The document provides an earthling system checking report for a construction project in the Zubair Oil Field in Iraq. It details the 14 items that were checked to verify the earthling system was installed according to design. It found the system was installed properly with all items checking positive. The document also includes measurements of soil electric resistivity using the Wenner method to test the earthling system performance. It provides details on the test equipment used and calibration dates. The foremen from the contractor and QC inspectors from the contractor and Eni signed off that the earthling system was installed correctly.
The document provides an earthling system checking report for a construction project in the Zubair Oil Field in Iraq. It details the 14 items that were checked to verify the earthling system was installed according to design. It found the system was installed properly with all items checking positive. The document also includes measurements of soil electric resistivity using the Wenner method to test the earthling system performance. It provides details on the test equipment used and calibration dates. The foremen from the contractor and QC inspectors from the contractor and Eni signed off that the earthling system was installed correctly.
The document provides an earthling system checking report for a construction project in the Zubair Oil Field in Iraq. It details the 14 items that were checked to verify the earthling system was installed according to design. It found the system was installed properly with all items checking positive. The document also includes measurements of soil electric resistivity using the Wenner method to test the earthling system performance. It provides details on the test equipment used and calibration dates. The foremen from the contractor and QC inspectors from the contractor and Eni signed off that the earthling system was installed correctly.
Eni Iraq bv 5000008489 ZUBAIR OIL FIELD DEVELOPMENT
CHECK PERFORMED P N N/A
1. Buried conductors and earth rods are located in accordance with the design. 2. Conductors installed without protection are sheathed (yellow/green). 3. The continuity of the protective conductors (PE), equipotential conductors and other conductors which form part of the earthing system has been verified. 4. Conductors rising from the floor or ground are protected by means of a conduit section. 5. Buried joints of conductors are protected against damp with a bitumen or similar compound. 6. Earthing of equipotential connections are provided for machines, panels, equipment, components and structures, including those outside the electrical installation, as anticipated in the design and in accordance with reference codes. 7. Air terminations and down conductors for lightning protection comply with the design. 8. Transformer neutrals are correctly earthed. 9. Earthing of concrete reinforcing bars has been carried out, if required by the design. 10. Terminals and earth bus-bars are correctly installed. 11. Protective conductors (PE) and earthing conductors are correctly fixed and protected. 12. Metal sheaths and cable armouring are earthed. 13. Bus-bar joints or conductor fixing bolts are well tightened. 14. Protection against corrosion has been provided and is complete or made good where necessary. REMARKS: P=POSITIVE N =NEGATIVE N/A =NOT APPLICABLE
MEASUREMENT OF SOIL ELECTRIC RESISTIVITY FOR CATHODIC PROTECTION – WENNER METHOD
Ambient Temperature = Measured Resistance Value (Ohms) with Spacing 5 Meter = Measured Resistance Value (Ohms) with Spacing 7.5 Meter = Measured Resistance Value (Ohms) with Spacing 10 Meter =
Test Equipment – Earth Resistivity Meter
Make – Megger, Model – DET4TCR2 Serial number – 101247729 Calibration Date – 19-06-2017 Next Calibration Due – 18-06-2018 Calibration Certificate number – 1170628-25