Professional Documents
Culture Documents
5 kW)
Grid-Connect Model
Owners Manual
Installation, Operation, & Maintenance
Page 2 of 26
1. SAFETY WARNING!
• Electrical shock hazard: The wind generator can produce
high voltages – sometimes more than 400 volts. These
voltage levels can cause serious injury or death. No wires
or electrical connections should be touched or handled
without ensuring that the wind generator has been braked
to a complete stop and the AC power to the inverter and
Voltage Clamp™ (grid-tie controller) is off. After these
steps are taken, approximately five (5) minutes is required
for system voltage to decay to safe levels.
Please Note:
ABUNDANT RENEWABLE ENERGY has made every effort to
ensure that the information presented in this manual is
accurate but assumes no responsibility for any errors or
omissions. Users of this information and ARE products
assume full responsibility and risk.
Page 3 of 26
2. Introduction
This manual contains all necessary information for assembling, operating, and
maintaining the ARE110 (2.5 kW) direct grid-connect wind generator. Please
read it carefully and retain it for future reference.
The ARE110 is ruggedly built. It operates at a relatively low rotational speeds
(low RPM), which – together with a small number of moving parts – ensures a very
long life with little maintenance. Its large swept area, high-efficiency blades and
alternator, and optimized power electronics ensure maximum energy capture from
low and high wind speeds. The simple, upwind side furling system (with gravity
return) protects the machine by reliably swinging the rotor out of winds higher than
11 m/sec (25 mph).
Page 4 of 26
3. Wind Generator Specifications
Configuration Three-blade upwind
Over-Speed Control, Mechanical Side furling with gravity return
Over-Speed Control, Electrical Pulse-width modulated resistor loading
Rated Power 2.5 kW (2500 watts)
Rotor Diameter 3.6 m (11.8 ft)
Swept Area of Blades 10.2 m2 (110 sq. ft.)
Cut-in Wind Speed 2.5 m/s (6 mph)
Start-up Wind Speed 3 m/s (7 mph)
Rated Wind Speed 12 m/s (25 mph)
Blade Quantity, Construction Three (3), molded fiberglass
Blade Rotational Speed 0–340 rpm
Alternator Type/Construction Neodymium permanent magnet
Alternator Electrical Output 3-phase, variable voltage (0 - 410 VAC)
Tower-Top Weight 143 kg (315 lbs.)
Maximum Lateral Thrust 160 Kg (350 lbs.)
Table 1. ARE110 specifications
2000
Power (watts)
ARE110 gen
power curve based
on measured data;
power data above
25 mph based on a
small number of
1000 data points
0
0 5 10 15 20 25 30 35 40
Wind Speed (mph)
Page 5 of 26
A R E 1 1 0 W in d G e n e r a to r s
M o n th ly E n e r g y E s tim a te s
800
600
Energy Production (kWh)
400
200
0
8 10 12 14
A v e r a g e L o c a l W in d S p e e d (m p h )
4. Equipment Supplied
Qty. Item Description
1 Alternator (high-voltage)
3 Bolts (alternator-mount) with star washer – M16-2.0 x 30mm
1 Yaw head with slip rings
4 Bolts (tower-mount) with self-locking nut - M16-2.0 x 70mm
3 Blades
6 Studs, hex (blade-mount) with self-locking nut - M12-1.75
1 Plate (blade-clamping)
1 Nose cone
3 Bolts (nose-cone mount) with washers & lock washers - M6-1.0 x 16mm
1 Tail boom, inner (gusset) with tail hinge pin, tail pin latch, & E-clip retainer
1 Tail boom, outer (sq. tube 1.5" x 92")
1 Bolt (tail boom) - M16-2.0 x 70mm
1 Tail fin (with ARE logo)
3 Bolts (tail fin mount) with (2) washers and self-locking nuts – M14-2.0 x 60mm
1 Tail weight (approx. 3 lbs.)
1 ARE Voltage ClampTM (grid-tie controller)
1 ARE resistor load
1 Inverter - 2500U SMA Windy Boy (2.5 kW)
Table 2. Equipment Supplied with grid-connect ARE110 wind generators
2H Turbulent airflow
H
2H 20 H
Sharp edges create turbulence Turbulent air flow created by obstructions
Figure 4. Turbulence illustrations (courtesy of P. Gipe)
As a general rule, therefore, wind turbines should be mounted at twice the height
of any “bluff body” obstructions. Alternatively, locate the turbine 10 meters (30
feet) plus the blade length above the tallest trees, buildings, or other (non-bluff
body) obstructions within 150 meters (500 feet). The power (P) obtainable from
the wind is proportional the cube of the wind speed (v3), and wind speed increases
with height (H) from the ground. [P α v3 and v α H]. According to this principle, a
26% increase in wind speed from a higher tower will yield a 100% increase in
power from the turbine. A little more money spent on a taller tower harvests the
same power as two (2) machines!
Preference should be given to the prevailing wind direction, but please note that
tall features downwind of the generator can also slow wind flow passing through
the turbine’s blades.
Page 7 of 26
7. Electronics Installation
It is important to install the ARE Voltage ClampTM (grid-tie controller), resistor
load, and Windy Boy inverter prior to installing the wind turbine. This will provide a
control system for the turbine and allow the brake to be used during turbine
installation.
Figure 5. ARE Voltage ClampTM, ARE resistor load, & SMA Windy Boy inverter
Installation Instructions
It is suggested that a piece of 3/4” plywood be mounted to the wall where your
wind turbine electronic equipment will be installed. This will provide a secure
substrate to which to mount equipment. It also provides for adequate flexibility in
mounting the equipment without needing to rely on stud spacing or special wall
anchors.
A. Resistor Load
The resistor load enclosure must be mounted so that the resistors are
horizontal and that the terminal block is in the lower right hand corner. Do not
locate this device near flammable substances or loose cloth. Ensure a
minimum of 12” clearance on all sides of the resistor load enclosure, as air
must be permitted to flow freely through the box.
B. Inverter
Follow the instructions included with the SMA Windy Boy inverter for
mounting procedures and requirements.
CAUTION: The SMA Windy Boy 2500U inverter is heavy (approximately 30
kg / 65 lbs.) and requires proper mounting. Please see SMA installation
instructions.
C. Voltage ClampTM
The ARE Voltage Clamp™ should be mounted on a vertical surface in a dry
location. It should be mounted in suitable location to provide easy access to
the red “STOP” button and so that the enclosure door may be opened fully.
Conduit holes must be sawed or drilled in the bottom of the Voltage Clamp™
(see Figure 6 below).
Page 8 of 26
Figure 6. Suggested drilling/sawing locations on bottom of Voltage Clamp™
See the Wiring Diagram for proper connection and wire sizes. Ensure all
wiring is in accordance with local codes and laws. Wire the Windy Boy to the
“– OUT” and “+ OUT” slots of the Voltage Clamp’s din-rail mounted terminal
block (pictured below in Figure 7)
POLARITY IS IMPORTANT! Wiring the Windy Boy inverter with reverse
polarity will damage the equipment and result in an expensive repair bill. See
your SMA Windy Boy manual for instructions on wiring and operating the
Windy Boy inverter.
Bi-metallic temperature
switch terminal locations
(+TS, -TS)
After all electrical equipment has been installed and all connections made,
press the “STOP” button to ensure that the brake is engaged. Also turn off
the circuit breakers to the inverter and to the Voltage ClampTM. This will
ensure that the equipment will not be energized while the wind turbine is
being installed.
Page 9 of 26
D. Electrical Schematic
Page 10 of 26
Figure 8. ARE110 electrical schematic
NOTE: All wire sizes 12 – 10
AWG, 600V minimum unless
noted otherwise (see Table 3
for run from turbine to
Voltage Clamp)
8. Towers & Rigging
Great care should be taken in the selection and preparation of the wind turbine
tower, as this can be the most difficult and most crucial aspect of a wind energy
equipment installation. Guyed, tilt-up pipe tower kits manufactured by ARE are
specifically designed for the ARE110 and are recommended. ARE assumes no
responsible for assuring the suitability of towers provided by other suppliers. ARE
tilt-up towers can be easily lowered for servicing and do not require climbing.
Consult with ARE for assistance with alternative tower selection and qualification.
Assembly Procedure:
A. Position the Tower
If using an ARE tilt-up tower kit, the top of the lowered tower should be
supported at approximately 1 meter (3 feet) above the ground.
Page 11 of 26
B. Check the Yaw Head Axle
Ensure that the yaw head axle rotates freely within the outer housing (see
Figure 9 below).
NOTE: DO NOT
TIGHTEN THIS NUT.
It is intended to be
loose in order to allow
yaw head rotation.
Four (4) wire connections are made at the yaw head – three (3) for the power
from the generator leads (black) and one (1) for the ground (green).
Page 12 of 26
D. Mount Yaw Head to Tower
Attach the yaw head to the tower top flange using M16-2.0 x 70mm bolts,
washers, and self-locking nuts (provided). Fasteners should be tightened to
163 N-m (120 lb-ft) torque. Ensure that the wires are not pinched between
the top flange and the yaw head mounting flange (see Figure 11 below).
Install M14 bolts so
that bolt heads face
the generator (i.e. bolt
heads face upward on
the erect tower).
Ensure wires
are not pinched
during
assembly.
Figure 11. Mating the tower top to the yaw head flange
It may be
necessary to
remove the yaw
head access
door in order to
fasten all bolts.
Page 13 of 26
F. Wire the Yaw Head Terminal Strip
Connect the alternator lead wires to the terminal strip mounted on the yaw
head access door. Match the label of each wire to labels on the terminal strip
(see Figure 13 below). Alternator power output leads are labeled ‘A’, ‘B’, and
‘C’; lead ‘Z’ is used with ARE’s optional Lightning Protection System and
must also be attached to the terminal strip. The ground stud is used for the
Lightning Protection System. Do not attach any of the generator wires to the
ground stud.
Attach alternator
lead wires to the
terminal block on
the yaw head
access door and
secure wire with
screw and
clamping plate.
Ground Stud –
Do NOT attach
generator wires here
Page 14 of 26
Examine all the slip ring brushes to verify firm contact with the slip rings (see
Figure 15 below). Check to see that brushes can be pulled back from the
rings and return freely. If a brush sticks: Loosen the top nut in quarter-turn
increments until the brush springs back. CAUTION: Do not loosen the top
nut excessively, as this may result in improperly seated brushes.
Adjustment
Nut
Slip Ring
Slip Ring
Brush
Bottom slip
ring to be
used only
for ground
connection
Spacer
Reattach and close the yaw head access door (if removed in prior step).
While closing the access door, make certain that wires are not pinched and
do not interfere with the slip ring mechanisms. Use the M6 bolt to hold the
door in place (as shown in Figure 16 below).
Page 15 of 26
G. Test the Electrical Connections
Manually rotate the turbine blades at a steady rate while another person (at
the tower base junction box) uses a voltmeter to verify consistent AC voltage
readings across the three wires lead wires. This verification will require three
voltage readings: A-B, B-C, A-C). During this step, the lead wires should not
be connected to electronic equipment (Voltage ClampTM / grid-tie controller).
Page 16 of 26
Remove the pin latch plate from the inner tail boom section (see Figure 17
above). Align the two (2) hinge eyes of the inner tail boom section with the
two (2) bronze bushings (inserted in holders on the rear of the yaw head).
Install the tail pivot pin to join the tail to the yaw head (see Figure 18 below).
Notch
Tail Pin
Groove
Align the notch in the hinge pin with the pin latch plate and secure in place.
Apply thread-locking compound and tighten the two M6-1.0 x 16mm bolts
to 10 N-m (7 lb-ft) torque. Install the E-clip retainer into the groove at the
bottom of the hinge pin. Vise grips are a useful tool for the E-clip retainer
installation (see Figure 19 below).
Latch
plate:
Install in
notch
E-clip: Install
in groove.
Figure 19. Close-up views of tail pin latch plate & E-clip retainer installation
Page 17 of 26
Note Figure 20 below for the correct holes to use when mounting the tail fin to
the tail boom. Mount the tail fin to the outer tail boom section (square tube)
with the two (2) inner bolt holes. Use M14-2.0 x 60mm bolts with washers
and self-locking nuts.
Install these
two bolts first
The bolt in this
hole acts as a
“stop” for the
tail weight
[Bolt & tail fin
omitted for
clarity]
Figure 20. Mounting the tail fin Figure 21. Inserting the tail weight
Install the tail weight in the end of the outer tail boom, as shown in Figure 21
(above). Install the last (outermost) bolt to secure the tail fin. The tail weight
will be captured between the two (2) outer bolts (see Figure 21 above).
Tighten the M14 fasteners to 60 N-m (45 lb-ft) torque.
Install the outer tail boom into the inner tail boom, and secure with an M16-2.0
x 60mm bolt and self-locking nut (see Figure 22 below). Tighten the M16
fastener to 80 N-m (60 lb-ft) torque.
Inner tail
boom
M16-2.0 x
60mm bolt with
self-locking nut
Outer tail
boom
Install the three blades onto the blade studs. The studs are equally spaced,
so you may start with any two studs. Orient the blades so that the blue
leading edges will rotate clockwise (CW – see Figure 24 below).
After placing the three (3) blades, install the blade clamping plate over the six
(6) blade studs with the nose cone mounting brackets between the blades
and pointing toward the alternator (see Figure 25 below). Secure the plate
with M12-1.75 self-locking nuts, tightened to 20 N-m (15 lb-ft) of torque.
Page 19 of 26
Nose cone mounting
brackets: locate between
blades and orient pointing
toward the alternator.
Install the nose cone and secure with three (3) M6-1.0 x 16mm bolts, washers
and lock washers (see Figure 26 below).
M6-1.0 x 16mm
bolts, washers,
and lock washers
Rotate the blades slightly about the alternator’s axis to verify that the rotor
can turn freely. Double check all fasteners and electrical connections are
secure.
Ensure that the turbine will not encounter any physical interference prior to
beginning the tower-raising.
IMPORTANT: Ensure that the STOP button on the Voltage ClampTM (grid-tie
controller) is pressed. This will engage the brake and keep the turbine from rotating
during the tower raising. Raise the tower and secure base and/or guy cables.
Ensure that the tower is vertical so that the turbine can properly yaw (turn to face into
the wind).
Page 21 of 26
12. Voltage ClampTM Operation & Faults
Lights
Mode Green Yellow Red Mode / Fault Description Solution / Comments
START UP MODE: The system is
Slow Slow flash: ON for 2 seconds,
Flash
initializing and going through system
OFF for 2 seconds
checks.
WAITING MODE: The generator’s
rectified voltage has reached
Normal Operation
14. Troubleshooting
Symptoms Possible Causes Solutions
Shorted wires or alternator
Turbine fails to turn (or Remove short
windings
turns very slowly) in
Shorted diodes Replace faulty diode(s)
significantly windy
conditions Failed bearings Replace bearings
Foreign body in generator Remove obstruction
Low output Insufficient wind Improve tower location/height
Turbine vibrates
Blades out of balance Check blades for water intrusion
excessively
Turbine fails to swing Tower top not vertical Adjust guy cables
into the wind Yaw bearing worn Replace yaw bearing
Turbine running at high Cables disconnected Fix cables
speed no output Slip Rings Failed Replace Slip Rings
Voltage Clamp RED TM
See “Voltage Clamp Operation & Faults” section above.
light illuminates (solid)
Table 6. Troubleshooting Guide
Page 23 of 26
15. Component List & Drawing
WARRANTY AGREEMENT
In order to validate this Warranty Agreement, the Customer must detach, complete, and return the
ARE Mail-in Warranty Form (page 2 of this Agreement) within one (1) month of installation or seven
(7) months of receipt of warranted ARE products, whichever occurs first.
Abundant Renewable Energy (ARE) warrants that the wind turbines it manufactures will be in good
working order, in accordance with ARE standard specifications, upon delivery to its customers and for
a period of 66 months from the date of delivery or 60 months from the date of installation, whichever
occurs first. During the warranty period ARE will, at its sole discretion, repair, replace, or refund the
purchase price of defective components and assemblies. Repair parts or replacement product may be
new, remanufactured, or refurbished, at the sole discretion of ARE. ARE is not responsible for any
costs associated with the installation, removal, reinstallation, or transportation to ARE (or to an ARE
dealer) of defective ARE products. Return freight to the customer will be provided by ARE. Product or
components returned to ARE, which are not defective or which sustained damage not covered under
this warranty, will be tested and/or repaired at ARE’s standard labor rates. Only warranty claims
submitted to ARE in writing within 15 days of problem origin will be honored.
In the event that any dispute, controversy, or claim between the Parties arising out of or relating to this
Agreement cannot be settled by negotiation or mediation, the parties agree to have the dispute or
claim submitted for private arbitration. Any arbitration is to be conducted in Multnomah or Yamhill
County, Oregon. Judgment upon the award may be entered into the Circuit Court of Multnomah
County.
EXCLUSIONS
This warranty does not cover the following:
• Towers, equipment, materials, or supplies not manufactured or supplied by ARE (Towers
manufactured or sold by ARE are covered by their own separate warranty.)
• ARE equipment which has been improperly installed or modified without approval from ARE
• Damage or loss from winds in excess of 45 m/s (100 mph)
• Lightning damage or other “acts of God”. (The ARE lightning protection package provides its
own individual warranty related to lightning damage to wind generators and related controls)
• Incidental or consequential damages
• Damage to product incurred during shipping
PRODUCT CHANGES
ARE reserves the right to make design changes, improvements, or additions to its products without
obligation to install such changes or improvements in existing products.
Page 25 of 26
ARE Wind Generators
Warranty Agreement Form
______________________________________________________________
______________________________________________________________
______________________________________________________________
Page 26 of 26