You are on page 1of 4

CHECK LIST FOR COMMISSIONING

Fire Protection System

1) Check all hydrant & other valves by opening and closing. Any valve found to be open
shall be closed.

2) Check all clamps, supports and hangers provided for the pipes.

3) All the pump sets shall be run continuously for 30 minutes (with temporary piping back
to tank from the nearest hydrant, using canvas hose pipes).

4) Fire Hydrant System - Pressurise the fire hydrant system by running the jockey pump
and after it attains the shutoff pressure of the pump, then

Open bypass valve and allow the pressure to drop in the system. Check that the jockey pump
cuts-in and cuts-out at the preset pressure. If necessary adjust the pressure switch for the
jockey pump. Close by-pass valve.

Open hydrant valve and allow the water to flow into the fire water tank in order to avoid
wastage of water. The main fire pump shall cut-in at the preset pressure and shall not cutout
automatically on reaching the normal line pressure. The main fire pump shall stop only by
manual push button. However the jockey pump shall cut-out as soon as the main pump starts,.

Operate booster pump continuously for 30 minutes with piping back to underground tanks from
the hydrant nearest to plant room.

Check each landing valve, male and female couplings and branch pipes, for compatibility with
each other. Any fitting which is found to be incompatible and do not fit into the other properly
shall be replaced by the Contractor. Each landing valve shall also be checked by opening and
closing under pressure.

Check air cushion tanks on the terrace for proper functioning.

Sprinkler System

Close the floor isolation valve (fitted with tamper switch) and check for annunciation in Fire
Panel in control room / BMS. Also check in Fire panel in control room / BMS, whether the flow
switch indication is registered for the particular floor / zone with test drain open.
Sr. Pump Start Start Shut 1 1 2 2 Motor LPM Design Remarks
No. Time Manual Off Cut - Off Cut – In Cut off Cut – In Amps at Cut- Head
/ Auto Press Pressure Pressure Pressure Pressure & In
Volts press
(As
per
Curve)
1 Jockey Pump - #1 Water piped back to
Tank / water let into
2 Jockey Pump - #2 storm water drain

Sr. Pump Start Cut – In Shut Off Shut Pressure Amps Pressure Amps Pressure Amps Design Pressure Remarks
No. Auto / Pressure Pressure Off with 1 with 1 with 2 with 2 with 3 with 3 operating at 120%
Manual (Start) Amps Hydrant Hydrant Hydrant Hydrant Hydrant Hydrant Head design
ON ON ON ON ON ON flow
3 Main Hydrant
Pump

Sr. Pump Start Cut – In Shut Off Shut Pressure Amps Remarks
No. Auto / Pressure Pressure Off with Test
Manual (Start) Amps Drain
Open
4 Main Sprinkler
Pump

Sr. Pump Start Cut – In Shut Off Pump Remarks


No. Auto / Pressure Pressure Stop
Manual (Start) manual
5 Diesel Driven Pump
CHECKLIST FOR COMMISSIONING.

Water Supply, Drainage and Water Treatment Equipment

1) Operate each and every valve on the system to see if the valves are functioning
properly.

2) Check all clamps, support and hangers provided for the pipes.

3) Check rotation of each motor and correct the same if required.

4) All the pumps shall run continuously for one hour. Record the pressure and motor
current and voltage readings.

5) Check all annunciations by simulating the alarm conditions if any at site.

6) Remove grease trap manhole covers. Check for cleanliness, check for partitions, and
put back the cover.

7) Remove manhole covers on sewer lines, inspect for cleanliness. After they are
found to be clean, pour water into the first manhole and see that all the lines are
clear. Make sure that all the covers are put back after the inspection.

8) Check gully traps by opening of covers and check that water seal in the traps are
maintained. Check for general cleanliness.

9) Check installation of proper vents and cowls at the roof level for all soil and waste
pipes.

10) Performance test to be carried out and recorded in the following table for the
pumps.

Sr. Pump Tag No. Model Desig Actual P Full Remark


No. No. n Flow Flow kg/cm2 load s
LPS LPS Amps
1) Domestic Water Hydro-
pneumatic Pump No. 1
2) Domestic Water Hydro-
pneumatic Pump No. 2
3) Domestic Water Hydro-
pneumatic Pump No. 3
4) Filter feed Pump no. 1
5) Filter feed Pump no. 2
6) Softener transfer Pump
no. 1
5) Softener transfer Pump
no. 2

(Similar Readings shall be taken for all other pumps)

11) Simulate low level in the domestic water tanks to trip domestic Filter Feed Pumps.
Simulate high level in treated water tanks to trip softener feed pumps. Simulate
low level in treated water tanks to trip treated water hydro-pneumatic pumps.
Submersible Sump Pumps

1) Fill the sump with water, while observing the level.

2) Keep the pump starter switch on ‘OFF’ position to check for start of pump.

3) By keeping the starter switch on ‘Auto’ position, both the pumps should start. As
the water level starts receeding, one pump should switch off by itself. The second
pump should switch off on further reduction in water level.

4) Fill the sump with a little water and check both the pumps in ‘Manual’ position
momentarily.

5) Leave the switches in ‘Auto’ position for both the pumps.

MGF , ACF AND SOFTENER

- Thoroughly back wash the filters, before putting them on line.


- Operate the filter feed pump and record the pressure at the inlet and outlet ports of
the filters. This will give us the pressure drop across clean filters for record purposes.

Softening Plant

The plant shall be run for 3 regenerations + 3 service cycles to establish output, quality of
treated water.

You might also like