Professional Documents
Culture Documents
CHAPTER – 1
INTRODUCTION
1.1 BACKGROUND
The project road is a part of NH-2 connecting Delhi-Agra-Allahabad-Varanasi-
Aurangabad-Kolkata and is one of the important links of the National Highway network
and also one of the arms of the Golden Quadrilateral. The Project road is the stretch
between Varanasi to Aurangabad, which has been planned for widening to a 6-lane
configuration by National Highways Authority of India (NHAI).
The National Highways Authority of India (NHAI) has been entrusted with the
development, maintenance and management of the National Highways as entrusted to it
by the Government. Under NHDP Phase – V programme, the Government has decided
to convert some of the existing four lane highways into six lane highways. These
projects are to be executed by private entrepreneurs as DBFO projects. (Design – Build
– Finance – Operate)
Keeping the above requirement in mind National Highways Authority of India (NHAI) had
invited Proposals for the preparation of Feasibility from Various Consultants for the
Package No.NHDPV/MC-II/BOT/DPR/11 from Varanasi to Aurangabad ( NH 2)
NHAI has appointed M/s STUP Consultants P Ltd, Vashi as consultants for carrying out
the above mentioned assignments vide their letter/Work Order ref NHAI/Phase – V/MC-
II/BOT/DPR/11/179 dated August 29th, 2007.
The present stretch of National Highway NH-2 considered for six laning starts from Varanasi
(Ch.786.000) and ends at Aurangabad (Ch.978.400). The total length of the section is 192.4
km between the two places mentioned above. The project road in its present condition is a
four lane divided highway from Ch.786.000 to Ch.978.400 and service roads at few
locations in urban sections. Total length is 192.4 km in which 85.2 km (km 862.100 – km
907.100 & km 938.200 – km 978.400) are concrete pavement and remaining 107.2 km are
flexible (bituminous) pavement.
The location map indicating the project road is presented in Figure - 1.1.
The Geotechnical investigation report, Traffic survey report, Benkelman Deflection Test
Analysis, Analysis of Axle load survey data/VDF, Inventory & condition survey for Road &
Bridges, Roughness Survey & Analysis will be included as an Annexure to this report in
separate volume.
CHAPTER 2
SOCIO ECONOMIC PROFILE
2.1 General
Within the context of Socio- economic analysis, the “broad” and “immediate” influence
areas of the project road are delineated; distinguishing the areas directly served by the
project road. The broad influence area of the project road, being part of NH-2 traversing
over 1490 km in length, extends to a large part of India particularly the North Eastern
India comprising States of Delhi, Haryana, Uttar Pradesh, extending in the East to States
of Bihar, Jharkhand and West Bengal. The length of NH-2 in the state of Uttar Pradesh is
756 Km which shows that about 50% of this highway is traversing in this state passing
through the major cities Agra, Kanpur, Allahabad, and Varanasi. The length of NH-2 in
the State of Bihar is 202 Km. Also this NH-2 is passing through the major industrial
centers of all these states. All these States contribute traffic to the project road section in
varied proportion. It is observed that over 80 percent of the vehicular traffic on the
project corridor originates or terminates in these States. Therefore, the Socio-economic
analysis of the broad influence area is majorly confined to the states of Uttar Pradesh
and Bihar.
Uttar Pradesh and Bihar states, for administrative purpose, have been divided into 70
and 37 districts respectively. The project road Section transverse through five districts
Varanasi and Chandauli in Uttar Pradesh, Bhabua, Rothas and Aurangabad in Bihar.
These districts thus form an immediate influence area of the Project Road. This
influence area is termed as Project influence Area (PIA). This chapter deals with Socio –
economic profile of the immediate PIA.
The demographic features of the state of Uttar Pradesh and for two districts of Uttar
Pradesh State forming an immediate influence area (PIA) are presented in
Table - 2.3(a). The districts forming the PIA of the Project account for 1.7 percent of the
State’s total area and 3 percent of its total population.
The total geographical area of Uttar Pradesh is 238566 sq.km, accounting for 7.26
percent of the total geographical area of India. The total population of Uttar Pradesh
State is 166.2 million. The rural population is over 79 percent and urban population
around 21 percent. The average density in the state is 783 persons per sq. km. The
average annual growth rate of population during 1991 -2001 has been 2.58 percent as
against 2.56 percent between 1981 -91.
In the PIA, Varanasi and Chandauli districts, the total population is around 3.13 and 1.64
million respectively. The average density of population in Varanasi and Chandauli is
1995 and 660 person per sq.km respectively. Urban population in Varanasi is over 36.71
percent while in Chandauli it is 10.56 percent. These districts have the highest density of
population which gives the lowest per capita land. Uttar Pradesh attracts a large number
of both national and international visitors. There are two regions in the state where a
majority of the tourists go. These are the city of Agra, the holy cities: the cities of
Varanasi, Ayodhya, Mathura and Allahabad, by the sacred rivers — the Ganga and the
Yamuna are all located in the state. The state hosts a Kumbha Mela every 12 years,
where over 10 million Hindus congregate — the largest gathering of human beings in the
world. Varanasi is widely considered to be the second oldest city in the world after
Jerusalem. It is famous for its ghats (steps along the river) which are populated year
round with people who want to take a dip in the holy Ganges River.The influence area is
thus densely populated with average density at 1995 persons per sq.km. It is also highly
urbanized with over 36.71 percent of the population residing in cities and urban
agglomerations.
The demographic features of the state of Bihar and for three districts of Bihar State
forming an immediate influence area (PIA) are presented in Table - 2.3(b). The districts
forming the PIA of the Project account for 11 percent of the State’s total area and 6.8
percent of its total population.
The total geographical area of Bihar is 94,164 sq-km, accounting for 2.86 % of the total
geographical area of India. The total population of Uttar Pradesh State is 82.9 million.
The rural population is over 89.53 % and urban population around 10.47 %. The average
density in the state is 880 persons per sq. km. The average annual growth rate of
population during 1991 -2001 has been 2.33 percent as against 2.84 percent between
1981 -91.
In the PIA, Kaimur, Rohtas & Aurangabad districts, the total population is around 1.28,
2.44 & 2.0 million respectively. The average density of population in Kaimur, Rohtas &
Aurangabad districts is 382, 635 and 607 person per sq.km respectively. Urban
population in Kaimur is over 3.2% while in Chandauli it is 13.33% & in Aurangabad it is
7.7%. These districts have the highest density of population which gives the lowest per
capita land.
The employment patterns for UP state (Varanasi and Chandauli districts) are shown in
table - 2.4(a).
As per 2001 Census, the total workforce in UP State is 53.9 million comprising 39.3
million main workers and 14.6 million marginal workers. The work participation rate
(percentage of main work force to total population) as per 2001 census, in Uttar Pradesh
State is 32.5 as against 39.1 percent in India as a whole.
In the PIA district Varanasi 51 percent of the main workforce is engaged in agricultural
activities and nearly 34 percent in the service sector. The household industry workers
account for 14.5 percent.
The data of the district Chandauli is not readily available and thus it is not reported in this
study
The employment patterns for Bihar state (Kaimur, Rohtas & Aurangabad districts) are
shown in table - 2.4(b)
As per 2001 Census, the total workforce in Bihar State is 27.9 million comprising 21.1
million main workers and 6.9 million marginal workers. The work participation rate
(percentage of main work force to total population) as per 2001 census, in Bihar State is
33.9 as against 39.1 percent in India as a whole.
The data of the PIA districts is not readily available and thus it is not reported in this
study
The NSDP of Uttar Pradesh State, at current prices, has increased from Rs. 709.35
billion to Rs. 1694.79 billion from 1993 -94 to 2002–03 registering an average annual
growth rate of 14.4 percent. The per Capita State income in 1995-96 at current prices for
Uttar Pradesh state was Rs. 11,306 which was higher than the all India average of Rs.
9,321.
The state income for Uttar Pradesh State, at constant prices, during the period 1980-81
to 1995 -96 has increased from 65.5 billion to Rs. 142.1 billion with an average annual
growth rate of 5.3 percent . It is worth mentioning that the national income during the
same period grew at the rate of 5.42 percent. The state per capita income at constant
prices in Uttar Pradesh State in 1995 – 96 was Rs. 3,172, comparatively higher than the
national per capita income of Rs. 2,573.00. The NSDP at constant prices and current
prices for Uttar Pradesh is given in Table - 2.6.
The time series data on Net State Domestic Product by industry of origin at current and
constant prices for Uttar Pradesh is presented in tables - 2.12(a), and 2.13(a)
respectively.
The share of various economic sectors in NSDP shows a fluctuating trend. In Uttar
Pradesh, the agriculture sector has declined from 34.5 percent in 2002-03 to 34 percent
in 2003-04 and further 33.7 percent in 2004-05. The share of manufacturing sector
increased from 11.1 percent in 2002-03 to 11.4 percent in 2003-04 and further to 11.5
percent in 2004-05. In service sector, the share of transport and communication sector
decreased from 20.5 percent in 2002-03 to 20.0 percent in 2003-04 and remained the
same in 2004-05. Changes in NSDP composition indicate structural change in the
economy as the share of secondary sector had increased and share of primary & tertiary
sector, particularly agriculture declined.
The growth rates in NSDP at constant prices over a period of time are presented in Table
- 2.6. In Uttar Pradesh, the state economy has registered an annual growth rate of 8
percent during 2001-02. In terms of sectoral growth in Uttar Pradesh the share of each
sector i.e. agriculture, manufacturing and tertiary are given in the table - 2.7 for different
years.
The income data for the PIA districts is not readily available and thus it is not reported in
the study.
The NSDP of Bihar State, at current prices, has increased from Rs. 207.8 billion to Rs.
479.7 billion from 1993 -94 to 2002–03 registering an average annual growth rate of 10.4
percent. The per Capita State income in 1995-96 at current prices for Uttar Pradesh
state was Rs. 5683 which was higher than the all India average of Rs. 9,321.
The time series data on Net State Domestic Product by industry of origin at current and
constant prices for Bihar is presented in tables - 2.12(b) and 2.13(b) respectively.
0.6 percent in 2002-03 to 0.7 percent in 2003-04 and further to 0.6 percent in 2004-05.
In service sector, the share of transport and communication sector changed from 20.9
percent in 2002-03 to 20.6 percent in 2003-04 and further to 21.5 in 2004-05. Changes
in NSDP composition indicate structural change in the economy as the share of primary
secondary & tertiary sector have been indicated in Table - 2.7.
The NSDP at constant prices over a period of time are presented in Table - 2.7. In Bihar,
the state economy has registered an annual growth rate of 10 percent during 2001-02. In
terms of sectoral growth in Bihar the share of each sector i.e. agriculture, manufacturing
and tertiary are given in the table - 2.7 for different years.
The income data for the PIA districts is not readily available and thus it is not reported in
the study.
2.5.2.1 Agriculture
According to the land use pattern in Uttar Pradesh, by 2003-04, in the reported
area for landuse about 17.29 percent of lands are covered by forest. The net
area sown is about 58.6 percent while land not available for cultivation and
culturable waste are 11.8 and 3.17 percent respectively.
In Bihar according to land use pattern by 2003-04, in the reported area for
landuse about 17.02 percent of lands are covered by forest. The net area sown is
about 42.34 percent while land not available for cultivation and culturable waste
are 19.56 and 2.04 percent respectively.
The land use pattern of UP & Bihar are shown in the table - 2.8
ii) Irrigation
The inadequate and erratic distribution of rainfall is the risk factor in growth of
agriculture in both the state. Lack of dependable source of irrigation continues to
be the biggest constraint in raising farm output. The areas irrigated by source are
indicated in Table - 2.9(a) & Table - 2.9(b).
In Uttar Pradesh there are three types of irrigation facilities are available e.g.
canal & tank, well and others. However, 57 percent of net area sown is covered
by irrigation facilities.
In Bihar only 47.96 % of the net sown area is covered by irrigation facilities. The
major types of irrigation are canals, tanks, tube wells etc.
In Uttar Pradesh food grains covered 77.3 percent of the Total cropped area.
Total cereals covered 9 percent. Pulses covered around 8 percent of the Total
cropped area. The details are shown in Table - 2.10(a).
In Bihar, the principal agricultural crops are rice, paddy, wheat, jute, maize and oil
seeds. Cauliflower, cabbage, tomato, radish, carrot, beat etc. are some of the
vegetables grown in the state. Sugarcane, potato and barley are some of the
non-cereal crops grown. The entire agricultural operations is divided into two
crop seasons Kharif and Rabi. The Kharif season starts from the third week of
May and lasts till the end of October followed by the Rabi season The area,
production and yield of various major crops are shown in Table - 2.10(b).
2.5.2.2 Forestry
Forest cover has gone down considerably after the formation of Uttaranchal State, the
hilly/forest part of UP earlier. Only 17% of UP’s geographical area is under forest cover
now.
In Bihar, the sub Himalayan foothill of Someshwar and Dun ranges in Champaran
constitute another belt of moist deciduous forests. These also consists of scrub, grass
and reeds. Here the rainfall is above 1,600 mm and thus promotes luxuriant Sal forests
in the favoured areas. The hot and dry summer gives the deduous forests. The most
important trees are Shorea Robusta (Sal), Shisham, Cedrela Toona, Khair, and Semal.
This type of forests also occurs in Saharasa and Purnia districts.
In Bihar, The major minerals present in the state are steatite, Quartzite, pyrites, crude
mica & limestone. The production of these minerals in tones are given under.
2.5.2.4 Industry
There are different types of minerals and several industries have came up based on the
minerals. There are cement plants in the Mirzapur area in the Vindhya region, a bauxite
based aluminium plant in the Banda area and copper in Pithora Garh, Almora Chamboli
and Tehri Garhwal. In the hills a number of minerals are to be found, mainly non-metallic
minerals which are used as industrial raw materials. Coal deposits are found in the
Singrauli area. The industries include a large printing establishment units engaged in
manufacturing of scales, locks, letter boxes, furniture, badges and belts, leather goods,
scissors etc. Handloom, carpet, glass, electrical goods, electro plating, building material
industries are also found in some of the cities.
The information about the industries present in the PIA districts is not readily available
and thus it is not reported in the study
Bihar has a number of major public sector projects like the Oil refinery of Indian Oil
Corporation and Fertilizer manufacturing plant of Hindustan Fertilizer Corporation Ltd
(HPCL) at Barauni, Pyrites, Phosphates and Chemicals Ltd (PPCL) at Amjhor; Cotton
spinning mills at Siwan, Pandaul, Bhagalpur, Mokamah and Gaya; 13 sugar mills in
private sector and 15 in public section located in South and North Bihar. In addition
distilleries at Gopalganj, West Champaran, Bhagalpur and Riga (Sitamarhi District);
finish leather industry in West Champaran, Muzaffarpur and Barauni; Jute mills at
Katihar and Samastipur; Medicine manufacturing unit at Hajipur; Food processing units
and Vanaspati manufacturing units at Aurangabad and Patna; Kalyanpur Cement Ltd at
Banjari are some of the notable industries in Bihar. Bihar has tremendous resources and
their utilisation in the interest of its growing population has to be the supreme
responsibility of both the state administration and the national planners.
The information about the industries present in the PIA districts is not readily available
and thus it is not reported in the study
The long – term economic perspective, in terms of annual growth rates of the NSDP in
real terms, has been studied over at a time horizon of 3 years. The time-trend
analysis of state income showed a annual growth rate of 8 percent in Uttar Pradesh. At
the national level, the planning commission has forecast at the average rate of growth of
GDP (at Current prices) at 14.45 percent per annum during the same year, as against 8
percent growth per annum attained during the year 2001-02.
The full impact of liberalization and privatization is yet to be realized. The future growth
in the economy hinges on the readiness of private sector (domestic and / foreign)
investment in different sectors of the economy, including basic infrastructure essential for
industrial growth and exports. The size of investment and its diversification in
different economic sectors will be a critical factor in determining the future rate of growth
of the economy.
A conservative projection of the most plausible growth rates for Uttar Pradesh based on
the past trend in private investments in different states of India, are shown in the table
below.
The long – term economic perspective, in terms of annual growth rates of the NSDP in
real terms, has been studied over at a time horizon of 3 years. The time-trend
analysis of state income showed an annual growth rate of 10 percent in Bihar. At the
national level, the planning commission has forecast at the average rate of growth of
GDP (at Current prices) at 14.45 percent per annum during the same year, as against 10
percent growth per annum attained during the year 2001-02.
The full impact of liberalization and privatization is yet to be realized. The future growth
in the economy hinges on the readiness of private sector (domestic and / foreign)
investment in different sectors of the economy, including basic infrastructure essential for
industrial growth and exports. The size of investment and its diversification in
different economic sectors will be a critical factor in determining the future rate of growth
of the economy.
A conservative projection of the most plausible growth rates for Bihar based on the past
trend in private investments in different states of India, are shown in the table below.
Period UP Bihar
1990-1995 5.5 4.83
1995-2000 5.3 5.3
2000-2005 5.0 4.49
Table - 2.3(a) : Demographic Features of UP and the PIA Districts, 2001 Census
Sl. State / District Area Total Rural Urban % of Avg.
No. (km2) Popn. Popn. Popn. Urban Density
(million) (million) (million) Popn. (Pop/km2)
1 UP 238566 166.2 131.7 34.5 20.0% 690
2 Varanasi 1550 3.13 1.15 1.98 36.7% 1995
3 Chandauli 2485 1.64 1.5 0.14 8.3% 660
4 All India 3287590 1,028 741.7 285.4 27.8% 313
Source: Census of India 2001,
Table - 2.3(b): Demographic Features of Bihar and the PIA Districts, 2001 Census
Sl. State / District Area Total Popn. Rural Urban % of Avg.
No. (km2) (million) Popn. Popn. Urban Density
(million) (million) Popn. (Pop/km2)
1 Bihar 94,164 82.9 74.5 8.4 10.47% 880
2 Kaimur 3305 1.29 1.24 0.042 3.2% 382
3 Rohtas 3847 2.44 2.12 0.33 13.33% 635
4 Aurangabad 3363 2.00 1.846 0.154 7.7% 607
5 All India 3287590 1,028 741.7 285.4 27.8% 313
Source: Census of India 2001,
Table - 2.7: Net State Domestic Product Composition by Industry of Origin at Constant Prices (2002-2003)
Sl. Industry UP Bihar All India
No. 2002- 2003- 2004- 2002- 2003- 2004- 2001- 2002- 2003-
03 04 05 03 04 05 01 03 04
1 Primary 36.1 36.3 35.3 46.8 42.2 44.0 25.8 22.8 23.3
Agriculture 34.5 34.7 33.7 43.3 38.3 40.5 23.6 20.7 21.2
2 Secondary 13.1 13.1 13.3 3.1 3.4 2.9 17.1 18.4 17.8
Manufacturing 11.1 11.4 11.5 0.6 0.7 0.6 14.3 15.3 14.8
3 Tertiary 50.9 50.6 51.4 50.1 54.5 53.1 57.1 58.7 58.9
Transport , 20.5 20.0 20.0 20.9 20.6 21.5 20.7 22.1 22.3
Storage
and
Communication,
trade, hotels and
restaurants
Quick Estimates
.Table - 2.8: Land Use Pattern of UP & Bihar (Area in ‘000 ha)
AREA
(‘000
Source of irrigation ha)
Canals 1011
Tanks 117
Tube-wells 1834
Other Wells 23
Other Sources 535
Total Net Area
irrigated 3519
Table - 2.12(a): Net State Domestic Product of UP by Industrial Origin at Current Prices
Year/Industry 1995-96 1996-97 1997-98 1998-99 1999-00 2000-01 2001-02 2002-03 2003-04 2004-05
Primary 35818.2 43562.4 44419.8 50405.7 54880.8 56193.1 57313.5 61680.5 67638.6 72373.7
Agriculture 35240.5 42850.4 43467.4 48047.7 52575.8 53547.7 55342.8 59024.6 64638.4 69223
Forestry & logging 213 338.1 545.6 1870 1772 2050.8 1316 1925.9 2178.6 2289
Fishing 364.8 374 406.8 488.1 533 594.6 654.8 730 821.6 861.7
Secondary 15886.7 19400.3 19765.9 20167.3 22060.4 19942.5 19616.5 22355.8 24506 27316.6
Mining & quarrying 680.3 773.1 907.9 1198.6 1419.8 1638.2 1729.2 2143.5 1956.5 2019.1
Manufacturing 13127.2 16654.7 16210.9 15266 17271 16607.8 17142.6 19016.3 21171.5 23647.2
Registered 7747.4 11128.4 9257.8 7813.3 9278.9 8662 8459.2 9667.4 10423.3 11393.6
Unregistered 5379.9 5526.3 6953.1 7452.7 7992.2 7945.8 8683.4 9348.9 10748.2 12253.6
Electricity, gas and 2079.2 1972.5 2647.1 3702.7 3369.6 1696.5 744.7 1195.9 1378 1650.3
water supply
Tertiary 41106 49183.4 55939.2 62449.2 67219 74540.5 79923.5 87023.5 94288.8 105558.4
Construction 4425.7 5269.6 6426.3 8018.2 8602.1 9165.7 9601.5 11106 12021.3 13421.3
Transport, storage & 4108.4 4876.8 5543.1 6454.8 7243.9 7537.2 8944.4 10239 10983 12611.8
communication
Trade, hotels and 14584.1 18339.8 20067 20590.2 21204.7 24606.9 24112.2 24796.6 26377.3 28487.9
restaurants
Banking & insurance 3038.1 3945.5 4594.6 4482.2 4970.5 5570 6505.4 7756.1 8595.3 9525.4
Real estate, owner- ship 4674.7 5018.3 5376.3 5988.3 6909.4 8046.3 9383.2 10896.4 12132.7 13409.1
of dwelling and
business services
Public administration 3898.6 4436.6 5665.1 6512.8 7420.8 7685.6 8016.2 8222 9432.4 10982.9
Other services 6376.4 7296.8 8266.7 10402.7 10867.6 11928.9 13360.7 14007.5 14746.8 17120.2
Table - 2.13(a): Net State Domestic Product of UP by Industrial Origin at Constant Prices
Industry/year 1995-96 1996-97 1997-98 1998-99 1999-00 2000-01 2001-02 200203 2003-04 2004-05
Primary 30478.1 33466.8 31588.9 32647.5 35625.8 35205.7 36192.9 36804.0 37841.0 38255.7
Agriculture 29885.3 32721.4 30642.7 30797.7 33700.7 33173.2 34068.5 34580.9 35534.7 35880.4
Forestry & logging 228.3 373.2 556.8 1392.4 1438.3 1500.9 1549.5 1584.7 1624.2 1667.3
Fishing 364.5 372.2 389.4 457.4 486.7 531.6 574.9 638.5 682.1 708.1
Secondary 12925.0 15318.8 14196.3 12231.7 12840.6 12484.6 12433.5 13897.0 14495.1 15326.9
Mining & quarrying 555.9 654.8 680.6 733.4 855.1 819.5 660.3 1069.9 974.6 1006.4
Manufacturing 11024.0 13401.4 12276.4 10142.6 11120.3 10775.6 10761.6 11944.7 12546.7 13302.0
Registered 6552.6 8993.0 7125.2 5163.7 5994.3 5741.3 5397.9 6249.0 6452.7 6696.5
Unregistered 4471.4 4408.3 5151.1 4978.9 5126.0 5034.3 5363.7 5695.7 6094.0 6605.5
Electricity, gas and water 1345.1 1262.6 1239.4 1355.7 865.2 889.5 1011.6 882.3 973.9 1018.5
supply
Tertiary 33643.2 36811.5 38901.3 40431.0 42734.7 43999.5 45666.9 49400.3 52392.3 56185.1
Construction 3733.4 3883.8 4547.9 5159.2 5436.1 5872.2 5982.6 6563.5 6950.8 7345.6
Transport, storage & 3510.6 3873.2 4071.8 4341.8 4893.9 5269.9 5861.2 7548.8 8378.6 9389.2
communication
Trade, hotels and 11247.8 12557.0 12018.9 12419.5 13188.5 13009.4 13278.5 13720.6 14226.0 14409.8
restaurants
Banking & insurance 2244.5 3197.4 3994.0 3508.3 3683.8 3950.2 4083.0 5012.3 5385.7 5786.8
Real estate, owner- ship 4414.3 4471.9 4552.6 4599.9 4627.1 4647.2 4764.6 4916.2 5073.1 5510.5
of dwelling and business
services
Public administration 3214.0 3348.4 3995.1 4057.8 4475.8 4466.0 4466.3 4401.7 4865.4 5447.9
Other services 5278.6 5479.7 5720.9 6344.5 6429.6 6784.6 7230.8 7237.2 7512.8 8295.3
Table - 2.12(b): Net State Domestic Product of Bihar by Industrial Origin at Current Prices
Industry/year 1995-96 1996-97 1997-98 1998-99 1999-00 2000-01 2001-02 2002-03 2003-04 2004-05
Primary 10294.7 14982.8 13527.1 16637.1 15744.2 17566.0 16896.7 19978.1 19158.2 20722.1
Agriculture 9391.5 13954.2 12417.3 15379.6 14302.6 15959.7 15074.3 18030.2 17108.8 18568.8
Forestry & logging 532.2 580.0 647.6 741.9 824.8 899.0 921.0 973.8 1036.9 1103.2
Fishing 370.9 448.7 462.2 515.6 616.8 707.3 901.4 974.2 1012.5 1050.1
Secondary 999.4 1112.9 1976.2 838.9 1955.8 1403.6 1508.2 1473.3 1422.5 1366.2
Mining & quarrying 19.6 23.8 27.2 82.2 75.3 85.7 141.0 133.4 123.8 112.9
Manufacturing 341.5 297.7 579.3 169.4 854.4 561.3 434.1 425.9 413.1 398.9
Registered 446.7 495.7 1026.3 403.5 643.0 647.7 665.9 643.1 611.8 576.0
Unregistered 788.3 793.4 1605.7 572.9 1497.4 1208.9 1099.9 1068.9 1024.9 974.9
Electricity, gas and
water supply 191.5 295.7 343.4 183.9 383.0 109.0 267.3 271.0 273.8 278.5
Tertiary 10540.6 13352.8 14804.0 17360.9 20477.8 23254.8 23779.2 27181.2 29800.1 34021.5
Construction 833.7 952.4 1032.9 1352.0 1883.9 2277.9 1986.5 2184.8 2384.1 2622.0
Transport, storage &
communication 902.1 956.4 1124.7 1242.7 1432.5 1724.5 1953.6 2068.4 2266.0 2517.2
Trade, hotels and
restaurants 3099.0 4637.7 4992.5 5881.1 6229.7 7316.9 6759.0 7861.3 8039.0 9394.7
Banking & insurance 843.4 1160.4 1396.6 1518.0 1562.6 1767.3 2045.4 2575.7 3048.2 3607.2
Real estate, owner- ship
of dwelling and
business services 645.7 697.0 766.0 907.8 989.7 1190.2 1547.0 1839.6 2109.4 2425.9
Public administration 1778.4 2067.8 2379.6 2947.5 3437.4 3565.4 4447.2 5007.3 5634.5 6349.7
Other services 2438.3 2881.1 3111.8 3511.8 4942.0 5412.7 5040.4 5644.2 6319.0 7104.7
Table - 2.13(b).: Net State Domestic Product of Bihar by Industrial Origin at Constant Prices
Industry/year 1995-96 1996-97 1997-98 1998-99 1999-00 2000-01 2001-02 2002-03 2003-04 2004-05
Primary 9688.9 13022.5 10359.2 12299.0 11247.4 14459.6 12177.8 15737.3 13074.6 15727.9
Agriculture 8880.7 12184.0 9573.9 11428.4 10315.8 13481.6 11056.4 14552.9 11863.1 14489.1
Forestry & logging 446.7 444.3 454.5 499.1 530.0 551.8 557.2 568.0 583.2 598.6
Fishing 361.6 394.1 330.8 371.5 401.7 426.2 564.2 616.4 628.2 640.2
Secondary 839.5 855.5 1610.8 584.9 1335.0 1112.5 1016.6 1032.9 1038.6 1054.6
Mining & quarrying 17.4 17.9 18.7 54.2 51.6 77.2 158.3 158.5 157.6 157.8
Manufacturing 269.6 218.1 529.5 34.5 543.0 289.7 206.4 206.9 204.2 203.8
Registered 387.3 436.9 857.5 323.0 500.6 580.7 468.5 463.4 453.1 446.2
Unregistered 656.9 655.0 1387.0 357.4 1043.6 870.4 674.9 670.2 657.4 650.0
Electricity, gas and
water supply 165.3 182.5 205.2 173.2 239.7 164.9 183.4 204.3 223.7 246.8
Tertiary 9053.6 10690.9 11433.7 11995.1 13554.3 15523.6 14960.2 16848.5 16889.0 18990.2
Construction 711.0 784.6 847.6 1072.6 1462.4 1605.4 1350.4 1455.8 1538.7 1661.8
Transport, storage &
communication 809.0 837.0 878.0 977.1 1110.2 1336.9 1483.6 1635.5 1770.0 1974.4
Trade, hotels and
restaurants 2676.9 3830.7 3695.3 4056.1 4114.8 5230.6 4390.4 5398.5 4627.2 5725.7
Banking & insurance 643.6 890.1 1231.9 1082.4 1079.8 1110.3 1263.1 1408.6 1559.0 1725.4
Real estate, owner-
ship of dwelling and
business services 600.2 633.6 673.5 728.3 759.0 816.6 861.1 926.4 1001.5 1091.4
Public administration 1516.5 1546.2 1779.4 1853.3 2052.6 2149.6 2636.6 2846.9 3018.6 3204.9
Other services 2096.4 2168.8 2328.1 2225.4 2975.6 3274.2 2974.9 3176.9 3374.0 3606.6
CHAPTER – 3
HIGHWAY DETAILS – PROPOSED PROVISIONS
3.1 GENERAL
Details regarding proposed provision for the project road form the important part of
Feasibility Report. This Chapter summarises the final choices that have been made
for various aspects of the Project Road from Varanasi (Ch.786.000) and ends at
Aurangabad (Ch.978.400) of NH-2 between Delhi and Kolkata. To some extent,
this Chapter also serves as an ‘Executive Summary” of the Feasibility Report.
The decisions regarding various design aspects have been taken after discussions
with NHAI officials. The full details of the methodology considered, or the logic
behind the choice of any provision etc., are presented here whereas the main
discussions covered in the subsequent Chapters.
The traffic survey data have been analysed and the details are enclosed as
Annexure - III of this report for reference.
The average daily traffic (ADT) for different count station in terms of nos. are indicated hereunder in Table - 3.2 whereas the
details are attached in Annexure III
Table No - 3.2: The average daily traffic (ADT)
Thre
Tract
e Other
or
Two Whe Car / Multi Tractor Cycle Bullo (Pleas
Mini ST 2- With Cycl
Location Whe eler / Jeep LCV 3-Axle - With Ricksh ck Horse e Total
Bus BUS Axle out e
eler Auto / Van Axle Trailer aw Cart Specif
Trail
Rick y)
er
shaw
ADT
1867 46 1433 38 116 428 1596 3514 648 263 73 1755 208 0 4 0 11991
Km 837 IN
PCU 933 46 1433 57 348 642 4788 10543 2914 1184 110 878 415 3 18 0 24313
ADT 1219 49 947 51 186 127 1486 2937 1334 283 110 688 308 32 15 6 9778
Km 887
IN
PCU 609 49 947 76 559 191 4459 8811 6002 1275 165 344 615 256 59 19 24437
ADT
1279 113 852 118 230 285 1904 2713 502 186 27 648 25 0 0 1 8883
Km 950 IN
PCU 640 113 852 176 689 428 5713 8140 2257 836 40 324 51 0 0 4 20262
TYPE OF
LENGTH
SR.NO CROSS DESCRIPTION
(Km)
SECTION
Typical cross section with 5.0m median with both side
1 Type-II 42.558
service road ( 3+3lane)
Typical cross section with 5.0m median with both side
2 TYPE-II’ 56.795
service road ( 3+3lane)
Typical cross section with 1.2m median with both side
3 Type-III 8.145
service road ( 3+3lane)
Typical cross section with 1.2m median with both side
4 TYPE-III’ 0.899
service road ( 3+3lane)
Typical cross section with 1.2m median with left side
5 Type-IV 0.825
service road ( 3+3lane)
Typical cross section with 5.0m median with left side
6 Type-VI 14.654
service road ( 3+3lane)
Typical cross section with 1.2m median with both side
7 Type-VIII 6.590
service road ( 2+2ane)
Typical cross section with 1.2m median with both side
8 TYPE-VIII’ 0.825
service road ( 2+2ane)
Fig – 3.1: Typical C/S with 5.0 m Median without Service Road (Type-I)
Fig – 3.2: Typical C/S with 5.0 m Median with Service Road (Type-II)
SHOULDER
SHOULDER
SHOULDER
SHOULDER
SHOULDER
SHOULDER
SHOULDER
SHOULDER
STRIP
STRIP
EDGE
EDGE
COVERED
COVERED
EARTHEN
EARTHEN
EARTHEN
EARTHEN
PAVED
PAVED
PAVED
PAVED
DRAIN
DRAIN
PEDESTRIAN PEDESTRIAN
GUARD RAIL 3% 3% GUARD RAIL
SELECTED SELECTED
2.5% 2.5%
EARTH 2.5% 2. 5% EARTH
3% 3%
2 2
1 1
Fig – 3.3: Typical C/S with 1.2 m Median with existing Service Road on both sides (Type-III)
51200
1500 500 7000/5500 500 1500 2000 1500 10500 500 1200 500 10500 1500 2000 1500 500 7000/5500 500 1500
SERVICE ROAD NEW CARRIAGEWAY MEDIAN NEW CARRIAGEWAY SERVICE ROAD
SHOULDER
SHOULDER
SHOULDER
SHOULDER
SHOULDER
SHOULDER
SHOULDER
SHOULDER
FOOTPATH
FOOTPATH
STRIP
STRIP
EARTHEN
EDGE
EDGE
EARTHEN
PAVED
PAVED
PAVED
PAVED
PAVED
PAVED
DRAIN
DRAIN
DRAIN
DRAIN
CUM
CUM
C OF CARRIAGEWAY
PROPOSED FLEXIBLE PAVEMENT PROPOSED FLEXIBLE PAVEMENT EXISTING FLEXIBLE PAVEMENT PROPOSED FLEXIBLE PAVEMENT PROPOSED FLEXIBLE PAVEMENT
RIGHT SIDE
PART PLAN
Fig – 3.4: Typical C/S with 1.2 m Median with Existing Service Road on Left Side (Type-IV)
51956
1500 500 7000/5500 500 15 00 2 000 1500 10500 500 1200 500 102 50 150 0 2000 1500 500 70 00/5500 50 0 1500
SER VICE ROAD N EW CA RRIAGEWAY MEDIAN NEW CARRIA GEWAY SERVICE ROAD
SHOULDER
SHOULDER
SHOULDER
SHOULDER
SHOULDER
SHOULDER
SHOULDER
SHOULDER
FOOTPATH
FOOTPATH
STRIP
STRIP
EDGE
EDGE
EARTHEN
EARTHEN
PAVED
PAVED
PAVED
PAVED
PAVED
PAVED
DRAIN
DRAIN
DRAIN
DRAIN
CUM
CUM
C OF CARRIAGEWAY
PROPOSED FLEXIBLE PAVEMENT PROPOSED FLEXIBLE PAVEMENT EXISTING FLEXIBLE PAVEMENT PROPOSED FLEXIBLE PAVEMENT PROPOSED FLEXIBLE PAVEMENT
MEDIAN
CARRIAGEWAY
PAVED SHOULDER
EARTHEN SHOULDER
RIGHT SIDE
PART PLAN
Fig – 3.5: Typical C/S with 5.0 m Median with Existing Service Road on LHS (Type-VI)
STRIP
EDGE
STRIP
EDGE
SHOULDER
SHOULDER
SHOULDER
SHOULDER
SHOULDER
SHOULDER
SHOULDER
SHOULDER
COVERED
COVERED
EARTHEN
EARTHEN
PAVED
PAVED
PAVED
PAVED
PAVED
PAVED
DRAIN
DRAIN
PEDESTRI AN PED ESTR IAN
S ELECTED GU ARD RA IL GUA RD RAI L
3% 3% SELECTED
EAR TH 2.5% 2.5% EAR TH
3% 2.5 % 3%
2 2
1 1
P ROPOSED FLEX IB LE PA VEMENT E XI STING FLEXI BLE PAVEMENT PROPOSE D FLEX IB LE PA VEMENT PROPOSED FLEXIB LE PAVEM ENT
PART PLAN
Fig – 3.6: Typical C/S with 5.0 m Median with Service Road (Type-II’)
STRIP
STRIP
EDGE
EDGE
SHOULDER
SHOULDER
SHOULDER
SHOULDER
SHOULDER
SHOULDER
SHOULDER
SHOULDER
COVERED
COVERED
EARTHEN
EARTHEN
EARTHEN
EARTHEN
PAVED
PAVED
PAVED
PAVED
DRAIN
DRAIN
PEDESTRIAN PEDESTRIAN
GUARD RAIL GUARD RAIL
SELECTED 3% 3% SELECTED
2.5% 2.5%
EARTH 3% 2.5% 2.5% EARTH
3%
2 2
1 1
Fig – 3.7: Typical C/S with 1.2 m Median with Existing Service Road on Both sides (Type-III’)
51200
1500 500 7000/5500 500 1500 2000 1500 10500 500 1200 500 10500 1500 2000 1500 500 7000/5500 500 1500
SERVICE ROAD NEW CARRIAGEW AY MEDIAN NEW CARRIAGEWAY SERVICE ROAD
SHOULDER
SHOUL DER
SHOULDER
SHOUL DER
SHOULDER
SHOULDER
SHOULDER
SHOULDER
F OOTPATH
FOOTPATH
STRIP
STRIP
EARTHEN
EARTHEN
EDGE
EDGE
PAVED
PAVED
PAVED
PAVED
PAVED
PAVED
DRAIN
DRAIN
DRAIN
DRAIN
CUM
CUM
C OF CARRIAGEWAY
PROPOSED FLEXIBLE PAVEMENT PROPOSED RIGID PAVEM ENT EXISTING RIGID PAVEMENT PROPOSED RIGID PAVEMENT PROPOSED FLEXIBLE PAVEMENT
TOTAL(KM) 0.899
RIGHT SIDE
PART PLAN
Fig – 3.8: Typical C/S with 1.2 m Median with existing Service Road on both sides (Type-VIII)
1500 500 7000/5500 500 1500 2000 1500 7250 500 1200 500 7250 1500 2000 1500 500 7000/5500 500 1500
SERVICE ROAD NEW CARRIAGEWAY MEDIAN NEW CARRIAGEWAY SERVICE ROAD
SHOULDER
SHOULDER
SHOULDER
SHOULDER
SHOULDER
FOOTPATH
SHOULDER
SHOULDER
SHOULDER
FOOTPATH
STRIP
EDGE
STRIP
EDGE
EARTHEN
EARTHEN
PAVED
PAVED
PAVED
PAVED
PAVED
PAVED
DRAIN
DRAIN
DRAIN
DRAIN
CUM
CUM
C OF CARRIAGEWAY
PROPO SED RIG ID PAVEMENT EXISTING FLEXIBLE PAVEMENT PROPOSED RIGID PAVEMENT
RIGHT SIDE
PART PLAN
Fig – 3.9: Typical C/S with 1.2 m Median with existing Service Road on both sides (Type-VIII’)
1500 500 7000/5500 500 1500 2000 1500 7250 500 1200 500 7250 1500 2000 1500 500 7000/ 5500 50 0 1500
SERVICE ROAD NE W CARRIAGEWAY ME DIAN NEW CARRIAGEWAY SERVICE ROAD
SHOULDER
SHOULDER
SHOULDER
SHOULDER
FOOTPATH
SHOULDER
SHOULDER
SHOULDER
SHOULDER
FOOTPATH
STRIP
EARTHEN
EDGE
STRIP
EDGE
EARTHEN
PAVED
PAVED
DRAI N
PAVED
PAVED
PAVED
PAVED
DRAI N
DRAIN
DRAIN
CUM
CUM
C OFC ARRIAGEWAY
PRO POSED RIGID PAVEM ENT E XISTIN GR IGID PAV EMENT PR OPOS ED RIGID PAVEM ENT
RIGHT S IDE
PART PLAN
3.5 PAVEMENT
This section provides pavement structure adopted for the proposed project road.
As already mentioned that about 85.2 km of existing 4 lane C/W is with concrete
pavement whereas 107.2 km is with bituminous pavement. While widening the
existing 4 lane C/W to 6 lane C/W, the existing C/w with bituminous pavement has
been proposed to be widened with bituminous pavement and the existing C/W with
concrete pavement has been proposed to be widened with concrete pavement.
Pavement structure mainly consist of subgrade, sub-base coarse, base coarse,
Binder and surface coarse for new construction whereas only wearing coarse for
strengthening work.
Pavement Composition
Bituminous Pavement Concrete Pavement
BC = 50 mm PQC = 340 mm
DBM = 160 mm DLC = 150 mm
WMM = 250 mm GSB = 150 mm
GSB = 300 mm Over 500 mm Sub grade with 7% CBR
Over 500 mm thick Sub grade of 7% CBR
Detailed overlay design have been carried for existing flexible pavements of
various sections based Benkelman Beam deflection tests results. An overlay
thickness of 50mm BC with profile correction have been proposed for existing c/w.
The results of BBD are attached with annexure-IV. As the four laning of the project
road has been completed recently, only wearing course with 50mm BC has been
found adequate for strengthening. No overlay has been proposed over existing
concrete pavement.
Lists of various types of CD structure (Pipe Culvert & Slab Culvert) for the total project
road are presented hereunder:
Overall Type of
Sl. Dia. of No of Carriageway Type of Hand
Location width Protection General Conditions and Observations
No. pipe(mm) Pipes width(m) head walls rails
(m) works
2 x 7.5 + Blocked water way. Longitudinal road
789 + 600 PCC head
1 750 1 service 24.8 Nil Nil side drain in between main & service
Barvan walls
roads roads
793 + 050 PCC head
2 1200 1 2 x 7.5 24.8 Nil Nil Satisfactory Condition.
Khushipur walls
794 + 800 2 x 7.5 + Blocked water way. Structure not
PCC head
3 Rampur 1200 1 service 48 Nil Nil vissible. Longitudinal road side drain in
walls
Lathiya roads between main & service roads.
2 x 7.5 + Blocked water way. Longitudinal road
796 + 950 PCC head
4 1200 1 service 48 Nil Nil side drain in between main & service
Amra walls
roads roads
2 x 7.5 + Blocked water way. Structure not
798 + 020 PCC head
5 1200 1 service 48 Nil Nil vissible. Longitudinal road side drain in
Amra walls
roads between main & service roads.
2 x 7.5 +
811 + 850 PCC head
6 600 1 service 48 Nil Nil Satisfactory Condition.
Chandauli walls
roads
819 + 100 PCC head
7 1200 1 2 x 7.5 36 Nil Nil Satisfactory Condition.
Devasa walls
823 + 700 PCC head
8 1200 1 2 x 7.5 36 Nil Nil Satisfactory Condition.
Baloni walls
824 + 900 Syphon crossing from a tube well,
9 600 1 2 x 7.5 36 Nil Nil
Hinauta burried structure.
Satisfactory Condition, Invert level of
829 + 620 PCC head
10 1200 1 2 x 7.5 36 Nil Nil culvert higher than surrounding nalla bed
Chandauli walls
level
Overall
Sl. Type of Size Carriageway Type of Type of Hand General Conditions and
Location width
No. structure (NoxWxH) width(m) superstructure substructure rails Observations
(m)
Blocked water way. Thus
2 x 7.5 + Inside of structure not
790 + 770 Box
1 1 x 1.0 x 1.0 service 24.8 PCC wing walls Nil visible. Longitudinal road
Barvan culvert
roads side drain in between main
& service roads
Sl. Type of Size Carriageway Overall Type of Type of Hand General Conditions and
Location width
No. structure (NoxWxH) width(m) superstructure substructure rails Observations
(m) Satisfactory Condition.
2 x 7.5 +
791 + 220 Box RCC Longitudinal road side
2 1 x 1.0 x 1.0 service 24.8 PCC wing walls
Barvan culvert parapet drain in between main &
roads
service roads
Satisfactory Condition.
2 x 7.5 +
791 + 785 Box RCC Longitudinal road side
3 1 x 1.0 x 1.0 service 24.8 PCC wing walls
Barvan culvert parapet drain in between main &
roads
service roads
Satisfactory Condition.
2 x 7.5 +
792 + 020 Box RCC Longitudinal road side
4 1 x 1.0 x 1.0 service 24.8 PCC wing walls
Barvan culvert parapet drain in between main &
roads
service roads
Satisfactory Condition.
2 x 7.5 +
792 + 385 Box RCC Longitudinal road side
5 1 x 1.0 x 1.0 service 24.8 PCC wing walls
Barvan culvert parapet drain in between main &
roads
service roads
Satisfactory Condition.
2 x 7.5 +
792 + 800 Box RCC Longitudinal road side
6 1 x 3.0 x 2.0 service 24.8 PCC wing walls
Khushipur culvert parapet drain in between main &
roads
service roads
Satisfactory Condition.
2 x 7.5 +
792 + 900 Box RCC Longitudinal road side
7 2 x 5.5 x 4.0 service 24.8 PCC wing walls
Khushipur culvert parapet drain in between main &
roads
service roads
Satisfactory Condition.
2 x 7.5 +
793 + 700 Box RCC Longitudinal road side
8 1 x 1.0 x 1.0 service 24.8 PCC wing walls
Khushipur culvert parapet drain in between main &
roads
service roads
Satisfactory Condition.
2 x 7.5 +
793 + 985 Box RCC Longitudinal road side
9 1 x 1.0 x 1.0 service 24.8 PCC wing walls
Khushipur culvert parapet drain in between main &
roads
service roads
Sl. Type of Size Carriageway Overall Type of Type of Hand General Conditions and
Location width
No. structure (NoxWxH) width(m) superstructure substructure rails Observations
(m) Satisfactory Condition.
794 + 700 2 x 7.5 +
Box RCC Longitudinal road side
10 Rampur 1 x 1.0 x 1.0 service 48 PCC wing walls
culvert Railing drain in between main &
Lathiya roads
service roads
Blocked water way. Thus
795 + 025 2 x 7.5 + Inside of structure not
Box
11 Rampur 1 x 1.0 x 1.0 service 48 PCC wing walls Nil visible. Longitudinal road
culvert
Lathiya roads side drain in between main
& service roads
Blocked water way. Thus
2 x 7.5 + Inside of structure not
797 + 015 Box
12 1 x 1.0 x 1.0 service 48 PCC wing walls Nil visible. Longitudinal road
Amra culvert
roads side drain in between main
& service roads
Blocked water way. Thus
2 x 7.5 + Inside of structure not
797 + 900 Box RCC
13 1 x 1.0 x 1.0 service 48 PCC wing walls visible. Longitudinal road
Amra culvert parapet
roads side drain in between main
& service roads
Very poor condition.
2 x 7.5 +
798 + 200 Box RCC Longitudinal road side
14 1 x 1.0 x 1.0 service 48 PCC wing walls
Amra culvert parapet drain in between main &
roads
service roads
Poor condition.
2 x 7.5 +
798 + 900 Box RCC Longitudinal road side
15 1 x 1.0 x 1.0 service 48 PCC wing walls
Amra culvert parapet drain in between main &
roads
service roads
Poor condition.
2 x 7.5 +
799 + 700 Box RCC Longitudinal road side
16 1 x 3.0 x 2.0 service 23 PCC wing walls
Dafi culvert parapet drain in between main &
roads
service roads
Sl. Type of Size Carriageway Overall Type of Type of Hand General Conditions and
Location width
No. structure (NoxWxH) width(m) superstructure substructure rails Observations
(m) Satisfactory condition.
2 x 7.5 +
800 + 500 Box Brick Existing culvert invert level
17 1 x 5.0 x 3.0 service 23 PCC wing walls
Dafi culvert parapet above surrounding nalla
roads
bed level.
Satisfactory Condition.
2 x 7.5 +
805 + 800 Box RCC Longitudinal road side
18 1 x 4.0 x 3.0 service 48 PCC wing walls
Ramnagar culvert parapet drain in between main &
roads
service roads
Satisfactory Condition.
2 x 7.5 +
806 + 040 Box RCC Longitudinal road side
19 1 x 3.7 x 3.5 service 48 PCC wing walls
Ramnagar culvert parapet drain in between main &
roads
service roads
Satisfactory Condition.
2 x 7.5 +
806 + 600 Box RCC Longitudinal road side
20 1 x 2.6 x 1.8 service 48 PCC wing walls
Ramnagar culvert parapet drain in between main &
roads
service roads
Satisfactory Condition.
2 x 7.5 +
807 + 220 Box RCC Longitudinal road side
21 1 x 1.6 x 1.0 service 48 PCC wing walls
Ramnagar culvert parapet drain in between main &
roads
service roads
Satisfactory Condition.
2 x 7.5 +
810 + 000 Box RCC Longitudinal road side
22 1 x 3.8 x 2.5 service 48 PCC wing walls
Chandauli culvert parapet drain in between main &
roads
service roads
Satisfactory Condition.
2 x 7.5 +
812 + 300 Box RCC Longitudinal road side
23 1 x 4.5 x 2.5 service 48 PCC wing walls
Chandauli culvert parapet drain in between main &
roads
service roads
812 + 800 Box RCC
24 1 x 3.5 x 2.5 2 x 7.5 23.5 PCC wing walls Satisfactory Condition.
Chandauli culvert parapet
813 + 200 Box RCC Satisfactory Condition,
25 1 x 3.5 x 2.5 2 x 7.5 23.5 PCC wing walls
Chandauli culvert parapet Canal crossing.
Sl. Type of Size Carriageway Overall Type of Type of Hand General Conditions and
Location width
No. structure (NoxWxH) width(m) superstructure substructure rails Observations
813 + 300 Box (m) RCC
26 1 x 3.7 x 2.5 2 x 7.5 23.5 PCC wing walls Satisfactory Condition.
Chandauli culvert parapet
813 + 900 Box RCC Satisfactory Condition,
27 1 x 4.0 x 2.5 2 x 7.5 23.5 PCC wing walls
Chandauli culvert parapet Canal crossing.
814 + 450 Box RCC
28 1 x 3.7 x 2.5 2 x 7.5 36 PCC wing walls Satisfactory Condition.
Chandauli culvert parapet
815 + 230 Box RCC Satisfactory Condition,
29 1 x 3.7 x 2.5 2 x 7.5 23.5 PCC wing walls
Mugalsarai culvert parapet Canal crossing.
816 + 900 Box RCC
30 1 x 6.0 x 2.5 2 x 7.5 36 PCC wing walls Satisfactory Condition.
Mugalsarai culvert parapet
821 + 820 Box RCC
31 1 x 1.8 x 2.5 2 x 7.5 36 PCC wing walls Satisfactory Condition.
Rampur culvert parapet
824 + 700 Box RCC
32 1 x 3.7 x 2.5 2 x 7.5 36 PCC wing walls Satisfactory Condition.
Katsila culvert parapet
825 + 300 Box RCC
33 1 x 2.0 x 2.5 2 x 7.5 23.5 PCC wing walls Satisfactory Condition.
Hinauta culvert parapet
825 + 785 Box RCC
34 1 x 2.0 x 2.5 2 x 7.5 23.5 PCC wing walls Satisfactory Condition.
Bichhiya Palli culvert parapet
828 + 380 Box RCC
35 1 x 4.7 x 2.5 2 x 7.5 23.5 PCC wing walls Satisfactory Condition.
Chandauli culvert parapet
828 + 700 Box RCC
36 1 x 3.7 x 2.5 2 x 7.5 23.5 PCC wing walls Satisfactory Condition.
Chandauli culvert parapet
830 + 150 Box RCC
37 1 x 3.7 x 2.5 2 x 7.5 26 PCC wing walls Satisfactory Condition.
Chandauli culvert parapet
830 + 900
Box RCC
38 Rampur 1 x 3.7 x 2.5 2 x 7.5 26 PCC wing walls Satisfactory Condition.
culvert parapet
Chandauli
832 + 900 Box RCC
39 1 x 3.7 x 2.5 2 x 7.5 26 PCC wing walls Satisfactory Condition.
Seruka culvert parapet
Sl. Type of Size Carriageway Overall Type of Type of Hand General Conditions and
Location width
No. structure (NoxWxH) width(m) superstructure substructure rails Observations
836 + 300 Box (m) RCC
40 1 x 1.6 x 3.0 2 x 7.5 48 PCC wing walls Satisfactory Condition.
Saiyad raja culvert parapet
836 + 780 Box RCC
41 1 x 2.1 x 1.0 2 x 7.5 48 PCC wing walls Satisfactory Condition.
Saiyad raja culvert parapet
839 + 250 Box RCC
42 1 x 6.0 x 2.0 2 x 7.5 25 PCC wing walls Satisfactory Condition.
Saiyad raja culvert parapet
3 cells of
3.00m x
2.50m 3 cell box on
839 + 550 2 x 7.5 + Brick masonry on RCC
43 box on 11 25 LHS, Solid Satisfactory Condition
Barathi Meadian RHS parapet.
LHS. Slab on RHS.
3 x 3.5 on
RHS.
840 + 200 Box RCC
44 1 x 4.7 x 2.5 2 x 7.5 23.5 PCC wing walls Satisfactory Condition.
Bharathi culvert parapet
840 + 580 Box RCC
45 1 x 2.7 x 2.0 2 x 7.5 23.5 PCC wing walls Satisfactory Condition.
Bharathi culvert parapet
841 + 500 Box RCC
46 1 x 2.7 x 2.0 2 x 7.5 23.5 PCC wing walls Satisfactory Condition.
Bharathi culvert parapet
844 + 550 Box RCC
47 1 x 4.7 x 2.5 2 x 7.5 23.5 PCC wing walls Satisfactory Condition.
Naubatpur culvert parapet
844 + 600 2 x 7.5 + RCC Solid Brick masonry Brick
48 1 x 6.7 6.7 23.5 Poor Condition.
Naubatpur Meadian Slab Abutments parapet
Structure in satisfactory
844 + 620 Box RCC
49 1 x 3.7 x 2.5 2 x 7.5 23.5 PCC wing walls condition. Waterway fully
Naubatpur culvert parapet
blocked.
844 + 780 Box RCC
50 1 x 2.7 x 2.5 2 x 7.5 23.5 PCC wing walls Satisfactory Condition.
Karmnasa culvert parapet
845 + 220 Box RCC
51 1 x 2.7 x 2.5 2 x 7.5 23.5 PCC wing walls Satisfactory Condition.
Karmnasa culvert parapet
Sl. Type of Size Carriageway Overall Type of Type of Hand General Conditions and
Location width
No. structure (NoxWxH) width(m) superstructure substructure rails Observations
845 + 700 Box (m) RCC
52 1 x 2.7 x 2.5 2 x 7.5 23.5 Satisfactory Condition.
Karmnasa culvert parapet
846 + 750 Box RCC
53 1 x 3.7 x 2.5 2 x 7.5 23.5 PCC wing walls Satisfactory Condition.
Karmnasa culvert parapet
846 + 980 Box RCC
54 1 x 3.7 x 2.5 2 x 7.5 23.5 PCC wing walls Satisfactory Condition.
Karmnasa culvert parapet
848 + 900 Box RCC
55 1 x 4.7 x 2.5 2 x 7.5 23.5 PCC wing walls Satisfactory Condition.
Chipli culvert parapet
851 + 200 Box RCC
56 1 x 3.7 x 2.5 2 x 7.5 23.5 PCC wing walls Satisfactory Condition.
Dhanchha culvert parapet
Brick masonry
854 + 800 2 x 7.5 + RCC Solid
57 1 x 7.5 7.5 25 abutments and Railing Poor Condition
Savad Meadian slab
wing walls.
854 + 900 Box PCC wing / return RCC
58 1 x 6.0 x 3.0 2 x 7.5 23.5 Satisfactory Condition.
Durgavati culvert walls parapet
15 on
3 cell box on Brick masonry
855 + 200 2 x 7.5 + LHS, RCC
59 3 x 3.5 10.5 LHS, Solid substructure and Satisfactory Condition
Darauli Meadian 10 on parapet.
Slab on RHS. wing walls on RHS.
RHS
15 on
3 cell box on Brick masonry
855 + 300 2 x 7.5 + LHS, RCC
60 3 x 4.0 12 LHS, Solid substructure and Satisfactory Condition
Darauli Meadian 8.3 on parapet.
Slab on RHS. wing walls on RHS.
RHS
15 on
2 cell box on Brick masonry
855 + 550 2 x 7.5 + LHS, RCC
61 2 x 4.0 8 LHS, Solid substructure and Satisfactory Condition
Darauli Meadian 8.3 on parapet.
Slab on RHS. wing walls on RHS.
RHS
Sl. Type of Size Carriageway Overall Type of Type of Hand General Conditions and
Location width
No. structure (NoxWxH) width(m) superstructure substructure rails Observations
15(m)
on
2 cell box on Brick masonry
855 + 650 2 x 7.5 + LHS, RCC
62 2 x 4.0 8 LHS, Solid substructure and Satisfactory Condition
Dahiya Meadian 8.3 on parapet.
Slab on RHS. wing walls on RHS.
RHS
15 on
2 cell box on Brick masonry
855 + 900 2 x 7.5 + LHS, RCC
63 2 x 4.0 8 LHS, Solid substructure and Satisfactory Condition
Dahiya Meadian 8.3 on parapet.
Slab on RHS. wing walls on RHS.
RHS
15 on
3 cell box on Brick masonry
856 + 020 2 x 7.5 + LHS, RCC
64 3 x 3.65 11 LHS, Solid substructure and Satisfactory Condition
Dahiya Meadian 8.3 on parapet.
Slab on RHS. wing walls on RHS.
RHS
Box
15 on
culvert on Brick masonry
856 + 150 LHS, Solid slab on RCC
65 LHS, Slab 1x6 6 substructure on Poor Condition.
Dahiya 8.3 on RHS. parapet
culvert on RHS.
RHS
RHS.
15 on
3 cell box on Brick masonry
856 + 350 2 x 7.5 + LHS, RCC
66 3 x 3.65 11 LHS, Solid substructure and Satisfactory Condition
Bhabhua Meadian 8.3 on parapet.
Slab on RHS. wing walls on RHS.
RHS
857 + 400 Box PCC wing / return RCC
67 1 x 3.7 x 2.5 2 x 7.5 23.5 Satisfactory Condition.
Bhabhua culvert walls parapet
857 + 750 Box PCC wing / return RCC
68 1 x 3.7 x 2.5 2 x 7.5 23.5 Satisfactory Condition.
Bhabhua culvert walls parapet
858 + 030 Box PCC wing / return RCC
69 1 x 2.6 x 2.0 2 x 7.5 23.5 Satisfactory Condition.
Bhabhua culvert walls parapet
858 + 220 Box PCC wing / return RCC
70 1 x 2.6 x 2.0 2 x 7.5 23.5 Satisfactory Condition.
Bhabhua culvert walls parapet
858 + 950 Box PCC wing / return RCC
71 1 x 3.6 x 2.0 2 x 7.5 23.5 Satisfactory Condition.
Bhabhua culvert walls parapet
Sl. Type of Size Carriageway Overall Type of Type of Hand General Conditions and
Location width
No. structure (NoxWxH) width(m) superstructure substructure rails Observations
860 + 050 Box (m) PCC wing / return RCC
72 1 x 2.7 x 2.0 2 x 7.5 23.5 Satisfactory Condition.
Bhabhua culvert walls parapet
15 on
2 cell box on Brick masonry
860 + 350 2 x 7.5 + LHS, RCC
73 2 x 5.75 11.5 LHS, Solid substructure and Satisfactory Condition
Bhabhua Meadian 8.3 on parapet.
Slab on RHS. wing walls on RHS.
RHS
860 + 650 Box PCC wing / return RCC
74 1 x 4.3 x 2.0 2 x 7.5 23.5 Satisfactory Condition.
Bhabhua culvert walls parapet
Box
culvert on Brick masonry
860 + 820 Solid slab on RCC
75 LHS, Slab 1 x 3.8 2 x 7.5 23.5 substructure on Satisfactory Condition.
Bhabhua RHS. parapet
culvert on RHS.
RHS.
Box
15 on
culvert on Brick masonry
861 + 350 LHS, Solid slab on RCC
76 LHS, Slab 1 x 3.7 2 x 7.5 substructure on Satisfactory Condition.
Bhabhua 8.3 on RHS. parapet
culvert on RHS.
RHS
RHS.
861 + 985 Box PCC wing / return RCC
77 1 x 3.7 x 2.0 2 x 7.5 23.5 Satisfactory Condition.
Bhabhua culvert walls parapet
17.4 on RCC
3 cell box on Brick masonry
863 + 800 2 x 7.5 + LHS, parapet
78 3 x 4.8 14.5 LHS, Solid substructure and Satisfactory Condition
Bhabhua Meadian 10 on &
Slab on RHS. wing walls on RHS.
RHS railing.
17.4 on RCC
3 cell box on Brick masonry
864 + 300 2 x 7.5 + LHS, parapet
79 3 x 4.8 14.5 LHS, Solid substructure and Satisfactory Condition
Shivpur Meadian 10 on &
Slab on RHS. wing walls on RHS.
RHS railing.
Sl. Type of Size Carriageway Overall Type of Type of Hand General Conditions and
Location width
No. structure (NoxWxH) width(m) superstructure substructure rails Observations
2 x 3.75 (m)on
17.4 RCC
2 cell box on Brick masonry
864 + 500 LHS, 2 2 x 7.5 + LHS, parapet
80 9 LHS, Solid substructure and Satisfactory Condition
Shivpur x 4.5 Meadian 10 on &
Slab on RHS. wing walls on RHS.
RHS. RHS railing.
2 x 3.8 17.4 on RCC
2 cell box on Brick masonry
864 + 650 LHS, 2 x 7.5 + LHS, parapet
81 7.6 LHS, Solid substructure and Satisfactory Condition
Shivpur 2 x 3.8 Meadian 10 on &
Slab on RHS. wing walls on RHS.
RHS. RHS railing.
2 x 4.5 15 on RCC
2 cell box on Brick masonry
864 + 900 LHS, 2 x 7.5 + LHS, parapet
82 9 LHS, Solid substructure and Satisfactory Condition
Shivpur 2 x 4.5 Meadian 8.5 on &
Slab on RHS. wing walls on RHS.
RHS. RHS railing.
868 + 700 Slab PCC substructure RCC
83 1 x 4.6 2 x 7.5 23.5 Solid slab Satisfactory Condition.
Mohaniya culvert & wing walls parapet
10 on
869 + 700 Slab LHS, PCC substructure RCC
84 1 x 4.2 2 x 7.5 Solid slab Satisfactory Condition.
Mohaniya culvert 10.8 on & wing walls parapet
RHS
RCC
874 + 010
2 x 7.5 + 3 cell box parapet
85 Mandevi 3 x 3.75 11.5 25 PCC Returns Satisfactory Condition.
Meadian culvert. & MS
Mazavi
Railing
874 + 500
Box RCC
86 Mandevi 1 x 4.5 x 3.0 2 x 7.5 25 PCC wing walls Satisfactory Condition.
culvert parapet
Mazavi
874 + 850 Slab PCC substructure RCC
87 1 x 3.5 2 x 7.5 25 Solid slab Satisfactory Condition.
Bhitti culvert & wing walls parapet
875 + 200 Box RCC
88 1 x 2.6 x 2.0 2 x 7.5 25 PCC wing walls Satisfactory Condition.
Bhitti culvert parapet
Sl. Type of Size Carriageway Overall Type of Type of Hand General Conditions and
Location width
No. structure (NoxWxH) width(m) superstructure substructure rails Observations
875 + 600 Box (m) RCC
89 1 x 3.7 x 2.0 2 x 7.5 25 PCC wing walls Satisfactory Condition.
Bhitti culvert parapet
877 + 550 Box RCC
90 1 x 4.7 x 3.0 2 x 7.5 25 PCC wing walls Satisfactory Condition.
Bhitti culvert parapet
17.4 on Brick masonry RCC
3 cell box on
877 + 850 2 x 7.5 + LHS, substructure and parapet
91 3 x 3.1 9.5 LHS, Solid Poor Condition
Pusauli Meadian 10.0 on return walls on & MS
Slab on RHS.
RHS RHS. Railing
17.4 on
2 cell box on Brick masonry
878 + 850 2 x 7.5 + LHS, RCC
92 2 x 3.5 7 LHS, Solid substructure and Satisfactory Condition
Pusauli Meadian 10.0 on parapet.
Slab on RHS. wing walls on RHS.
RHS
Brick
Brick masonry
880 + 300 Slab maso-
93 1 x 5.3 2 x 7.5 25 Solid slab substructure & Poor Condition.
Ghatari culvert nry
wing walls
parapet
880 + 800 Slab PCC substructure RCC
94 1 x 5.3 2 x 7.5 25 Solid slab Satisfactory Condition.
Ghatari culvert & wing walls parapet
1 x 5.3 on 15.0 on
Brick masonry
881 + 200 Slab LHS, LHS, RCC
95 2 x 7.5 Solid slab substructure & Satisfactory Condition.
Ghatari culvert 2 x 2.65 on 10.0 on parapet
wing walls
RHS RHS
15 on RCC
3 cell box on Brick masonry
881 + 900 2 x 7.5 + LHS, parapet
96 3 x 3.35 7 LHS, Solid substructure and Poor repaired Condition.
Pusauli Meadian 10.0 on & MS
Slab on RHS. wing walls on RHS.
RHS Railing
15 on RCC
RCC / Brick
892 + 200 2 x 7.5 + LHS, RCC Solid parapet Satisfactory Condition.
97 1 x 9.3 9.3 Abutments, Wing
Kudra Meadian 10.0 on Slab & MS Canal crossing.
walls
RHS Railing
Sl. Type of Size Carriageway Overall Type of Type of Hand General Conditions and
Location width
No. structure (NoxWxH) width(m) superstructure substructure rails Observations
895 + 550 Box (m) RCC
98 1 x 2.7 x 3.0 2 x 7.5 25 PCC wing walls Satisfactory Condition.
Khurmabad culvert parapet
897 + 050 Box RCC
99 1 x 4.7 x 3.5 2 x 7.5 25 PCC wing walls Satisfactory Condition.
Khurmabad culvert parapet
897 + 700 Box RCC
100 1 x 1.6 x 1.5 2 x 7.5 25 PCC wing walls Blocked waterway.
Khurmabad culvert parapet
898 + 600 Box RCC
101 1 x 3.7 x 2.5 2 x 7.5 25 PCC wing walls Blocked waterway.
Tekari culvert parapet
900 + 600 Box RCC
102 1 x 3.7 x 2.0 2 x 7.5 25 PCC wing walls Blocked waterway.
Tekari culvert parapet
901 + 600 Box RCC
103 1 x 1.6 x 1.5 2 x 7.5 25 PCC wing walls Blocked waterway.
Monidih culvert parapet
902 + 200 Box RCC
104 1 x 2.4 x 2.0 2 x 7.5 25 PCC wing walls Satisfactory Condition.
Monidih culvert parapet
2x4.8 17.0 on RCC Abutments, RCC
2 cell box on Satisfactory Condition on
905 +150 LHS, 2 x 7.5 + LHS, Brick masonry parapet
105 11 LHS, Solid LHS. Repaired poor
Monidih 2x5.5 Meadian 8.0 on substructure and & MS
Slab on RHS. condition on RHS.
RHS RHS wing walls on RHS. Railing
15.0 on
Brick masonry
907 + 200 Slab LHS, RCC
107 1 x 3.7 2 x 7.5 Solid slab substructure & Satisfactory Condition.
Monidih culvert 10.0 on parapet
wing walls
RHS
908 + 800 Box RCC Satisfactory Condition.
108 1 x 3.6 x 3.0 2 x 7.5 25 PCC wing walls
Morava Sarai culvert parapet Canal crossing.
916 + 400 Box RCC
109 1 x 2.7 x 2.0 2 x 7.5 25 PCC wing walls Good Condition.
Morava Sarai culvert parapet
Sl. Type of Size Carriageway Overall Type of Type of Hand General Conditions and
Location width
No. structure (NoxWxH) width(m) superstructure substructure rails Observations
918 + 400 Box (m) RCC
110 1 x 4.7 x 1.5 2 x 7.5 25 PCC wing walls Satisfactory Condition.
Gavaliya Tola culvert parapet
918 + 500 Box RCC
111 1 x 3.7 x 1.0 2 x 7.5 25 PCC wing walls Satisfactory Condition.
Gavaliya Tola culvert parapet
920 + 200 Box RCC
112 1 x 4.7 x 1.5 2 x 7.5 25 PCC wing walls Blocked waterway.
Suara culvert parapet
920 + 300 Box RCC
113 1 x 4.6 x 1.5 2 x 7.5 25 PCC wing walls Blocked waterway.
Suara culvert parapet
920 + 400 Box RCC
114 1 x 4.6 x 1.5 2 x 7.5 25 PCC wing walls Satisfactory Condition.
Manora culvert parapet
920 + 600 Box RCC
115 1 x 4.6 x 1.5 2 x 7.5 25 PCC wing walls Satisfactory Condition.
Manora culvert parapet
943 + 730 Box RCC
116 1 x 2.5 x 2.5 2 x 7.5 25 PCC wing walls Satisfactory Condition.
Barunganj culvert parapet
944 + 600 Box RCC
117 1 x 3.5 x 2.0 2 x 7.5 25 PCC wing walls Satisfactory Condition.
Barunganj culvert parapet
Sl. Type of Size Carriageway Overall Type of Type of Hand General Conditions and
Location width
No. structure (NoxWxH) width(m) superstructure substructure rails Observations
946 + 800 Slab (m) PCC abutments RCC
123 1 x 3.5 2 x 7.5 25 Solid slab Satisfactory Condition.
Rayapura. culvert and wing walls parapet
956 + 200 Slab PCC abutments RCC
124 1 x 3.4 2 x 7.5 25 Solid slab Satisfactory Condition.
Rayapura. culvert and wing walls parapet
951 + 380 RCC Solid PCC abutments RCC
125 1x6.9 6.9 2 x 7.5 25 Satisfactory Condition.
Rayapura. Slab and wing walls. parapet.
951 + 500 RCC Solid PCC abutments RCC
126 1x6.9 6.9 2 x 7.5 25 Satisfactory Condition.
Rayapura. Slab and wing walls. parapet.
951 + 900 RCC Solid PCC abutments RCC
127 1x6.9 6.9 2 x 7.5 25 Satisfactory Condition.
Rayapura. Slab and wing walls. parapet.
953 + 580 RCC Solid PCC abutments RCC
128 1x7.5 7.5 2 x 7.5 25 Satisfactory Condition.
Rayapura. Slab and wing walls. parapet.
PCC abutments
Good Condition on LHS,
954 + 990 RCC Solid and wing walls on RCC
129 1x6.9 7.5 2 x 7.5 25 Repaired poor condition on
Rayapura. Slab LHS, Brick parapet.
RHS.
masonry on RHS.
Brick masonry
10.0 on abutments and
Poor condition on LHS and
961 + 500 Slab LHS, wing walls on LHS. RCC
130 1x4 2 x 7.5 Solid slab Satisfactory condition on
Aurangabad. culvert 10.0 on PCC abutments parapet
RHS.
RHS and wing walls on
RHS.
961 + 800 Slab PCC abutments RCC
131 1 x 3.7 2 x 7.5 25 Solid slab Satisfactory Condition.
Aurangabad. culvert and wing walls parapet
962 + 300 Slab PCC abutments RCC
132 1 x 4.5 2 x 7.5 25 Solid slab Satisfactory Condition.
Aurangabad. culvert and wing walls parapet
15.0 on PCC abutments
Good Condition on LHS,
964 + 985 LHS, RCC Solid and wing walls on RCC
133 1x9.0 9.00 2 x 7.5 Repaired poor condition on
Mufsil. 10.0 on Slab LHS, Brick parapet.
RHS. Canal Crossing.
RHS masonry on RHS.
Sl. Type of Size Carriageway Overall Type of Type of Hand General Conditions and
Location width
No. structure (NoxWxH) width(m) superstructure substructure rails Observations
(m)on
15.4 RCC abutments
Good Condition on LHS,
968 +200 LHS, RCC Solid and wing walls on RCC
134 1x6.8 6.80 2 x 7.5 Repaired poor condition on
Karhara 10.4 on Slab LHS, Brick parapet.
RHS.
RHS masonry on RHS.
15.4 on RCC abutments
Good Condition on LHS,
968 + 900 LHS, RCC Solid and wing walls on RCC
135 1x6.8 6.80 2 x 7.5 Repaired poor condition on
Karhara 10.4 on Slab LHS, Brick parapet.
RHS.
RHS masonry on RHS.
970 + 470 Slab PCC abutments RCC
136 1 x 3.6 2 x 7.5 25.8 Solid slab Satisfactory Condition.
Manjurkha. culvert and wing walls parapet
971 + 030 Slab PCC abutments RCC Satisfactory Condition.
137 1 x 6.8 2 x 7.5 25.8 Solid slab
Manjurkha. culvert and wing walls parapet Canal crossing.
973 + 200 Box RCC Satisfactory Condition.
138 1 x 2.6 x 2.0 2 x 7.5 25.8 PCC wing walls
Dev. culvert parapet Canal crossing.
973 + 250 Box RCC Satisfactory Condition.
139 1 x 2.6 x 2.0 2 x 7.5 25.8 PCC wing walls
Dev. culvert parapet Canal crossing.
PCC abutments
15.4 on and wing walls on
Satisfactory condition on
973 + 300 Slab LHS, LHS. Brick RCC
140 1 x 6.5 2 x 7.5 Solid slab LHS. Poor condition on
Dev. culvert 15.4 on masonry parapet
RHS
RHS abutments and
wing walls on RHS.
10.0 on RCC abutments
Good Condition on LHS,
974 + 000 LHS, RCC Solid and wing walls on RCC
141 1x10.0 10.00 2 x 7.5 Repaired poor condition on
Dev. 10.4 on Slab LHS, Stone parapet.
RHS.
RHS masonry on RHS.
974 + 650 Box RCC
142 1 x 3.6 x 2.0 2 x 7.5 25 PCC wing walls Satisfactory Condition.
Rafiganj. culvert parapet
Sl. Type of Size Carriageway Overall Type of Type of Hand General Conditions and
Location width
No. structure (NoxWxH) width(m) superstructure substructure rails Observations
Box (m) PCC wing walls on
15.4 on
culvert on LHS. Brick Satisfactory condition on
976 + 180 LHS, RCC
143 LHS, Slab 1 x 3.6 2 x 7.5 masonry LHS. Poor condition on
Rafiganj. 10.4 on parapet
culvert on substructure on RHS
RHS
RHS. RHS.
The general arrangement for the structure at above mentioned are enclosed in
Fig - 3.8 to Fig - 3.18. The list of existing Major, Minor bridge, underpass, ROB and
proposed underpasses & flyover are indicated hereunder:
Fig - 3.13 : Typical C/S for Widening of Major Bridges in Urban areas
Fig - 3.17 : Typical C/S for Widening of Minor Bridges in Urban areas
Fig - 3.18 : Typical C/S for Widening of Minor Bridges (Total Reconstruction)
Fig - 3.19 : Typical C/S for Widening of Minor Bridges (Total Reconstruction)
Fig - 3.30 : Typical C/S for Widening of Existing Slab culvert/ Bridge
Sl. Chainage and Span Overall Carriageway Overall Type of Type of Hand General Conditions
No. Name of Arrangement Length(m) width(m) width superstructure substructure rails and Observations
Crossing (m)
RCC
railing
Stone Masonry
Solid slab on on
8.4 on Substructure
33 x 5.5 on LHS, PSC LHS. Poor Condition on
853 + 900 2 x 7.5 + LHS, on LHS. RCC
7 LHS 6 x 33 206.6 Continuous RCC LHS. Good condition
Savad Foot paths 10.5 on wall type pier,
on RHS girders on crash on RHS.
RHS abutment on
RHS. barrier
RHS.
on
RHS.
RCC
railing
Stone Masonry
Solid slab on on
2x9.0 + 4x26.5 8.5 on Substructure
LHS, PSC LHS. Poor Condition on
854 + 000 on LHS, 2 x 7.5 + LHS, on LHS. RCC
8 124 Continuous RCC LHS. Good condition
Savad 3 x 38.5 on Foot paths 10.5 on wall type pier,
girders on crash on RHS.
RHS RHS abutment on
RHS. barrier
RHS.
on
RHS.
RCC wall type
PSC pier, spill
RCC
13.7 on Continuous through
crash Good condition on
893 + 700 3x25 on LHS, 2 x 7.5 + LHS, girders on LHS, abutment on
9 75 barrier LHS. Poor repaired
Kudra 4x15.3 on RHS Foot paths 8.0 on Stone masonry LHS. Stone
& MS condition on RHS.
RHS arch bridge on Masonry
railing.
RHS. Substructure
on RHS.
10.4 on RCC wall RCC
3x36 on LHS,
932 + 000 2 x 7.5 + LHS, piers, parapet
10 2x25 + 2x24.5 108 PSC girders. Good Condition.
Dehari Onson Foot paths 10.4 on Abutments and & MS
+8.3 on RHS
RHS returns. Railing
Sl. Chainage and Span Overall Carriageway Overall Type of Type of Hand General Conditions
No. Name of Arrangement Length(m) width(m) width superstructure substructure rails and Observations
Crossing (m) RCC wall
935 + 500 10.4 on PSC box RCC
46x66 on piers,
Son River, 2 x 7.5 + LHS, girders on LHS, parapet
11 LHS, 3036 Abutments and Good Condition.
Dalmiya nagar, Foot paths 10.4 on PSC 'I' girders & MS
92x33 on RHS returns. Well
Dehari. RHS on RHS. Railing
foundations.
RCC wall RCC
945 + 400 2 x 7.5 + piers, parapet
12 3 x 42.8 128.4 25 T giders. Good Condition.
Barunganj. Foot paths Abutments and & MS
returns. Railing
10.4 on RCC wall RCC
953 + 800 2 x 7.5 + LHS, piers, parapet
13 5 x 37.8 189 PSC girders. Good Condition.
Rayapura. Foot paths 10.4 on Abutments and & MS
RHS returns. Railing
15 on RCC wall RCC
962 + 500
2 x 7.5 + LHS, piers, parapet
14 Adri river, 3 x 26.75 80.25 PSC girders. Good Condition.
Foot paths 10 on Abutments and & MS
Aurangabad.
RHS returns. Railing
15 on RCC wall RCC
966 + 950
2 x 7.5 + LHS, piers, parapet
15 Terar river, 4 x 21.5 86 PSC girders. Good Condition.
Foot paths 10 on Abutments and & MS
Mufsil
RHS returns. Railing
RCC
Abutments and
10.5 on RCC
1 x 45.9 on Box girder on returns on Good condition on
974 + 150 2 x 7.5 + LHS, parapet
16 LHS, 4 x 11 on 46 LHS. Solid slab LHS. Stone LHS. Poor repaired
Kesar Foot paths 8.5 on & MS
RHS. on RHS. masonry condition on RHS.
RHS Railing
substructure
on RHS.
Sl. Chainage and Span Overall Carriageway Overall Type of Type of General Conditions
Hand rails
No. Name of Arrangement Length(m) width(m) width superstructure substructure and Observations
RCC Abutments,
15.7 on
871 + 800 Voided slab on brick masonry RCC Good Condition on
1x19.5 LHS, 2 x 7.5 + LHS,
10 Mandevi 19.5 LHS, Solid slab substructure and parapet & LHS, Repaired poor
4x4.75RHS Meadian 10.5 on
Mazavi on RHS. wing walls on MS Railing condition on RHS.
RHS
RHS.
15.7 on RCC Abutments,
872 + 700 Voided slab on RCC Good Condition on
1x18.5 LHS, 2 x 7.5 + LHS, PCC substructure
11 Mandevi 18.5 LHS, Solid slab parapet & LHS, Repaired poor
4x4.5 RHS Meadian 10.5 on and wing walls on
Mazavi on RHS. MS Railing condition on RHS.
RHS RHS.
RCC Abutments,
15.0 on
Voided slab on brick masonry RCC
878 + 000 1x18.8 LHS, 2 x 7.5 + LHS, Poor Condition.
12 18.8 LHS, Solid slab substructure and parapet &
Pusauli 4x4.75 RHS Meadian 10.0 on Blocked water way.
on RHS. wing walls on MS Railing
RHS
RHS.
RCC Abutments,
15.0 on
Voided slab on brick masonry RCC
878 + 400 1x18.75 LHS, 2 x 7.5 + LHS, Poor Condition.
13 18.8 LHS, Solid slab substructure and parapet &
Pusauli 4x4.65 RHS Meadian 10.0 on Blocked water way.
on RHS. wing walls on MS Railing
RHS
RHS.
RCC
889 + 300 2 x 7.5 +
14 1 x 14 14 25 Voided slab RCC Abutments parapet & Good Condition.
Kudra Meadian
MS Railing
Satisfactory
RCC Abutments,
15.0 on Condition. Canal
Voided slab on Brick masonry RCC
893 + 010 1x17.8 LHS, 2 x 7.5 + LHS, crossing.
15 18 LHS, Solid slab substructure and parapet &
Kudra 2x8.85 RHS Meadian 10.0 on
on RHS. wing walls on MS Railing
RHS
RHS.
RCC
909 + 000 2 x 7.5 + RCC abutment Good Condition.
16 1 x 39 39 24.4 PSC box girders. parapet &
Morava Sarai Meadian and return walls Canal Crossing.
MS Railing
RCC
915 + 200 2 x 7.5 + RCC abutment
17 1 x 39 39 24.4 PSC girders. parapet & Good Condition.
Morava Sarai Meadian and return walls
MS Railing
Sl. Chainage and Span Overall Carriageway Overall Type of Type of General Conditions
Hand rails
No. Name of Arrangement Length(m) width(m) width superstructure substructure and Observations
RCC
930 + 500 2 x 7.5 + RCC abutment Good Condition.
18 1 x 39.4 39.4 25 PSC girders. parapet &
Dehari Onson Meadian and return walls Canal Crossing.
MS Railing
RCC abutment on
15.0 on
Voided slab on LHS. Brick RCC Good Condition on
939 + 950 1x20.5 LHS, LHS,
19 24 2 x 7.5 LHS, Solid slab masonry parapet & LHS, Repaired poor
Barun 3x8.0 RHS 10.0 on
on RHS. abutments and MS Railing condition on RHS.
RHS
piers on RHS.
15.0 on
RCC wall type RCC
940 + 100 1x44 LHS, LHS, Good Condition.
20 44 2 x 7.5 Box girder. piers and parapet &
Barunganj 2x26.6 RHS 10.0 on Canal Crossing.
abutments. MS Railing
RHS
RCC
940 + 200 RCC abutments Good Condition.
21 1x19.5 19.5 2 x 7.5 25 Voided slab. parapet &
Barunganj and returns. Canal Crossing.
MS Railing
PCC abutments on
15.0 on
1x21.0 on LHS, Voided slab on LHS, Brick Good Condition on
948 + 100 LHS, RCC
22 2x10.5 on 21 2 x 7.5 LHS, Solid slab masonry LHS, Repaired poor
Rayapura. 10.0 on parapet.
RHS. on RHS. substructure on condition on RHS.
RHS
RHS.
15.0 on PCC abutments
Good Condition on
958 + 300 1x18.0 on LHS, LHS, and wing walls on RCC
23 7.5 2 x 7.5 RCC Solid Slab LHS, Repaired poor
Raniganj. 2x9.0 on RHS. 10.0 on LHS, Brick parapet.
condition on RHS.
RHS masonry on RHS.
15.4 on RCC abutments Good Condition on
Voided slab on
968 + 010 1x23.6 on LHS, LHS, and wing walls on RCC LHS, Repaired poor
24 23.60 2 x 7.5 LHS, Solid slab
Mufsil. 4x5.8 on RHS. 10.4 on LHS, Brick parapet. condition on RHS.
on RHS.
RHS masonry on RHS. Canal Crossing.
5 854.420 - - - - - - - -
2 x 7.5 +
912 + 900 RCC box RCC
6 1 x 7.8m box 7.8 Foot paths + 25 - Good Condition.
Morava Sarai culvert. Parapet
Meadian
2 x 7.5 +
913 + 300 RCC box RCC
7 1 x 8m box 8 Foot paths + 45 - Good Condition.
Morava Sarai culvert. Parapet
Meadian
2 x 7.5 + Good Condition.
920 + 000 RCC box RCC
8 1 x 7.7m box 7.7 Foot paths + 25 -
Suara culvert. Parapet
Meadian
2 x 7.5 +
923 + 000 RCC box RCC
9 1 x 8m box 8 Foot paths + 25 - Good Condition.
Dehari culvert. Parapet
Meadian
10 932.750 - - - - - - - -
Sl. Chainage and Span Overall Carriageway Overall Type of Type of Hand General Conditions and
No. Name of Arrangement Length(m) width(m) width superstructure substructure rails Observations
Crossing 2 x 7.5 + (m)
962 + 400 RCC box RCC
11 1 x 6.7m box 6.7 Foot paths + 25 - Improper layout
Aurangabad. culvert. Parapet
Meadian
Sl. Chainage and Span Overall Carriageway Overall Type of Type of Hand General Conditions and
No. Name of Arrangement (m) Length(m) width(m) width superstructure substructure rails Observations
Crossing (m) RCC multiple
column with
804 + 800 2 x 7.5 + Foot
2 x 18.4 + T girder + deck common pier RCC
6 Ramnagar 61.8 paths + 26.2 Good Condition
1 x 25.0 slab cap. Spill rails
bypass Meadian
through
abutment.
2 x 7.5 + Foot RCC pier & cap
817 + 300 RCC
7 1 x 15.1 20 paths + 23.5 Voided slab RE wall Good Condition
Pachfedva Parapet
Meadian approaches
2 x 7.5 + Foot
828 + 200 RCC Good Condition.
8 1 x 8.5 8.5 paths + 23 RCC box culvert. -
Chandauli Parapet Non-standard size.
Meadian
866 + 800 2 x 7.5 + Foot RCC pier & cap RCC
9 Chandni Chauk 1 x 22 22 paths + 23.5 Box girder RE wall Parapet Good Condition.
Mohaniya Meadian approaches & rails
2 x 7.5 + Foot
888 + 500 Solid ramp RCC Good Condition.
10 1 x 7.8m box 7.8 paths + 23.5 RCC box culvert
Kudra approaches. Parapet Non-standard size.
Meadian
2 x 7.5 + Foot
911 + 000 Solid ramp RCC Good Condition.
11 1 x 8.0m box 8.5 paths + 25 RCC box culvert
Morava Sarai approaches. Parapet Non-standard size.
Meadian
2 x 7.5 + Foot
913 + 600 RCC
12 1 x 15.0m box 15 paths + 25 RCC box culvert PCC Wing walls Good Condition.
Morava Sarai Parapet
Meadian
2 x 7.5 + Foot
918 + 000 RCC
13 1 x 8.0m box 8 paths + 25 RCC box culvert PCC Wing walls Good Condition.
Gavaliya Tola Parapet
Meadian
15.0 on RCC
2 x 7.5 + Foot PSC girders on
922 + 100 1 x 39.4 on LHS. LHS, RCC abutment parapet
14 39.4 paths + LHS, RCC Satisfactory Condition.
Dehari Onson 2 x 12m on RHS. 10.0 on and return walls & MS
Meadian girders on RHS.
RHS Railing
15 932.050 - - - - - - - -
Sl. Chainage and Span Overall Carriageway Overall Type of Type of Hand General Conditions and
No. Name of Arrangement (m) Length(m) width(m) width superstructure substructure rails Observations
Crossing (m)
16 933+500 - - - - - - - -
RCC
2 x 7.5 + Foot RCC wall pier.
959 + 800 parapet
17 2 x 15.0 30 paths + 25 Voided slab RE wall Good Condition.
Aurangabad & MS
Meadian approaches.
Railing
RCC abutment
1 x 26.3m on 10.5 on and return walls RCC
2 x 7.5 + Foot Voided slab on Good Condition on LHS.
974 + 350 LHS. LHS, on LHS. Stone parapet
18 26.3 paths + LHS, Solid slab Poor repaired condition
Dev 3 x 8.6m on 8.5 on masonry & MS
Meadian on RHS. on RHS.
RHS. RHS substructure on Railing
RHS.
Location /
Sl. Approximate
Name of Required Action.
No. chainage.
bridge
1 Chandauli 809 + 850 To be widened by additional 2 lane Bridge on either side.
2 Naubatpur 842 + 400 To be widened by additional 2 lane Bridge on either side.
3 Naubatpur 842 + 600 To be widened by additional 2 lane Bridge on either side.
4 Naubatpur 842 + 800 To be widened by additional 2 lane Bridge on either side.
Reconstruct LHS with 4 lane Bridge, Widen RHS by
5 Ruhava 853 + 600
additional 2 lane Bridge.
Reconstruct LHS with 4 lane Bridge, Widen RHS by
6 Savad 853 + 900
additional 2 lane Bridge.
Reconstruct LHS with 4 lane Bridge, Widen RHS by
7 Savad 854 + 000
additional 2 lane Bridge.
Widen LHS by additional 2 lane Bridge, Reconstruct RHS
8 Kudra 893 + 700
with 4 lane Bridge.
Dehari
9 932 + 000 To be widened by additional 2 lane Bridge on either side.
Onson
10 Barunganj. 945 + 400 To be widened by additional 2 lane Bridge on either side.
11 Rayapura. 953 + 800 To be widened by additional 2 lane Bridge on either side.
Adri river,
12 962 + 500 To be widened by additional 2 lane Bridge on either side.
Aurangabad.
Terar river,
13 966 + 950 To be widened by additional 2 lane Bridge on either side.
Mufsil
Widen LHS by additional 2 lane Bridge, Reconstruct RHS
14 Kesar 974 + 150
with 4 lane Bridge.
Location /
Sl. Name of Approximate
No. bridge chainage. Required Action.
1 Katsila 824 + 150 To be widened by additional 4 lane Bridge on either side.
2 Bargana 833 + 550 Widen LHS by additional 4 lane, Reconstruct RHS with 5
lane Bridge.
3 Bargana 835 + 850 To be widened by additional 4 lane Bridge on either side.
4 Saiyad raja 837 + 620 To be widened by additional 4 lane Bridge on either side.
5 Naubatpur 843 + 980 Widen LHS by additional 4 lane, Reconstruct RHS with 5
lane Bridge.
6 Naubatpur 844 + 200 Widen LHS by additional 4 lane, Reconstruct RHS with 5
lane Bridge.
7 Naubatpur 844 + 420 Widen LHS by additional 4 lane, Reconstruct RHS with 5
lane Bridge.
8 Ruhava 853 + 800 Reconstruct LHS with 5 lane Bridge, Widen RHS by
additional 4 lane Bridge.
9 Mandevi 870 + 500 To be widened by additional 4 lane Bridge on either side.
Mazavi
Location /
Sl. Name of Approximate
No. bridge chainage. Required Action.
10 Mandevi 871 + 800 Widen LHS by additional 4 lane, Reconstruct RHS with 5
Mazavi lane Bridge.
11 Mandevi 872 + 700 Widen LHS by additional 4 lane, Reconstruct RHS with 5
Mazavi lane Bridge.
22 Rayapura. 948 + 100 Widen LHS by additional 4 lane, Reconstruct RHS with 5
lane Bridge.
23 Raniganj. 958 + 300 Widen LHS by additional 4 lane, Reconstruct RHS with 5
lane Bridge.
24 Mufsil. 968 + 010 Widen LHS by additional 4 lane, Reconstruct RHS with 5
lane Bridge.
Sl. Approximate
Location Existing size Required Action.
No. chainage.
No widening is proposed due to Land
1 Barvan 787 + 500 26 x 5
constraint.
To be reconstructed to a standard size
2 Rampur 794 + 325 8x6
six lane VUP.
3 Amra Bypass 796 + 125 10 x 5 To be widened to six lane configuration.
To be reconstructed to a standard size
4 Dafi 801 + 600 7x6
six lane VUP.
To be reconstructed to a standard size
5 Ramnagar 802 + 010 8x5
six lane VUP.
To be reconstructed to a standard size
6 Ramnagar 802 + 700 6x4
six lane VUP.
Ramnagar
7 805 + 400 62 x 5 To be widened to six lane configuration.
bypass
8 Pachfedva 817 + 000 15 x 5 To be widened to six lane configuration.
No widening is proposed due to Land
9 Chandauli 828 + 200 8.5 x 4.0
constraint.
Chandni Chauk No widening is proposed due to Land
10 866 + 600 22 x 5.5
Mohaniya constraint..
No widening is proposed due to Land
11 Kudra 888 + 400 8x5
constraint.
To be reconstructed to a standard size
12 Morava Sarai 907 + 600 8x3
six lane VUP.
To be reconstructed to a standard size
13 Morava Sarai 911 + 000 8x4
six lane VUP.
To be widened to six lane
14 Morava Sarai 913 + 600 15 x 4
configuration.
To be reconstructed to a standard size
15 Gavaliya Tola 918 + 000 8x5
six lane VUP.
35 x 4 on LHS Widen LHS , Reconstruct RHS so as
16 Dehari Onson 922 + 100
2x 12 x 3 on RHS to have six lane configuration.
17 Aurangabad 959 + 800 2 x 15 x 5.5 To be widened to six lane configuration.
26 x 5 on LHS Widen LHS , Reconstruct RHS so as
18 Dev 974 + 350
3x 8 x 5 on RHS to have six lane configuration.
Sl. Approximate
Location Required Action.
No. chainage.
1 Barvan 788 + 650 To be widened to six lane configuration.
2 Ramnagar 809 + 050 To be widened to six lane configuration.
3 Barunganj 940 + 800 To be widened to six lane configuration.
3.9.2 30 nos of new Vehicular Underpass are proposed and the locations are indicated
in Table - 3.22
Chainages
Sr No Type Size
From To
1 792.230 792.730 PROPOSED VEHICULAR UNDERPASS 13.5 x 5 m
2 798.705 799.205 PROPOSED VEHICULAR UNDERPASS 13.5 x 5 m
3 807.020 807.520 PROPOSED VEHICULAR UNDERPASS 13.5 x 5 m
4 812.255 812.755 PROPOSED VEHICULAR UNDERPASS 13.5 x 5 m
5 823.150 823.650 PROPOSED VEHICULAR UNDERPASS 13.5 x 5 m
6 827.150 827.710 PROPOSED VEHICULAR UNDERPASS 13.5 x 5 m
7 828.750 829.250 PROPOSED VEHICULAR UNDERPASS 13.5 x 5 m
8 830.520 831.000 PROPOSED VEHICULAR UNDERPASS 13.5 x 5 m
9 834.930 835.430 PROPOSED VEHICULAR UNDERPASS 13.5 x 5 m
10 837.861 838.401 PROPOSED VEHICULAR UNDERPASS 13.5 x 5 m
11 841.950 842.375 PROPOSED VEHICULAR UNDERPASS 13.5 x 5 m
12 847.450 848.000 PROPOSED VEHICULAR UNDERPASS 13.5 x 5 m
13 851.950 852.420 PROPOSED VEHICULAR UNDERPASS 13.5 x 5 m
14 856.550 857.050 PROPOSED VEHICULAR UNDERPASS 13.5 x 5 m
15 860.850 861.350 PROPOSED VEHICULAR UNDERPASS 13.5 x 5 m
16 872.780 873.280 PROPOSED VEHICULAR UNDERPASS 13.5 x 5 m
17 876.550 877.050 PROPOSED VEHICULAR UNDERPASS 13.5 x 5 m
18 879.430 879.630 PROPOSED VEHICULAR UNDERPASS 13.5 x 5 m
19 883.251 883.751 PROPOSED VEHICULAR UNDERPASS 13.5 x 5 m
20 894.150 894.650 PROPOSED VEHICULAR UNDERPASS 13.5 x 5 m
21 899.690 900.190 PROPOSED VEHICULAR UNDERPASS 13.5 x 5 m
22 902.600 903.100 PROPOSED VEHICULAR UNDERPASS 13.5 x 5 m
23 937.550 938.050 PROPOSED VEHICULAR UNDERPASS 13.5 x 5 m
24 941.800 942.300 PROPOSED VEHICULAR UNDERPASS 13.5 x 5 m
25 945.700 946.200 PROPOSED VEHICULAR UNDERPASS 13.5 x 5 m
26 949.300 949.800 PROPOSED VEHICULAR UNDERPASS 13.5 x 5 m
27 953.044 953.544 PROPOSED VEHICULAR UNDERPASS 13.5 x 5 m
28 957.650 958.093 PROPOSED VEHICULAR UNDERPASS 13.5 x 5 m
29 968.200 968.700 PROPOSED VEHICULAR UNDERPASS 13.5 x 5 m
30 972.820 973.320 PROPOSED VEHICULAR UNDERPASS 13.5 x 5 m
3.9.3 75 nos of new Pedetrian Underpass are proposed and the locations are indicated
in Table - 3.23
Chainages
Sr No Type Size
From To
1 789.275 789.525 PROPOSED PEDESTRAIN UNDERPASS 4.0 x 2.5 m
2 790.794 791.014 PROPOSED PEDESTRAIN UNDERPASS 10.0 x 3.5 m
3 793.175 793.425 PROPOSED PEDESTRAIN UNDERPASS 10.0 x 3.5 m
4 797.450 797.700 PROPOSED PEDESTRAIN UNDERPASS 4.0 x 2.5 m
5 805.875 806.125 PROPOSED PEDESTRAIN UNDERPASS 10.0 x 3.5 m
6 808.685 808.935 PROPOSED PEDESTRAIN UNDERPASS 4.0 x 2.5 m
7 810.300 810.550 PROPOSED PEDESTRAIN UNDERPASS 4.0 x 2.5 m
8 812.975 813.225 PROPOSED PEDESTRAIN UNDERPASS 10.0 x 3.5 m
9 817.925 818.175 PROPOSED PEDESTRAIN UNDERPASS 4.0 x 2.5 m
10 819.155 819.300 PROPOSED PEDESTRAIN UNDERPASS 4.0 x 2.5 m
11 820.491 820.741 PROPOSED PEDESTRAIN UNDERPASS 4.0 x 2.5 m
12 821.376 821.626 PROPOSED PEDESTRAIN UNDERPASS 4.0 x 2.5 m
13 822.325 822.575 PROPOSED PEDESTRAIN UNDERPASS 4.0 x 2.5 m
14 824.675 824.925 PROPOSED PEDESTRAIN UNDERPASS 10.0 x 3.5 m
15 825.740 825.989 PROPOSED PEDESTRAIN UNDERPASS 10.0 x 3.5 m
16 830.085 830.330 PROPOSED PEDESTRAIN UNDERPASS 10.0 x 3.5 m
17 832.000 832.350 PROPOSED PEDESTRAIN UNDERPASS 4.0 x 2.5 m
18 834.095 834.345 PROPOSED PEDESTRAIN UNDERPASS 4.0 x 2.5 m
19 836.857 837.107 PROPOSED PEDESTRAIN UNDERPASS 4.0 x 2.5 m
20 840.475 840.725 PROPOSED PEDESTRAIN UNDERPASS 4.0 x 2.5 m
21 843.478 843.728 PROPOSED PEDESTRAIN UNDERPASS 4.0 x 2.5 m
22 845.030 845.280 PROPOSED PEDESTRAIN UNDERPASS 4.0 x 2.5 m
23 846.235 846.485 PROPOSED PEDESTRAIN UNDERPASS 10.0 x 3.5 m
24 848.775 849.025 PROPOSED PEDESTRAIN UNDERPASS 4.0 x 2.5 m
25 849.675 849.925 PROPOSED PEDESTRAIN UNDERPASS 4.0 x 2.5 m
26 850.478 850.728 PROPOSED PEDESTRAIN UNDERPASS 10.0 x 3.5 m
27 855.403 855.653 PROPOSED PEDESTRAIN UNDERPASS 4.0 x 2.5 m
28 857.900 858.155 PROPOSED PEDESTRAIN UNDERPASS 4.0 x 2.5 m
29 858.985 859.235 PROPOSED PEDESTRAIN UNDERPASS 4.0 x 2.5 m
30 862.905 863.055 PROPOSED PEDESTRAIN UNDERPASS 10.0 x 3.5 m
31 863.905 864.155 PROPOSED PEDESTRAIN UNDERPASS 4.0 x 2.5 m
32 864.835 865.185 PROPOSED PEDESTRAIN UNDERPASS 4.0 x 2.5 m
33 865.875 865.125 PROPOSED PEDESTRAIN UNDERPASS 10.0 x 3.5 m
34 868.925 869.175 PROPOSED PEDESTRAIN UNDERPASS 4.0 x 2.5 m
35 870.775 871.025 PROPOSED PEDESTRAIN UNDERPASS 10.0 x 3.5 m
36 871.328 871.578 PROPOSED PEDESTRAIN UNDERPASS 10.0 x 3.5 m
37 874.334 874.584 PROPOSED PEDESTRAIN UNDERPASS 4.0 x 2.5 m
38 875.475 875.725 PROPOSED PEDESTRAIN UNDERPASS 10.0 x 3.5 m
39 878.574 878.824 PROPOSED PEDESTRAIN UNDERPASS 10.0 x 3.5 m
Chainages
Sr No Type Size
From To
40 881.425 881.675 PROPOSED PEDESTRAIN UNDERPASS 4.0 x 2.5 m
41 882.510 882.765 PROPOSED PEDESTRAIN UNDERPASS 4.0 x 2.5 m
42 884.845 885.095 PROPOSED PEDESTRAIN UNDERPASS 4.0 x 2.5 m
43 885.825 886.175 PROPOSED PEDESTRAIN UNDERPASS 4.0 x 2.5 m
44 887.055 887.305 PROPOSED PEDESTRAIN UNDERPASS 4.0 x 2.5 m
45 889.575 889.825 PROPOSED PEDESTRAIN UNDERPASS 10.0 x 3.5 m
46 890.975 891.225 PROPOSED PEDESTRAIN UNDERPASS 10.0 x 3.5 m
47 891.875 892.125 PROPOSED PEDESTRAIN UNDERPASS 4.0 x 2.5 m
48 895.775 896.025 PROPOSED PEDESTRAIN UNDERPASS 4.0 x 2.5 m
49 896.985 897.235 PROPOSED PEDESTRAIN UNDERPASS 10.0 x 3.5 m
50 898.375 898.625 PROPOSED PEDESTRAIN UNDERPASS 10.0 x 3.5 m
51 901.335 901.585 PROPOSED PEDESTRAIN UNDERPASS 4.0 x 2.5 m
52 903.275 903.525 PROPOSED PEDESTRAIN UNDERPASS 4.0 x 2.5 m
53 904.925 905.175 PROPOSED PEDESTRAIN UNDERPASS 10.0 x 3.5 m
54 906.175 906.425 PROPOSED PEDESTRAIN UNDERPASS 10.0 x 3.5 m
55 912.276 912.526 PROPOSED PEDESTRAIN UNDERPASS 10.0 x 3.5 m
56 915.362 915.612 PROPOSED PEDESTRAIN UNDERPASS 10.0 x 3.5 m
57 930.025 930.275 PROPOSED PEDESTRAIN UNDERPASS 10.0 x 3.5 m
58 939.395 939.645 PROPOSED PEDESTRAIN UNDERPASS 10.0 x 3.5 m
59 942.775 943.025 PROPOSED PEDESTRAIN UNDERPASS 10.0 x 3.5 m
60 944.475 944.725 PROPOSED PEDESTRAIN UNDERPASS 4.0 x 2.5 m
61 946.375 946.625 PROPOSED PEDESTRAIN UNDERPASS 4.0 x 2.5 m
62 948.175 948.425 PROPOSED PEDESTRAIN UNDERPASS 4.0 x 2.5 m
63 951.060 951.308 PROPOSED PEDESTRAIN UNDERPASS 10.0 x 3.5 m
64 952.315 952.565 PROPOSED PEDESTRAIN UNDERPASS 10.0 x 3.5 m
65 955.275 955.525 PROPOSED PEDESTRAIN UNDERPASS 10.0 x 3.5 m
66 960.964 961.214 PROPOSED PEDESTRAIN UNDERPASS 10.0 x 3.5 m
67 964.925 965.175 PROPOSED PEDESTRAIN UNDERPASS 10.0 x 3.5 m
68 965.955 966.205 PROPOSED PEDESTRAIN UNDERPASS 10.0 x 3.5 m
69 967.475 967.725 PROPOSED PEDESTRAIN UNDERPASS 10.0 x 3.5 m
70 969.575 969.825 PROPOSED PEDESTRAIN UNDERPASS 10.0 x 3.5 m
71 970.600 970.850 PROPOSED PEDESTRAIN UNDERPASS 10.0 x 3.5 m
72 971.195 971.445 PROPOSED PEDESTRAIN UNDERPASS 10.0 x 3.5 m
73 974.650 974.900 PROPOSED PEDESTRAIN UNDERPASS 10.0 x 3.5 m
74 976.155 976.405 PROPOSED PEDESTRAIN UNDERPASS 10.0 x 3.5 m
75 977.275 977.525 PROPOSED PEDESTRAIN UNDERPASS 4.0 x 2.5 m
3.9.6 7 nos new Truck Lay bye are proposed in the project road & there locations are
indicated in Table - 3.26
3.10 Comparison of existing & proposed facilities are indicated in Table - 3.27
i) Traffic lane lines shall be single broken lines. Their width shall be 100 mm and
the length of segments and gaps shall be as under.
On straight reaches, 1.50 m segments and 3.0 m gaps.
On curves and approaches to intersections 1.50 m segments and 1.50m
gaps.
The colour of lane markings is white and it is visible in the dark under car/truck
head lights.
ii) Continuous yellow lines, 150 mm wide are used to show the extent of the
travelled carriageway.
The traffic sign’s design is standardised for mandatory/regulatory types are as per
standard IRC-67 design.
Some of the signs will be in the verges mounted on steel posts in the usual manner. On
the approaches to junctions, overhead signs mounted on gantries have been designed.
This enables the signs to span the road and allow the driver on the moderately high
speed road to easily read the sign and take appropriate action.
The signs are proposed to be bi-lingual, in English and Hindi.
The minimum letter size is 150mm and is in accordance with the guidelines.
Hectometer/Kilometer stones and Marker Posts, Marker Stones are proposed at each
kilometer as is the practice on the Urban Roads.
i) Rigid Barriers
Rigid barriers are proposed on bridges, the details of which are provided in
the volume containing the design of standard drawings.
ii) Flexible Barriers
Flexible metal beam crash barriers are proposed at high embankment
locations & bridge/flyover approaches & the details are indicated in drawings
volume.
3.12 ENVIRONMENTAL ASPECTS
As, this is an already existing road and the work is of its up gradation to 6 lane from 4
lane, there will be no adverse effects on the environment. The existing road passes
mostly through semi – barren & agriculture areas with building and private properties on
both sides of the road at discrete locations. However at few places, it passes through
Industrial, commercial & residential areas. This aspect has been in view while proposing
cutting and filling on the existing road so as to cause the least possible disturbance to
the harmony between proposed levels of the road and the levels of the existing buildings
and internal roads. However, the widening / upgradation of the project road will result in
overall improvement of quality of environment in the surrounding region. During
construction, local environment impact is unavoidable. The mitigative measures to be
undertaken to address the following areas:
Quarrying and Earth Materials
Disposal of construction waste
Controls of traffic during construction
Movement of people, animals and noise control
Other General Aspects
These measures are discussed in detail in Chapter 6.0 of this Report separately.
CHAPTER – 4
FIELD INVESTIGATION
4.1 General
The field investigation report based on, Inventory & condition Survey, Traffic Surveys &
analysis, Topographic survey, Subgrade investigation & Soil Investigation are presented
in this chapter.
4.2 Inventory & Condition Survey for Roads, Culverts & Bridges
Inventory and condition survey of Roads, culverts and bridges of the project road have
been already completed in compliance with the IRC:SP - 19 - 2001 and TOR.
The details of inventory and condition survey of roads and bridges are indicated in
Annexure – VI & VII of the report in a separate volume.
4.3.1 General
The present stretch of National Highway NH-2 considered for six laning starts from
Varanasi (Ch.786.000) and ends at Aurangabad (Ch.978.400). The total length of the
section is 192.4km between the two places mentioned above. The project road in its
present condition is a four lane divided highway from Ch.786.000 to Ch.978.400 and
service roads at few locations in urban sections. Total length is 192.4 km in which 85.2
km (km 862.100 – km 907.100 & km 938.200 – km 978.400) are concrete pavement and
remaining 107.2 km are flexible (bituminous) pavement.
The road users in this section are having both public transport and private transport
system facilities. But the intensity of public mass transportation is very less when
compared with other. Majority of passenger traffic modes observed are private mini
buses and cars.
Classified volume counts, origin – Destination & Willing to pay surveys have been
conducted at representative count station.
Whereas Turning movement counts have been taken two major junctions and speed
delay survey have been conducted for the complete project road.
use. The normal practice is to take classified traffic volume count to evaluate the traffic
plying on a road project.
The traffic using a Junction consists of a variety of vehicles ranging from the simple
pedal cycles to the motor car and the heavy commercial vehicles, each type having an
influence on the performance of the Junction on its own way. The normal practice is to
take classified turning movement counts i.e left turn, right turn and straight ahead
movements to evaluate the traffic in a Junction.
Knowledge of the vehicular traffic volume using existing road is important for
understanding the future traffic flow characteristics on project road. The expected future
traffic on any new road is generally estimated from the O – D survey result. The traffic
from the existing road diverting away and diverting towards due to improvement of new
facility is also estimated from the O – D survey result. The specific uses of O-D studies
are
To determine the amount of by-passable traffic those enters a town and thus
establish the need of bye-pass.
To develop trip generation and trip distribution models in transportation models in
transport planning process.
To determine the extent to which the present highway system is adequate and to
plan for new facilities.
To asses the adequacy of parking facilities and to plan for future.
Speed is one of the most important characteristics of traffic and its measurement is
necessary in Traffic engineering studies. Speed studies are needed for a number of
purposes as given
The cost of the Journey depends on the speed at which it is made. In all the Highway
economic studies Journey speed and Running speed is important to know the modal
choice.
Journey time studies on a road network in town are useful to find out congestion,
Level of service, capacity and there by gives an inference for Traffic management
studies.
In transportation planning studies, the determination of the travel time is necessary
for carrying out the trip assignment.
Delay studies at the intersections provide date for the design and installation of
appropriate traffic control device.
The approach to traffic survey study was to conduct the survey for seven consecutive
days at three locations at Mid-Blocks as mentioned above. Traffic volume count was
carried in three shifts of 8 hrs in each day.
For the traffic counting purpose, a day has been divided into three shifts of 8 hours each
and separate enumerators with a supervisor assigned for each unit. Enumerators were
literate persons. Recording has been done for each direction of travel separately. For
this it was necessary to divide staff for every shift into two parties. Recording was done
in a prescribed standard format as per IRC: SP: 19-2001 “Manual for survey,
Investigation and Preparation of Road Projects (Second Revision)”.
4.3.5.1 Analysis:
From the analysis of the field data the average daily traffic (ADT), average hourly traffic
and composition of traffic have been determined.
ADT, Hourly variation, Daily variation & traffic composition at all count stations are
presented in Table-4.1 and Fig-4.1 to fig-4.9 repetitively.
ADT
Location
In Total No. of Vehicles In Terms of PCU’s
Fig – 4.1 : Hourly Variation at Km 837.0 Fig – 4.2 : Hourly Variation at Km 887.0
Fig – 4.4 : Daily Variation at Km 837.0 Fig – 4.5 : Daily Variation at Km 887.0
Fig – 4.7 : Traffic Composition at Km 837.0 Fig – 4.8 : Traffic Composition at Km 887.0
In a transportation study, it is often necessary to know the exact origin and destination of
the trips. It is very essential to know the group of trips originating from particular zones of
the study area. The other information obtained from O-D studies are Land use of the
study area, House-hold information, Socio-economic characters, trip pattern of the
individuals from that particular origin and destination, trip purpose and mode split
analysis. From this information the traffic attracting and generating can be accessed.
Origin is defined as the place from where the trip begins and destination is the place
where it ends.
To know the exact origin and destination of trips and to determine the adequacy of
proposed development plan, Origin-Destination survey was planned and conducted for
different types of vehicles for the above mentioned locations for 16 hours. For O-D
survey four enumerators in each direction were assigned for road side interview of
vehicles.
Origin-Destination study was conducted at the same place of volume count as per IRC
guidelines and data was recorded in the format given in the above reference. The
different types of vehicles were broadly divided into two categories as Passenger
vehicles and Goods Vehicles. Passenger vehicles constitute Two Wheeler, Three
wheeler, Car, Jeep, van, Bus, Cycle. Goods Vehicles constitute LCV, 2 - Axle, Multi –
Axle, Tractor. Data was recorded in the given format based on the above mentioned
categories.
4.3.6.2 Analysis
From O-D analysis, it can be seen that the local traffic % at Km 837, at Km 887 & at Km
950 is 1.20%, 2.26 % &1.77% respectively. The local traffic at all three locations, which
comprises mostly of two wheelers, three wheelers, cycles and cycle rickshaw which
does not affect the tollable traffic at those location. Also at km 837 where the local
traffic comprises of cars, at Km 887 local traffic comprises minibus, ST Bus, and LCV, at
km 950 local traffic comprises Car and ST Bus.
Speed is one of the most important characteristics of traffic and its measurement is
necessary in Traffic engineering studies. In our present studies Journey speed and
Running speeds are taken in to consideration.
Running speed is the average speed maintained by a vehicle over a given course while
the vehicle is in motion.
Journey speed is the average speed maintained by a vehicle over the entire given
course.
The approach to the speed study was to conduct the survey by Moving observer
method. In this method the speed can be obtained by traveling through out the project
corridor. Speed studies have been carried in a single stretch.
For the speed study purpose, Enumerators travel throughout the project corridor and
recording has been done for delays and running time separately. Two enumerators were
assigned separately for each task. Enumerators were literate persons. Recording was
done in a prescribed standard format as per IRC: SP: 19-2001 “Manual for survey,
Investigation and Preparation of Road Projects (Second Revision)”.
4.3.7.1 Analysis
Desirable speed on a National Highway is 100 kmph, but the running speed from the
Speed – Delay studies is 61.22 kmph, this is because certain segments of project
corridor are under construction. However, once the project road is widened to 6 lanes
with proposed facilities, vehicles will be able to ply at design speed.
The approach to traffic survey study at junctions was to conduct the survey for one day
i.e. 24 hrs at two junctions as mentioned above. Traffic volume count was done in three
shifts of 8 hrs in each day.
For the traffic counting purpose, a day has been divided into three shifts of 8 hours each
and separate enumerators with a supervisor were assigned for each unit. All the turning
movements like left turn, right turn, and straight-a-head movements for each leg are
Recorded separately. Enumerators were literate persons. Recording has been done for
each leg of Junction in both the directions separately. For this it was necessary to divide
staff for every shift into two parties. Recording was done in a prescribed standard format
as per IRC: SP: 19-2001 “Manual for survey, Investigation and Preparation of Road
Projects (Second Revision)” which is attached as annexure- III with this report.
Turning traffic summary for all the locations are given in the annexure-III. Information in
this sheet has been compiled from the field data sheets recorded for each duration of
hours for all the legs in separate forms.
4.3.8.2 Analysis
For the analysis, traffic volume in each leg of the junction have been identified and the
details are given as under:
VARANASI
TO W ARDS
730
972
331
359
337
545
62
68
TOWARDS
MUGHAL SARAI
167
278
783 1130
751 1156
180
128
1072
1304
1663 425
1864 366
166
195 AURANGABAD
TOWARDS
TO W ARDS
NH-7
104
126
429
723
71
71
604
920
IN NO's IN NO's
IN PCU's IN PCU's
TRAFFIC ANALYSIS
AT KM. 804.000 (NH-7) JUNCTION
TOWARDS
VARANASI
452
675
455
164
288
220
TOWARDS
PATNA
120
171 184
64 324
153
AURANGABAD
TOWARDS
580
263
14
27
277
607
IN NO's
IN PCU's
TRAFFIC ANALYSIS
AT KM. 867.900 JUNCTION
Adopting the well renowned elasticity method, traffic forecast has been carried out to
estimate the traffic growth by vehicle type. The time horizon considered for the study is
20 years. While the forecast is considered to be reliable for a period of 10 years, the
forecast beyond 10 years can only be indicative, as there are certain policy variables
that could change in the long run can not be predicted based on the past performance.
However, discussions were held with the State Planning authorities to make sure that
such changes are taken into account in our forecast to the extent possible.
To start with, the historical growths of vehicles have to be examined based on the traffic
surveys conducted in the past along the study corridor. Having examined the accuracy
and reliability of data, further analysis for the motor vehicle registration statistics at the
State level to establish a relationship between the economic variables and the
registration data, as a proxy for the traffic growth. The relationship has provided the
elasticity values by vehicle type, which are then compared with the results of other
studies of similar nature carried out in the recent past.
The above procedure is fully in compliance with the international practice as well as the
procedure recommended by IRC: 108: 1996, which provides guidelines on the
estimation of traffic demand elasticity values for Indian conditions.
Elasticity of traffic demand is defined as the rate at which traffic changes due to changes
in the corresponding economic variables selected. Therefore, to estimate the elasticity of
traffic demand, we have established the relationship between the traffic growth of a
particular vehicle with any one of the economic variables considered, such as NSDP, per
capita income and population growth.
The econometric model and the form of equation for estimation of the traffic demand
elasticity are as follows:
A0 = Constant
A1 = Coefficient (Elasticity Value)
Based on the above selected fit, elasticity values can be computed. It may be noted that
the values obtained based on our analysis are comparable to that of the ADB
recommended values for Indian conditions.
However, in future, the vehicle composition may change due to user preference, caused
by their increase in economic purchasing power. Also, change in technology, reduction in
unit transport costs and improvement in road conditions could cause a shift from smaller
motorized personal vehicles to bigger and more powerful vehicles. Further, smaller
capacity vehicles will give way for higher payload vehicles. Therefore, it is imperative to
consider these phenomenon in order to make the forecast a reliable one.
The forecast growth rate of economic variables and the elasticity values are used in the
following form to estimate the annual growth rate of traffic, by vehicle type.
The following growth rates were adopted based on IRC 108:1996 from the received data
for the project corridor.
The approach to Axle load survey study was to conduct the survey for 16 hours (Friday,
18th of November 2007 at km 838 of NH-2). Axle load survey was done in two shifts of 8
hrs for one day. The survey was conducted for eight hours in Varanasi-Aurangabad
direction and eight hours in Aurangabad-Varanasi direction. Two policemen were
available for the 16 hours (One police per eight hours) to stop the different types of
vehicles. The axle load of different commercial vehicles have been measured using an
axle load pad whose weighing accuracy is 20kg.
Axle load Survey was conducted at SYED RAJA (Km.838+000) and data was recorded
in the format as per IRC: SP: 19-2001. The different types of vehicles that were taken for
conducting survey are LCV, 2 - Axle, Multi - Axle, Bus. All the vehicles (LCV’s, Buses, 2
- Axles, Multi - Axles) whose Gross Vehicles Weight is greater than 3 Tonnes have been
considered for the survey.
The analysis involves converting the axle loads of all commercial vehicles into
Equivalent Standard Axle Loads (ESAL) of 8.16 tonnes and hence obtain the vehicle
damage factor, a parameter required in design of Flexible Pavement design. The axle
loads of different commercial vehicles are converted into ESAL using the fourth power
law as given in IRC: 37-2001. For a given axle load the
4
Axle Load
Standard Axle Load
Equivalent Standard Axle Load (ESAL) =
Ni
Where
i = The vehicle type under consideration i.e., LCV or Bus or 2-Axle or Multi - Axle
4.4.2 Analysis
The axle load survey data have been analysed to arrive at the VDF values for each
category of vehicles. The following VDF values have been arrived for various categories
of vehicles.
Table – 4.4 : Vehicle Damage Factors
VDF Values
Syed Raja Prithambore
Type of Vehicle Km 838.000 Km 950.000
Bus 0.6 0.5
LCV 4.0 3.7
2 – Axle 4.8 4.5
Multiaxle 6.5 6.1
layout have been superimposed thereon in a distinct colour. The plan and L-section
showing all the features existing within the right of way ( such as embankment toe lines,
protection works done, drains, service roads, planted trees, fencing, noise barriers ,
relocated utilities, etc.) as well as outside it(such as abutting properties). All such existing
features on the ground requiring to be demolished, or removed, or relocated, these
clearly shown on the drawings as well as in a separate schedule to the drawings in order
to work out innovative engineering solutions (e.g. containing the roadway within toe
wall/retaining wall, depressing the subway floor levels, box pushed structures, etc.) to
save them.
BBD tests have been conducted as per the requirement of TOR at site in compliance
with the specification of IRC: 81- 1997. After completion of field work, BBD tests data
have been analysed for the design of overlay and the details is submitted as an
Annexure-IV of this report in a separate volume.
4.6.2 ROUGHNESS
Roughness Survey have been conducted by car mounted bump Integrator on each lane
separately for the complete length of the project road.
It is observed that about 70% of the project road have good surface condition & the
remaining 30% have fair surface condition.
The detailed analysis of results is enclosed in Annexure- VIII in a separate volume.
Trial pit has been planned @ regular interval along the project road for evaluating the
subgrade properties. (Soil type, field density & CBR) and composition of existing
pavement and its individual layer thickness.
From the Sub grade investigation report, the composition of existing pavement have
been established as under:
- Bituminous Surfacing : 200 – 250 mm
- Granular Base, Sub – Base : 550 – 700 mm
- Subgrade CBR : > 10%
(With Geo – textile Layer)
This work had been assigned to a geotechnical investigation agency and completed
report is enclosed in Annexure – II in a separate volume.
4.7 SOIL & MATERIAL INVESTIGASTION
4.7.1 GENERAL
The present work involves widening of existing 4 lane road (From Varanasi to
Aurangabad (NH-2) to 6 lane divided carriageway and strengthening of existing
pavement crust. To carryout the widening and strengthening activities, we have
conducted an extensive sub grade investigation for the complete length of the project
road. In addition to the subgrade investigation, bore holes were also taken at all
Structure locations. The details of soil investigation and its findings are enclosed in
Annexure – I in a separate volume.
- Determining in-situ density (bulk and dry) and moisture content of the
subgrade under pavement.
Investigation categories (i) above are in-situ operations, while that mentioned at (ii)
involves laboratory testing.
Test pits have been located at the average rate of one in every 5 km., but the location of
the test pit within a particular km can be varied to a certain extent for obtaining
representative conditions with respect to terrain, embankment height / cut depth, soil
conditions, etc.
Where no paved shoulders are present, the test pit have been located entirely inside the
pavement, more or less along the outer wheel track on one side. Where paved
shoulders are present, the test pit might extend along its length about one-third within
the paved shoulder and two-third into the pavement proper. Alternative test pits have
been staggered on either sides of the road.
The pavement / paved shoulder layers exposed in the test pit should be identified as
regards composition and measured carefully for thickness at several points. The ‘log’ of
the test pit, i.e., the record of layer compositions and thicknesses along with pit location
details, have been recorded.
If the test pit might reveal discontinuity in pavement structure due to earlier widening, the
layer thickness and compositions for both kinds of pavement structures are to be
recorded.
If free water, soft subgrade, voids or other weaknesses / unusual conditions (e.g., rock
exposure) are encountered in the test pit, the details thereof should be specifically noted
in the test pit log.
sample bag for being drawn upon for different tests. The sample bags with the leftovers
of the samples should be preserved till the test data have been accepted.
All subgrade samples have been tested for the following:
- Particle size analysis
- Atterberg limits (LL, PL, PI)
- Laboratory compaction test using light compaction (IS : 2720 – Part-VIII), which
is appropriate for most existing poorly or unevenly compacted sub-grades of
existing pavements.
Based on the above test data and taking local geology into account, the subgrade soils
have been classified into homogeneous groups. Representative samples, equal to one-
third the total number of samples in each group and rounded off to the next higher
integer, should be selected for CBR testing.
For each sample selected for CBR testing, minimum 3 remoulded specimens are tested
at different levels of dynamic compaction. The moisture content of remoulding for all the
specimens were the optimum moisture content.
The CBR specimens have been tested after 4 days soaking. Swelling observations
have taken carried out during soaking.
For expansive and structured soils (if encountered at the subgrade level), CBR tests
have been conducted on a case-specific basis (i.e, using different levels of compaction
as also varying moulding moisture contents).
The relevant Indian Standards have been followed for testing soils in the laboratory.
Data for individual tests are compiled according to data formats given in the applicable
Indian Standards and are enclosed in Annexure - I
Abstract data road section-wise for all laboratory and field investigations are compiled
together to facilitate evaluation and interpretation.
Two formats are enclosed here with to record the following information.
Field records of layer composition & thickness of existing pavement crust.
Abstract of subgrade density tests and sampling
4.7.4.2 Soil and rock samples taken for bore holes have been tested in laboratory. The
Laboratory tests in Soil and rock sample were in compliance with relevant British
codes/Standard.
4.7.4.3 The details of soil investigation results are included in Annexure – I in a separate
volume.
CHAPTER – 5
PRELIMINARY DESIGN
The Preliminary design of project road Alignment & Geometry and Pavement are
presented in this chapter.
5.1 ALIGNMENT AND GEOMETRY
5.1.1 GENERAL
The assignment involves widening of existing 4 – lane project road from Varanasi -
Aurangabad (NH-2) to 6 lane divided carriageway keeping the existing geometry intact
and strengthening of its pavement crust.
The existing road is 4 lane divided carriageway with total length of 192.4 km in which
85.2 km (km 862.100 – km 907.100 & km 938.200 – km 978.400) is concrete pavement
and remaining 107.2 km is flexible (bituminous) pavement.
Geometric parameters proposed for the design of Horizontal alignment and Vertical
profile of the project road are indicated here under:
(b) Shoulder
(i) Paved “ m 1.50 ,,
(d) Median
(Flushed/Raised) m 20/1.2 Each direction
4 Cross fall
Terrain is classified by the general slope of the area across the road alignment. The
Project roads passes through plain, rolling and Maintenance terrain. The percent cross
slope for plain and rolling terrain is given as:
The ruling and the minimum design speed for different terrain is tabulated as under:
Terrain
Design speed (Kmph)
Ruling Minimum
Plain 100 80
Rolling 80 65
Mountainous 50 40
The ruling design speed should normally be the guiding criteria for correlating the
various geometric design features. Minimum design speed may, however, be
adopted in sections where site conditions or economics do not permit a design
based on the ruling design speed.
Formation Width
A formation width of 55.00 m is considered for the design of the main road which is
having a configuration of 6-lane divided carriageway. However, the formation width may
vary at the approaches of junction to accommodate speed change lane and also at
locations of Service roads, built-up areas, etc.
The Project road shall be designed as a dual carriage way with three lanes on either
side. The width of each lane shall be 3.5m, giving a total width of 10.5m for each
carriage way.
However, at 5 – congested built up areas, main C/W has been kept as 2+2 lanes with 2
lanes slip road with similar pavement composition as that of main C/W due to land
constraint.
Median Width
The width of the central median in Rural Section shall be 4.5 & 7.0 for Raised &
Depressed median respectively. Similarly, the width of the central median in Urban
Section shall be 2.0 & 1.2 for Flush & Raised median respectively As far as possible,
the median should be of uniform width in a particular stretch. Wherever, changes are
unavoidable, a transition in 1 in 15 to 1 in 20 must be provided.
The central median will be provided with channel kerb stone on both sides.
Service Road
The width of Service road carriageway width is 5.5/7.0 m in general in each side. A
paved shoulder of 0.5m width shall be provided on both sides. However, provision of
paved shoulder shall be dispensed with wherever there is land constraint.
Paved Shoulder
Paved shoulder is generally 1.5 m width for both Urban & Rural section.
The earthen shoulder for Urban section shall be 1.5m to 2.0m. Similarly the earthen
shoulder for Rural section shall be 2.0m.
Provision of earthen shoulder is made
To accommodate break down vehicle on the paved shoulder, it will be mainly used by
cyclists and pedestrians.
Earthen shoulder will provide some confinement to shoulder pavement and protect it
from rain cut.
Cross Slope
The cross slope for the main carriageway and the paved shoulder is 2.5%. The cross
slope for the earthen shoulder is kept as 3.0 % for better drainage of surface water.
The widening of pavement on curves shall be worked out from the following formulae:
0.10V
We = n 18/Rc +
Rc
Where,
We = Widening in metre
N = Number of lanes
Rc = Radius of horizontal curve in metre
V = Speed in Km/hr
Side Slope
The side slope of cuttings depends on soil type. The following values are suggested for different types of
soil:
Material type Slope of cutting
1 Soil 1.5H:1V to 0.5H:1V
2 Disintegrated rock (soft to medium rock) 0.5H:1V
3 Hard rock 0.25H:1V
In case of deep cuttings in soil more than 5.0m in depth, appropriate benching is to be
provided.
Super Elevation
Super elevation required on horizontal curves should be calculated using the following
formulae:
e = V2 / 225 R, where
Our proposed road passes through plain, rolling and mountainous area. Hence the super
elevation obtained from the above expression should be kept limited to 7%. However,
on urban sections, with frequent intersection, it will be desirable to limit the super
elevation to 4 percent for convenience in construction and for facilitating easy and safe
turning movement of vehicles.
The detailed design of horizontal alignment shall be carried out in accordance with IRC :
38 – 1988 “Guide lines for design of horizontal curves for highways and design tables”.
The minimum radius of horizontal curves for different terrain is given as under:
The minimum radius of sharpest horizontal curve without super elevation for a road
camber of 2.5 % is presented below:
50 450
40 280
As per Indian practice, super elevation is calculated on the assumption that it should
counter act the centrifugal force developed at three fourth the design speed.
e =
0.75V 2
V2
127R 225R
Transition Curves
Transition curves are necessary for a vehicle to have smooth entry from a straight
section into a circular curve. The minimum length of transition curve should be
determined from the following two considerations and the larger of the two values should
be adopted for design:
The rate of change of centrifugal acceleration should not cause discomfort to the
driver. From this consideration, the length of transition curve is given by:
Ls = 0.0215 V3 / CR where
The rate of change of super elevation ( ie., longitudinal grade developed at the
pavement edge compared to through grade along the central line ) should not be
steeper than 1 in 150. Formula for minimum length of transition on this basis is given
as under:
Ls = 2.7 V3 / R
The detailed design of vertical profile shall be carried out in accordance with IRC:SP:23-
1993 “Vertical curves for highways”.
Gradient
The recommended gradient for various roads in plain / rolling terrain are presented
below:
Normally the ruling gradient should be used in the design. The limiting gradient may be
used where the topography of a place compels this course or where the adoption of
gentler gradient would add enormously to the cost. We should try to avoid the use of
exceptional gradient.
On unkerbed pavements in embankments, near level grades are not objectionable when
the pavement has sufficient camber to drain the storm water laterally. However, a
desirable minimum gradient should be 0.3 % as per the general practice.
The minimum distance between points of change in vertical grades shall be 150m.
The exceptional gradient, if at all provided, shall not be for a length of more than 100m.
However, for existing carriageway, this criteria may not be possible to adopt due to
economic consideration. In this case, the design profile shall generally follow the existing
profile with reasonable improvement.
Vertical Curves
Summit curves shall be designed for safe stopping site distance. Valley curve
shall be designed for head light sight distance.
Curve should be provided at all grade changes exceeding those as indicated in the table
below. For satisfactory appearance, the minimum length of vertical curve should be as
indicated below:
Case I: When the stopping sight distance (S) is less than the length of
curve (L)
L = NS2 / 4.4
Case II: When the stopping sight distance (S) is greater than the
length of curve (L)
L = 2 S – 4.4 / N
The length of valley curve is determined by the following two criteria and the higher
value is adopted:
1. Rider comfort
5.1.2.5 INTERSECTION
For the design of elements not covered in the said publications the AASHTO
publication, “A Policy on the Geometric Design of Highway and Streets” shall be
followed.
5.1.2.6 INTERCHANGE
For Interchange elements, design Guidelines IRC-92 supplemented by relevant
MoRT&H and the AASHTO publication, “A Policy on the Geometric Design of
Highway and Streets” shall be used.
5.1.2.7 Road Signs
Highway Signs shall be designed in compliance with IRC : 67 “Code of Practice for Road
Signs” Typical drawings for road signs as indicated in the drawings volume shall
generally be followed with corrections / modifications wherever required.
All major junctions have been converted to Grade Separated Structures. Whereas minor
junctions have been kept as intersections with adequate connectivity with service roads.
Junctions have been developed as per new alignment and proposed cross section,
providing speed change lane wherever possible with service roads. In already developed
areas where speed change lane is not possible to provide, Junctions have been
developed by introducing suitable Chanelissing islands at appropriate locations with
adequate signs and markings.
5.2.1 General
The flexible pavement for the proposed road from Varanasi – Aurangabad (of NH- 2),
both for widened portion as new Construction as well as Strengthening of existing
Carriageway have been designed as per the guidelines of IRC: 37 – 2001- “Guidelines
for the Design of Flexible Pavements” and IRC: 81-1997 – “Guidelines for
Strengthening of flexible road pavements using Benkelman Beam Deflection Technique”
respectively. The following three main steps have been followed in designing the new
flexible pavement.
Estimating the volume of traffic and the cumulative number of equivalent
standard axles that will use the road over the selected design life of 20 years.
Assessing the strength of the sub grade soil over which the road is to be built
Selecting the most economical combination of pavement materials and layer
thickness that will provide satisfactory service for the design life of the pavement.
The requirement of new crust composition for the widened portion will be established as
discussed above.
For strengthening of Existing Pavement, we have made an attempt to establish the crust
composition of the existing carriageway.
The difference between the new crust compositions with that of the existing crust are
generally considered as the requirement of Strengthening for existing carriageway.
However, in this case, Benkelman Beam Deflection (BBD) tests have been conducted on
the existing carriageway for designing the overlay. The details are elaborated in
Separate sections.
Flexible pavement has been proposed for the widening of existing C/W with flexible
pavement. Whereas existing C/W with concrete pavement has been proposed to be
widened with concrete pavement. In addition to the above, all the underpass have been
proposed with concrete pavement below main C/W.
5.2.2 Traffic
Only trucks, tractor – trailers and Buses etc. which have got an unladen weight of 3000
kg or more would be used for pavement design. The proposed Varanasi - Aurangabad
section is being widened & strengthened to accumulate the present & increasing traffic.
Traffic studies at Mid-Blocks are conducted at three different locations after a detailed
site investigation. The following locations were found suitable and were adopted for the
midblock classified traffic Vol. counts.
Near Syed Raja (Km. 837.000) (Mid-Block counts for 7 days 24 hours)
Near Kudara (Km. 887.000) (Mid-Block counts for 7 days 24 hours)
Near Prithambur (Km. 950.000) (Mid-Block counts for 7 days 24 hours)
Commercial traffic considered for Pavement design at various sections are given as
under:
Near Syed Raja (Km. 837.000)
Present traffic at Syed Raja (Km. 837.000) are as under:
Bus = 154 nos.
LCV = 428 nos.
2 axle Truck = 1596 nos.
3 axle truck = 3514 nos.
Multi axle Vehicle = 648 nos.
The following growth rates have been adopted based on IRC 108:1996 from the
received data for the project corridor.
The design Life is defined in terms of the cumulative numbers of the standard Axles that
can be carried over the pavement before its Strengthening is required. A Design life of
20 years has been considered in the present study for estimating the traffic loading for
pavement design.
VDF is a multiplier for converting the number of commercial vehicles of different axle
loads to the number of standard axle load repetitions. VDF is calculated on the basis of
axle load survey data. Axle load survey have been conducted in the project road during
the month of Dec’2007(at Syed Raja). Detailed analysis have been carried out to arrive
the value of VDF for different categories of vehicles which are indicated as under:
Bus = 0.5
LCV = 4.0
2 axle Truck = 4.8
Multi axle Vehicle = 6.5
The detailed analysis of axle load survey data including calculation of VDF are presented
in Annexure V in a separate volume.
The following equation has been used to calculate the design traffic:
Ns = 365 x A x [(1+r)n – 1] x F
r
Where,
The design traffic calculated using the above formula is presented below:
Cumulative number of standard axles to be carried over the initial stage of 15 years
=74 msa
Cumulative number of standard axles to be carried over the initial stage of 10 years
= 45 msa
Cumulative number of standard axles to be carried over the initial stage of 5 years
= 21 msa
MULTI– AXL. TRUCK= 365x 4162 x{(1.09) 5 -1} x 0.30x 6.5= 15.45 msa
0.09
TOTAL = 20.85 msa
Say 21.0 msa
Design Traffic for initial 10 years
2 – AXLE TRUCK = 4.37+365 x 2456 x {(1.085) 5 -1} x 0.30 x 4.8 = 9.51 msa
0.085
2 – AXLE TRUCK = 15.52+365 x 5179 x {(1.065) 5 -1} x 0.30 x 4.8 = 86.83 msa
0.065
2 – AXLE TRUCK = 6.11+365 x 1989 x {(1.055) 5 -1} x 0.30 x 4.8 = 12.54 msa
0.055
2 – AXLE TRUCK = 18.46+365 x 3317 x {(1.045) 5 -1} x 0.30 x 4.8 = 26.85 msa
0.045
MULTI–AXLE.TRUCK=17.91+365x4305x{(1.055)5-1}x0.30x6.5=36.75msa
0.055
0.05
2 – AXLE TRUCK = 16.06+365 x 3330 x {(1.05) 5 -1} x0.30 x 4.8 = 23.65 msa
0.05
5
MULTI–AXLE TRUCK= 54.11+365x7181 x{(1.045) -1} x 0.30x6.5=78.71msa
0.045
strength. A sub grade CBR value of 7% has been established – from soil investigation
Report for borrow materials considered to be used for Subgrade construction.
Pavement thickness is obtained on the basis of design traffic and sub grade strength
using pavement thickness design chart as per IRC: 37 – 2001 – “Guidelines for the
design of flexible pavement”.
For New Construction
Flexible pavement has been proposed for the widened lane adjacent to existing C/W
with flexible pavement whereas concrete pavement has been proposed for the widened
lane adjacent to existing C/W having concrete pavement.
Total thickness for 20 years traffic of 150.0msa with a subgrade of 7% CBR = 760mm for
flexible pavement. However, the following Pavement composition proposed for the new
construction in case of flexible pavement.
- Pavement Composition
BC = 50mm
DBM = 160mm
WMM = 250mm
GSB = 300mm
Over 500mm thick Subgrade of 7% CBR
The composition for concrete pavement has been proposed as under:
PQC = 340 mm
DLC = 150 mm
GSB = 150 mm
500 mm sub grade with 7% CBR
Total thickness for 20 years traffic of 20.0msa with a subgrade of 7% CBR = 680mm.
Now Pavement layer composition required to take care of 20 years traffic of 20msa are
as under:
Paved Shoulder shall be used by traffic during the maintenance stage of main
carriageway and also it will be used by the break down Vehicles. We may consider that
the traffic will use the shoulder for about 1.0 month in each year during the maintenance
stages (for stage construction sections). Hence about 10% of the main carriageway
traffic shall be adequate for the design of paved Shoulder.
However, for subsurface drainage purpose, the granular sub base layer shall be
continued throughout the formation width. Though the Pavement thickness for the paved
shoulder is required for traffic of 10% of Main carriageway i.e. about 15 msa, the same
composition as that of Main carriageway has been proposed for the shoulder because of
its smaller widths and construction conveyance. Moreover, it will be convenient for future
widening, if it is required.
General
The pavement designs are also required to be carried out for strengthening of the
existing carriageway in the form of overlay. The overlay design depends on the
functional as well as the structural performance of the existing pavement. In the present
study, the main importance of overlay design was given to the remaining structural
strength of the existing pavement which was carried out by Benkelman Beam Deflection
(BBD) tests.
BASIC PRINCIPLES
5.2.4.3 PROCEDURE
CONDITION SURVEY
Before actual deflection measurement, the project road is divided into sections of more
or less equal performance on the basis of visual observation supplemented by simple
measurements of rut depth. The length of each section shall not generally be less than
500 m.
MEASUREMENT OF DEFLECTION (As per IRC: 81-1997)
5.2.4.4 CORRECTIONS
Temperature Corrections
The stiffness of bituminous layers changes with temperatures. Hence the
deflection also varies with change in temperature. The standard temperature for
BBD tests have been considered as 35ºC for tropical climate. To apply the
temperature corrections, pavement temperature is measured during BBD Tests.
A correction of 0.001 mm for each degree centigrade change from standard
temperature of 35ºC is applied on deflection values measured at pavement
temperature other than 35ºC. However, temperature correction is not applicable
wherever the road is subject to severe cracking or the bituminous layer is
substantially stripped.
Seasonal Correction
Pavement deflection is influenced by the change in climatic condition during
different season of the year. It is desirable to conduct BBD tests just after
monsoon as the pavement subgrade is in the weakest condition during the period
of the year. Hence a seasonal correction factor is applied on the deflection
values when the BBD tests are conducted on dry season. Normally a correction
factor of 2.0 for clayey subgrade and 1.2 - 1.3 for sandy subgrades are applied
when the deflection tests are conducted in the season other than the worst. For
intermediate soil types, the value may be interpolated.
The analysis of BBD test & overlay design are attached separately in subsequent
sections.
In cut areas also, the strength of the top of sub grade should satisfy the above criteria.
In case, soft compressible soil exposes at the sub grade level after cutting, at least the
top 500 mm of the sub grade is to be replaced with selected material and compacted in
layers of compacted thickness of 200 mm to a minimum of 98% of maximum dry density
of modified proctor compaction tests. The CBR value of the compacted sub grade top
shall be at least 7 percent.
300mm thick granular sub base (GSB) has been recommended for the pavement in case
of flexible pavement. The bottom 150mm layer acts drainage layer shall be continued
over the full formation width. Only 150 mm granular sub base has been proposed for
concrete pavement. It is an important load-spreading layer in the completed pavement.
It reduces the traffic stress to acceptable levels in the sub grade, acts as a working
platform for the construction of upper pavement layers and also acts as a separation
layer between sub grade and road base. The sub base material should have a minimum
CBR of 30% at the highest anticipated moisture content when compacted to a minimum
of 98% of maximum dry density in the modified proctor Compaction Tests. Particle size
and plasticity requirements of sub base materials should be as specified in the technical
specification.
5.2.5.3 Base
250mm thick Wet Mix macadam (WMM) has been proposed as base for the construction
of flexible pavement. The minimum CBR value of granular base material should be
100% and the plasticity Index less than 7%. The gradation and compaction criteria of
base materials should be as per the technical specification. In case of concrete
pavement, 150 mm DLC has been proposed.
5.2.5.4 Surfacing
Binder Course
For new carriageway 160mm thick Dense Bituminous Macadam (DBM) has been
proposed as Binder Course for the pavement. The grading and the bitumen content of
DBM shall be as per the relevant clause of Technical specifications. Where as for the
existing carriageway, binder course will be provided over the profile corrective course
and its requirements are indicated earlier in tabular form Km. wise.
Wearing Course
50mm thick bituminous Concrete (BC) has been proposed for as wearing course for
flexible pavement. The grading and bitumen content of BC shall be as per the relevant
clause of MORT& H specifications. For existing carriageway also, 50mm thick wearing
course is proposed over the binder/Profile corrective course (as applicable and indicated
earlier Km.wise in tabular form). In case of concrete pavement, 340 mm PQC has been
proposed.
The cross fall for the carriageway and paved shoulder has been provided as 2.5% to
facilitate quick run off of rain water harmlessly over shoulder.
Reasonably thick bituminous surfacing has been proposed for carriageways to
prevent penetration of rainwater through surface to a certain extent.
The granular sub bases (Drainage layer) have been proposed to extend right across
the formation up to drainage ditches. This should drain off the rainwater that
penetrates the bituminous surface.
The top of the sub grade level have been fixed sufficiently above the ground water level
& H.F.L to prevent any possible infiltration through sub grade.
CHAPTER 6
6.1 General
The environmental impact assessment study presented in this chapter has been done to
evolve a suitable mitigative and management plan for the project corridor from km
786.000 to km 978.400 of the Project Road: Varanasi – Aurangabad Section of NH-2.
The objective of the present study is to carry out the environmental impact assessment
and to prepare the EIA report and EMP for the Project Road Section.
For such cases, the EIA report should be placed for Public Hearing conducted by the
State Pollution Control Board.
A considerable variety of environmental impacts for the road project can be mitigated
through judicious engineering design. However, there are 2 (two) specific areas where
impacts can not be mitigated by mere engineering design.
These are:
The responsibility for preparing the plan for land acquisition and disbursal of
compensation rests with the project promoter acting in tandem with the Collector of the
concerned districts. After completing the Feasibility Report, the project promoter would
show on maps of villages and towns the locations of the properties required to be
acquired and would request the District Collector to complete the formalities of land
acquisition. The Collector in turn would engage his Revenue Officers to measure the
area and to access the value of the property and identify their rightful ownership. The
District Collector would compute the compensation such that the rightful owners receive
in tune with existing entitlement policy of the State. The compensation should be
transferred by the project promoter to the office of the concerned District Collector for
disbursement.
The responsibility to prepare the plan for tree felling and compensatory afforestation
rests with the project promoter, the Department of Forests and the District Collector
working in tandem. The forest department would jointly survey with the project promoter
the areas where such trees exist and prepare a report by indicating the nature of trees
classified by species, size, numbers, values of such trees and certify that no endangered
or endemic species of trees are likely to be cut. The Forest Department would prepare a
statement according to the existing norms of the State showing the values of the trees to
be cut, the area required to raise those trees in requisite numbers and the cost of
regeneration of trees. The District Collector is required to identify the land areas, which
would be used for raising the compensatory forest, specify the value of such lands for
acquisition. Total cost would be paid by the project promoter to the State Forest
Department.
The compensatory afforestation plan must also contain a certificate from the concerned
Wild Life Warden stating the status of endemic or endangered species of animals, which
would be adversely affected by the tree-felling programme.
The legal custodian of all National Highways in India is the Ministry of Surface Transport
(MOST), Government of India. However, the Roads Wing of the Public Works
Department of the State through which National Highway sections pass, carryout the
responsibilities of road maintenance and road improvement through a special cell placed
within the purview of the department. The existing overall administrative set up of the
Project Road is looked up by the following organization of the National Highway Division
in the State of UP & Bihar.
According to the MoE&F stipulations, the EIA should take into account the attributes of
physical environment and social environment with reference to the territorial limits of 20
km corridor, 10 km on either side of the ROW. For the present report, the Talukas are
considered as the units of territories. The details of administrative territories along road
segment are compiled below:
Administrative Territories
For convenience and easy reference, the present EIA report has been divided into the
following sections:
¸ Section 6.2 describes the attributes of the physical environment within the project
influence area (PIA).
¸ Section 6.3 describes the attributes of the social environment within the PIA.
¸ Section 6.4 describes the environmental attributes within the ROW.
¸ Section 6.5 describes the apprehended impacts of this project on the proposed
ROW and on land immediately abutting it and the required mitigation measures.
¸ Section 6.6 brings out the organizational set up for implementing the mitigative
measures.
The need for collaboration between the various institutions has been brought in the
report. The report also describes the system of monitoring to be carried out. All these
together constitute environmental management plan (EMP).
A brief description of the major physical features along the Project road corridor is
presented in the paragraphs that follow. The available data and the information for the
PIA relate to a 20-km (i.e. 10 km on either side) wide corridor along the existing
alignment.
6.2.1 Physiography
The project road is generally plain with gentle slope. The highway traverses eastward
through the eastern Gangetic plain of the sub-continent for about 85km. The project
highway is part of the flat flood plain of the Ganga and Sone rivers.
6.2.2 Geology
The region through which the project highway passes is structurally a part of the Ganga
plain. This has been formed by the in-filling of the Indo-Ganga trough during the
Pleistocene period. It has an alluvial cover of 400-1500mm deep. Geologists distinguish
the Gangetic plain between older and the newer alluvium. The older is usually composed
of agrillaceous beds where kanker, an impure carbonate of lime and pislitic ferruginous
concretions are disseminated.
6.2.3 Soil
Soils in the stretch of the project highway through out are silty clay or sandy loam, where
soils in some stretches are residual soils duly covered with vegetation growth of
forestland. As the soils mostly are of alluvial nature with medium to low plasticity, as
such, the soil erosion is not the problem in the entire project stretch. Coarse and clear
sands having high siliceous and feldspar minerals occur along riverbeds throughout the
route.
Erosion is not considered to be an issue in this project, as major portion of the road runs
in the Indo-Gangtic plain with practically no or very low grading. Embankment erosion
may exist on high embankment in case of inadequate compaction/design. Under the
proposed engineering design, all such high embankments are provided with flat slopes
with reinforced earth/retaining wall/turfing etc. to practically eliminate any chance of
damage to such high embankments.
6.2.4 DRAINAGE
The project highway, which traverses through the flood plains of the Ganga and the
Yamuna and other smaller rivers is prone to water-logging and local flooding in some
stretches. However, the NH-2 is a very old highway and normally pass through the ridge
line along all its alignment. The drainage problem, as such do not exist in terms of
waterway requirements. Man-made drainage problems occur mosty at the built-up
stretches due to raising of shoulders/kerbs by the local residents. Detailed hydraulic and
hydroligical survey have been done through out the project stretch and all
locations/stretches having even marginally possible inundation have been suitably raised
and upgraded drainage structure have been provided, wherever required. No inundation
problem, therefore, is anticipated.
Detailed drainage surveys and hydrological investigations have been carried out in this
project. Detailed engineering solutions have been provided in the design of the project.
Service lanes and roadside drains on either side of the project highway have been
proposed. The roadside drains will be cleaned by the NHAI periodically to ensure proper
drainage during the operation stage of the project. With these provisions, the drainage
problem would become minimal.
6.2.5 SEISMOLOGY
The entire stretch of the project highway traverses partly through seismic zone II and III
as defined by IRC 6:1966, seismic zoning classification system, i.e., a zone of relative
stability. The horizontal Seismic coefficient for zone II is 0.02 and for zone III is 0.04
measured on a scale from I to V zones where zone I is most stable and zone V is
considered to be least stable.
6.2.6 Climate
The project road from Varanasi to Aurangabad (the NH-2) is located in a sub-tropical
region with marked monsoon effects. Due to large variations in temperature and rainfall,
the climate has a characteristic seasonality. The climate is distinguished by three distinct
seasons of
Hot Summer (from April to June),
Warm humid Rainy season (from July to September), and
Cold Winter (from November to February).
October and March constitute the transitional months between rainy, winter and summer
seasons respectively.
The region enjoys fairly high temperature throughout the year, a distinct characteristic of
the tropical climate. The summer season is usually dry with high temperatures ranging
between 300 to 470 C. During rainy seasons the temperatures vary between 240 to 36o C.
Temperature during winter varies between 100 to 260 C. January is coldest month with
temperatures dipping to less than 5o C and May is the hottest month with temperatures
going above 40o C. It can be inferred that the extremities of temperature gradually
decrease eastward along the highway from Varanasi to Aurangabad.
Wind direction, speed and seasonal variation determine the manner in which air
pollutants from the vehicle emissions are dispersed. High wind velocities may cause soil
erosion both during the wet and dry seasons.
In all the stretches, the predominant wind direction is westerly and north-westerly from
October to April and shifts to easterly or south-easterly from June to September. Dust
storms having wind velocity of more than 75km/h are the typical features of the summer
weather, but in October winds are variable both in direction and speed. Wind velocity of
more than 75km/h are the typical features of the summer weather, but in
October winds are variable both in direction and speed.
The project area receives most of its rainfall from the Bay of Bengal Current of the
southwestern Monsoon, which normally bursts over the region towards the last week of
June and continues till October. The rainfall is derived mainly from the Bay of Bengal,
which in north gets deflected by the Himalayas and sweeps up the Gangetic plan falling
along the project highway. During winter, occasional light rains are received from
retreating western monsoon. The region enjoys a moderate annual rainfall of about
980mm of which over 90% occur during the four rainy months. Overall, the annual
rainfall varies between 800mm and 1100mm per annum.
The region, on an average records a relative humidity of 64%. The air is very humid
during rainy seasons when the relative humidity averages reach up to 79%O. The
highest relative humidity is observed during August (90.48%), which together with high
temperature makes the weather sultry.
The Central Pollution Control Board (CPCB) in India is responsible for setting air quality
Standards. The national ambient air quality standards (NAAQS) for gases monitored on
routine basis were notified under the Air Act in 1985. In India, only annual mean and 24-
hour average standards have been described, except for carbon monoxide for which 8
hours and 1-hour standards have been notified. There are no Indian standards for
hydrocarbons and aldehydes.
European Union has regulated standard for airborne benzene at 10 µg/m3. The
permissible air quality standards for particulate and gaseous pollutants are presented in
Table - 6.1.
*Annual Arithmetic mean of minimum 104 measurements in a year taken for a week 24
hourly at uniform interval.
** 24 hourly/8 hourly values should meet 98 percent of the time in a year
Sources Anon (1996-97), Ambient Air quality Status and Trends in Delhi (1989-1993)
National Ambient Air Quality
Monitoring Series NAQMSIa/1996-97, Central Pollution Control Board, Delhi
Ambient Air Quality was monitored at various locations having different land uses such
as residential, commercial, agricultural, industrial etc. Air Quality was measured with
Respirable High Volume Sampler. Ambient Air quality monitoring data suggest that SPM
and RPM are major pollutants of concern throughout the road corridor. Even during rainy
season, the SPM concentration exceeded the national air quality standards of
200 µg/M3 for 24 hours at many stations.
SO2 and NO2 concentrations were within acceptable limits. Carbon monoxide
concentrations crossed the NAAQ standards at many locations in rainy season and at
most of the locations during winter. The ambient air quality as monitored at various
locations along the project highway is as given in following Tables.
Table - 6.2 : Baseline Air Quality along the Project Highway (Rainy Season)
Table - 6.3 : Baseline Air Quality along the Project Highway (Winter Season)
The condition as above is a reality under the existing road. One of the key reasons for
them is the present condition of the existing road, which get accentuated due to
congestion, poorly maintained flanks, higher roughness, pot holes, etc., apart from the
type, age of the vehicle and their maintenance level. As the proposed improvement
provides a much improved- road surface along with hard shoulders, plantation of large
number of trees etc., these indicators are likely to have much reduced levels with the
proposed improvement as compared to the present scenario.
Most of the physico-chemical characteristics of river water are found to be within the
range of acceptable limits of CPCB. Some of the rivers, however, showed higher BOD
and total coliform count. The values observed for different characteristics of canal water
were within the standards set by CPCB. Among the ponds, physico-chemical
characteristics at Shivsagar pond are critical. The Shivsagar pond showed eutrophic
condition with high BOD and colliform count and low DO. The water quality at various
locations along the NH2 has been listed in following Tables. The Indian Standards for
Drinking Water (IS:10500-1991) are given as part of the Environmental Monitoring Plan.
Conducti Total
Sl. Water
vity Chlori Alkalin Oil and Coliform
N Resou pH TSS TDS DO BOD COD Lead
micro de ity Grease Count
o rce
mhos/cm MPN/100 ml.
River Not
1 PunPu 7.2 1450 100 500 6 2.4 8 16.02 95 Dete 0.01 Not Detected
n cted
Not Not
River
2 8.0 1540 400 500 7 1.8 1.5 14.02 130 Dete Detect Not Detected
Batane
cted ed
Not Not
3 Adri 7.4 1420 - - 6 2.3 4.3 16.02 135 Dete Detect Not Detected
cted ed
Not
4 Terar 7.7 1510 - - 6 2.1 4.8 14.02 125 Dete - 35
cted
5 Keshar 7.1 1280 55 5.8 2.8 140 8.5 27 69 0.08 0.04 400
The baseline noise level of an area is the existing noise resulting from the contribution of
all natural and man – made noise within the area. To determine the existing noise
levels, information have been collected by the Consultants.
An unwanted sound affects the health of a person, his activities and interferes with the
mental ability of a person. The noise issues from are addressed in two phases i.e., the
constructional phase and operational phase. During construction phase, different
activities produce different levels ranging between 80-90 dBA. Road noise depends on
factors such as traffic intensity, the type and condition of the vehicles plying on the road,
acceleration/deceleration/gear changes by the vehicles depending on the level of
congestion and smoothness of road surface (IRC: 104- 1988). Excessively high noise
levels are a concern for sensitive receptors, i.e., hospitals, educational institutions,
wildlife, etc.
Central Pollution Control Board, India has specified noise standards for different
activities. Importance was given to the timing of exposure and areas designated as
sensitive. The following Table gives the noise standards set.
The noise levels observed along various location on the project highway are as given in
the following Table.
Table - 6.7:Base line noise level recorded along the Project Highway
Day Time (6am - 9pm) Night Time (9pm - 6am)
Sl. No Place noise levels dBA noise levels dBA
Max Min Max Min
A Dehri-on-sone 86 50 74 48
B Aurangabad 80 52 65 43
C End of the Project 78 50 55 40
6.2.10.1 Flora
Due to intense agricultural activities in the region, natural forests have depleted.
However, plantations of orchards and groves of Mango, Guava, and Banana and Mahua
have been reported in some of the stretches. There is no reserve forest within 10 km
from both the sides of the project highway.
State Government Forest Departments have planted a variety of trees under the social
forestry and the plantation forestry projects from 1983/84 onwards all along the road on
both the sides. Social forestry plantations in Uttar Pradesh are mainly comprised of
Dalbergia sissoo (Shisham), Eucalyptus hybrid (Safeda), Cassia siamea (Kala sins) and
Delonix regia (Gulmohar). Plantation in Bihar mainly comprise of Acacia arabica (Kateri
Babul), Prosopis juliflora (Vilayati Babul), Albizzia lebbeck (Siris), Cassia siamea
(Kalasiris), Dalbergia sissoo.(Shisham) Parkinsonia aculeta (Klkar), Tectona grandls
(Saguan) and Eucalyptus hybrid (Safeda).
6.2.10.2 Fauna
Domesticated animals constitute the major proportion of faunal density in the area
surrounding the project highway. No endangered species has been reported in the area.
Aquatic birds are relatively very less in the project area. Common bird population
comprises bater, sone cheraela, crow, maina, woodpecker, etc. Six types of rare birds
have been reported at Rajpur near SAIL Chowk (Kanpur district). However, no
endangered species of avian fauna has been recorded in the influence zone of the
proposed project.
6.2.11.1 Quarries:
Identification and assessment of suitability of materials (in the form of rocks for road
metal and soil for road base) suitable for use in the road construction is a very essential
ingredient of the highway design. The assessment of the environmental concerns of
these quarry areas, from which the materials are to be procured, normally becomes
critical due to the following concerns:
It needs however, to be noted that list of quarries as furnished in the above Table are
recommendatory in nature to serve as a ready guideline to the prospective bidders. The
contractor can, however, procure material from quarries other than those listed, provided
that
The material obtained is of acceptable quality.
The selected quarries are either already in operation and in case the new
selected quarries are not in operation then the contractor will ensure that such
quarry satisfy the statutory requirements prescribed for such purposes.
The soils to be used as sub-grade, select sub-grade and shoulder materials need to be
hauled from designated borrow areas. Similar to the identification of suitable quarries,
the individual consultants identified suitable borrow areas for supply of soil to the new
road formation. Based on the total requirement and availability of each soil type,
estimates of soil quantity to be obtained form each of the borrow areas were worked out
in accordance with the National Standards, recommended by the Indian Roads
Congress (IRC).
In the selection of the borrow areas, care was taken to ensure that:
Sufficient quantity of suitable soil is available from the borrow pit
The borrow areas are as close to the project road as possible
The loss of productive and fertile agricultural soil is minimum
There is minimum loss of vegetation
The borrow pits as per specification from temporarily acquired cultivated lands,
the topsoil to a specified depth will be stripped and set aside with microbial
preservation methods.
Most of the area recommended to be used for borrowing in this project is,
however, infertile and therefore preservation of the topsoil will not be a major
issue.
Borrow pits have been identified for the project with manageable leads. Borrow material
can also be obtained from the banks of the river which is 7km south of Aurangabad.
Most of the borrow areas selected are either barren land or mounds. Some of these are
to be developed into ponds as per the scheme of Fishery Deptt. of State Govt.
Agricultural parcels of land have not been generally included in the list of borrow areas.
However, in some cases, the landowners themselves have requested to include their
land in the list of borrow areas. The reasons for this are two. First, some of the farmers
want to create ponds (mainly for fish culture) in their land. Second, sometimes the
agricultural parcel of land is located on an elevation above the immediate surrounding
and lowering (by borrowing) would help such parcels of land become better irrigable.
Moreover, some other areas have been identified for borrowing, where the State
Fisheries Departments wants to develop ponds for fisheries. The details of the quantity
of borrow material available from these locations along with details of size, land use,
etc., have been listed in the following tables. From the tables it may be observed that not
much borrowing is proposed to be done from fertile lands and as such impact on this
account may not be considered significant.
Table - 6.9: Borrow Locations
Distance
SL.
Km. Place from NH- 2 Remarks
No.
(km)
Karwandia
1 928 1.3 Hillocks
hills
Banks of
2 926 7 km.south of Aurangabad town
Domuhan
3 920 Kariaram 0.2 High agricultural land
4 920 Kariaram 0.2 Barren Land
5 853 Tendua 1.0 Barren Land
6 852 Sinduria 0.2 High Mound
Jasuya/Hann
7 842 1.0 High agricultural land
soli
High agricultural land / Barren
8 836 Rawal Bigha 1.5
land
9 834 Munshi Villa 0.2 Barren land
10 834 Munishi Villa 0.2 Barren land
11 833-834 Munishi Villa 1.0 High agricultural land
12 832-833 Munishi Villa 1.0 High agricultural land
13 834-835 Karhara 1.5 High agricultural land
14 835 Kanbehri 1.0 High agricultural land
15 834.2 Kanbehri 0.1 Shallow pond
16 834 Bheriya 0.2 Barren land
17 833.5 Bheriya 1.5 High agricultural land
18 833 0.2 Barren land
19 832 Sherganj 0.2 Barren land
20 832 Sherganj 0.2 Barren land
21 832 Sherganj 0.2 Barren land
22 832 Teldiha 1.0 High agricultural land
23 832 Teldiha 1.5 High agricultural land
24 831-832 Datpi 0.5 High agricultural land
25 830.5 Sherganj 0.2 Barren land
26 830 1.0 Barren land
27 829.5 Raniganj Mor 0.2 Barren land
Mirzapur
28 829 0.2-2.5 High agricultural land
(Bao)
29 828 Raniganj Mor 0.2 Barren land
6.3.1 General
The road widening project of NH- 2 from Km 787.000 to km 977.000 falls in Utter
Pradesh & Bihar states. The project road passes through 2 districts of UP & 3 districts of
Bihar.
The demographic profile and worker category features of these districts as are
presented below.
Table - 6.10 : Demographic Features of UP and the PIA Districts, 2001 Census
Sl. State / District Area Total Rural Urban % of Avg.
No. (km2) Popn. Popn. Popn. Urban Density
(million) (million) (million) Popn. (Pop/km2)
1 UP 238566 166.2 131.7 34.5 20.0% 690
2 Varanasi 1550 3.13 1.15 1.98 36.7% 1995
3 Chandauli 2485 1.64 1.5 0.14 8.3% 660
4 All India 3287590 1,028 741.7 285.4 27.8% 313
Table - 6.11: Demographic Features of Bihar and the PIA Districts, 2001 Census
Sl. State / District Area Total Popn. Rural Urban % of Avg.
No. (km2) (million) Popn. Popn. Urban Density
(million) (million) Popn. (Pop/km2)
1 Bihar 94,164 82.9 74.5 8.4 10.47% 880
2 Kaimur 3305 1.29 1.24 0.042 3.2% 382
3 Rohtas 3847 2.44 2.12 0.33 13.33% 635
4 Aurangabad 3363 2.00 1.846 0.154 7.7% 607
5 All India 3287590 1,028 741.7 285.4 27.8% 313
(million) Rate
Broad influence Area
Bihar 82.9 27,974,606 21,052,875 6,921,731 33.7%
Immediate Influence Area
Kaimur 1,289,074 442,887 312,872 130,015 34.36%
Rohtas 2,450,748 744,183 544,731 199,452 30.37%
Aurangabad 2,013,055 671,011 476,390 194,621 33.33%
All India* 1,028,610,328 402,234,724 313,004,983 89,229,741 39.1%
Table - 6.14: Land Use Pattern of UP & Bihar (Area in ‘000 ha)
The existing ROW width varies from 45 m to 60m except at Aurangabad with 41m ROW.
The present proposal is to widen the existing 4 lane road to 6 lane configuration with
service road at few places.
The design proposals apart from rehabilitation and widening of the road cover the
improvement of existing highway features, notably, the existing road junctions, bridges
and cross drainage structures. The salient environmental features within the proposed
ROW are complied below.
Salient Environmental features within the Right – of-Way
The improvement of the highway section would cause certain impacts on the immediate
environment along the alignment. Specific features of improvement proposals from
environmental impact consideration are listed below:
Felling of Trees
4 Drainage Not affected
5 Most of soil would be obtained from cutting. Earth movement
Earth Movement would mostly be by mechanical means and dust nuisance
during construction operation would be minimized by
watering the area prior to cutting of earth.
6 Quarry Material Quarry stone, gravel, sand, stone metal, etc.,would be
procured from existing designated quarries.
7 Dislocation of Population None
8 Will the project construction operations result in
excessive soil erosion and/or silt run-off from cut and
fill area? No
Though the primary purpose of the environmental impact assessment study is to identify
negative impacts on the environment that may be caused due to the implementation of
the project, there would, however, understandably be several benefits to the human and
natural environment as a result of rehabilitation and upgrading of the Road Project.
The traffic currently using Project road of NH-2 consists of local (intra-regional) as well
as long distance through traffic (inter- regional). The existing road section has a four-lane
divided carriageway configuration. The high traffic volume has been responsible for the
congestion along the road. The prevailing congested condition has, in turn, been
responsible for the increased travel time, higher vehicle operating costs and reduced
road safety. Widening of the road section to divide 6-lane configuration will greatly
reduce these problems and will provide comfortable and efficient road transportation in
the area.
Air Pollution
The upgrading of the Project Road section would improve regional air quality. There
would be decline emission of air pollutants as limited access facility would allow traffic to
move more freely and efficiently on NH-2 with fewer stalls and hear shifts, less idling and
reduces grade changes, all of which result in decreased pollutant emission form
vehicles.
A comparative analysis has been carried out for the ‘With Project’ and ‘Without Project’
scenarios by estimating the total emission of different pollutants contributed by the
project traffic. The total daily emissions are computed by the product of projected
vehicles that will be plying on the corridor per day, length of the corridor and the
emission factor for each type of pollutant emitted by various modes of vehicle moving at
different speeds. The relationship used for estimation of pollutants is as given under.
TEjk = Ni * Lk * Eijs
Where,
The average operating speeds assumed for “with” and “without” Project Scenario are
given below.
The analysis of the data presented above indicates that the implementation of the
project would have positive impacts on the air quality levels.
Noise Pollution
To estimate the approximate distances from the road section at which 65 dB (A) and 55
dB(A) (permissible noise levels stipulated by the Central Pollution Control Board for
commercial and residential land use) noise contour would run for ‘With Project’ and
‘Without Project’ situations, the following relationship observed in western conditions has
been used:
Where,
L is mean noise level at receiver located at distance (d) from the source (dB(A))
d is distance between receiver and pseudolane at the centre of the traffic lanes
q is traffic volume, vehicles/hour
u is mean speed of traffic, miles/hour
(Source: Edward K Morlok, Introduction to Transportation Engineering and Planning)
The above relationship assumes that there is no obstruction (such as building or high
wall) between the roadway and the point at which the noise level is being predicted.
The estimated distances from carriageway centre line for 65 dB(A) and 55 dB(A) noise
contours are complied below:
The implementation of the project may have some adverse impacts on the environment.
Suitable mitigative measures should be taken to eliminate or minimize the intensities of
these negative impacts. Impacts of road project on the environment are broadly related
to:
¸ Project Location
¸ Construction of labour camps
¸ Construction of road
¸ Operation or use of road
The type and magnitude of impacts depend on the location of specific attributes of the
given environment. No scale is available for quantitative measuring of the magnitude of
impacts. A qualitative scale has been devised such that it can be used as a method to
indicative varying orders of caution while dealing with road projects.
The possible impacts due to project location have been examined. The tools required to
design the mitigative measures can be broadly classified as under:
¸ Engineering Design
¸ Project Scheduling
¸ Afforestation and Tree Planting
Mitigative measures for these impacts have been suggested and presented below:
It is recommended that all mitigative measures are addressed and acceptable solutions
arrived at before implementation of the Road Project.
A variety of impacts arise from location and operation of construction camps. There
have been listed below:
It is necessary that the required mitigative measures are considered and control
documents prepared before establishing the site for such camps. The tools required to
implement the mitigative measures are as follows:
The implementation of the project may lead to a variety of impacts on the environment.
These are listed below:
The mitigative measures include equally varied techniques, which are as under:
¸ Engineering Design
¸ Site Planning and Project Scheduling
¸ Compensation
¸ Afforestation
¸ Tender Document
¸ Monitoring
The movement of traffic along the improved highway corridor may have some adverse
impact on the environment. These impacts along with mitigative measures are listed
below. Implementation of these measures may come through the following tools:
¸ Afforestation
¸ Controls and Monitoring
given by the society on the basis of a set of assurances from the project promoter.
These assurances broadly refer to the following aspects:
The central issues to be honoured in this regard are discussed in this section. The EMP
starts by identifying the required mitigative measures at their specific contexts. These
contexts are to be understood by interpreting the defined impacts upon environment.
The degree of caution and comprehensiveness required to design the given mitigative
measures are indicated by the magnitude of expected impacts.
The responsibilities for designing the mitigative measures are delegated to the project –
promoting institution, which in the present context is the National Highways Authority of
India (NHAI). It is to mobilize appropriate expertise to design diverse types of mitigative
measures. All of these may not be available within the same department. NHAI will
need to collaborate with other institutions in the public and public sectors. For example,
Department of Forest of the Government of UP & Bihar is authorized to design and
implement afforestation measures. Similarly, designing of mitigative measures related to
engineering solutions may be assigned to a firm competent in highway designing. NHAI
has already done this by engaging a Consulting firm to carry out the detailed design for
the rehabilitation and upgrading works.
¸ Supervisory Engineer: The role of Supervisory Engineer would be to ensure that all
engineering structures are laid according to specification. He may observe it for deviation of
the design and it would be obligatory upon this part to obtain approval of his plan of deviation.
This should be made a part of the Tender Document for appointment of Supervisory Engineer
for imposition of penalty to the violators, particularly contractors.
¸ Construction Contractor: The problems arising out of construction sites and labour camps
are to be controlled by him. This role of the Construction Contractor should be entered in the
Tender Document.
¸ District Collector: The District Collector’s responsibility would include reporting the progress
made in acquiring land together with disbursal of compensation.
¸ Forest Department: The responsibilities include implementation and reporting the progress
achieved in the area of Compensatory Afforestation.
¸ Project Promoter: The responsibilities of the Project Promoter include :
This report will be extremely valuable in identifying the types of additional actions to be
taken to make the highway hazard free.
¸ Revenue Department: Responsible for estimation of compensation for land acquisition and
disbursal of compensation.
¸ Highway Maintenance: The Highway Maintenance people will assume responsibility for
everything concerning operation, monitoring and reporting to the assigned authority. This
shall necessarily be the State PWD that is accountable to the society for implementing the
assurances made regarding the project.
The PWD as the apex co-ordinator will need to schedule all mitigative actions envisaged
to yield the most satisfactory results. For example, the disbursal of compensation for
acquisition of land should be completed before construction begins. However,
afforestation programmes may extend into the operation stage. Scheduling of all these
actions will constitute the Monitoring Plan. Environmental aspects, which are to be
regularly monitored, are listed below:
Road side All along the Regular inspection Throughout the year
plantation highway stretch
maintenance from km 786.0 to
km 978.4
Prevention of road All along the Regular inspection Throughout the year
side squatter highway stretch
settlements from km 786.0 to
km 978.4
The cost of mitigative measures should be included in the project cost to form a
component of Final Project Design and be prepared in three parts. These are as
follows:
¸ The first part shall include all costs related to measures incorporated into Land Acquisition,
Engineering Designs, Project Scheduling. Site Planning and Preparation of Tender
Documents. These are to be seen as the normal cost of a road building project.
¸ The second part shall include precise cost of Compensatory Afforestation.
¸ The third part will be cost for administering the EMP & monitoring.
For field monitoring and laboratory analysis of air, water and noise for the proposed
monitoring programme, the indicative rates are given below:
The Government of India, through National Highways Authority of India (NHAI), intends
to rehabilitate and upgrade the existing 4-lane Varanasi - Aurangabad Section of NH2
from km 786.0 to km 978.4 to 6-lane carriageway facility with the provisions for further
widening in the future.
STUP Consultants P. Ltd has been appointed as Consultants by the NHAI for this
assignment.
On the positive side, the road widening and strengthening is likely to have significant
long-term benefits for inhabitants living in settlements near the road and all road users.
For local residents, these benefits include increased economic and employment
opportunities; improved access to services and facilities and reliability of transport
services for the freight traffic; and improvement in the regional air quality. For the road
users, the benefits are in terms of reduction in travel time, vehicle operating costs, traffic
congestion, road accidents and saving on fuel.
Negative impacts due to the road-upgrading project include a few direct negative
impacts on the physical, biological and socio-economic environments. Negative impacts
on biological environment include reduction of vegetation on the existing road
embankment. On socio-economic aspects negative impacts include possible disruption
of utility lines, accident risks during construction, risk of transmission of communicable
disease through contact of residents with road workers and drivers of freight trucks and
disruption of community cohesion and social fabric. These negative impacts can be
mitigated by implementing the recommendations as described in brief.
It is concluded that although the widening of the road project will have a positive impact
on the region through improvement of regional transport links decreased transport costs
and increased economic opportunities for local residents some negative impacts of
moderate nature will also occur. However, the localized direct negative impacts can be
mitigated and managed if the recommended mitigation measures are implemented.
Destruction of trees Increased tree cutting Increased tree Avoid locating construction
and vegetation for in the road side cutting to sell camps near roadside
fuelwood plantation for fuelwood wood to satisfy plantation.
to supply workers in the needs of new Supply construction camps
construction camps settlers attracted with kerosene stoves
by the improved Liaise with the State Forest
road and Department to enforce
associated wood cutting restrictions,
oppurtunities issue licences, and
establish legal wood cutting
areas.
Archaeological and Cultural Impact
Archaeological and No impact No impact
Cultural sites
Tourism No impacts Increased tourism Encourage the Department
may have long of Tourism to develop
term benefits for tourism infrastructure in the
the local economy region
Socio-Economic Site Preparation and Operation Mitigation and Optimization
Impact Construction
Pedestrian Access Decreased pedestrian Decreased Provide underpasses at
access across road pedestrian access locations in village
across road due settlement.
to installation of
controlled access
facility.
Disruption of Traffic No impacts as two Long term benefit
lanes will be open for through improved
traffic flow throughout flow of traffic
construction
Transport of Goods No impact Increased
opportunities and
potentially
reduced costs of
transporting
goods may be a
shift from using
rail to road
transport
Access to services No impacts to services Potential long
and Facilities and facilities term increase in
access to services
if efficient public
transport service
is promoted
Economic Presence of labour Increased traffic
Opportunities force will increase volume will have
health risks.
CHAPTER 7
7.1 General
This chapter presents the Social-Impact Assessment in the immediate influence area of
the project road (Km 786+000 to km 978+400) in varanasi, Chandauli districts of the
Uttar Pradesh state & in Kaimur, Rohtas & Aurangabad districts in Bihar State. It gives
the likely social impacts, evaluation of their consequence, alternative options for avoiding
or minimizing displacement of people, resettlement and rehabilitation of the Project
Affected Persons (PAPs).
7.2 Methodology
The guidelines of the Asian Development Bank (1994) and World Bank Directives on
Indigenous Peoples (O.D.4.20) and Involuntary Resettlement (O.D.4.30) broadly formed
the basis of this study. Field investigations were undertaken using a variety of
techniques including socio-economic survey of the selected sample villages within the
2.5 km distance on either side of the ROW. Information was collected through
participatory appraisal, focus group discussions, meeting with Panchayat leaders of the
villages and knowledgeable local persons. Investigations were also carried out to
identify specific land acquisition requirements and likely social impacts foreseen due to
the project, such as loss of land, homes, structure and earning opportunities, besides
issues relating to access to common resources and facilities, loss of standing crops,
orchards etc.
Socio-economic analysis has been confined to the immediate influence area of the
project road. In the Project Influence Area (PIA), the total population of all the PIA
districts along with the states are given in the tables below. Majority of work force in the
PIA is involved in agricultural activities. The principal crops are sugarcane, groundnut,
paddy, mango (Alphanso) and chikoo. Majority of industrial units is small-scale units
scattered along the project road.
Table - 7.1: Demographic Features of UP and the PIA Districts, 2001 Census
Sl. State / District Area Total Rural Urban % of Avg.
No. (km2) Popn. Popn. Popn. Urban Density
(million) (million) (million) Popn. (Pop/km2)
1 UP 238566 166.2 131.7 34.5 20.0% 690
2 Varanasi 1550 3.13 1.15 1.98 36.7% 1995
3 Chandauli 2485 1.64 1.5 0.14 8.3% 660
4 All India 3287590 1,028 741.7 285.4 27.8% 313
Source: Census of India 2001,
Table - 7.2: Demographic Features of Bihar and the PIA Districts, 2001 Census
Social impact assessment was carried out to identify specific land acquisition
requirements, and to foresee the likely impacts, such as loss of land, homes, structure
and income earning opportunities, besides issues relating to access to common
resources and facilities, loss of standing crops, orchards etc.
Adequate care has been taken to minimize social impacts. In fact adequate land
acquisition has been made during 4-laning of the project road. At present for this present
work of 6 laning land acquisition requirement is not very significant. In order to further
reduce the land acquisition requirement, adequate care has been taken by providing
retaining walls / toe wall at places of requirement.
The detailed location wise requirements for land acquisition is indicated in the strip map
prepared and submitted showing the existing features and the proposed facilities of the
Project road.
The entire R & R Plan would be executed through National Highways Authority of India
(NHAI) by a competent Project Implementation Unit (PIU), the responsibility of which will
include – planning, implementing and monitoring R & R programmes of the project. The
PIU will have a R&R officer (specially hired for the project) who will be assisted by a
computer operator for maintaining and continuous updating of R&R database featuring
all relevant information on each individual household and its members required for
implementation of the entitlements. At the project level, the project director and the R&R
officer will be responsible for the co-ordination of all activities relating to the
implementation of the R&R programmes. The project R&R officer should be a
sociologist or anthropologist with post-graduate academic qualifications and extensive
fieldwork experience working with Non-Governmental Organisations (NGOs) and
community organizations.
Involuntary resettlement being a human problem requires a personal touch and careful
handling of the PAPs. It was, therefore, considered necessary to involve NGOs who
have had experience of working with local people in the filed of rural development and
allied activities and were able to comprehend the feelings of the PAPs and work with
them interactively.
Monitoring and evaluation will be concurrently undertaken with the implementation of the
Resettlement Action Plan (RAP). The implementing agency will submit the progress
report to NHAI and obtain their guidance. Monitoring would be carried out under the
arrangements of NHAI. The Monitoring Team will be monitoring (a) general local opinion
about the ongoing project activities, (b) perception of the population regarding impact of
rehabilitation, (c) development of communities, (d) roadside amenities prescribed and (e)
relations between the construction team and the local community.
7.9 Conclusion
In sum, there is a unanimous opinion that the project would benefit the people and their
co-operation in its implementation would be forthcoming even though it may entail some
inconvenience.
CHAPTER – 8
PUBLIC CONSULTATIONS
8.1 General
As per the requirements of the project, Para 4.9, Request for Proposal, public
consultations have been conducted at strategic locations in the month of December
2007. The purpose of conducting public consultations was to inform and explain the
features of the project including operational and safety requirements to local people and
to understand their concerns and perceptions with regard to adverse impact on their
requirements, livelihood, social relations, access to various facilities and resources, etc.
The present stretch of National Highway NH-2 considered for six laning starts from
Varanasi (Ch.786.000) and ends at Aurangabad (Ch.978.400). The total length of the
section is 192.4 km between the two places mentioned above. The project road in its
present condition is a four lane divided highway from Ch.786.000 to Ch.978.400 and
service roads at few locations in urban sections. Total length is 192.4 km in which 85.2
km (km 862.100 – km 907.100 & km 938.200 – km 978.400) are concrete pavement and
remaining 107.2 km are flexible (bituminous) pavement. Some of the major villages and
towns along the corridor are Varanasi, Chandauli, Mohania, Kudara, Dehri, Aurangabad.
Mohansarai
Panchpadva
Chandauli
UP – Bihar border
Mohania
Kudara
Bhediya
Rafiganj
8.3.1 Name of the place where public consultation was held –MohanSarai (km 787 on NH-2)
Date – 2nd December, 2007
Participants: Villagers & local road users
Issues discussed -
There is not enough space on either sides and this should be kept in view while
formulating the widening scheme.
Keeping in mind the safety measures, some kind of barrier (railing) should be
provided in the built-up area and in the median of the road.
Drainage facility was not adequate and was demanded to provide especially near the
existing underpass and on the service roads
Villagers have demanded a footpath along the road.
8.3.2 Name of the place where the consultation was held Panchpadva (km 818+000 on NH-2)
Date – 4th December 2007
Lot of accidents are reported to occur at this particular location due to the people
crossing the highway.
Closing of the median opening and U-turn and railing/fencing of the built-up area and
both sides of the median is urgently required in order to reduce the number of
accidents.
Construction of an underpass has been demanded by the villagers so that crossing
becomes easy and safe.
8.3.3. Name of the place where public consultation was undertaken – Chandauli (Km 826.000
– km 829+000 on NH-2).
Date – 5th December 2007
Issues discussed –
The participants have requested to provide an additional underpass along with the
existing because there is built-up area on both sides of the road and this provision
would make crossing of the roads easier and also avoid accidents.
Pucca drainage is required on both sides of the road.
Footpath along with proper railing/ barrier is also a requisite.
8.3.4 Name of the place where the public consultation was undertaken – Navatpur (km
843.000 on NH-2)
Date – 18th January 2007
Introduction – Navatpur is a village which is present at the border of the two states i.e
Uttar Pradesh and Bihar. Here still the old GT road is being used as the bridge in the
four lane alignment is under construction.
Issues Discussed –
The trucks are being parked on either side of the road for a stretch of 2 – 3 km,
because of the UP border check post
The truck drivers also requested for provision of parking space in this particular
location and also at the Bihar border check post
The people also suggested to speed up the construction of the bridge which is under
progress
8.3.5 Name of the place where the public consultation was undertaken – Mohania (km
865+500 to km 867.800 on NH-2)
Date – 8th February, 2007
Participants – local residents, road users.
Issues Discussed –
The space available will not be sufficient for the widening of the project road to 6
lane.
There is a temple just beside the existing underpass and was suggested not be
shifted or demolished
NH-30 meets the project road at km 867+800 and a flyover is demanded in this
location for traffic to move smoothly and safely.
Underpass and/or overpass should be made available in all the built up areas on the
NH.
8.3.6 Name of the place where the public consultation was undertaken – Kudara (km
889+000 on NH-2)
Date – 9th December, 2007
Issues Discussed –
Lots of accidents are reported to occur in and around the area. This is mainly due to
trucks and vehicles traveling in the wrong direction because of no sufficient gaps in
the median for long distances.
There must be signboards about the various facilities provided on the project road.
Underpass and/or overpass should be provided in every built up area so as to avoid
accidents and facilitating the smooth movement of traffic. At the major built up area,
fly over should be constructed.
8.3.7 Name of the place where the public consultation was undertaken – Dehri & Bhediya
Date – 14th December 2007
Issues Discussed –
The embankment is very high and the business people are having lot of problems for
their business because of the same.
There is no need for the widening as there is not enough traffic and also not enough
space for widening.
The road portion is incomplete and should be immediately constructed.
The drainage facilities are very poor and causing lot of problems in the rainy season
and should be improved
8.1.8 Name of the place where the public consultation was undertaken – Rafiganj & Dev
Junction
Date – 16th December 2007
Chainage – km 973+000, km 974+450 on NH-2
Issues Discussed –
Dev junction is a place where a road from the project road diverts to the Dev Temple
and recently lot of accidents occurred at this location and an underpass is suggested
at this particular location.
There is an existing underpass near Rafiganj and is of no use as it is not at the
correct location and an underpass is demanded at exact location (entrance to
sivganj).
The existing underpass is always having drainage problems and becomes useless
during rainy season because it gets filled with water so proper improvement for
drainage should be done
Along with the above locations, public consultation has been carried at various locations on
the site itself near major junctions, urban establishments, etc and information is gathered
regarding their various requirements like flyovers, service roads, underpasses and all.
And also we have visited all the police stations along the project road to collect the accident
data and the all the accident spots along the corridor to make proper improvements at all the
major accident spots
The ROW is available for the major part of the project road. But in urban
locations, the Row is not sufficient for the widening to 6 lanes and people may
oppose for the land acquisition.
Flyovers, underpasses were demanded at major junctions & urban
establishments
One of the common demands was to provide pucca drainage facility in the built
up area.
Lot of accidents due to wrong direction travel and this should be minimized by
providing proper cross connectivity.
Truck lay byes are to be provided along the project corridor for every 30 – 40 km
CHAPTER – 9
SAFETY MEASURES
9.1 INTRODUCTION
Safety is the crucial factor for any road design and hence this chapter deals with the
aspects related to road safety for both road users as well as vehicles. The basic
approach is to give adequate warning and guidance to the drivers about the driving
conditions ahead and to impose certain traffic discipline to avoid probable accidents.
The second feature is to provide barriers in such a way that an errant vehicle is
streamlined on the road, thus avoiding the vehicle to runoff the road. All signs, marking
and safety measures are proposed with reference to IRC codes.
9.2.1 Traffic signs inform, guide, and warn the driver about driving environment to be
met ahead. They also provide information about traffic discipline needed to be followed.
Hence, there are three types of traffic signs found on roads.
i) Regulatory / Mandatory signs
ii) Cautionary signs
iii) Informatory signs:
These signs are designed to provide following services to the driver:
- Speed Breaker Ahead sign.
- Warn of the approach to junctions.
- Speed limit restrictions on particular sections, give destination/distance
Information.
9.2.2 Some of the signs will be in the verges mounted on steel posts in the usual manner. On
the approaches to junctions the provision of overhead signs mounted on gantries will be
explored at few locations. This will enable the signs to span the road and allow the driver
on the moderately high-speed road to easily read the sign and take appropriate action.
These overhead gantry signs are recommended as per IRC: 67-2001 in relation to
background colour, text colour and its border, letter size etc. While proposing traffic signs
for project Road IRC: 67-2001 “Code of practice for Road signs (First Revision)” is
referred.
9.2.3 The signs are proposed to be bi-lingual, Hindi and English.
9.2.4 The minimum letter size is 150mm.
9.2.5 It is proposed that all sign use the retro-reflective surface for clarity and visibility.
9.2.6 Kilometer Stones and Marker Posts are proposed at each kilometer as is the practice
on the national highway roads.
CHAPTER – 10
10.1 General
The preceding chapters of this report give detailed discussions on the various aspects of
the study carried out by the consultants for the Feasibility for 6 – laning of NH-2 from
Varanasi – Aurangabad (length- 192.4 Km.) in the state of UP & Bihar under NHDP
phase - V.
The details of existing road sections, design proposal and recommendations are
summarized in this chapter.
The project road form Varanasi – Aurangabad (NH- 2) Km. 786.000 to Km. 978.400 is
192.4 Km. long.
The present project road is 4 lane divided carriageway with service road at few places.
However, in urban areas, for about 23 km, the existing project road is provided with 6
lanes with service road. It is proposed to widen the existing 4 lane into 6 lane divided
carriageway for the complete project road length with service roads at specified location.
However, at 5 congested areas (Mohan saria, Chandauli, Mohania, Kudara and Dehri),
main C/W has ben proposed to retain as 2+2 lanes on either side of median with 2 lane
slip road with concrete pavement having same pavement composition as that of main
C/W.
As indicated earlier, the length of project road is about 192.4 km. in which about 85.2
km (km 862.100 – km 907.100 & km 938.200 – km 978.400) concrete pavement &
remaining 107.2 km bituminous / flexible pavement.
The Project road pavement condition have been surveyed and investigated in detail to
ascertain its structural capacity. It has been observed that the condition of the existing
pavement is fairly good as it is widened few years back only. However at few places
where construction is underway, pavement condition is not very good.
The terrain along the highway is mostly plain. The predominant lands use along the road
is agricultural with ribbon development with a mix of commercial and residential
activities. Many a places, it passes through barren lands.
10.3Proposed up gradation:
The rehabilitation and upgrading proposals are made based on the findings of the
detailed field investigation results and preliminary design. The proposal mainly covers
widening of the existing 4 lanes divided carriageway to 6 lanes with provision of
additional facilities like service roads, underpasses & over passes at place of
requirements.
However, at 5 congested areas (Mohan saria, Chandauli, Mohania, Kudara and Dehri),
main C/W has been proposed to retain as 2+2 lanes on either side of median with 2 lane
slip road with concrete pavement having same pavement composition as that of main
C/W.
The horizontal geometry of the existing 4 lane highways have been kept intact whereas
the vertical profile have been modified as per existing profile and design speed
requirement.
The design speed of 100 kmph has been considered in general with a minimum of 80
kmph.
Flexible pavement have been proposed for the widened lane adjacent to existing 2 lane
flexible pavement. Similarly concrete pavement have been proposed for the widening of
additional lane adjacent to existing concrete pavement.
The pavement composition for the new construction of additional one lane on each
carriageway was have been considered as under:
BC – 50mm
DBM – 160mm
WMM – 300mm
GSB – 300mm
DRAINAGE LAYER – 300mm
SUB GRADE – 500mm with 7% CBR
The pavement composition for the construction of concrete pavement for additional lane
adjacent to existing concrete pavement are as under:
PQC = 340 mm
DLC = 150 mm
GSB = 150 mm
Sub grade 500 mm with 7% CBR
The strengthening of existing 4 lanes of flexible pavement C/W has been proposed with
50mm BC over profile correction course as the 4 laning is completed recently.
The exact requirement of overlay after every five years of completion the widening /
Strengthening activities shall be established on the basis actual BBD tests data at that point of
time.
No strengthening have been proposed for the existing concrete pavement portion.
10.4 Recommendation:
From the feasibility study, it is seen that project is technically feasible and economically
viable. Hence it is recommended to implement the 6 – laning of NH- 2 from Varanasi –
Aurangabad.
------------------------