BA Hours $165 $660
Application
P.5.5 Programmer - Host P.5.5 Programmer
1 12 12 $165 $1,980
Cobol Hours
C.3.1 Client BA 1 2 2 C.3.1 Client BA Hours $0 $0
Pre-Authorized
3.3.4 Transaction File P.3.2 BA - Banking 1 3 3 P.3.2 BA Hours $165 $495
Application
P.5.5 Programmer - Host P.5.5 Programmer
1 8 8 $165 $1,320
Cobol Hours
C.3.1 Client BA 1 2 2 C.3.1 Client BA Hours $0 $0
3.4 Audit Reports
Customer Information
3.4.1 P.3.2 BA - Banking 1 4 4 P.3.2 BA Hours $165 $660
File Application
P.5.5 Programmer - Host P.5.5 Programmer
1 12 12 $165 $1,980
Cobol Hours
C.3.1 Client BA 1 2 2 C.3.1 Client BA Hours $0 $0
3.4.2 Account File Application P.3.2 BA - Banking 1 4 4 P.3.2 BA Hours $165 $660
P.5.5 Programmer - Host P.5.5 Programmer
1 12 12 $165 $1,980
Cobol Hours
C.3.1 Client BA 1 2 2 C.3.1 Client BA Hours $0 $0
Account History File
3.4.3 P.3.2 BA - Banking 1 4 4 P.3.2 BA Hours $165 $660
Application
P.5.5 Programmer - Host P.5.5 Programmer
1 12 12 $165 $1,980
Cobol Hours
C.3.1 Client BA 1 2 2 C.3.1 Client BA Hours $0 $0
Pre-Authorized
3.4.4 Transaction File P.3.2 BA - Banking 1 3 3 P.3.2 BA Hours $165 $495
Application
P.5.5 Programmer - Host P.5.5 Programmer
1 12 12 $165 $1,980
Cobol Hours
C.3.1 Client BA 1 2 2 C.3.1 Client BA Hours $0 $0
Conversion Supporting
3.5
Forms
3.5.1 Balancing Spreadsheet P.3.2 BA - Banking 4 12 48 P.3.2 BA Hours $165 $7,920
P.3.1 BA Lead -
1 12 12 P.3.1 BA Lead Hours $185 $2,220
Banking
P.5.1 Conversion
1 12 12 P.5.1 Architect Hours $185 $2,220
Architect
C.3.1 Client BA 1 2 2 C.3.1 Client BA Hours $0 $0
C.2.1 Client Architect
C.2.1 Client Architect 1 2 2 $0 $0
Hours
Conversion Activity
3.5.2 P.1.4 Conversion PM 1 10 10 P.1.4 PM Hours $185 $1,850
Checklist
P.3.1 BA Lead -
1 10 10 P.3.1 BA Lead Hours $185 $1,850
Banking
P.5.1 Conversion
1 12 12 P.5.1 Architect Hours $185 $2,220
Architect
Conversion Extracts
(Note: each extract
consists of code library,
checklist, converted files,
4.0
balancing sheets, load
data analysis report,
exception report, audit
trail file)
C.4.1 Client C.4.1 Client
4.1 System Test Extract 1 4 4 $0 $0
Programmer - Source Programmer Hours
P.1.4 Conversion PM 1 16 16 P.1.4 PM Hours $185 $2,960
P.5.5 Programmer - Host P.5.5 Programmer
4 12 48 $165 $7,920
Cobol Hours
P.3.2 BA - Banking 4 12 48 P.3.2 BA Hours $165 $7,920
D.1.1 Local Media D.1.1 Media
1 1 1 $200 $200
Delivery Deliveries
C.4.1 Client C.4.1 Client
4.2 Dry Run Test Extract 1 4 4 $0 $0
Programmer - Source Programmer Hours
P.1.4 Conversion PM 1 16 16 P.1.4 PM Hours $185 $2,960
P.5.5 Programmer - Host P.5.5 Programmer
4 12 48 $165 $7,920
Cobol Hours
P.3.2 BA - Banking 4 12 48 P.3.2 BA Hours $165 $7,920
D.1.1 Local Media D.1.1 Media
1 1 1 $200 $200
Delivery Deliveries
C.4.1 Client C.4.1 Client
4.3 Conversion Extract 1 4 4 $0 $0
Programmer - Source Programmer Hours
P.1.4 Conversion PM 1 16 16 P.1.4 PM Hours $185 $2,960
P.5.5 Programmer - Host P.5.5 Programmer
4 12 48 $165 $7,920
Cobol Hours
P.3.2 BA - Banking 4 12 48 P.3.2 BA Hours $165 $7,920
D.1.1 Local Media D.1.1 Media
1 1 1 $200 $200
Delivery Deliveries
Project Completion
5.0
Analysis Report
5.1 Plan vs. Actuals ReportP.1.4 Conversion PM 1 16 16 P.1.4 PM Hours $185 $2,960
P.5.1 Conversion
1 8 8 P.5.1 Architect Hours $185 $1,480
Architect
5.2 Lessons Learned Report P.1.2 Principal 1 4 4 P.1.2 Principal Hours $230 $920
P.1.4 Conversion PM 1 8 8 P.1.4 PM Hours $185 $1,480
P.5.1 Conversion
1 8 8 P.5.1 Architect Hours $185 $1,480
Architect
P.3.1 BA Lead -
1 4 4 P.3.1 BA Lead Hours $185 $740
Banking
C.1.1 Client PM 1 4 4 C.1.1 Client PM Hours $0 $0
C.3.1 Client BA 1 4 4 C.3.1 Client BA Hours $0 $0
C.2.1 Client Architect
C.2.1 Client Architect 1 4 4 $0 $0
Hours
the two-day periods. As this is a supporting resource out of our control
and with no expert backup, this will be a greater challenge. Resource
leveling is critical on this – if not, then other mitigation must be
considered.
140
120
100
Hours
80
60
40
20
0
7
1/ 9
4
2/ 6
4
3/ 6
1/ 3
1/ 5
1/ 7
1/ 1
1/ 3
1/ 7
1/ 9
31
2/ 0
2/ 2
2/ 4
2/ 8
2/ 0
2/ 4
2/ 6
28
3/ 0
3/ 2
3/ 4
18
1/
1/
2/
2/
3/
3/
1
1
1
2
2
2
2
1
1
1
1
2
2
2
1
1
1
End Dates (2-day Work Periods)
140
120
120
100
8080 80
80
Hours
6464 6464646468 61
60 48 4848
40 40 40
40 32
20 14
8
0 0 0 0 0
0
7
1/ 9
2/4
2/ 6
4
3/ /6
1/ 3
1/ 5
1/ 7
1/ 1
1/23
1/ 7
1/ 9
31
2/ 0
2/ 2
2/14
2/ 8
2/ 0
2/ 4
2/ 6
28
3/ 0
3/12
3/ 4
18
1/
1/
2/
3/
1
1
1
2
1
1
1
2
2
1
2
2
2
1
3
En d D a t e s ( 2 - da y Wor k P e r i od s)
Project for Resource: P5.5 Prog - Host Cobol
120
96
100 88
80
6462 646468
Hours
60 48 4848
40
40 32 34 32
24 26
20
20
0 0 0 0 0 0 0 0 0
0
7
1/ 9
2/4
2/ 6
4
3/ /6
1/ 3
1/ 5
1/ 7
1/ 1
1/23
1/ 7
1/ 9
31
2/ 0
2/ 2
2/14
2/ 8
2/ 0
2/ 4
2/ 6
28
3/ 0
3/12
3/ 4
18
1/
1/
2/
3/
1
1
1
2
1
1
1
2
2
1
2
2
2
1
3
En d D a t e s ( 2 - da y Wor k P e r i od s)
70 63 6464
60
60
52
50
40
Hours
34
30
30
20
20 161816 14
10 1212
10 4 4
0 2 0 2 0 0 0 0 0
0
7
9
4
2/ 6
4
3/ /6
1/ 3
1/ 5
1/ 7
1/ 1
1/ 3
1/ 7
1/ 9
31
2/ 0
2/ 2
2/ 4
2/ 8
2/ 0
2/ 4
2/ 6
28
3/ 0
3/ 2
3/ 4
18
1/
1/
3/
2/
2/
2
2
2
1
1
1
1
2
2
2
1
1
1
2
1
1
1
3
1/
En d D a t e s ( 2 - da y Wor k P e r i od s)
Project for Resource: P5.1 Conversion Architect
35 32
30 28
24
25 22
20 20
20 18
Hours
1616 16 16 16 16
15
10 8 8
5 2
0 0 0 0 0 0 0 0 0 0
0
7
9
4
2/ 6
4
3/ /6
1/ 3
1/ 5
1/ 7
1/ 1
1/ 3
1/ 7
1/ 9
31
2/ 0
2/ 2
2/ 4
2/ 8
2/ 0
2/ 4
2/ 6
28
3/ 0
3/ 2
3/ 4
18
1/
1/
3/
2/
2/
2
2
2
1
1
1
1
2
2
2
1
1
1
2
1
1
1
3
1/
En d D a t e s ( 2 - da y Wor k P e r i od s)
50
44
45
40 36
35 30
30
Hours
24
25
20 18
16 16 16 16
14
15 10 12
10
4
5 2
0 0 0 0 0 0 0 0 0 0 0 0
0
7
9
4
2/ 6
4
3/ /6
1/ 3
1/ 5
1/ 7
1/ 1
1/ 3
1/ 7
1/ 9
31
2/ 0
2/ 2
2/ 4
2/ 8
2/ 0
2/ 4
2/ 6
28
3/ 0
3/ 2
3/ 4
18
1/
1/
3/
2/
2/
2
2
2
1
1
1
1
2
2
2
1
1
1
2
1
1
1
3
1/
En d D a t e s ( 2 - da y Wor k P e r i od s)
140
120
100
Hours
80
60
40
20
0
1/7 1/9 1/13 1/15 1/17 1/21 1/23 1/27
End Dates (2-day Work Periods)
P3.2 BA - Banking C.3.1 Client BA P.5.1 Conversion Arch P.3.1 BA Lead P5.5 Programmer - Cobol
100
80
Hours 60
40
20
0
1/15 1/17 1/21 1/23 1/27 1/29 1/31 2/4 2/6
End Dates (2-Day Work Periods)
100
80
Hours
60
40
20
0
2/12 2/14 2/18 2/20 2/24 2/26 2/28
End Dates (2-Day Work Periods)
60
50
Hours 40
30
20
10
0
2/28 3/4 3/6 3/10
End Dates (2-Day Work Periods)
60000
50000
40000
Cost ($)
30000
20000
10000
0
7
9
2/ 6
4
6
13
15
17
21
23
27
29
31
10
12
14
18
20
24
26
28
10
12
14
18
1/
1/
2/
3/
2/
3/
1/
1/
1/
1/
1/
1/
1/
1/
2/
2/
2/
2/
2/
2/
2/
3/
3/
3/
3/
1/7 1/9 1/13 1/15 1/17 1/21 1/23 1/27 1/29 1/31 2/4 2/6 2/10
Cash Flow
(Period) 4810 2960 14000 19070 16480 49700 25300 24400 14580 49750.4 28700.4 22182 24475.2
Cash Flow
(Cumulative) 4810 7770 21770 40840 57320 107020 132320 156720 171300 221050.4 249750.8 271932.8 296408
2/12 2/14 2/18 2/20 2/24 2/26 2/28 3/4 3/6 3/10 3/12 3/14 3/18
Cash Flow
(Period) 18620 31850 20625 17160 13530 13530 21910 19000 19000 12930 0 3700 5360
Cash Flow
(Cumulative) 315028 346878 367503 384663 398193 411723 433633 452633 471633 484563 484563 488263 493623
60000
49700
50000
40000
Cash ($)
30000
19070 16480 18220
20000 14000
4810 6760
10000 2960
0
1/7 1/9 1/13 1/15 1/17 1/21 1/23 1/27
Schedule (2-day work periods)
40000 36185.2
34210.4
35000
30000 27380.4 27438.4
25350
25000
Cash ($)
20000 15583.6
15000
10000 5600
5000 2220 2720
0
1/15 1/17 1/21 1/23 1/27 1/29 1/31 2/4 2/6
Schedule (2-day work periods)
35000 31850
30000
25000 20625
Cash ($)
19000 19000
20000
15000 12930
Cash ($)
10000
6070
5000
0
2/28 3/4 3/6 3/10
Schedule (2-day w ork periods)
6000 5360
5000
3700
Cash ($)
4000
3000
2000
1000
0
3/14 3/18
Schedule (2-day work periods)
\
Introduction
As the optimum total duration of the project is 412 hours, this assignment’s call for a
reduction of 15% amounts to 61.8 hours (to be considered as 62 hours).
Note that the following table provides data at the WBS element level only – a decrease in
the duration of a single element does not necessarily provide the same duration decrease
at the project level (e.g., multiple parallel tasks might need to be decreased by “x” hours
in order to achieve an “x” hours decrease at the project level). The impact at the project
level is discussed in the details following the table.
WBS Element Duration (Hours) Effort (Total Worker Hours) Cost ($)
% % %
Num Name Orig Compressed Chg Chg Orig CompressedChg Chg Orig Compressed Chg Chg
Source Application
& Interfaces
1.1.1 Report 40 28 -12 -30% 70 82 12 17% $9,250 $10,510 $1,260 14%
Mapping Specs -
Cust Info File
2.3.1 Specs 60 48 -12 -20% 294 314 20 7% $28,642 $30,662 $2,020 7%
Mapping Specs -
2.3.2 Acct File Specs 60 48 -12 -20% 294 314 20 7% $28,642 $30,662 $2,020 7%
Mapping Specs -
Acct Hist File
2.3.3 Specs 60 48 -12 -20% 294 314 20 7% $28,642 $30,662 $2,020 7%
Used/Unused
2.3.5 Source Report 24 16 -8 -33% 124 132 8 6% $12,520 $12,520 $0 0%
Application - Cust
3.1.1 Info File 60 40 -20 -33% 118 138 20 17% $17,610 $19,310 $1,700 10%
Application - Acct
3.1.2 File 60 40 -20 -33% 118 138 20 17% $17,610 $19,310 $1,700 10%
Application - Acct
3.1.3 Hist File 60 40 -20 -33% 118 138 20 17% $17,610 $19,310 $1,700 10%
Prove Report -
3.2.1 Cust Info File 16 12 -4 -25% 30 34 4 13% $4,290 $4,630 $340 8%
Prove Report -
3.2.2 Acct File 16 12 -4 -25% 30 34 4 13% $4,290 $4,630 $340 8%
Prove Report -
3.2.3 Acct Hist File 16 12 -4 -25% 30 34 4 13% $4,290 $4,630 $340 8%
System Test
4.1 Extract 16 13 -3 -19% 116 116 0 0% $19,000 $19,278 $278 1%
Dry Run Test
4.2 Extract 16 13 -3 -19% 116 116 0 0% $19,000 $19,278 $278 1%
TOTALS (WBS
SUBSET) --> (Not Meaningful) 1752 1904 152 9%$211,396 $225,391$13,995 7%
Duration
Duration
Intensity
Intensity
WBS
WBS Element Name Resource Effort Effort
Num
Duration
Duration
Intensity
Intensity
WBS
WBS Element Name Resource Effort Effort
Num
Customer Information
2.3.1 P.3.2 BA - Banking 1 60 60 1 48 48
File Specs
P.3.3 PA - Banking B8 0 0 0 1 32 32
P.3.1 BA Lead - Banking 1 8 8 1 8 8
P.1.4 Conversion PM 1 16 16 1 16 16
P.5.1 Conversion Architect 1 6 6 1 6 6
P.5.5 Programmer - Host Cobol 1 40 40 1 40 40
C.3.1 Client BA 1 60 60 2 30 60
C.1.1 Client PM 1 8 8 1 8 8
C.2.1 Client Architect 1 16 16 1 16 16
C.4.1 Client Programmer - Source 1 40 40 1 40 40
C.4.2 Client Programmer - Target 1 40 40 1 40 40
T.1.2 Remote Flight 4 1 4 4 1 4
T.2.2 Remote Resource Onsite A 4 3 12 4 3 12
F.2.3 Conf Room M 1 16 16 1 16 16
F.3.1 Deli Lunch 2 12 24 2 12 24
2.3.2 Account File Specs P.3.2 BA - Banking 1 60 60 1 48 48
P.3.3 PA - Banking B8 0 0 0 1 32 32
P.3.1 BA Lead - Banking 1 8 8 1 8 8
P.1.4 Conversion PM 1 16 16 1 16 16
P.5.1 Conversion Architect 1 6 6 1 6 6
P.5.5 Programmer - Host Cobol 1 40 40 1 40 40
C.3.1 Client BA 1 60 60 2 30 60
C.1.1 Client PM 1 8 8 1 8 8
C.2.1 Client Architect 1 16 16 1 16 16
C.4.1 Client Programmer - Source 1 40 40 1 40 40
C.4.2 Client Programmer - Target 1 40 40 1 40 40
T.1.2 Remote Flight 4 1 4 4 1 4
T.2.2 Remote Resource Onsite A 4 3 12 4 3 12
Original Compressed
Duration
Duration
Intensity
Intensity
WBS
WBS Element Name Resource Effort Effort
Num
Duration
Intensity
Intensity
WBS
WBS Element Name Resource Effort Effort
Num
Used/Unused Source
2.3.5 P.3.2 BA - Banking 4 8 32 4 8 32
Field Report
P.3.1 BA Lead - Banking 1 8 8 1 8 8
P.1.4 Conversion PM 1 8 8 1 8 8
P.5.1 Conversion Architect 1 16 16 1 16 16
P.5.5 Programmer - Host Cobol 4 2 8 4 2 8
C.3.1 Client BA 1 24 24 2 16 32
C.1.1 Client PM 1 4 4 1 4 4
C.2.1 Client Architect 1 8 8 1 8 8
C.4.1 Client Programmer - Source 1 8 8 1 8 8
C.4.2 Client Programmer - Target 1 8 8 1 8 8
Original Compressed
Duration
Duration
Intensity
Intensity
WBS
WBS Element Name Resource Effort Effort
Num
Customer Information
3.1.1 P.3.2 BA - Banking 1 40 40 1 40 40
File Application
P.3.1 BA Lead - Banking 1 6 6 1 6 6
P.5.5 Programmer - Host Cobol 1 60 60 1 40 40
P.5.6 Programmer - Host Cobol B8 0 0 0 1 40 40
C.3.1 Client BA 1 8 8 1 8 8
C.4.1 Client Programmer - Source 1 4 4 1 4 4
Account File
3.1.2 P.3.2 BA - Banking 1 40 40 1 40 40
Application
P.3.1 BA Lead - Banking 1 6 6 1 6 6
P.5.5 Programmer - Host Cobol 1 60 60 1 40 40
P.5.6 Programmer - Host Cobol B8 0 0 0 1 40 40
C.3.1 Client BA 1 8 8 1 8 8
C.4.1 Client Programmer - Source 1 4 4 1 4 4
Account History File
3.1.3 P.3.2 BA - Banking 1 40 40 1 40 40
Application
P.3.1 BA Lead - Banking 1 6 6 1 6 6
P.5.5 Programmer - Host Cobol 1 60 60 1 40 40
P.5.6 Programmer - Host Cobol B8 0 0 0 1 40 40
C.3.1 Client BA 1 8 8 1 8 8
C.4.1 Client Programmer - Source 1 4 4 1 4 4
Duration
Duration
Intensity
Intensity
WBS
WBS Element Name Resource Effort Effort
Num
Customer Information
3.2.1 P.3.2 BA - Banking 1 16 16 1 12 12
File Application
P.3.3 PA - Banking B8 0 0 0 1 8 8
P.5.5 Programmer - Host Cobol 1 10 10 1 10 10
C.3.1 Client BA 1 4 4 1 4 4
Account File
3.2.2 P.3.2 BA - Banking 1 16 16 1 12 12
Application
P.3.3 PA - Banking B8 0 0 0 1 8 8
P.5.5 Programmer - Host Cobol 1 10 10 1 10 10
C.3.1 Client BA 1 4 4 1 4 4
Account History File
3.2.3 P.3.2 BA - Banking 1 16 16 1 12 12
Application
P.3.3 PA - Banking B8 0 0 0 1 8 8
P.5.5 Programmer - Host Cobol 1 10 10 1 10 10
C.3.1 Client BA 1 4 4 1 4 4
Duration
Intensity
Intensity
WBS
WBS Element Name Resource Effort Effort
Num
Original Compressed
Duration
Duration
Intensity
Intensity
WBS
WBS Element Name Resource Effort Effort
Num
1.1.1, 1.3.1, 1.3.2, 2.1.2, 2.2, (2.3.1, 2.3.2, 2.3.3), (2.4.1, 2.3.5, 2.4.2, 2.4.3),
(3.1.1, 3.1.2, 3.1.3), (3.2.1, 3.2.2, 3.2.3), (3.3.1, 3.3.2, 3.3.3), 4.1, 4.2, 4.3, 5.1, 5.2
It is of interest to note that the critical path is now more populated than it was before the
compression. By compressing items on the former critical path as much as the slack of
parallel tasks allowed, these parallel tasks became part of the critical path as well.
Source Applications & Detailed Schedule of Mapping Customer Information File Customer Information File Customer Information File Customer Information File Customer Information File
WBS: 0.1.1.1 WBS: 0.2.2 WBS: 0.2.3.1 WBS: 0.2.4.1 WBS: 0.3.1.1 WBS: 0.3.2.1 WBS: 0.3.3.1 WBS: 0.4.1 System Test Extract WBS: 0.4.2 Dry Run Test Extract WBS: 0.4.3 Conversion Extract WBS: 0.5.1 Plan vs. Actuals Report WBS: 0.5.2 Lessons Learned Report
Interfaces Report Sessions Specs Balancing Design Application Application Application
Duration: 28 Duration: 8 Finish: Duration: 48 Duration: 16 Duration: 40 Finish: Duration: 12 Finish: Duration: 12 Finish: Duration: 13 Finish: Duration: 13 Finish: Duration: 16 Finish: Duration: 16 Duration: 8
Start: 1/6/03 Finish: 1/9/03 Start: 1/27/03 Start: 1/28/03 Finish: 2/5/03 Start: 2/5/03 Finish: 2/7/03 Start: 2/7/03 Start: 2/14/03 Start: 2/18/03 Start: 2/19/03 Start: 2/21/03 Start: 2/24/03 Start: 3/3/03 Finish: 3/5/03 Start: 3/5/03 Finish: 3/6/03
hrs hrs 1/28/03 hrs hrs hrs 2/14/03 hrs 2/17/03 hrs 2/19/03 hrs 2/21/03 hrs 2/24/03 hrs 2/26/03 hrs hrs
Total Slack: 0 Late Start: Late Finish: Total Slack: 0 Late Start: Late Finish: Total Slack: 0 Late Start: Late Finish: Total Slack: 0 Late Start: Late Finish: Total Slack: 0 Late Start: Late Finish: Total Slack: 0 Late Start: Late Finish: Total Slack: 0 Late Start: Late Finish: Total Slack: 0 Late Start: Late Finish: Total Slack: 0 Late Start: Late Finish: Total Slack: 0 Late Start: Late Finish: Total Slack: 0 Late Start: Late Finish: Total Slack: 0 Late Start: Late Finish:
hrs 1/6/03 1/9/03 hrs 1/27/03 1/28/03 hrs 1/28/03 2/5/03 hrs 2/5/03 2/7/03 hrs 2/7/03 2/14/03 hrs 2/14/03 2/17/03 hrs 2/18/03 2/19/03 hrs 2/19/03 2/21/03 hrs 2/21/03 2/24/03 hrs 2/24/03 2/26/03 hrs 3/3/03 3/5/03 hrs 3/5/03 3/6/03
Duration: 16
Start: 2/5/03 Finish: 2/7/03
hrs
Total Slack: 0 Late Start: Late Finish:
hrs 2/5/03 2/7/03
Account History File Balancing Account History File Account History File Account History File
WBS: 0.2.3.3 Account History File Specs WBS: 0.2.4.3 WBS: 0.3.1.3 WBS: 0.3.2.3 WBS: 0.3.3.3
Design Application Application Application
Duration: 48 Duration: 16 Duration: 40 Finish: Duration: 12 Finish: Duration: 12 Finish:
Start: 1/28/03 Finish: 2/5/03 Start: 2/5/03 Finish: 2/7/03 Start: 2/7/03 Start: 2/14/03 Start: 2/18/03
hrs hrs hrs 2/14/03 hrs 2/17/03 hrs 2/19/03
Total Slack: 0 Late Start: Late Finish: Total Slack: 0 Late Start: Late Finish: Total Slack: 0 Late Start: Late Finish: Total Slack: 0 Late Start: Late Finish: Total Slack: 0 Late Start: Late Finish:
hrs 1/28/03 2/5/03 hrs 2/5/03 2/7/03 hrs 2/7/03 2/14/03 hrs 2/14/03 2/17/03 hrs 2/18/03 2/19/03
Page 1
1.1.1, 1.3.1, 1.3.2, 2.1.2, 2.2, 2.3.3, 2.3.5, 3.1.3, 3.2.3, 3.3.3, 0.4.1, 0.4.2, 0.4.3,
0.5.1, 0.5.2
There are times in which the only way a good Project Manager can best serve his client is
to disappoint her by saying “No” to a request. This is one of those times. While every
client wants the shortest possible schedule, it is not always possible or, if possible, not
worth the risk of failure. Here are some of the reasons that I would not deliver a Project
Schedule of modified scope that is based on the original date:
1. Data Conversion projects have a high cost of failure. Specifically, these generally
involve moving millions of data elements and hundreds of millions of dollars, all
belonging to the client’s active customers. Any data improperly converted risks
the business relationship of valuable customers (recall that this is banking!). In
addition, having to reverse a conversion and/or missing the published schedule is
often worthy of note in the Wall Street Journal (I had one of these two years
ago!), resulting in embarrassment and loss of business to the client.
2. As noted above, the project began with a duration of 412 hours, but is now
projected at a total of 612 hours. To recover the schedule, would require a
duration reduction of 200 hours when there is only 178 hours left to the very
original project schedule. Roughly speaking, our productivity would have to
double over the remaining period. With all elements already at optimum duration,
and this short run-way, this is totally impractical.
3. The short runway also makes it very difficult to obtain and orient skilled
resources in time to contribute.
4. As the Schedule Performance Index (SPI) was calculated in assignment H as
being 0.83, and that is not factored into any of the above duration projections. If
we made a realistic projection, based on prior performance, we would be adding
about another 20% to the already-impossible duration.
The client can find another PM if they are not happy with the message, but “NO” is in
their best interest.
Detail Table
Completed at Status
Original Plan Remaining at New Cost Rates
Date (original rates)
Tot Units
Duration
Intensity
Tot Units
Duration
Intensity
Tot Units Extended Budget Budget
WBS Comp Unit Units Tot Cost Unit Tot Cost
Resource Cost To Cost Change Incr
Element (%) Cost Done (BCWP) Cost (BAC)
(BAC) Go (ETC) ($) (%)
P.5.5
Programmer
1 24 24 $3,960 47% $165 11.3 $1,861.20$163.35 12.7 $2,077.81 $3,939.01 (20.99) -0.5%
- Host
Cobol
C.3.1 Client
1 10 10 $0 47% $0 4.7 $0.00 $0.00 5.3 $0.00 $0.00 0.00 0.0%
BA
1.2.3 Name
& Address P.5.1
Scrubbing Conversion 1 2 2 $370 47% $185 0.9 $173.90$183.15 1.1 $194.14 $368.04 (1.96) -0.5%
Analysis Architect
Report
P.3.1 BA
Lead - 1 8 8 $1,480 47% $185 3.8 $695.60$197.95 4.2 $839.31 $1,534.91 54.91 3.7%
Banking
P.5.5
Programmer
1 16 16 $2,640 47% $165 7.5 $1,240.80$163.35 8.5 $1,385.21 $2,626.01 (13.99) -0.5%
- Host
Cobol
C.3.1 Client
1 4 4 $0 47% $0 1.9 $0.00 $0.00 2.1 $0.00 $0.00 0.00 0.0%
BA
1.2.4
P.5.1
Account File
Conversion 1 4 4 $740 47% $185 1.9 $347.80$183.15 2.1 $388.28 $736.08 (3.92) -0.5%
Analysis
Architect
Report
P.3.1 BA
Lead - 1 2 2 $370 47% $185 0.9 $173.90$197.95 1.1 $209.83 $383.73 13.73 3.7%
Banking
P.3.2 BA -
1 16 16 $2,640 47% $165 7.5 $1,240.80$176.55 8.5 $1,497.14 $2,737.94 97.94 3.7%
Banking
P.5.5
Programmer
1 24 24 $3,960 47% $165 11.3 $1,861.20$163.35 12.7 $2,077.81 $3,939.01 (20.99) -0.5%
- Host
Cobol
C.3.1 Client
1 10 10 $0 47% $0 4.7 $0.00 $0.00 5.3 $0.00 $0.00 0.00 0.0%
BA
1.2.5
Account P.5.1
History File Conversion 1 4 4 $740 47% $185 1.9 $347.80$183.15 2.1 $388.28 $736.08 (3.92) -0.5%
Analysis Architect
Report
P.3.1 BA
Lead - 1 2 2 $370 47% $185 0.9 $173.90$197.95 1.1 $209.83 $383.73 13.73 3.7%
Banking
P.3.2 BA -
1 16 16 $2,640 47% $165 7.5 $1,240.80$176.55 8.5 $1,497.14 $2,737.94 97.94 3.7%
Banking
P.5.5
Programmer
1 24 24 $3,960 47% $165 11.3 $1,861.20$163.35 12.7 $2,077.81 $3,939.01 (20.99) -0.5%
- Host
Cobol
C.3.1 Client
1 10 10 $0 47% $0 4.7 $0.00 $0.00 5.3 $0.00 $0.00 0.00 0.0%
BA
Completed at Status
Original Plan Remaining at New Cost Rates
Date (original rates)
Tot Units
Duration
Intensity
Tot Units Extended Budget Budget
WBS Comp Unit Units Tot Cost Unit Tot Cost
Resource Cost To Cost Change Incr
Element (%) Cost Done (BCWP) Cost (BAC)
(BAC) Go (ETC) ($) (%)
1.2.6 Pre-
Authorized P.5.1
Transaction Conversion 1 2 2 $370 47% $185 0.9 $173.90$183.15 1.1 $194.14 $368.04 (1.96) -0.5%
File Analysis Architect
Report
P.3.1 BA
Lead - 1 2 2 $370 47% $185 0.9 $173.90$197.95 1.1 $209.83 $383.73 13.73 3.7%
Banking
P.3.2 BA -
1 8 8 $1,320 47% $165 3.8 $620.40$176.55 4.2 $748.57 $1,368.97 48.97 3.7%
Banking
P.5.5
Programmer
1 16 16 $2,640 47% $165 7.5 $1,240.80$163.35 8.5 $1,385.21 $2,626.01 (13.99) -0.5%
- Host
Cobol
C.3.1 Client
1 5 5 $0 47% $0 2.4 $0.00 $0.00 2.7 $0.00 $0.00 0.00 0.0%
BA
1.3.1 Target
P.5.1
Application
Conversion 1 40 40 $7,400 47% $185 18.8 $3,478.00$183.15 21.2 $3,882.78 $7,360.78 (39.22) -0.5%
& Interfaces
Architect
Report
P.3.1 BA
Lead - 1 10 10 $1,850 47% $185 4.7 $869.50$197.95 5.3 $1,049.14 $1,918.64 68.63 3.7%
Banking
P.3.2 BA -
4 2 8 $1,320 47% $165 3.8 $620.40$176.55 4.2 $748.57 $1,368.97 48.97 3.7%
Banking
C.2.1 Client
1 10 10 $0 47% $0 4.7 $0.00 $0.00 5.3 $0.00 $0.00 0.00 0.0%
Architect
C.3.1 Client
1 10 10 $0 47% $0 4.7 $0.00 $0.00 5.3 $0.00 $0.00 0.00 0.0%
BA
1.3.2 Target P.5.1
Data Conversion 1 20 20 $3,700 43% $185 8.6 $1,591.00$183.15 11.4 $2,087.91 $3,678.91 (21.09) -0.6%
Dictionary Architect
P.3.1 BA
Lead - 1 40 40 $7,400 43% $185 17.2 $3,182.00$197.95 22.8 $4,513.26 $7,695.26 295.26 4.0%
Banking
P.3.2 BA -
4 40 160 $26,400 43% $165 68.8$11,352.00$176.55 91.2$16,101.36$27,453.36 1,053.36 4.0%
Banking
C.3.1 Client
1 40 40 $0 43% $0 17.2 $0.00 $0.00 22.8 $0.00 $0.00 0.00 0.0%
BA
2.1.1
Conversion
P.5.1
Dependency
Conversion 1 20 20 $3,700 47% $185 9.4 $1,739.00$183.15 10.6 $1,941.39 $3,680.39 (19.61) -0.5%
(Intra-Appl
Architect
& External)
Report
P.3.1 BA
Lead - 1 8 8 $1,480 47% $185 3.8 $695.60$197.95 4.2 $839.31 $1,534.91 54.91 3.7%
Banking
P.3.2 BA -
4 4 16 $2,640 47% $165 7.5 $1,240.80$176.55 8.5 $1,497.14 $2,737.94 97.94 3.7%
Banking
C.2.1 Client
1 4 4 $0 47% $0 1.9 $0.00 $0.00 2.1 $0.00 $0.00 0.00 0.0%
Architect
C.3.1 Client 1 4 4 $0 47% $0 1.9 $0.00 $0.00 2.1 $0.00 $0.00 0.00 0.0%
Completed at Status
Original Plan Remaining at New Cost Rates
Date (original rates)
Tot Units
Duration
Intensity
Tot Units Extended Budget Budget
WBS Comp Unit Units Tot Cost Unit Tot Cost
Resource Cost To Cost Change Incr
Element (%) Cost Done (BCWP) Cost (BAC)
(BAC) Go (ETC) ($) (%)
BA
2.1.2 Target
P.5.1
Record
Conversion 1 4 4 $740 43% $185 1.7 $318.20$183.15 2.3 $417.58 $735.78 (4.22) -0.6%
Layout
Architect
Definition
P.3.1 BA
Lead - 1 4 4 $740 43% $185 1.7 $318.20$197.95 2.3 $451.33 $769.53 29.53 4.0%
Banking
P.3.2 BA -
4 4 16 $2,640 43% $165 6.9 $1,135.20$176.55 9.1 $1,610.14 $2,745.34 105.34 4.0%
Banking
P.5.5
Programmer
4 16 64 $10,560 43% $165 27.5 $4,540.80$163.35 36.5 $5,959.01$10,499.81 (60.19) -0.6%
- Host
Cobol
C.2.1 Client
1 2 2 $0 43% $0 0.9 $0.00 $0.00 1.1 $0.00 $0.00 0.00 0.0%
Architect
C.3.1 Client
1 2 2 $0 43% $0 0.9 $0.00 $0.00 1.1 $0.00 $0.00 0.00 0.0%
BA
2.1.3
P.5.1
Exception
Conversion 1 8 8 $1,480 43% $185 3.4 $636.40$183.15 4.6 $835.16 $1,471.56 (8.44) -0.6%
Condition
Architect
Definition
P.3.1 BA
Lead - 1 4 4 $740 43% $185 1.7 $318.20$197.95 2.3 $451.33 $769.53 29.53 4.0%
Banking
P.3.2 BA -
4 8 32 $5,280 43% $165 13.8 $2,270.40$176.55 18.2 $3,220.27 $5,490.67 210.67 4.0%
Banking
C.2.1 Client
1 4 4 $0 43% $0 1.7 $0.00 $0.00 2.3 $0.00 $0.00 0.00 0.0%
Architect
C.3.1 Client
1 4 4 $0 43% $0 1.7 $0.00 $0.00 2.3 $0.00 $0.00 0.00 0.0%
BA
2.1.4 Job P.5.1
List Conversion 1 8 8 $1,480 43% $185 3.4 $636.40$183.15 4.6 $835.16 $1,471.56 (8.44) -0.6%
Definition Architect
P.3.1 BA
Lead - 1 2 2 $370 43% $185 0.9 $159.10$197.95 1.1 $225.66 $384.76 14.76 4.0%
Banking
P.5.5
Programmer
4 2 8 $1,320 43% $165 3.4 $567.60$163.35 4.6 $744.88 $1,312.48 (7.52) -0.6%
- Host
Cobol
2.1.5
P.5.1
Conversion
Conversion 1 8 8 $1,480 43% $185 3.4 $636.40$183.15 4.6 $835.16 $1,471.56 (8.44) -0.6%
Sequencing
Architect
Report
P.3.1 BA
Lead - 1 4 4 $740 43% $185 1.7 $318.20$197.95 2.3 $451.33 $769.53 29.53 4.0%
Banking
P.1.4
Conversion 1 2 2 $370 43% $185 0.9 $159.10$205.35 1.1 $234.10 $393.20 23.20 6.3%
PM
C.2.1 Client
1 4 4 $0 43% $0 1.7 $0.00 $0.00 2.3 $0.00 $0.00 0.00 0.0%
Architect
Completed at Status
Original Plan Remaining at New Cost Rates
Date (original rates)
Tot Units
Duration
Intensity
Tot Units Extended Budget Budget
WBS Comp Unit Units Tot Cost Unit Tot Cost
Resource Cost To Cost Change Incr
Element (%) Cost Done (BCWP) Cost (BAC)
(BAC) Go (ETC) ($) (%)
C.3.1 Client
1 2 2 $0 43% $0 0.9 $0.00 $0.00 1.1 $0.00 $0.00 0.00 0.0%
BA
2.2 Detailed
P.5.1
Schedule of
Conversion 1 2 2 $370 43% $185 0.9 $159.10$183.15 1.1 $208.79 $367.89 (2.11) -0.6%
Mapping
Architect
Sessions
P.3.1 BA
Lead - 1 8 8 $1,480 43% $185 3.4 $636.40$197.95 4.6 $902.65 $1,539.05 59.05 4.0%
Banking
P.3.2 BA -
4 2 8 $1,320 43% $165 3.4 $567.60$176.55 4.6 $805.07 $1,372.67 52.67 4.0%
Banking
P.1.4
Conversion 1 2 2 $370 43% $185 0.9 $159.10$205.35 1.1 $234.10 $393.20 23.20 6.3%
PM
2.3.1
Customer P.3.2 BA -
1 60 60 $9,900 43% $165 25.8 $4,257.00$176.55 34.2 $6,038.01$10,295.01 395.01 4.0%
Information Banking
File Specs
P.3.1 BA
Lead - 1 8 8 $1,480 43% $185 3.4 $636.40$197.95 4.6 $902.65 $1,539.05 59.05 4.0%
Banking
P.1.4
Conversion 1 16 16 $2,960 43% $185 6.9 $1,272.80$205.35 9.1 $1,872.79 $3,145.59 185.59 6.3%
PM
P.5.1
Conversion 1 6 6 $1,110 43% $185 2.6 $477.30$183.15 3.4 $626.37 $1,103.67 (6.33) -0.6%
Architect
P.5.5
Programmer
1 40 40 $6,600 43% $165 17.2 $2,838.00$163.35 22.8 $3,724.38 $6,562.38 (37.62) -0.6%
- Host
Cobol
C.3.1 Client
1 60 60 $0 43% $0 25.8 $0.00 $0.00 34.2 $0.00 $0.00 0.00 0.0%
BA
C.1.1 Client
1 8 8 $0 43% $0 3.4 $0.00 $0.00 4.6 $0.00 $0.00 0.00 0.0%
PM
C.2.1 Client
1 16 16 $0 43% $0 6.9 $0.00 $0.00 9.1 $0.00 $0.00 0.00 0.0%
Architect
C.4.1 Client
Programmer 1 40 40 $0 43% $0 17.2 $0.00 $0.00 22.8 $0.00 $0.00 0.00 0.0%
- Source
C.4.2 Client
Programmer 1 40 40 $0 43% $0 17.2 $0.00 $0.00 22.8 $0.00 $0.00 0.00 0.0%
- Target
T.1.2
Remote 4 1 4 $3,600 43% $900 1.7 $1,548.00$927.00 2.3 $2,113.56 $3,661.56 61.56 1.7%
Flight
T.2.2
Remote
4 3 12 $1,200 43% $100 5.2 $516.00$103.00 6.8 $704.52 $1,220.52 20.52 1.7%
Resource
Onsite A
F.2.3 Conf
1 16 16 $1,600 43% $100 6.9 $688.00$103.00 9.1 $939.36 $1,627.36 27.36 1.7%
Room M
F.3.1 Deli 2 12 24 $192 43% $8 10.3 $82.56 $8.24 13.7 $112.72 $195.28 3.28 1.7%
Completed at Status
Original Plan Remaining at New Cost Rates
Date (original rates)
Tot Units
Duration
Intensity
Tot Units Extended Budget Budget
WBS Comp Unit Units Tot Cost Unit Tot Cost
Resource Cost To Cost Change Incr
Element (%) Cost Done (BCWP) Cost (BAC)
(BAC) Go (ETC) ($) (%)
Lunch
2.3.2
P.3.2 BA -
Account File 1 60 60 $9,900 43% $165 25.8 $4,257.00$176.55 34.2 $6,038.01$10,295.01 395.01 4.0%
Banking
Specs
P.3.1 BA
Lead - 1 8 8 $1,480 43% $185 3.4 $636.40$197.95 4.6 $902.65 $1,539.05 59.05 4.0%
Banking
P.1.4
Conversion 1 16 16 $2,960 43% $185 6.9 $1,272.80$205.35 9.1 $1,872.79 $3,145.59 185.59 6.3%
PM
P.5.1
Conversion 1 6 6 $1,110 43% $185 2.6 $477.30$183.15 3.4 $626.37 $1,103.67 (6.33) -0.6%
Architect
P.5.5
Programmer
1 40 40 $6,600 43% $165 17.2 $2,838.00$163.35 22.8 $3,724.38 $6,562.38 (37.62) -0.6%
- Host
Cobol
C.3.1 Client
1 60 60 $0 43% $0 25.8 $0.00 $0.00 34.2 $0.00 $0.00 0.00 0.0%
BA
C.1.1 Client
1 8 8 $0 43% $0 3.4 $0.00 $0.00 4.6 $0.00 $0.00 0.00 0.0%
PM
C.2.1 Client
1 16 16 $0 43% $0 6.9 $0.00 $0.00 9.1 $0.00 $0.00 0.00 0.0%
Architect
C.4.1 Client
Programmer 1 40 40 $0 43% $0 17.2 $0.00 $0.00 22.8 $0.00 $0.00 0.00 0.0%
- Source
C.4.2 Client
Programmer 1 40 40 $0 43% $0 17.2 $0.00 $0.00 22.8 $0.00 $0.00 0.00 0.0%
- Target
T.1.2
Remote 4 1 4 $3,600 43% $900 1.7 $1,548.00$927.00 2.3 $2,113.56 $3,661.56 61.56 1.7%
Flight
T.2.2
Remote
4 3 12 $1,200 43% $100 5.2 $516.00$103.00 6.8 $704.52 $1,220.52 20.52 1.7%
Resource
Onsite A
F.2.3 Conf
1 16 16 $1,600 43% $100 6.9 $688.00$103.00 9.1 $939.36 $1,627.36 27.36 1.7%
Room M
F.3.1 Deli
2 12 24 $192 43% $8 10.3 $82.56 $8.24 13.7 $112.72 $195.28 3.28 1.7%
Lunch
2.3.3
Account P.3.2 BA -
1 60 60 $9,900 40% $165 24.0 $3,960.00$176.55 36.0 $6,355.80$10,315.80 415.80 4.2%
History File Banking
Specs
P.3.1 BA
Lead - 1 8 8 $1,480 40% $185 3.2 $592.00$197.95 4.8 $950.16 $1,542.16 62.16 4.2%
Banking
P.1.4
Conversion 1 16 16 $2,960 40% $185 6.4 $1,184.00$205.35 9.6 $1,971.36 $3,155.36 195.36 6.6%
PM
P.5.1
Conversion 1 6 6 $1,110 40% $185 2.4 $444.00$183.15 3.6 $659.34 $1,103.34 (6.66) -0.6%
Architect
Completed at Status
Original Plan Remaining at New Cost Rates
Date (original rates)
Tot Units
Duration
Intensity
Tot Units Extended Budget Budget
WBS Comp Unit Units Tot Cost Unit Tot Cost
Resource Cost To Cost Change Incr
Element (%) Cost Done (BCWP) Cost (BAC)
(BAC) Go (ETC) ($) (%)
P.5.5
Programmer
1 40 40 $6,600 40% $165 16.0 $2,640.00$163.35 24.0 $3,920.40 $6,560.40 (39.60) -0.6%
- Host
Cobol
C.3.1 Client
1 60 60 $0 40% $0 24.0 $0.00 $0.00 36.0 $0.00 $0.00 0.00 0.0%
BA
C.1.1 Client
1 8 8 $0 40% $0 3.2 $0.00 $0.00 4.8 $0.00 $0.00 0.00 0.0%
PM
C.2.1 Client
1 16 16 $0 40% $0 6.4 $0.00 $0.00 9.6 $0.00 $0.00 0.00 0.0%
Architect
C.4.1 Client
Programmer 1 40 40 $0 40% $0 16.0 $0.00 $0.00 24.0 $0.00 $0.00 0.00 0.0%
- Source
C.4.2 Client
Programmer 1 40 40 $0 40% $0 16.0 $0.00 $0.00 24.0 $0.00 $0.00 0.00 0.0%
- Target
T.1.2
Remote 4 1 4 $3,600 40% $900 1.6 $1,440.00$927.00 2.4 $2,224.80 $3,664.80 64.80 1.8%
Flight
T.2.2
Remote
4 3 12 $1,200 40% $100 4.8 $480.00$103.00 7.2 $741.60 $1,221.60 21.60 1.8%
Resource
Onsite A
F.2.3 Conf
1 16 16 $1,600 40% $100 6.4 $640.00$103.00 9.6 $988.80 $1,628.80 28.80 1.8%
Room M
F.3.1 Deli
2 12 24 $192 40% $8 9.6 $76.80 $8.24 14.4 $118.66 $195.46 3.46 1.8%
Lunch
2.3.4 Pre-
Authorized P.3.2 BA -
1 40 40 $6,600 43% $165 17.2 $2,838.00$176.55 22.8 $4,025.34 $6,863.34 263.34 4.0%
Transaction Banking
File Specs
P.3.1 BA
Lead - 1 6 6 $1,110 43% $185 2.6 $477.30$197.95 3.4 $676.99 $1,154.29 44.29 4.0%
Banking
P.1.4
Conversion 1 12 12 $2,220 43% $185 5.2 $954.60$205.35 6.8 $1,404.59 $2,359.19 139.19 6.3%
PM
P.5.1
Conversion 1 4 4 $740 43% $185 1.7 $318.20$183.15 2.3 $417.58 $735.78 (4.22) -0.6%
Architect
P.5.5
Programmer
1 30 30 $4,950 43% $165 12.9 $2,128.50$163.35 17.1 $2,793.29 $4,921.79 (28.22) -0.6%
- Host
Cobol
C.3.1 Client
1 40 40 $0 43% $0 17.2 $0.00 $0.00 22.8 $0.00 $0.00 0.00 0.0%
BA
C.1.1 Client
1 6 6 $0 43% $0 2.6 $0.00 $0.00 3.4 $0.00 $0.00 0.00 0.0%
PM
C.2.1 Client
1 12 12 $0 43% $0 5.2 $0.00 $0.00 6.8 $0.00 $0.00 0.00 0.0%
Architect
C.4.1 Client
Programmer 1 30 30 $0 43% $0 12.9 $0.00 $0.00 17.1 $0.00 $0.00 0.00 0.0%
- Source
Completed at Status
Original Plan Remaining at New Cost Rates
Date (original rates)
Tot Units
Duration
Intensity
Tot Units Extended Budget Budget
WBS Comp Unit Units Tot Cost Unit Tot Cost
Resource Cost To Cost Change Incr
Element (%) Cost Done (BCWP) Cost (BAC)
(BAC) Go (ETC) ($) (%)
C.4.2 Client
Programmer 1 30 30 $0 43% $0 12.9 $0.00 $0.00 17.1 $0.00 $0.00 0.00 0.0%
- Target
T.1.2
Remote 4 1 4 $3,600 43% $900 1.7 $1,548.00$927.00 2.3 $2,113.56 $3,661.56 61.56 1.7%
Flight
T.2.2
Remote
4 3 12 $1,200 43% $100 5.2 $516.00$103.00 6.8 $704.52 $1,220.52 20.52 1.7%
Resource
Onsite A
F.2.3 Conf
1 16 16 $1,600 43% $100 6.9 $688.00$103.00 9.1 $939.36 $1,627.36 27.36 1.7%
Room M
F.3.1 Deli
2 12 24 $192 43% $8 10.3 $82.56 $8.24 13.7 $112.72 $195.28 3.28 1.7%
Lunch
2.3.5
Used/Unused P.3.2 BA -
4 8 32 $5,280 40% $165 12.8 $2,112.00$176.55 19.2 $3,389.76 $5,501.76 221.76 4.2%
Source Field Banking
Report
P.3.1 BA
Lead - 1 8 8 $1,480 40% $185 3.2 $592.00$197.95 4.8 $950.16 $1,542.16 62.16 4.2%
Banking
P.1.4
Conversion 1 8 8 $1,480 40% $185 3.2 $592.00$205.35 4.8 $985.68 $1,577.68 97.68 6.6%
PM
P.5.1
Conversion 1 16 16 $2,960 40% $185 6.4 $1,184.00$183.15 9.6 $1,758.24 $2,942.24 (17.76) -0.6%
Architect
P.5.5
Programmer
4 2 8 $1,320 40% $165 3.2 $528.00$163.35 4.8 $784.08 $1,312.08 (7.92) -0.6%
- Host
Cobol
C.3.1 Client
1 24 24 $0 40% $0 9.6 $0.00 $0.00 14.4 $0.00 $0.00 0.00 0.0%
BA
C.1.1 Client
1 4 4 $0 40% $0 1.6 $0.00 $0.00 2.4 $0.00 $0.00 0.00 0.0%
PM
C.2.1 Client
1 8 8 $0 40% $0 3.2 $0.00 $0.00 4.8 $0.00 $0.00 0.00 0.0%
Architect
C.4.1 Client
Programmer 1 8 8 $0 40% $0 3.2 $0.00 $0.00 4.8 $0.00 $0.00 0.00 0.0%
- Source
C.4.2 Client
Programmer 1 8 8 $0 40% $0 3.2 $0.00 $0.00 4.8 $0.00 $0.00 0.00 0.0%
- Target
2.4.1
Customer
Information P.3.2 BA -
1 16 16 $2,640 40% $165 6.4 $1,056.00$176.55 9.6 $1,694.88 $2,750.88 110.88 4.2%
File Banking
Balancing
Design
P.3.1 BA
Lead - 1 4 4 $740 40% $185 1.6 $296.00$197.95 2.4 $475.08 $771.08 31.08 4.2%
Banking
Completed at Status
Original Plan Remaining at New Cost Rates
Date (original rates)
Tot Units
Duration
Intensity
Tot Units Extended Budget Budget
WBS Comp Unit Units Tot Cost Unit Tot Cost
Resource Cost To Cost Change Incr
Element (%) Cost Done (BCWP) Cost (BAC)
(BAC) Go (ETC) ($) (%)
P.5.1
Conversion 1 4 4 $740 40% $185 1.6 $296.00$183.15 2.4 $439.56 $735.56 (4.44) -0.6%
Architect
P.5.5
Programmer
1 4 4 $660 40% $165 1.6 $264.00$163.35 2.4 $392.04 $656.04 (3.96) -0.6%
- Host
Cobol
C.3.1 Client
1 8 8 $0 40% $0 3.2 $0.00 $0.00 4.8 $0.00 $0.00 0.00 0.0%
BA
C.2.1 Client
1 4 4 $0 40% $0 1.6 $0.00 $0.00 2.4 $0.00 $0.00 0.00 0.0%
Architect
C.4.1 Client
Programmer 1 4 4 $0 40% $0 1.6 $0.00 $0.00 2.4 $0.00 $0.00 0.00 0.0%
- Source
C.4.2 Client
Programmer 1 4 4 $0 40% $0 1.6 $0.00 $0.00 2.4 $0.00 $0.00 0.00 0.0%
- Target
2.4.2
Account File P.3.2 BA -
1 16 16 $2,640 40% $165 6.4 $1,056.00$176.55 9.6 $1,694.88 $2,750.88 110.88 4.2%
Balancing Banking
Design
P.3.1 BA
Lead - 1 4 4 $740 40% $185 1.6 $296.00$197.95 2.4 $475.08 $771.08 31.08 4.2%
Banking
P.5.1
Conversion 1 4 4 $740 40% $185 1.6 $296.00$183.15 2.4 $439.56 $735.56 (4.44) -0.6%
Architect
P.5.5
Programmer
1 4 4 $660 40% $165 1.6 $264.00$163.35 2.4 $392.04 $656.04 (3.96) -0.6%
- Host
Cobol
C.3.1 Client
1 8 8 $0 40% $0 3.2 $0.00 $0.00 4.8 $0.00 $0.00 0.00 0.0%
BA
C.2.1 Client
1 4 4 $0 40% $0 1.6 $0.00 $0.00 2.4 $0.00 $0.00 0.00 0.0%
Architect
C.4.1 Client
Programmer 1 4 4 $0 40% $0 1.6 $0.00 $0.00 2.4 $0.00 $0.00 0.00 0.0%
- Source
C.4.2 Client
Programmer 1 4 4 $0 40% $0 1.6 $0.00 $0.00 2.4 $0.00 $0.00 0.00 0.0%
- Target
2.4.3
Account
P.3.2 BA -
History File 1 16 16 $2,640 40% $165 6.4 $1,056.00$176.55 9.6 $1,694.88 $2,750.88 110.88 4.2%
Banking
Balancing
Design
P.3.1 BA
Lead - 1 4 4 $740 40% $185 1.6 $296.00$197.95 2.4 $475.08 $771.08 31.08 4.2%
Banking
P.5.1
Conversion 1 4 4 $740 40% $185 1.6 $296.00$183.15 2.4 $439.56 $735.56 (4.44) -0.6%
Architect
Completed at Status
Original Plan Remaining at New Cost Rates
Date (original rates)
Tot Units
Duration
Intensity
Tot Units Extended Budget Budget
WBS Comp Unit Units Tot Cost Unit Tot Cost
Resource Cost To Cost Change Incr
Element (%) Cost Done (BCWP) Cost (BAC)
(BAC) Go (ETC) ($) (%)
P.5.5
Programmer
1 4 4 $660 40% $165 1.6 $264.00$163.35 2.4 $392.04 $656.04 (3.96) -0.6%
- Host
Cobol
C.3.1 Client
1 8 8 $0 40% $0 3.2 $0.00 $0.00 4.8 $0.00 $0.00 0.00 0.0%
BA
C.2.1 Client
1 4 4 $0 40% $0 1.6 $0.00 $0.00 2.4 $0.00 $0.00 0.00 0.0%
Architect
C.4.1 Client
Programmer 1 4 4 $0 40% $0 1.6 $0.00 $0.00 2.4 $0.00 $0.00 0.00 0.0%
- Source
C.4.2 Client
Programmer 1 4 4 $0 40% $0 1.6 $0.00 $0.00 2.4 $0.00 $0.00 0.00 0.0%
- Target
2.4.4 Pre-
Authorized
Transaction P.3.2 BA -
1 8 8 $1,320 43% $165 3.4 $567.60$176.55 4.6 $805.07 $1,372.67 52.67 4.0%
File Banking
Balancing
Design
P.3.1 BA
Lead - 1 2 2 $370 43% $185 0.9 $159.10$197.95 1.1 $225.66 $384.76 14.76 4.0%
Banking
P.5.1
Conversion 1 2 2 $370 43% $185 0.9 $159.10$183.15 1.1 $208.79 $367.89 (2.11) -0.6%
Architect
P.5.5
Programmer
1 2 2 $330 43% $165 0.9 $141.90$163.35 1.1 $186.22 $328.12 (1.88) -0.6%
- Host
Cobol
C.3.1 Client
1 4 4 $0 43% $0 1.7 $0.00 $0.00 2.3 $0.00 $0.00 0.00 0.0%
BA
C.2.1 Client
1 2 2 $0 43% $0 0.9 $0.00 $0.00 1.1 $0.00 $0.00 0.00 0.0%
Architect
C.4.1 Client
Programmer 1 2 2 $0 43% $0 0.9 $0.00 $0.00 1.1 $0.00 $0.00 0.00 0.0%
- Source
C.4.2 Client
Programmer 1 2 2 $0 43% $0 0.9 $0.00 $0.00 1.1 $0.00 $0.00 0.00 0.0%
- Target
3.1.1
Customer
P.3.2 BA -
Information 1 40 40 $6,600 40% $165 16.0 $2,640.00$176.55 24.0 $4,237.20 $6,877.20 277.20 4.2%
Banking
File
Application
P.3.1 BA
Lead - 1 6 6 $1,110 40% $185 2.4 $444.00$197.95 3.6 $712.62 $1,156.62 46.62 4.2%
Banking
P.5.5
Programmer
1 60 60 $9,900 40% $165 24.0 $3,960.00$163.35 36.0 $5,880.60 $9,840.60 (59.40) -0.6%
- Host
Cobol
C.3.1 Client 1 8 8 $0 40% $0 3.2 $0.00 $0.00 4.8 $0.00 $0.00 0.00 0.0%
Completed at Status
Original Plan Remaining at New Cost Rates
Date (original rates)
Tot Units
Duration
Intensity
Tot Units Extended Budget Budget
WBS Comp Unit Units Tot Cost Unit Tot Cost
Resource Cost To Cost Change Incr
Element (%) Cost Done (BCWP) Cost (BAC)
(BAC) Go (ETC) ($) (%)
BA
C.4.1 Client
Programmer 1 4 4 $0 40% $0 1.6 $0.00 $0.00 2.4 $0.00 $0.00 0.00 0.0%
- Source
3.1.2
P.3.2 BA -
Account File 1 40 40 $6,600 30% $165 12.0 $1,980.00$176.55 28.0 $4,943.40 $6,923.40 323.40 4.9%
Banking
Application
P.3.1 BA
Lead - 1 6 6 $1,110 30% $185 1.8 $333.00$197.95 4.2 $831.39 $1,164.39 54.39 4.9%
Banking
P.5.5
Programmer
1 60 60 $9,900 30% $165 18.0 $2,970.00$163.35 42.0 $6,860.70 $9,830.70 (69.30) -0.7%
- Host
Cobol
C.3.1 Client
1 8 8 $0 30% $0 2.4 $0.00 $0.00 5.6 $0.00 $0.00 0.00 0.0%
BA
C.4.1 Client
Programmer 1 4 4 $0 30% $0 1.2 $0.00 $0.00 2.8 $0.00 $0.00 0.00 0.0%
- Source
3.1.3
Account P.3.2 BA -
1 40 40 $6,600 30% $165 12.0 $1,980.00$176.55 28.0 $4,943.40 $6,923.40 323.40 4.9%
History File Banking
Application
P.3.1 BA
Lead - 1 6 6 $1,110 30% $185 1.8 $333.00$197.95 4.2 $831.39 $1,164.39 54.39 4.9%
Banking
P.5.5
Programmer
1 60 60 $9,900 30% $165 18.0 $2,970.00$163.35 42.0 $6,860.70 $9,830.70 (69.30) -0.7%
- Host
Cobol
C.3.1 Client
1 8 8 $0 30% $0 2.4 $0.00 $0.00 5.6 $0.00 $0.00 0.00 0.0%
BA
C.4.1 Client
Programmer 1 4 4 $0 30% $0 1.2 $0.00 $0.00 2.8 $0.00 $0.00 0.00 0.0%
- Source
3.1.4 Pre-
Authorized
P.3.2 BA -
Transaction 1 25 25 $4,125 40% $165 10.0 $1,650.00$176.55 15.0 $2,648.25 $4,298.25 173.25 4.2%
Banking
File
Application
P.3.1 BA
Lead - 1 4 4 $740 40% $185 1.6 $296.00$197.95 2.4 $475.08 $771.08 31.08 4.2%
Banking
P.5.5
Programmer
1 40 40 $6,600 40% $165 16.0 $2,640.00$163.35 24.0 $3,920.40 $6,560.40 (39.60) -0.6%
- Host
Cobol
C.3.1 Client
1 6 6 $0 40% $0 2.4 $0.00 $0.00 3.6 $0.00 $0.00 0.00 0.0%
BA
C.4.1 Client
Programmer 1 3 3 $0 40% $0 1.2 $0.00 $0.00 1.8 $0.00 $0.00 0.00 0.0%
- Source
Completed at Status
Original Plan Remaining at New Cost Rates
Date (original rates)
Tot Units
Duration
Intensity
Tot Units Extended Budget Budget
WBS Comp Unit Units Tot Cost Unit Tot Cost
Resource Cost To Cost Change Incr
Element (%) Cost Done (BCWP) Cost (BAC)
(BAC) Go (ETC) ($) (%)
3.2.1
Customer
P.3.2 BA -
Information 1 16 16 $2,640 30% $165 4.8 $792.00$176.55 11.2 $1,977.36 $2,769.36 129.36 4.9%
Banking
File
Application
P.5.5
Programmer
1 10 10 $1,650 30% $165 3.0 $495.00$163.35 7.0 $1,143.45 $1,638.45 (11.55) -0.7%
- Host
Cobol
C.3.1 Client
1 4 4 $0 30% $0 1.2 $0.00 $0.00 2.8 $0.00 $0.00 0.00 0.0%
BA
3.2.2
P.3.2 BA -
Account File 1 16 16 $2,640 30% $165 4.8 $792.00$176.55 11.2 $1,977.36 $2,769.36 129.36 4.9%
Banking
Application
P.5.5
Programmer
1 10 10 $1,650 30% $165 3.0 $495.00$163.35 7.0 $1,143.45 $1,638.45 (11.55) -0.7%
- Host
Cobol
C.3.1 Client
1 4 4 $0 30% $0 1.2 $0.00 $0.00 2.8 $0.00 $0.00 0.00 0.0%
BA
3.2.3
Account P.3.2 BA -
1 16 16 $2,640 30% $165 4.8 $792.00$176.55 11.2 $1,977.36 $2,769.36 129.36 4.9%
History File Banking
Application
P.5.5
Programmer
1 10 10 $1,650 30% $165 3.0 $495.00$163.35 7.0 $1,143.45 $1,638.45 (11.55) -0.7%
- Host
Cobol
C.3.1 Client
1 4 4 $0 30% $0 1.2 $0.00 $0.00 2.8 $0.00 $0.00 0.00 0.0%
BA
3.2.4 Pre-
Authorized
P.3.2 BA -
Transaction 1 12 12 $1,980 40% $165 4.8 $792.00$176.55 7.2 $1,271.16 $2,063.16 83.16 4.2%
Banking
File
Application
P.5.5
Programmer
1 8 8 $1,320 40% $165 3.2 $528.00$163.35 4.8 $784.08 $1,312.08 (7.92) -0.6%
- Host
Cobol
C.3.1 Client
1 2 2 $0 40% $0 0.8 $0.00 $0.00 1.2 $0.00 $0.00 0.00 0.0%
BA
3.3.1
Customer
P.3.2 BA -
Information 1 4 4 $660 30% $165 1.2 $198.00$176.55 2.8 $494.34 $692.34 32.34 4.9%
Banking
File
Application
P.5.5
Programmer
1 12 12 $1,980 30% $165 3.6 $594.00$163.35 8.4 $1,372.14 $1,966.14 (13.86) -0.7%
- Host
Cobol
C.3.1 Client
1 2 2 $0 30% $0 0.6 $0.00 $0.00 1.4 $0.00 $0.00 0.00 0.0%
BA
Completed at Status
Original Plan Remaining at New Cost Rates
Date (original rates)
Tot Units
Duration
Intensity
Tot Units Extended Budget Budget
WBS Comp Unit Units Tot Cost Unit Tot Cost
Resource Cost To Cost Change Incr
Element (%) Cost Done (BCWP) Cost (BAC)
(BAC) Go (ETC) ($) (%)
3.3.2
P.3.2 BA -
Account File 1 4 4 $660 30% $165 1.2 $198.00$176.55 2.8 $494.34 $692.34 32.34 4.9%
Banking
Application
P.5.5
Programmer
1 12 12 $1,980 30% $165 3.6 $594.00$163.35 8.4 $1,372.14 $1,966.14 (13.86) -0.7%
- Host
Cobol
C.3.1 Client
1 2 2 $0 30% $0 0.6 $0.00 $0.00 1.4 $0.00 $0.00 0.00 0.0%
BA
3.3.3
Account P.3.2 BA -
1 4 4 $660 30% $165 1.2 $198.00$176.55 2.8 $494.34 $692.34 32.34 4.9%
History File Banking
Application
P.5.5
Programmer
1 12 12 $1,980 30% $165 3.6 $594.00$163.35 8.4 $1,372.14 $1,966.14 (13.86) -0.7%
- Host
Cobol
C.3.1 Client
1 2 2 $0 30% $0 0.6 $0.00 $0.00 1.4 $0.00 $0.00 0.00 0.0%
BA
3.3.4 Pre-
Authorized
P.3.2 BA -
Transaction 1 3 3 $495 30% $165 0.9 $148.50$176.55 2.1 $370.76 $519.26 24.26 4.9%
Banking
File
Application
P.5.5
Programmer
1 8 8 $1,320 30% $165 2.4 $396.00$163.35 5.6 $914.76 $1,310.76 (9.24) -0.7%
- Host
Cobol
C.3.1 Client
1 2 2 $0 30% $0 0.6 $0.00 $0.00 1.4 $0.00 $0.00 0.00 0.0%
BA
3.4.1
Customer
P.3.2 BA -
Information 1 4 4 $660 30% $165 1.2 $198.00$176.55 2.8 $494.34 $692.34 32.34 4.9%
Banking
File
Application
P.5.5
Programmer
1 12 12 $1,980 30% $165 3.6 $594.00$163.35 8.4 $1,372.14 $1,966.14 (13.86) -0.7%
- Host
Cobol
C.3.1 Client
1 2 2 $0 30% $0 0.6 $0.00 $0.00 1.4 $0.00 $0.00 0.00 0.0%
BA
3.4.2
P.3.2 BA -
Account File 1 4 4 $660 30% $165 1.2 $198.00$176.55 2.8 $494.34 $692.34 32.34 4.9%
Banking
Application
P.5.5
Programmer
1 12 12 $1,980 30% $165 3.6 $594.00$163.35 8.4 $1,372.14 $1,966.14 (13.86) -0.7%
- Host
Cobol
C.3.1 Client
1 2 2 $0 30% $0 0.6 $0.00 $0.00 1.4 $0.00 $0.00 0.00 0.0%
BA
3.4.3
Account P.3.2 BA -
1 4 4 $660 30% $165 1.2 $198.00$176.55 2.8 $494.34 $692.34 32.34 4.9%
History File Banking
Application
Completed at Status
Original Plan Remaining at New Cost Rates
Date (original rates)
Tot Units
Duration
Intensity
Tot Units Extended Budget Budget
WBS Comp Unit Units Tot Cost Unit Tot Cost
Resource Cost To Cost Change Incr
Element (%) Cost Done (BCWP) Cost (BAC)
(BAC) Go (ETC) ($) (%)
P.5.5
Programmer
1 12 12 $1,980 30% $165 3.6 $594.00$163.35 8.4 $1,372.14 $1,966.14 (13.86) -0.7%
- Host
Cobol
C.3.1 Client
1 2 2 $0 30% $0 0.6 $0.00 $0.00 1.4 $0.00 $0.00 0.00 0.0%
BA
3.4.4 Pre-
Authorized
P.3.2 BA -
Transaction 1 3 3 $495 30% $165 0.9 $148.50$176.55 2.1 $370.76 $519.26 24.26 4.9%
Banking
File
Application
P.5.5
Programmer
1 12 12 $1,980 30% $165 3.6 $594.00$163.35 8.4 $1,372.14 $1,966.14 (13.86) -0.7%
- Host
Cobol
C.3.1 Client
1 2 2 $0 30% $0 0.6 $0.00 $0.00 1.4 $0.00 $0.00 0.00 0.0%
BA
3.5.1
P.3.2 BA -
Balancing 4 12 48 $7,920 40% $165 19.2 $3,168.00$176.55 28.8 $5,084.64 $8,252.64 332.64 4.2%
Banking
Spreadsheet
P.3.1 BA
Lead - 1 12 12 $2,220 40% $185 4.8 $888.00$197.95 7.2 $1,425.24 $2,313.24 93.24 4.2%
Banking
P.5.1
Conversion 1 12 12 $2,220 40% $185 4.8 $888.00$183.15 7.2 $1,318.68 $2,206.68 (13.32) -0.6%
Architect
C.3.1 Client
1 2 2 $0 40% $0 0.8 $0.00 $0.00 1.2 $0.00 $0.00 0.00 0.0%
BA
C.2.1 Client
1 2 2 $0 40% $0 0.8 $0.00 $0.00 1.2 $0.00 $0.00 0.00 0.0%
Architect
3.5.2
P.1.4
Conversion
Conversion 1 10 10 $1,850 40% $185 4.0 $740.00$205.35 6.0 $1,232.10 $1,972.10 122.10 6.6%
Activity
PM
Checklist
P.3.1 BA
Lead - 1 10 10 $1,850 40% $185 4.0 $740.00$197.95 6.0 $1,187.70 $1,927.70 77.70 4.2%
Banking
P.5.1
Conversion 1 12 12 $2,220 40% $185 4.8 $888.00$183.15 7.2 $1,318.68 $2,206.68 (13.32) -0.6%
Architect
C.4.1 Client
4.1 System
Programmer 1 4 4 $0 30% $0 1.2 $0.00 $0.00 2.8 $0.00 $0.00 0.00 0.0%
Test Extract
- Source
P.1.4
Conversion 1 16 16 $2,960 30% $185 4.8 $888.00$205.35 11.2 $2,299.92 $3,187.92 227.92 7.7%
PM
P.5.5
Programmer
4 12 48 $7,920 30% $165 14.4 $2,376.00$163.35 33.6 $5,488.56 $7,864.56 (55.44) -0.7%
- Host
Cobol
P.3.2 BA -
4 12 48 $7,920 30% $165 14.4 $2,376.00$176.55 33.6 $5,932.08 $8,308.08 388.08 4.9%
Banking
Completed at Status
Original Plan Remaining at New Cost Rates
Date (original rates)
Tot Units
Duration
Intensity
Tot Units Extended Budget Budget
WBS Comp Unit Units Tot Cost Unit Tot Cost
Resource Cost To Cost Change Incr
Element (%) Cost Done (BCWP) Cost (BAC)
(BAC) Go (ETC) ($) (%)
D.1.1 Local
Media 1 1 1 $200 30% $200 0.3 $60.00$206.00 0.7 $144.20 $204.20 4.20 2.1%
Delivery
C.4.1 Client
4.2 Dry Run
Programmer 1 4 4 $0 30% $0 1.2 $0.00 $0.00 2.8 $0.00 $0.00 0.00 0.0%
Test Extract
- Source
P.1.4
Conversion 1 16 16 $2,960 30% $185 4.8 $888.00$205.35 11.2 $2,299.92 $3,187.92 227.92 7.7%
PM
P.5.5
Programmer
4 12 48 $7,920 30% $165 14.4 $2,376.00$163.35 33.6 $5,488.56 $7,864.56 (55.44) -0.7%
- Host
Cobol
P.3.2 BA -
4 12 48 $7,920 30% $165 14.4 $2,376.00$176.55 33.6 $5,932.08 $8,308.08 388.08 4.9%
Banking
D.1.1 Local
Media 1 1 1 $200 30% $200 0.3 $60.00$206.00 0.7 $144.20 $204.20 4.20 2.1%
Delivery
4.3 C.4.1 Client
Conversion Programmer 1 4 4 $0 30% $0 1.2 $0.00 $0.00 2.8 $0.00 $0.00 0.00 0.0%
Extract - Source
P.1.4
Conversion 1 16 16 $2,960 30% $185 4.8 $888.00$205.35 11.2 $2,299.92 $3,187.92 227.92 7.7%
PM
P.5.5
Programmer
4 12 48 $7,920 30% $165 14.4 $2,376.00$163.35 33.6 $5,488.56 $7,864.56 (55.44) -0.7%
- Host
Cobol
P.3.2 BA -
4 12 48 $7,920 30% $165 14.4 $2,376.00$176.55 33.6 $5,932.08 $8,308.08 388.08 4.9%
Banking
D.1.1 Local
Media 1 1 1 $200 30% $200 0.3 $60.00$206.00 0.7 $144.20 $204.20 4.20 2.1%
Delivery
5.1 Plan vs. P.1.4
Actuals Conversion 1 16 16 $2,960 30% $185 4.8 $888.00$205.35 11.2 $2,299.92 $3,187.92 227.92 7.7%
Report PM
P.5.1
Conversion 1 8 8 $1,480 30% $185 2.4 $444.00$183.15 5.6 $1,025.64 $1,469.64 (10.36) -0.7%
Architect
5.2 Lessons
P.1.2
Learned 1 4 4 $920 30% $230 1.2 $276.00$255.30 2.8 $714.84 $990.84 70.84 7.7%
Principal
Report
P.1.4
Conversion 1 8 8 $1,480 30% $185 2.4 $444.00$205.35 5.6 $1,149.96 $1,593.96 113.96 7.7%
PM
P.5.1
Conversion 1 8 8 $1,480 30% $185 2.4 $444.00$183.15 5.6 $1,025.64 $1,469.64 (10.36) -0.7%
Architect
P.3.1 BA
Lead - 1 4 4 $740 30% $185 1.2 $222.00$197.95 2.8 $554.26 $776.26 36.26 4.9%
Banking
C.1.1 Client
1 4 4 $0 30% $0 1.2 $0.00 $0.00 2.8 $0.00 $0.00 0.00 0.0%
PM
Completed at Status
Original Plan Remaining at New Cost Rates
Date (original rates)
Tot Units
Duration
Intensity
Tot Units Extended Budget Budget
WBS Comp Unit Units Tot Cost Unit Tot Cost
Resource Cost To Cost Change Incr
Element (%) Cost Done (BCWP) Cost (BAC)
(BAC) Go (ETC) ($) (%)
C.3.1 Client
1 4 4 $0 30% $0 1.2 $0.00 $0.00 2.8 $0.00 $0.00 0.00 0.0%
BA
C.2.1 Client
1 4 4 $0 30% $0 1.2 $0.00 $0.00 2.8 $0.00 $0.00 0.00 0.0%
Architect
Totals --> $493,623 $195,710 $309,451 $505,16111,537.81 2.3%