The ABC Project has initial expenses of Rs. 15 crore for Land and Rs. 20 crore for Plant and Machinery. Spare parts costs are Rs. 5 crore for the first year, Rs. 3 crore for the second year, and Rs. 1 crore for the third year. The project has a 15 year life and will produce a total of 25 million tons of production. Production will start at 1 million tons per year from the second to sixth year. All production will be sold, with 60% going to non-power sector G9 and 40% to non-power sector 11. Annual expenses include Rs. 3 crore for wages, Rs. 0.5 lakh for POL, Rs
The ABC Project has initial expenses of Rs. 15 crore for Land and Rs. 20 crore for Plant and Machinery. Spare parts costs are Rs. 5 crore for the first year, Rs. 3 crore for the second year, and Rs. 1 crore for the third year. The project has a 15 year life and will produce a total of 25 million tons of production. Production will start at 1 million tons per year from the second to sixth year. All production will be sold, with 60% going to non-power sector G9 and 40% to non-power sector 11. Annual expenses include Rs. 3 crore for wages, Rs. 0.5 lakh for POL, Rs
The ABC Project has initial expenses of Rs. 15 crore for Land and Rs. 20 crore for Plant and Machinery. Spare parts costs are Rs. 5 crore for the first year, Rs. 3 crore for the second year, and Rs. 1 crore for the third year. The project has a 15 year life and will produce a total of 25 million tons of production. Production will start at 1 million tons per year from the second to sixth year. All production will be sold, with 60% going to non-power sector G9 and 40% to non-power sector 11. Annual expenses include Rs. 3 crore for wages, Rs. 0.5 lakh for POL, Rs