You are on page 1of 52

TECHNICAL SPECIFICATION

TECHNICAL WORKSCOPE

FOR PLATFORM

BASELINE INSPECTION

DOC: TML-OPS-GEN-PR-N-0017

REV: 2

DATE: 21/08/07

PAGE: 1 of 64

DOCUMENT ADMINISTRATION:

Document Administrator:

Document Expiry Date:

18/05/2010 or whenever this document is revised before that date.

IMSS Document Controller

Paper Master File:

Electronic Master File:

F:\IM_Work\Inspection\02.0 -TML Technical Inspection

Procedures\TML BASELINE INSPECTION – REV.B, CIMAGE when

approved
TML DCC

Distribution List:

Senior Inspection Engineer (TML)

Technical Services Superintendent (TML)

IMMS Inspection Planner

WORKSCOPE FOR PLATFORM BASELINE INSPECTION

DOCUMENT HISTORY:

Revision

Date

21/08/07

18/04/06

Description of change

Second Issue – Updating for Northern Field

First Issue – Inspection Planner

Approved by
DOCUMENT STATUS

APPROVAL

Reviewed by

Document Owner

Approved by

Document Authority

DESIGNATION

Senior Inspection & Corrosion Engineer

TML Technical Services Superintendent

Reproduction of this document without written permission of Talisman Malaysia Limited is


prohibited

SIGNATURE
TECHNICAL SPECIFICATION

TECHNICAL WORKSCOPE

FOR PLATFORM

BASELINE INSPECTION

DOC: TML-OPS-GEN-PR-N-0017

REV: 2

DATE: 21/08/07

PAGE: 2 of 64

CONTENTS

1.

INTRODUCTION

1.1. Background

1.2. Reference Documents

1.3. Glossary
5

2.

SCOPE

2.1. Corrosion Circuit Study

3.

BASELINE INSPECTION

3.1. Piping

3.2. Pressure Vessels

8
3.3. Pressure Relieving Devices (PRDs)

3.4. Corrosion Probes, Coupons, and Chemical Injection Quills

10

3.5. Thermowells

10

3.6. Structures

10

3.7. Pipelines

11

4.

12

DELIVERABLES

4.1. Review and Upload


12

4.2. Visual Inspection Report

12

4.3. Inspection Workpack

12

4.4. Wall Thickness Measurement Report

12

4.5. Corrosion Management Review Report

13

4.6. CREDO Asset Register

13

4.7. Structural Survey Report

14
5.

15

EXECUTION PLAN

5.1. Topsides Baseline Inspection

15

5.2. Structure Baseline Inspection

15

Reproduction of this document without written permission of Talisman Malaysia Limited is


prohibited
TECHNICAL SPECIFICATION

TECHNICAL WORKSCOPE

FOR PLATFORM

BASELINE INSPECTION

DOC: TML-OPS-GEN-PR-N-0017

REV: 2

DATE: 21/08/07

PAGE: 3 of 64

APPENDICES

APPENDIX 1: TMLGuidelines for Baseline Inspection of Pressure Vessel

APPENDIX 2: TMLGuidelines for Baseline Inspection of Piping

APPENDIX 3: TMLGuidelines for Baseline Inspection of Pressure Relieving Devices

APPENDIX 4: TML Inspection Report (Template)

APPENDIX 5: TML Anomaly Report (Template)

APPENDIX 6: TML Spreadsheet for Wall Thickness Measurement (Template)

APPENDIX 7: TML Guidelines for Baseline Inspection Ultrasonic Technique Wall thickness
Measurements

APPENDIX 8: TML Guidelines for Baseline Inspection of Structures

APPENDIX 9: CREDO Upload Reference Table

APPENDIX 10:TML Guidelines for Baseline Inspection Execution Plan

APPENDIX 11:TML Inspection Workpack (Example)

Reproduction of this document without written permission of Talisman Malaysia Limited is


prohibited
Page 17

Page 22

Page 26

Page 30

Page 33

Page 35

Page 37

Page 45

Page 50

Page 52

Page 62
TECHNICAL SPECIFICATION

TECHNICAL WORKSCOPE

FOR PLATFORM

BASELINE INSPECTION

DOC: TML-OPS-GEN-PR-N-0017

REV: 2

DATE: 21/08/07

PAGE: 4 of 64

1. INTRODUCTION

1.1. Background

TML is operating offshore oil field facilities situated in the PM3 and PM-305 CAA blocks located in

the Gulf of Thailand.

In compliance with TML's inspection strategy for TML offshore facilities in PM3 field, Baseline

Inspection has to be carried out on platform structures and topside static equipment.

The overall objectives of the baseline inspection are to:

Produce an asset register phase 1 in Excel format, ready to upload in the CIMS, for

managing corrective inspection events in the computerised inspection management system

(CIMS);

Produce an asset register phase 2 in Excel format, ready to upload in the CIMS, for

managing preventive inspections in the CIMS;

Measure piping and equipment thicknesses for corrosion monitoring purpose before first oil /

gas;

Document fabrication anomalies for inspection studies (RBI) and later inspection;

Get fabrication data (i.e. NDT drawings, weld summary records) of the structures for
inspection studies (RBI);

Get equipment datasheets, and inspection / calibration certificates;

Take photographs of the equipments & nameplates, piping supports, and structural members

(especially subsea structures with limited access when installed);

Raise any integrity issues that can be fixed on site to the project team and ensure these are

included in the construction punchlist;

Develop Inspection workpack including material take-off for Pressure Vessels & Heat

Exchangers;

Identify requirements for future piping inspection such as scaffolding, insulation removal and

other special needs.

This document details how to organize, carry out and report a platform baseline inspection.

1.2. Reference Documents

This document is based on the following references and guidelines:

Document No.

NO TML Doc Number

TML-OPS-GEN-PR-G-0059

TML-OPS-GEN-CP-N-0001

TML-OPS-GEN-CP-N-0002

Not Referenced in TML System

Not Referenced in TML System

Not Referenced in TML System

Description

TML Inspection Philosophy

TML Inspection Strategy

API 510, Pressure Vessel Inspection Code


API 570, Piping Inspection Code

API 572, Inspection of Pressure Vessels

(Tower, Drum, Reactors, Heat Exchanger, and Condensers)

API 580. Risk Based Inspection Process

API 576, Inspection of Pressure-Relieving Devices

TABLE 1: REFERENCE DOCUMENTS

Reproduction of this document without written permission of Talisman Malaysia Limited is


prohibited
TECHNICAL SPECIFICATION

TECHNICAL WORKSCOPE

FOR PLATFORM

BASELINE INSPECTION

DOC: TML-OPS-GEN-PR-N-0017

REV: 2

DATE: 21/08/07

PAGE: 5 of 64

1.3. Glossary

The following table gives a glossary of the meaning of terms used in this document.

Word/Abbreviation

API

CIMS

CMMS

Corrosion Circuit

Definition

American Petroleum Institute

Computerised Inspection Management System = CREDO

Computerised Maintenance Management System = MAXIMO

A section of piping of which all points are exposed to an environment of

similar corrosivity and which is of similar design conditions and material of

construction. Complex process units or piping systems are divided into


corrosion circuits to manage the necessary inspections, calculations, and

record keeping

CPP

Central Processing Platform

CREDO

Name of the TML Computerised Inspection Management System

Damage

Within this document, damage refers to a detrimental macroscopic change

in the condition of the equipment, for instance dents, gouges, bulging,

normally as a result of discrete events such as impact or fire.

Degradation

Degradation in equipment refers to a detrimental metallurgical change in the

material. It includes embrittlement, hydrogen attack, and creep before

macroscopic manifestation of a flaw.

DMS

Document Management System = CIMAGE

Failure

Within this document, any unintentional release of stored energy and/or

hazardous contents from a pressure system or containment constitutes a

failure. Failure usually involves a breach in the containment boundary and a

release of contents into the environment.

Inspection

Within this document, the term ‘inspection’ refers to the planning,

implementation and evaluation of examinations and/or testing to determine

the physical and metallurgical condition of equipment in terms of fitness-forservice.

Inspector

An individual who has been trained and has demonstrated the ability to
perform Pressure Piping and Vessel examinations in accordance with

standard practices, applicable codes, standards, and procedures.

MAXIMO

Name of the selected Computerised Maintenance Management System CMMS

Non Destructive Testing Non-destructive testing is an operation, which covers the inspection and/or

(NDT)

testing of any material, component or assembly by means, which do not

affect its ultimate serviceability.

Non Return Valves Non return valves offshore are also known as check valves. There are two

(NRV)

types used on TML platform; full bodied swing check valves and wafer types.

Offshore Structure

Offshore platform consisting of a framework of tubular members with a deck

(or decks) on top and piles driven through the framework to fix the structure

to the sea bed.

OPS

Operations Department of Talisman Malaysia Limited.

Pressure Vessel

A metal container generally cylindrical or spheroid, which is designed to hold

liquids or gases under pressure.

PRIMAVERA

Name of the selected Scheduling Software

Probability of Failure

The probability of failure of an item of equipment is mean frequency with

which the specified failure event would be expected to occur in a given

period of time, normally one year.

Risk
The risk of failure of an item of equipment combines the probability of failure

Reproduction of this document without written permission of Talisman Malaysia Limited is


prohibited
TECHNICAL SPECIFICATION

TECHNICAL WORKSCOPE

FOR PLATFORM

BASELINE INSPECTION

DOC: TML-OPS-GEN-PR-N-0017

REV: 2

DATE: 21/08/07

PAGE: 6 of 64

Word/Abbreviation

Definition

(mean failure rate) with a measure of the consequences of that failure. If

these are evaluated numerically, then the risk is defined as the product of

the probability of failure and the measure of consequence. There can

different risks for different measures of consequence.

Risk Based Inspection Risk based inspection is a process that involves the planning of an

(RBI)

inspection on the basis of the information obtained from a risk analysis of the

equipment.

Process Equipments

Refers to process equipments on topside which are within the inspection

scope. These include pressure vessels, heat exchangers, filters, piping,

accumulators, dampeners, tanks, PSVs, non return valves, corrosion

coupons, corrosion probes, sand probes, anodes (in pressure vessels) and
thermowells.

TML

Talisman Malaysia Limited

TMLs

Thickness Measurements Locations

UTWT

Ultrasonic Technique Wall Thickness Measurement

TABLE 2: GLOSSARY

TML will use this definition table as reference.

Reproduction of this document without written permission of Talisman Malaysia Limited is


prohibited
TECHNICAL SPECIFICATION

TECHNICAL WORKSCOPE

FOR PLATFORM

BASELINE INSPECTION

DOC: TML-OPS-GEN-PR-N-0017

REV: 2

DATE: 21/08/07

PAGE: 7 of 64

2. SCOPE

TML baseline inspection covers all piping, pipelines, topsides process equipments and structures

(sub-structures, topsides, bridges and flares).

However, TML want to concentrate baseline inspection on piping and process equipments that

belong to corrosion circuits which failure could generate health, safety, production or environmental

issues. Prior to site inspection, a corrosion circuits study shall be carried out.

2.1. Corrosion Circuit Study

All piping and topsides process equipments shall be assigned to a corrosion circuit, which is a

classification by material type and containment properties. The corrosion circuit study shall be

carried out by a Process Engineer and Inspection / Corrosion Engineer when the latest Approved for

Construction (AFC) drawings are available. This activity takes about 5 days for small platforms (i.e.

BKA, BKC), and about 2 to 3 weeks for larger platforms (i.e. BRA, SAA). During the corrosion circuit

review, the process engineer shall also check for any inappropriate pressure ratings of piping and

process equipments.

When all piping and process equipments assigned with a corrosion circuit, the table below shall be
utilised to prioritise the baseline inspection.

CC01 – Multiphase System

CC02 – Wet Unstablised Crude Oil

CC03 – Produced Water System

CC04 – Dry Stabilised Crude Oil

CC05 – Wet Gas

CC06 – Dry Gas

CC07 – Condensate

CC08 – Seawater

CC09 – Water

CC10 – Water Injection

CC11 – Flare / Vent *

CC12 – Drains

CC13 – Glycol

CC14 – Instrument / Utility

CC15 – Diesel

CC16 – Carbon Dioxide

CC17 – Chemical Treatment

CC18 – Lube / Hydraulic Oil

CC19 – Heat Medium

CC20 – Refrigerant – Propane Liquid

CC21 – Refrigerant – Propane Vapour

(A)

(B)
(C)

(D)

(E)

Duplex &

Stainless

Steel

Carbon

Steel

GRE

Epoxy

Copper

Nickel

Titanium

2
2

2*

3
3*

2*

0
0

1*

1
1

1*

TABLE 3: BASELINE INSPECTION PRIORITISATION BY CORROSION CIRCUIT

0 – No Baseline Inspection required


1 – Visual Inspection only

2 – Visual and UTTM (>30% Coverage) required

3 – Visual and UTTM (>90% Coverage) required

* Baseline required on flare system only; no baseline required on vent system.

Reproduction of this document without written permission of Talisman Malaysia Limited is


prohibited
TECHNICAL SPECIFICATION

TECHNICAL WORKSCOPE

FOR PLATFORM

BASELINE INSPECTION

DOC: TML-OPS-GEN-PR-N-0017

REV: 2

DATE: 21/08/07

PAGE: 8 of 64

3. BASELINE INSPECTION

3.1. Piping

Visual inspection (external) and wall thickness measurement shall be carried out on selected

platform topside piping. Following the corrosion circuit study, piping selection for baseline

inspection shall be carried out in accordance to Table 3 - Baseline Inspection Prioritisation by

Corrosion Circuit. Prior to site visit, workpack consisting of marked-up isometric and inspection

templates shall be prepared in two folders; one folder for the selected priority lines and the other

for the remaining lines.

Inspection and material verification shall be carried out as specified in the TML guidelines for

baseline inspection of piping (appendix 2 of the present document). Wall thickness measurement

of all the TML topside piping shall be carried out in order to get reference values before starting

operations. Measurements shall be carried out as specified in the TML guidelines for baseline

inspection UTWT measurements (appendix 7 of the present document).

Baseline inspection shall also be used to identify work requirements for subsequent inspection

campaigns. Piping that requires scaffolding and insulation removal to perform inspection in the

future, shall be noted and classified in the following categories.


Piping Accessible and Not Insulated (A&NI);

Piping Accessible and Insulated (A&I);

Piping Not Accessible and Not Insulated (NA&NI);

Piping Not Accessible and Insulated (NA&I).

TML inspection analyst when issuing the summary report indicating main issues noted during the

baseline inspection, will also quantify as part of inspection management information the number

piping which need abseiling, scaffolding and insulation removal.

For CREDO population, piping data shall be collected as per CREDO upload reference table

(appendix 9 of the present document). Essential piping data to be collected at site are indicated in

this table.

For above tasks, appointed third-party site Inspectors / controllers shall assist TML OPS Inspection

Engineer.

3.2. Pressure Vessels

Pressure vessels include all containers designed to withstand internal or external pressure. Typical

pressure vessels on TML platforms are Drums, Separators, Dryers, Filters, Scrubbers, Heat

Exchangers etc. Following the corrosion circuit study, pressure vessels selection for baseline

inspection shall be carried out in accordance to Table 3 – Baseline Inspection Prioritisation by

Corrosion Circuit. Prior to the site visit, marked up vessel general arrangements (GA) and inspection

templates shall be prepared in two folders; one folder for the selected priority vessels and the other

for the remaining vessels.


Pressure vessel within API 510 Inspection Code exemption (Appendix A of the API code), is only

subject to UTWT measurements and external inspection. The exemption includes vessel which are:

• less than 140 litres and 1724 Kpa design pressure,

• less than 42 litres and 4137 Kpa design pressure,

• less 152.4mm inside diameter width, height or cross section diagonal but no limitation on the

length or pressure, and,

• operating (internal or external) less than atmospheric (103.4 Kpa) with no limitation on size.

Reproduction of this document without written permission of Talisman Malaysia Limited is


prohibited
TECHNICAL SPECIFICATION

TECHNICAL WORKSCOPE

FOR PLATFORM

BASELINE INSPECTION

DOC: TML-OPS-GEN-PR-N-0017

REV: 2

DATE: 21/08/07

PAGE: 9 of 64

External and internal (when possible) visual inspection and photography, for all platform topside

pressure vessels. Inspection shall be carried out as specified in the TML guidelines for baseline

inspection of pressure vessel (appendix 1 of the present document). Wall thickness measurement

of all the TML topside pressure vessels shall be carried out in order to get reference values before

starting operations. Measurements shall be carried out as specified in the TML guidelines for

baseline inspection UTWT measurements, (appendix 7 of the present document).

Baseline inspection shall also be used to identify work requirements for subsequent inspection

campaigns. Vessel that requires scaffolding and insulation removal to perform inspections in the

future shall be noted and classified in the following categories.

Vessel Accessible and Not Insulated (A&NI),

Vessel Accessible and Insulated (A&I),


Vessel Not Accessible and Not Insulated (NA&NI),

Vessel Not Accessible and Insulated (NA&I).

TML inspection analyst when issuing the summary report indicating main issues noted during the

baseline inspection, will also quantify as part of inspection management information the number

vessels which need scaffolding and insulation removal.

All data and information required for planning future vessel inspection and performing the

inspection work offshore shall be documented into a workpack. An example of a workpack is given

in appendix 11. This inspection workpack shall as a minimum contain the following.

General information of the vessel (Platform, Tag Number, P&ID, Corrosion Circuit, etc.),

Photograph and drawing,

Work procedure (isolation requirement etc.),

Manpower requirement,

Spare parts requirement (Material take off), and,

Tools requirement.

For CREDO population, pressure vessel data shall be collected as per CREDO upload reference

table (appendix 9 of the present document). Essential vessel data to be collected at site are

indicated in this table. Photographs of the pressure vessel and respective nameplate shall be

captured and included in the baseline inspection report for future reference.
For above tasks, appointed third-party or TML site Inspectors / controllers shall assist TML OPS

Inspection Engineer.

3.3. Pressure Relieving Devices (PRDs)

Pressure Relieving Devices (PRDs) are equipments such as Pressure Safety Valves (PSVs),

Vacuum Relief Valves (VRVs), Air Relief Valves (ARVs) and Rupture Disks. All PRDs shall be

subject to an external inspection as specified in the TML guidelines for baseline inspection of

pressure safety valves (appendix 3 of the present document).

Prior to installation of PSVs on the process equipments, calibration and testing are carried out at

the yard to determine any damage or changes in the factory adjustment due to shipping. These

test certificates shall be gathered during the baseline inspection, for uploading into DMS

(CIMAGE).

If the platform start-up date is more than one year from the PSV yard inspection and testing date,

a recalibration and testing of the PSV shall be carried out during commissioning before start-up.

Reproduction of this document without written permission of Talisman Malaysia Limited is


prohibited
TECHNICAL SPECIFICATION

TECHNICAL WORKSCOPE

FOR PLATFORM

BASELINE INSPECTION

DOC: TML-OPS-GEN-PR-N-0017

REV: 2

DATE: 21/08/07

PAGE: 10 of 64

Inspection and testing of PSVs which are not in operations for extended periods will ensure that

tampering, corrosion or other acts that may impede the proper performance of the PSVs have not

occurred. In this case, both calibration certificates shall be collected for uploading into DMS

(CIMAGE).

For CREDO population, PRD’s data shall be collected as per CREDO upload reference table

(appendix 9 of the present document). Essential PRD data to be collected at site are indicated in

this table. Photographs of the PRD and respective nameplate shall be captured and included in the

baseline report for future reference.

3.4. Corrosion Probes, Coupons, and Chemical Injection Quills

The baseline inspection should include a review of all chemical injection locations, including injection

quills, fittings, pumps, tanks, injection lines, etc, to evaluate if the point is suitable for effective

injection and correlate it with the corrosion monitoring locations. Injection rates, atomization of

chemical and differential pressures must be correct for adequate corrosion inhibition or chemical

distribution into the applicable process phase.

The review shall also include all corrosion monitoring locations, including ER probes and coupons, to
evaluate if the location is suitable for effective corrosion monitoring; can be retrieved whilst online –

(i.e. not requiring process shutdown), space clearance for manipulation of retrieval tool and

accessibility of the locations – e.g. noting requirements for scaffolding etc.

Prior to the site visit, the corrosion engineer shall review the drawings to identify any issues with

corrosion probes, coupons and chemical injection quills.

For CREDO population, corrosion monitoring and inhibition device’s data shall be collected as per

CREDO upload reference table (appendix 9 of the present document). Essential data to be

collected at site, with respect to these devices, are indicated in this table. Photographs of the

corrosion monitoring location shall be captured and included in the baseline inspection report for

future reference.

For the corrosion monitoring review, appointed contractor corrosion engineer and site inspector
shall

assist TML OPS Inspection Engineer.

3.5. Thermowells

For CREDO population, Thermowell’s data shall be collected as per CREDO upload reference

table (appendix 9 of the present document). Essential data to be collected at site, with respect to

Thermowell, are indicated in this table. Photograph of the thermowell shall also be captured for

future reference.

3.6. Structures

Structures refer to all steel substructures, bridges, flares, topsides and accommodation modules.

The baseline inspection of structures and checks on fabrication quality shall be carried out as

specified in the TML guidelines for baseline inspection of structures (appendix 8 of the present

document). A detailed photographic survey shall accompany the structural visual inspection,

especially on substructure components to aid future subsea campaign. These photographs shall be

named accordingly, stored and controlled within the TML network at Kuala Lumpur office.

Fabrication documents required for RBI study and latest AFC drawings for structural tagging shall be
gathered at site.

When a construction or installation problem is identified, TML OPS Inspection Engineer will have to

check if this has not already been captured in the TML Project Deficiency / Punch list. If not, TML

Reproduction of this document without written permission of Talisman Malaysia Limited is


prohibited
TECHNICAL SPECIFICATION

TECHNICAL WORKSCOPE

FOR PLATFORM

BASELINE INSPECTION

DOC: TML-OPS-GEN-PR-N-0017

REV: 2

DATE: 21/08/07

PAGE: 11 of 64

OPS Inspection Engineer will have to report it to TML Project Inspection Engineer in order to include

the problem in the TML Project Deficiency / Punch list. All findings observations shall be recorded in

a report and uploaded into CIMS.

For the above tasks, appointed third-party Structural Engineer / Inspectors shall assist TML OPS

Inspection Engineer.

3.7. Pipelines

Pipelines will be subject to Gauging Pig (Base Plate Pig) survey and Side Scan Sonar (SSS) survey

following installation. The gauging pig utilises plate of size equivalent to the minimum allowable

internal diameter for each pipelines to rule out the possibility of damage (dent) to the pipeline
during

installation that may constrain normal pipeline operations.

Side scan sonar is performed to identify locations with span lengths exceeding allowable limits.

These spans will be rectified prior to hydrotesting the pipeline.

Both gauge pigging and SSS survey will be managed by TML Projects department. The reports of

these surveys will be submitted to the TML Operations department as part of the final
documentation
submission.

Reproduction of this document without written permission of Talisman Malaysia Limited is


prohibited
TECHNICAL SPECIFICATION

TECHNICAL WORKSCOPE

FOR PLATFORM

BASELINE INSPECTION

DOC: TML-OPS-GEN-PR-N-0017

REV: 2

DATE: 21/08/07

PAGE: 12 of 64

4. DELIVERABLES

4.1. Review and Upload

The reports produced from the baseline inspection will be reviewed by TML inspection analyst, and

subsequently uploaded into DMS (CIMAGE) and CIMS by TML Inspection Document Controller.
Reports

to be uploaded into DMS shall be limited to a file size of 2MB or lesser, to meet CIMAGE
requirements.

4.2. Visual Inspection Report

Upon completion of the baseline inspection, the TML OPS Inspection Engineer, prior to being

submitted to TML and entered into the inspection management system, shall review all findings,

recommendations, and documentation. TML OPS Inspection Engineer shall issue equipment

condition reports summarizing the scope of inspection, findings, and recommendations.

The visual inspection report shall include inspection of Pressure Vessels, Piping, PRDs, NRVs and

Thermowells. Visual inspection of process equipment shall be documented as follows:

• Tag number,

• Corrosion circuit,
• Date of inspection,

• Name of the Inspector,

• Description of the inspection performed,

• Results of the inspection,

• Digital photography.

For that, TML OPS Inspection Engineer shall use TML Inspection Report template provided in

Appendix 4. TML OPS Inspection Engineer shall produce hardcopy and softcopy documents to TML.

If any anomaly is detected during visual inspection, then TML Inspection Engineer shall raise an

anomaly report (refer to appendix 5 for template) and attach it with the equipment inspection
report.

4.3. Inspection Workpack

From the data and information gathered during the yard visit, an Inspection Workpack shall be

produced for each vessel. These workpack will be used for the future inspections of the vessel and

as a minimum shall include the following:

• General information of the vessel (Platform, Tag Number, P&ID, Corrosion Circuit, etc.),

• Photograph and drawing,

• Work procedure (isolation requirement etc.),

• Manpower requirement,

• Spare parts requirement (Material take off), and,

• Tools requirement.

TML Operations Inspector shall provide hardcopy and softcopy to TML Inspection Planner for review,

and safekeeping.

4.4. Wall Thickness Measurement Report

4.4.1. Pressure Vessels

Thickness Measurement Locations shall be identified on a copy of the pressure vessel

general arrangement drawing. Once carried out, wall thickness measurement shall be
reported on TML excel spreadsheets (template provided in Appendix 6). TML OPS Inspection

Engineer shall provide hardcopy and softcopy documents to TML.

Reproduction of this document without written permission of Talisman Malaysia Limited is


prohibited
TECHNICAL SPECIFICATION

TECHNICAL WORKSCOPE

FOR PLATFORM

BASELINE INSPECTION

DOC: TML-OPS-GEN-PR-N-0017

REV: 2

DATE: 21/08/07

PAGE: 13 of 64

If any anomaly is detected during wall thickness measurement, then TML OPS Inspection

Engineer shall raise an anomaly report (refer to appendix 5 for template) and attach it with the

pressure vessel inspection report.

4.4.2. Piping

Thickness Measurement Points, scaffolding and insulation removal requirements shall be

clearly identified on a copy of the piping isometrics. Wall thickness measurement shall be

reported on TML excel spreadsheets (template provided in Appendix 6). TML OPS Inspection

Engineer shall provide hardcopy and softcopy documents to TML.

If any anomaly is detected during wall thickness measurement of piping, then TML OPS

Inspection Engineer shall raise an anomaly report (refer to appendix 5 for template) and

attach it with the piping inspection report.

4.5. Corrosion Management Review Report

As part of the corrosion management review, a report shall be issued containing:


List of existing corrosion monitoring locations,

Existing corrosion monitoring equipment in place (including their type),

Accessibility of the locations (scaffolding and insulation removal requirement) ,

Adequacy of existing monitoring facilities and documentation,

Recommendation for improvement, including suggested changes to the existing monitoring

locations,

Recommended spare parts list,

Photographic database of corrosion probes and coupons locations.

TML OPS Inspection Engineer shall provide hardcopy and softcopy (excel format for CIMS upload)

documents to TML.

The report shall also contain a section dedicated to chemical injection locations, containing similar

information.

4.6. CREDO Asset Register

Excel spreadsheet for uploading computerized inspection management system shall be filled during

the Platform Baseline inspection for the following equipment types:


Pressure Vessels,

Heat Exchangers,

Portable tanks,

Gas Cylinders,

Piping,

Pipelines,

Pressure Safety Devices (PSVs & VSVs),

Non Return Valves (NRVs),

Accumulators and Dampeners,

Thermowells,

Corrosion Probes & Coupons,

Corrosion Inhibitor Injections.

Data not available on documents (datasheet, GA drawings…) will have to be collected from site.

The CREDO upload reference table indicate the essential data to be collected at site for the above

equipments.

Reproduction of this document without written permission of Talisman Malaysia Limited is


prohibited
TECHNICAL SPECIFICATION

TECHNICAL WORKSCOPE

FOR PLATFORM

BASELINE INSPECTION

DOC: TML-OPS-GEN-PR-N-0017

REV: 2

DATE: 21/08/07

PAGE: 14 of 64

4.7. Structural Survey Report

A final comprehensive report shall be compiled for identifying and recording significant construction
and

installation problems / issues that could impact structural integrity. This shall include:

List of construction / installation problems and issues that could impact structural integrity,

Photographs of sub-structures to aid future subsea inspection campaign,

Reference to some of the data and documentation collected on site for RBI study,

Recommended actions,

Recommendations applicable to future projects, if any.

TML OPS Inspection Engineer shall provide hardcopy and softcopy report to TML.
Reproduction of this document without written permission of Talisman Malaysia Limited is
prohibited
TECHNICAL SPECIFICATION

TECHNICAL WORKSCOPE

FOR PLATFORM

BASELINE INSPECTION

DOC: TML-OPS-GEN-PR-N-0017

REV: 2

DATE: 21/08/07

PAGE: 15 of 64

5. EXECUTION PLAN

5.1. Topsides Baseline Inspection

Figure 1 shows the typical topsides construction stages at the yard and the suitable time to execute

the baseline inspection activities. The project stages change depending on the delivery of materials

to site, topsides design, barge and lifting crane availability, work scheduled offshore etc. Typically all

structural work will be carried out first. When the structures are in place, the static equipment and

piping are installed, and then hydrotested. When the static equipments are in place, the electrical

and instrumentation works commence. Finally, the topside will be lifted or rolled out into a barge,

drilling derrick or similar vessel and sailed off for installation. Some work may be completed
offshore.

The number of trips to the yard for baseline inspection depends on the quantity of equipment,
piping

and corrosion monitoring devices requiring inspection. If these equipments can be inspected in one

trip to the yard, the trip shall be planned between mechanical completions date and electrical &

instrumentation completions date.

The objective is to ensure that there is enough time at the yard to inspect all equipment, piping, and

corrosion monitoring device in the critical corrosion circuit. Refer to prioritisation table in section 2.1
for the critical corrosion circuit.

Towards the end fabrication process there will many activities taking place including hydrotesting
and

the manning level will be high. This will slow down the baseline inspection activity, especially UTWT

survey, where some sections will be restricted due to hydrotests or activities. To lessen the workload

during congestion period, one or more visits to the yard shall be planned to partially complete the

baseline inspection workscope.

For detailed execution plan see Appendix 10.

5.2. Structure Baseline Inspection

The structural survey shall be carried out when the major welding, NDT and painting tasks are

completed, however there are enough scaffolds around the structures to perform adequate visual

inspection. This will normally be 1 week prior to load out dates, but shall be confirmed with the TML

site client representative.

Reproduction of this document without written permission of Talisman Malaysia Limited is


prohibited
TECHNICAL SPECIFICATION

DOC: TML-OPS-GEN-PR-N-0017

REV: 2

TECHNICAL WORKSCOPE FOR PLATFORM

BASELINE INSPECTION

Window for

1st UTWT and

Visual

Inspection

DATE: 21/08/07

PAGE: 16 of 64

Window for final UTWT &

Visual Inspection, and

Corrosion Monitoring Survey

Baseline

Schedules

TIMELINE

Structural

Completions

Date
Structural Work

Mechanical

Completions

Date

Piping & Equipment

Installation

E&I Completions

Date

Construction

Schedules

Hydrotesting

Electrical &

Instrumentation Installation

Topsides Load

Out Date

Seafastening

& Load Out

FIGURE 1: BASELINE VISUAL INSPECTION AND UTWT MEASUREMENTS TIMELINE

Reproduction of this document without written permission of Talisman Malaysia Limited is


prohibited

You might also like