Modernization & Expansion of Bhilai Steel Plant, Bhilai”
[Contract No: DGM/PCC/TK/2017/432 DTD 23.06.2017]
Contractor: M/s Voltas Limited, Thane.
Sl.No. Activity Initiated by Addressed to Copy to Remarks/ Action by
1. Submission of list of Contractor Jt. GM (Bhilai DGM (Proj-Utility Zone) & Project Manager - Executing Zone & Shop (WMD) to furnish the
drawings/ drawings/ Project), MECON, 2 copy + 1 soft copy comments to MECON within 3 days. A copy
documents along with soft Ranchi DGM (WMD) & Project Co-ordinator of list of drawings shall be sent to DGM (Proj-
copy of the drgs. - 1 copy + 1 soft copy PMC) also.
-6 copies + 1 soft GM, MECON, Bhilai- 1 copy + 1 soft copy
copy DGM (P-I, F & QC)- 1 Copy (QAP only)
DGM (Proj-PMC) (*)
DGM I/c (WMD) (*)
GM (Proj- Utility) (*)
2. Comments/ approval of Jt. GM (Bhilai Contractor - 1 copy + DGM (Proj-Utility Zone) & Project Manager - After clearance from MECON, In case
list of drawings/ drawings/ Project), MECON, 1 soft copy 1 copy + 1 soft copy drawings are OK, further, 07 copies to be
documents Ranchi, DGM (WMD) & Project Co-ordinator submitted at MECON, Bhilai addressed to
- 1 copy + 1 soft copy GM (MECON), Bhilai at 1st floor, Ispat
GM, MECON, Bhilai- 1 copy + 1 soft copy Bhawan, Bhilai (CG)- India-490001.
DGM (P-I, F & QC)- 1 Copy (QAP only) If drawings are not OK, Comments will be
DGM (Proj-PMC) (*) forwarded to M/s Voltas Limited, Thane by
DGM I/c (WMD) (*) MECON. M/s Voltas Limited shall follow
DGM I/c (Proj- Utility Zone) (*) sl.no.1 of protocol for submission of revised
drawings.
A copy of approved list of drawings shall be
sent to DGM (Proj-PMC)
3. Submission of certified Contractor Jt. GM (Bhilai Jt. GM (Bhilai Project), MECON, Ranchi - 1 Contractor will submit 07 copies to MECON,
(OK) drawing. Project), MECON, soft copy Ranchi addressed to Jt. GM (Bhilai Project),
Ranchi, GM, MECON, Bhilai- - 1 soft copy MECON, Doranda, Ranchi.
-7 copies MECON, Ranchi will distribute as per note 3.
4. BGs, Insurance Policies, Contractor DGM I/c (P-PCC) TK DGM (F&A-IPM) (*)
Power of Attorney, GM (Proj-Utility)
Custody cum Indemnity DGM (Proj-Utility Zone) & Project Manager
Bond
5. Billing Schedule Contractor DGM I/c (P-PCC) TK DGM (Proj-Utility Zone) & Project Manager PCC-TK will forward to MECON and
(Submission) Jt. GM (Bhilai Project), MECON, Ranchi Executing Zone for their comments. MECON
GM (Proj-Utility) (*) and Executing Zone to give their
recommendations/ comments to PCC-TK
within 7 days.
6. Approved Billing DGM I/c (P-PCC) TK Contractor DGM (Proj-Utility Zone) & Project Manager
Schedule DGM (WMD) & Project Co-ordinator
DGM (Proj-I, F & QC)
DGM (F&A- Proj)
Jt. GM (Bhilai Project), MECON, Ranchi
GM, MECON, Bhilai
GM (Proj-Utility) (*)
7. Correspondence for site Contractor GM (Proj-Utility) DGM (Proj-Utility Zone) & Project Manager Proj- Utility Zone will coordinate with Shop
activities, shut down, DGM I/c (Utilities) (WMD) for Protocol/ Shut Down Jobs. Any
safety, gate pass etc. DGM (WMD) & Project Co-ordinator other issues observed shall be communicated
DGM (Proj-Safety) to zone.
DGM (Proj-PMC)
:2:
1. Contractor shall submit 3 hard copies (and soft copy) of duly filled in inspection calls in the proforma duly filled in and signed along with all enclosures addressed to Jt. GM
(Bhilai Project), MECON, Ranchi and submit 1 hard copy (including soft copy) to DGM (Proj-I, F & QC). Soft copy along with all attachments shall also be sent to DGM (P-
Utility Zone) & Project Manager and DGM(WMD) & Project Co-ordinator. Soft copy to be sent to MECON at following email ID : projsailbsp@meconlimited.co.in;
krpc@meconlimited.co.in; inspranchi@meconlimited.co.in).
2. Inspection call performa is enclosed.
3. After approval of drawings, Contractor shall submit all 10 sets of approved/ KFR drawings to GM (MECON), Bhilai for distribution. MECON, Bhilai shall distribute as per
following schedule : Construction archive – 10 copies