Control Accounts With Negative Open Commitments And ETCs

Control Account ID And Description Percent Element Unit Actual Open Total ETC EAC
Complete To Date Commitment Commitment

20.EC1.ASU.50 E&C Engineering / Technical Support 0 OTHR 0 45,000 45,000 -3,750 41,250
30.EQP.MC1.01 450kgal Tank (LIN Pumps, Scales, Pre 0 OTHR 0 625,880 625,880 -74,825 551,055
30.EQP.PWA.01 Cooling Water Pump (P-62 A) 0 OTHR 0 68,124 68,124 -4,914 63,210
40.SUB.OTH.55 Site Improvements 100 OTHR 105,415 43,930 149,345 -45,829 103,516
60.DEV.MIC.00 Project development General 81 OTHR 248,457 120,206 368,663 -62,651 306,011