Daewoo - Contract #4 Tentative Target Schedule for EHV Diversions NCC - Qatar.

EHV Diversion Works


ID Task Name Duration Start Finish Predecessors Resource Names 2018
Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr
1 Al Jaber & Makhlouf (JV) - 132kV Overhead Works(2 Nos of Pylons) 275 days 5/22/18 4/7/19

2 Award of Contract 1 day 5/22/18 5/22/18

3 Mobilization (effective date of contract) 7 days 5/26/18 6/2/18 2FS+2 days

4 Collection of As Built Drawings / Property Documents from JABMAK / Kahramaa 1 day 6/3/18 6/3/18 3

5 Detailed Survey as per Kahramaa Specification 7 days 6/4/18 6/11/18 4

6 Technical Submittal for 132kV to Kahramaa 11 days 6/12/18 6/24/18 5

7 Kahramaa Approvals 15 days 6/25/18 7/11/18 6

8 Environment permit / Excavation permit from JABMAK / Kahramaa 5 days 7/12/18 7/17/18 7

9 Geotechnical Investigation 15 days 7/18/18 8/4/18 8

10 Foundation Design Submisison 15 days 8/5/18 8/21/18 9

11 Kahramaa Approvals 21 days 8/22/18 9/15/18 10

12 Material Procurement 154 days 7/12/18 1/7/19

13 Stubs & Cleats 120 days 7/12/18 11/8/18 7

14 Towers 180 days 7/12/18 1/7/19 7

15 Conductor 150 days 7/12/18 12/8/18 7

16 OPGW & Accessories 180 days 7/12/18 1/7/19 7

17 Electrical Insulators 180 days 7/12/18 1/7/19 7

18 Hardware Fittings 180 days 7/12/18 1/7/19 7

19 Misc. Items 150 days 7/12/18 12/8/18 7

20 Works under Outage - 66kV OHL Works 128 days 11/10/18 4/7/19

21 Stage-1 Shutdown (Circuit by Circuit) 14 days 11/10/18 11/25/18

22 Augur Drilling at 132kV OHL Wakrah 2 - Mesaeed A P/P, Circuit #1 7 days 11/10/18 11/17/18 13,11

23 Augur Drilling at 132kV OHL Wakrah 2 - Mesaeed A P/P, Circuit #2 7 days 11/18/18 11/25/18 22

24 Foundation Works Without Outage 14 days 11/26/18 12/11/18

25 132kV OHL Wakrah 2 - Mesaeed A P/P, Circuit 1&2 - Tower Nos. 2A, 3A & 4A 14 days 11/26/18 12/11/18 23

26 Stage-2 Full Shutdown (both circuits) 100 days 12/12/18 4/7/19

27 Shut down approval Kahramaaqa 20 days 12/12/18 1/3/19 25

28 Installation of New Towers, Stringing of Conductors & OPGW, Removal of Towers, Conductors & OPGW and 53 days 1/8/19 3/10/19 27,14,15,16,17,1
demolition of foundations
29 Testing & Commissioning 2 days 3/11/19 3/12/19 28

30 Kahramaa Inspection 2 days 3/13/19 3/14/19 29

31 Line Energization 1 day 3/16/19 3/16/19 30

32 As built submittal 9 days 3/17/19 3/26/19 31

33 As built Approval 10 days 3/27/19 4/7/19 32

Task Summary External Milestone Manual Task Manual Summary External Tasks Deadline
Project: Daewoo - EHV Relocation Wo
Date: 7/26/18 Split Project Summary Inactive Milestone Duration-only Start-only External Milestone
Milestone External Tasks Inactive Summary Manual Summary Rollup Finish-only Progress

Page 1