Daily Progress Report

As of April 12, 2018


LIST OF PROJECTS

A. BATTERY PROJECTS
1) PBI & RTI STEEL FENCE REPAINTING PROJECT – (On Progress)
2) MCB EMPLOYEE’S LOUNGE – (Waiting for delivery of unserved items)
3) PBI Bridge Repainting – (Complete)
4) PBI Court Floor Repainting – (Complete)

B. SPECIAL PROJECTS
1) AGUS DORMITORY REHABILITATION 2017 PLUMBING WORKS – (wall tile installation still on progress)
2) REPAINTING OF COMMON CR (Dorm1 & 2) – (waiting for advise prior to mobilization)
3) SMIP ILOILO STEEL YARD

C. STORE PROJECTS
1) KFC TANAY – (Pre Fab works already completed waiting for advise prior to delivery on site)
2) KFC SINDALAN – (Pre Fab works already completed including delivery of precast items on site)
3) KFC SAN DIONISIO – (Pre Fab works already completed waiting for advise prior to delivery on site)
4) KFC CAVITE – (Pre Fab works already completed, delivery of precast fence from SMIP to Site still on progress)

D. FABRICATION INVENTORY
1) CHB Fabrication – (On progress)
2) Container Van Inventory (20 & 40 footer)
BATTERY PROJECTS UPDATE
PBI & RTI STEEL FENCE
REPAINTING PROJECT
SITE ACTIVITIES
“no site activity as of to date”
Project Status as of April 12
Other Site Issues & Concerns
1.0 Waiting for pre-mixed paint for RTI Fence
PBI MCB LOCKER EXPANSION &
EMPLOYEE’S LOUNGE
Project Status (Employee’s
Lounge) as of April 12
Additional Works
“Adjustment of lighting fixture opening at
ceiling already done as of today April 5.
Manpower (3carp)”
Site Pictures
Site Pictures
Site Pictures
Site Status (Female Locker
Expansion) as of April 12
Manpower
“No manpower on site”
Site Activity
“No activity on site since April 7”
Site Photos
Site Photos
Site Photos
Site Photos
Site Photos
Site Photos
Site Photos
PBI BRIDGE REPAINTING

Complete
Project Status as of April 12
Manpower
1. Foreman – 1/1
2. Painter – 7/7
Site Status
Site Photos
Site Photos
Site Photos
Site Photos
PBI COURT FLOOR REPAINTING

“Complete”
STORE PROJECTS UPDATE
KFC TANAY
KFC SINDALAN
KFC SAN DIONISIO
KFC CAVITE CITY
Site Photo
(KFC Cavite 3rd Gen.)
Site Photo
(KFC Tanay, Sindalan & San Dionisio
3rd Gen.)
SPECIAL PROJECTS UPDATE
DORM 1 & 2 COMMON CR
PLUMBING REPAIR
Project Status (Dorm 1 & 2) as of
April 12
Iloilo Steel Project
Site Dev’t Status
Site Status
On going spreading of delivered base coarse on
site
Base coarse Inventory (Directly
delivered on site)
1st batch – more or less 18 cubic meter only
2nd batch – more or less 18 cubic meter only
3rd batch – more or less 18 cubic meter only
4th batch – more or less 30 cubic meter only
5th batch – more or less 30 cubic meter only
6th batch – more or less 30 cubic meter only
7th batch – more or less 30 cubic meter only
FABRICATION INVENTORY UPDATE
Precast Fence Fab. Status
Site Activity
1. On going fabrication of precast column, panel & beam for
KFC 3rd Gen.
2. On going fabrication of tobleron post 8’ long for RCA project
CHB Fabrication Inventory as of
April 12
1. CHB # 3” - 940pcs.
2. CHB # 4” - 7035pcs.
3. CHB # 6” Ord. - 3765pcs.
4. CHB # 6” Load Bearing - 310pcs.
5. CHB # 8” - 740pcs.
6. Turf 3-1/2” - 315pcs.
7. Turf 5” - 1840pcs.
8. Diamond 3” - 40pcs.
9. Louver - 900pcs.
CHB Fabrication Inventory as of
April 12
10. Tobleron Post 6’ - 170pcs.
11. Tobleron Post 8’ - 91pcs.
12. Tobleron Post 8’ (RCA Orchids) - 174pcs.
12. RCPipe 18” - 5pcs.
13. RCPipe 24” - 66pcs.
14. RCPipe 30” - 58pcs.
15. RCPipe 36” - 9pcs.
16. RCPipe 42” - 0pcs.
17. RCPipe 48” - 3pcs.
18. L-Block # 4” - 600pcs.
CHB Fabrication Inventory as of
April 12
19. Column Block 12” x 12” - 170pcs.
20. Half CHB 4” - 20pcs.
21. Column L-BLOCK 12” x 12” x 6 - 15pcs.
22. Precast Pipe Duct - 10pcs.
23. Precast Pipe Duct w/ slab - 3pcs.
24. Precast Column 1 - 43pcs.
25. Precast Column 2 - 0pcs.
26. Precast Panel - 347pcs.
27. Precast Beam - 17pcs.
20 & 40 footer CV Inventory
Remaining CV’s as of February 20
1.0 20 footer CV = 10pcs.
2.0 40 footer CV = 3pcs.
20 Footer CV Breakdown
1. Slag Block Fence Balasing Boundary (Genarro Proj.) - 1unit
2. KFC Sto. Tomas - 7units
3. KFC Cabuyao - 8units
4. KFC Solano - 9units
5. KFC Mabalacat - 8units
6. KFC Sta. Cruz, Laguna - 8units
7. KFC Malolos - 7units
8. Qesi (requested by Sir Tim) - 4units
9. Qesi (delivered last February 3, 2018) - 2units
10. Waste Water - 1unit
11. Farm 6 - 1units
12. Central Warehouse - 1units
13. Used as stock Room of PBI Admin Painting Materials - 1unit
14. QSM (Barracks for Electrician) - 1unit
15. Current Stock - 10unit
TOTAL = 69units
40 Footer CV’s
1.0 Motorpool – 2pcs.
2.0 Current Stock of 40 footer – 3pcs.
Total – 5pcs. (3pcs. From BIGHOO)
Thank you!