IPPNew Checklist
IPPNew Checklist
A. General Requirements
(3) P10,000.00
C. Technical Qualification
(4) Sworn Statement that each of the Facility complies with and will
continue to comply with the Philippine Grid and Distribution Code
(PGDC) for the duration of the COC (Form No.4);
(5) Sworn Statement that the company and its generating facilities
comply with and will continue to comply with the Wholesale
Electricity Spot Market (WESM) Rules for the duration of the COC,
when applicable (Form No.5);
/conversion/tmp/scratch/393599324.doc 1
(10.3) Technical Description of the Load to be
served (for those in isolated areas and those
serving dedicated loads);
D. Financial Capability
E. Ownership/Control
(18) Complete list of its Board of Directors and Senior Officials down to
the level of Plant Managers;
(19) Types of long term debt and equity instrument, including amount
and proportion to total capitalization;
(20) Sworn Statement that the company complies with and will
continue to comply with the provisions on cross ownership and
market share restrictions under Republic Act No. 9136, its
Implementing Rules and Regulations, and the Guidelines for
Issuance of Certificates of Compliance for Generation
Companies/Facilities for the duration of the COC (Form No.6);
(22) PSE Certificate that they are listed with PSE, if applicable.
/conversion/tmp/scratch/393599324.doc 2
F. Other Requirements
Evaluator’s Comment/Recommendation:
Legend:
Note:
* Only forms/documents with complete entries will be accepted; otherwise it
will be returned to the applicant for re--
submission of forms with complete entries