Issue: Sequence of number (seriel number) is getting changed for PR, RFQ and PO.

Sequence of steps followed:

Step 1:T.code : CJ20N

Create project : clin/16.38

Select WBS Screen under project


Step2: Materials are added in the Network Activity level of the Project WBS

Step3: Services are added in the Network Activity level of the Project WBS Service activity
Step 4: On Saving Service PR is created.

Step5. Click on Activate PR .on the network level and ,material PR is created in CJ20N