Cat "A" - Punch items must be cleared before electrical power energized pre-commissioning activities. For “A” punch items
defective or missing equipment, malfunction and missing document which must be completed prior to the start of commis
Cat "B" - Punch items must be cleared before signing-off each subsystem Mechanical Completion Certification (MCC). For “
delay or affect the applicable commissioning works but must be cleared before signing-off each subsystem MCC.
Cat "C" - Punch items must be cleared before initial products filling.
Cat "D" - Punch items, as per mutually agreed by main contractor, consultant and client, but that must be cleared before Fi
NG PUNCH LIST
Project : JIMT
Equip Spec: General
Punch list completion
CIWE PMC SRC
Date Sign Date Sign Date Sign
Cat "A" - Punch items must be cleared before electrical power energized pre-commissioning activities. For “A” punch items
defective or missing equipment, malfunction and missing document which must be completed prior to the start of commis
Cat "B" - Punch items must be cleared before signing-off each subsystem Mechanical Completion Certification (MCC). For “
delay or affect the applicable commissioning works but must be cleared before signing-off each subsystem MCC.
Cat "C" - Punch items must be cleared before initial products filling.
Cat "D" - Punch items, as per mutually agreed by main contractor, consultant and client, but that must be cleared before Fi
NG PUNCH LIST
Project : JIMT
Equip Spec: Painting
Punch list completion
CIWE PMC SRC
Date Sign Date Sign Date Sign
Cat "A" - Punch items must be cleared before electrical power energized pre-commissioning activities. For “A” punch items
defective or missing equipment, malfunction and missing document which must be completed prior to the start of commis
Cat "B" - Punch items must be cleared before signing-off each subsystem Mechanical Completion Certification (MCC). For “
delay or affect the applicable commissioning works but must be cleared before signing-off each subsystem MCC.
Cat "C" - Punch items must be cleared before initial products filling.
Cat "D" - Punch items, as per mutually agreed by main contractor, consultant and client, but that must be cleared before Fi
NG PUNCH LIST
Project : JIMT
Equip Spec: Process Piping
Punch list completion
CIWE PMC SRC
Date Sign Date Sign Date Sign
Cat "A" - Punch items must be cleared before electrical power energized pre-commissioning activities. For “A” punch items
defective or missing equipment, malfunction and missing document which must be completed prior to the start of commis
Cat "B" - Punch items must be cleared before signing-off each subsystem Mechanical Completion Certification (MCC). For “
delay or affect the applicable commissioning works but must be cleared before signing-off each subsystem MCC.
Cat "C" - Punch items must be cleared before initial products filling.
Cat "D" - Punch items, as per mutually agreed by main contractor, consultant and client, but that must be cleared before Fi
NG PUNCH LIST
Project : JIMT
Equip Spec: PRV
Punch list completion
CIWE PMC SRC
Date Sign Date Sign Date Sign
Cat "A" - Punch items must be cleared before electrical power energized pre-commissioning activities. For “A” punch items
defective or missing equipment, malfunction and missing document which must be completed prior to the start of commis
Cat "B" - Punch items must be cleared before signing-off each subsystem Mechanical Completion Certification (MCC). For “
delay or affect the applicable commissioning works but must be cleared before signing-off each subsystem MCC.
Cat "C" - Punch items must be cleared before initial products filling.
Cat "D" - Punch items, as per mutually agreed by main contractor, consultant and client, but that must be cleared before Fi
NG PUNCH LIST
Project : JIMT
Equip Spec: Electrical
Punch list completion
CIWE PMC SRC
Date Sign Date Sign Date Sign
Cat "A" - Punch items must be cleared before electrical power energized pre-commissioning activities. For “A” punch items
defective or missing equipment, malfunction and missing document which must be completed prior to the start of commis
Cat "B" - Punch items must be cleared before signing-off each subsystem Mechanical Completion Certification (MCC). For “
delay or affect the applicable commissioning works but must be cleared before signing-off each subsystem MCC.
Cat "C" - Punch items must be cleared before initial products filling.
Cat "D" - Punch items, as per mutually agreed by main contractor, consultant and client, but that must be cleared before Fi
NG PUNCH LIST
Project : JIMT
Equip Spec: Instrument
Punch list completion
CIWE PMC SRC
Date Sign Date Sign Date Sign
Cat "A" - Punch items must be cleared before electrical power energized pre-commissioning activities. For “A” punch items
defective or missing equipment, malfunction and missing document which must be completed prior to the start of commis
Cat "B" - Punch items must be cleared before signing-off each subsystem Mechanical Completion Certification (MCC). For “
delay or affect the applicable commissioning works but must be cleared before signing-off each subsystem MCC.
Cat "C" - Punch items must be cleared before initial products filling.
Cat "D" - Punch items, as per mutually agreed by main contractor, consultant and client, but that must be cleared before Fi
NG PUNCH LIST
Project : JIMT
Equip Spec: MOV
Punch list completion
CIWE PMC SRC
Date Sign Date Sign Date Sign
Cat "A" - Punch items must be cleared before electrical power energized pre-commissioning activities. For “A” punch items
defective or missing equipment, malfunction and missing document which must be completed prior to the start of commis
Cat "B" - Punch items must be cleared before signing-off each subsystem Mechanical Completion Certification (MCC). For “
delay or affect the applicable commissioning works but must be cleared before signing-off each subsystem MCC.
Cat "C" - Punch items must be cleared before initial products filling.
Cat "D" - Punch items, as per mutually agreed by main contractor, consultant and client, but that must be cleared before Fi
NG PUNCH LIST
Project : JIMT
Equip Spec: Civil & Structure
Punch list completion
CIWE PMC SRC
Date Sign Date Sign Date Sign
Cat "A" - Punch items must be cleared before electrical power energized pre-commissioning activities. For “A” punch items
defective or missing equipment, malfunction and missing document which must be completed prior to the start of commis
Cat "B" - Punch items must be cleared before signing-off each subsystem Mechanical Completion Certification (MCC). For “
delay or affect the applicable commissioning works but must be cleared before signing-off each subsystem MCC.
Cat "C" - Punch items must be cleared before initial products filling.
Cat "D" - Punch items, as per mutually agreed by main contractor, consultant and client, but that must be cleared before Fi
NG PUNCH LIST
Project : JIMT
Equip Spec: Pumps alignment
Punch list completion
CIWE PMC SRC
Date Sign Date Sign Date Sign
Cat "A" - Punch items must be cleared before electrical power energized pre-commissioning activities. For “A” punch items
defective or missing equipment, malfunction and missing document which must be completed prior to the start of commis
Cat "B" - Punch items must be cleared before signing-off each subsystem Mechanical Completion Certification (MCC). For “
delay or affect the applicable commissioning works but must be cleared before signing-off each subsystem MCC.
Cat "C" - Punch items must be cleared before initial products filling.
Cat "D" - Punch items, as per mutually agreed by main contractor, consultant and client, but that must be cleared before Fi
NG PUNCH LIST
Project : JIMT
Equip Spec: Tank
Punch list completion
CIWE PMC SRC
Date Sign Date Sign Date Sign
Cat "A" - Punch items must be cleared before electrical power energized pre-commissioning activities. For “A” punch items
defective or missing equipment, malfunction and missing document which must be completed prior to the start of commis
Cat "B" - Punch items must be cleared before signing-off each subsystem Mechanical Completion Certification (MCC). For “
delay or affect the applicable commissioning works but must be cleared before signing-off each subsystem MCC.
Cat "C" - Punch items must be cleared before initial products filling.
Cat "D" - Punch items, as per mutually agreed by main contractor, consultant and client, but that must be cleared before Fi
NG PUNCH LIST
Project : JIMT
Equip Spec: Inner floater
Punch list completion
CIWE PMC SRC
Date Sign Date Sign Date Sign
Cat "A" - Punch items must be cleared before electrical power energized pre-commissioning activities. For “A” punch items
defective or missing equipment, malfunction and missing document which must be completed prior to the start of commis
Cat "B" - Punch items must be cleared before signing-off each subsystem Mechanical Completion Certification (MCC). For “
delay or affect the applicable commissioning works but must be cleared before signing-off each subsystem MCC.
Cat "C" - Punch items must be cleared before initial products filling.
Cat "D" - Punch items, as per mutually agreed by main contractor, consultant and client, but that must be cleared before Fi
NG PUNCH LIST
Project : JIMT
Equip Spec: Diffuser
Punch list completion
CIWE PMC SRC
Date Sign Date Sign Date Sign
Cat "A" - Punch items must be cleared before electrical power energized pre-commissioning activities. For “A” punch items
defective or missing equipment, malfunction and missing document which must be completed prior to the start of commis
Cat "B" - Punch items must be cleared before signing-off each subsystem Mechanical Completion Certification (MCC). For “
delay or affect the applicable commissioning works but must be cleared before signing-off each subsystem MCC.
Cat "C" - Punch items must be cleared before initial products filling.
Cat "D" - Punch items, as per mutually agreed by main contractor, consultant and client, but that must be cleared before Fi
NG PUNCH LIST
Project : JIMT
Equip Spec: Electrical
Punch list completion
CIWE PMC SRC
Date Sign Date Sign Date Sign
Cat "A" - Punch items must be cleared before electrical power energized pre-commissioning activities. For “A” punch items
defective or missing equipment, malfunction and missing document which must be completed prior to the start of commis
Cat "B" - Punch items must be cleared before signing-off each subsystem Mechanical Completion Certification (MCC). For “
delay or affect the applicable commissioning works but must be cleared before signing-off each subsystem MCC.
Cat "C" - Punch items must be cleared before initial products filling.
Cat "D" - Punch items, as per mutually agreed by main contractor, consultant and client, but that must be cleared before Fi
NG PUNCH LIST
Project : JIMT
Equip Spec: Instrument
Punch list completion
CIWE PMC SRC
Date Sign Date Sign Date Sign
Cat "A" - Punch items must be cleared before electrical power energized pre-commissioning activities. For “A” punch items
defective or missing equipment, malfunction and missing document which must be completed prior to the start of commis
Cat "B" - Punch items must be cleared before signing-off each subsystem Mechanical Completion Certification (MCC). For “
delay or affect the applicable commissioning works but must be cleared before signing-off each subsystem MCC.
Cat "C" - Punch items must be cleared before initial products filling.
Cat "D" - Punch items, as per mutually agreed by main contractor, consultant and client, but that must be cleared before Fi
NG PUNCH LIST
Project : JIMT
Equip Spec: Civil & structure
Punch list completion
CIWE PMC SRC
Date Sign Date Sign Date Sign
14-May-18 Setting pressure for trv, tag number for all the instrument
3 Daniel B
items shall be provided
Cat "A" - Punch items must be cleared before electrical power energized pre-commissioning activities. For “A” punch items
defective or missing equipment, malfunction and missing document which must be completed prior to the start of commis
Cat "B" - Punch items must be cleared before signing-off each subsystem Mechanical Completion Certification (MCC). For “
delay or affect the applicable commissioning works but must be cleared before signing-off each subsystem MCC.
Cat "C" - Punch items must be cleared before initial products filling.
Cat "D" - Punch items, as per mutually agreed by main contractor, consultant and client, but that must be cleared before Fi
NG PUNCH LIST
Project : JIMT
Equip Spec: Loading Arms
Punch list completion
CIWE PMC SRC
Date Sign Date Sign Date Sign
8 RANDY 24-May-18 PG-005 not installed near piperack to the truck loading bay. A
24-May-18 TRV piping supports are not installed before the filter and
10 RANDY A
coalescer area.
All Tag plate to be cleaned due to paint dropping and rust
11 RANDY 24-May-18 particles. Some tag numbers are not readible. To recheck B
during sign off.
Cat "C" - Punch items must be cleared before initial products filling.
Cat "D" - Punch items, as per mutually agreed by main contractor, consultant and client, but that must be cleared before Fi
NG PUNCH LIST
Project : JIMT
Equip Spec: Filter
Punch list completion
CIWE PMC SRC
Date Sign Date Sign Date Sign
ctivities. For “A” punch items, outstanding items related to damaged,
d prior to the start of commissioning works.
on Certification (MCC). For “B” punch items, outstanding items will not
h subsystem MCC.
4 Daniel/Xi 14-May-18 Seal between pipe and collar across bundwall not complete B
onghui
Daniel/Xi 14-May-18 Color ring and flow arrows to the pipe not complete
5 B
onghui
Daniel/Xi 14-May-18 Spring support installation record to be provided
6 B
onghui
Daniel/Xi 14-May-18 All cap for valve shall be provided
7 B
onghui
Daniel/Xi 14-May-18 All tag number for valve, instrument items shall be provided
8 B
onghui as per P&ID
Daniel/Xi 14-May-18 All 2" S6A/B/C elevation shall be mark for sample nozzle
9 B
onghui
Daniel/Xi 14-May-18 Blind glange for drain valve to be provide
10 B
onghui
Daniel/Xi 14-May-18 Manual inside sample jar shall be remove
11 B
onghui
Daniel/Xi 14-May-18 Sample point from sample jar clash with other pipe
12 B
onghui
Daniel/Xi 14-May-18 Y- tools inside quick flush tanks missing
13 B
onghui
Daniel/Xi 14-May-18 Level gauge for quick flush tanks missing and block the
14 B
onghui walkway
Daniel/Xi 14-May-18 Access stairway for quick flush tank not complete
15 B
onghui
Daniel/Xi 14-May-18 Addition tapping point shall blind and update to P&ID
16 B
onghui
Daniel/Xi 14-May-18 Preservation on Specatacle blind require, surface corrosion
17 B
onghui
Daniel/Xi 14-May-18 10SBV003 spring valve operation manual shall be submitted
18 B
onghui
Daniel/Xi 14-May-18 Cleaning of quick flush tank require
19 onghui B
Cat "A" - Punch items must be cleared before electrical power energized pre-commissioning activities. For “A” punch items
defective or missing equipment, malfunction and missing document which must be completed prior to the start of commis
Cat "B" - Punch items must be cleared before signing-off each subsystem Mechanical Completion Certification (MCC). For “
delay or affect the applicable commissioning works but must be cleared before signing-off each subsystem MCC.
Cat "C" - Punch items must be cleared before initial products filling.
Cat "D" - Punch items, as per mutually agreed by main contractor, consultant and client, but that must be cleared before Fi
NG PUNCH LIST
Project : JIMT
Equip Spec: Piping
Punch list completion
CIWE PMC SRC
Date Sign Date Sign Date Sign
ctivities. For “A” punch items, outstanding items related to damaged,
d prior to the start of commissioning works.
on Certification (MCC). For “B” punch items, outstanding items will not
h subsystem MCC.
Cat "A" - Punch items must be cleared before electrical power energized pre-commissioning activities. For “A” punch items
defective or missing equipment, malfunction and missing document which must be completed prior to the start of commis
Cat "B" - Punch items must be cleared before signing-off each subsystem Mechanical Completion Certification (MCC). For “
delay or affect the applicable commissioning works but must be cleared before signing-off each subsystem MCC.
Cat "C" - Punch items must be cleared before initial products filling.
Cat "D" - Punch items, as per mutually agreed by main contractor, consultant and client, but that must be cleared before Fi
NG PUNCH LIST
Project : JIMT
Equip Spec: Electrical
Punch list completion
CIWE PMC SRC
Date Sign Date Sign Date Sign
Cat "A" - Punch items must be cleared before electrical power energized pre-commissioning activities. For “A” punch items
defective or missing equipment, malfunction and missing document which must be completed prior to the start of commis
Cat "B" - Punch items must be cleared before signing-off each subsystem Mechanical Completion Certification (MCC). For “
delay or affect the applicable commissioning works but must be cleared before signing-off each subsystem MCC.
Cat "C" - Punch items must be cleared before initial products filling.
Cat "D" - Punch items, as per mutually agreed by main contractor, consultant and client, but that must be cleared before Fi
NG PUNCH LIST
Project : JIMT
Equip Spec: Instrument
Punch list completion
CIWE PMC SRC
Date Sign Date Sign Date Sign
Cat "A" - Punch items must be cleared before electrical power energized pre-commissioning activities. For “A” punch items
defective or missing equipment, malfunction and missing document which must be completed prior to the start of commis
Cat "B" - Punch items must be cleared before signing-off each subsystem Mechanical Completion Certification (MCC). For “
delay or affect the applicable commissioning works but must be cleared before signing-off each subsystem MCC.
Cat "C" - Punch items must be cleared before initial products filling.
Cat "D" - Punch items, as per mutually agreed by main contractor, consultant and client, but that must be cleared before Fi
NG PUNCH LIST
Project : JIMT
Equip Spec: Civil Structure
Punch list completion
CIWE PMC SRC
Date Sign Date Sign Date Sign