PHASE 1
Already coordinated to
Clearing works still Constech & committed Clearing works still
ongoing at Area 3 & 4 by to handover the whole ongoing at Area 3 & 4 by Already coordinated to To monitor clearing
Constech area of area 4 on Sept. Constech constech progress.
27.
Low productivity rate Waiting for deployment Low productivity rate To follow up the
per day which result to of additional hacker per day which result to For revision of schedule progress from MSTM
negative variance from MSTM negative variance
Design length for 188 Already coordinated to Design length for 188 Still waiting for advise To follow up to Constech
positions Constech positions
Design & no. of pos. For Already coordinated to Design length for two Already coordinated to To follow up to Constech
Tower Crane Pile Tower Crane Pile
location Constech location Constech
PHASE 2
Constech committed to To coordinate from
start clearing works last Constech regarding the Still waiting for clearing Already coordinated to To monitor and follow
week but did not clearing works and works at Phase 2 constech up from Constech.
materialized. when will they start.
Prepared by:
PHASE 1
Already coordinated to Already coordinated to
Clearing works still Constech & committed Clearing works still Constech & committed To monitor clearing
ongoing at Area 3 & 4 by to handover the partial ongoing at Area 3 & 4 by to handover the whole progress.
Constech area of area 4 on Sept. Constech area of area 4 on Sept.
24. 27.
Waiting for Constech to Already coordinated to Still waiting for Constech Already coordinated to
hand over the remaining Constech & committed to hand over the
remaining area of 11m Constech
& committed To follow up the clearing
area of 11m (GL-18- to handover the area to handover the area
24/D-D') in order for (GL-18-24/D-D') in order (GL - 18-24/D-D') works
DMWAI to drive in the (GL
- 18-24/D-D') on on
for DMWAI to drive in Sept. 27.
Sept. 24.
area the area
Prepared by:
PHASE 1
Waiting for Constech to Already coordinated to Waiting for Constech to Already coordinated to
hand over the remaining Constech and hand over the remaining Constech & committed
area of 11m (GL-18- committed to hand over area of 11m (GL-18- to handover the area To start driving at area
24/D-D') in order for 24/D-D') in order for by Sept. 25.
DMWAI to drive in the partial
area (GL-18/D-D') DMWAI to drive in the (GL - 18-24/D-D') on
area on September 14, 2018 area Sept. 24.
Already coordinated to
Constech committed to To coordinate from constech and committed
start clearing works last Constech regarding the Still waiting for clearing to clear the area by first To monitor and follow
week but did not clearing works and works at Phase 2 week of October in up from Constech.
materialized. when will they start. order to start the driving
of test pile
Prepared by:
PHASE 1
Low productivity rate Reduced pile length of Waiting for fabrication Sequence already issued To follow up the
per day of 320t static regular pile as per of MSTM as per by Constech. To follow progress of clearing
instruction of Constech
pile driver due to cutting to improve the Constech priority up fabrication schedule from MSTM and
issues productivity rate sequence from MSTM Constech
Constech instructed
DMWAI/MSTM to
DMWAI/MSTM to Unstable ground at GL- Already coordinated to
convert 600T static pile convert the equipment 11/A'-D' which result to Constech and To finish driving in the
driver from center pile after the completion of mbility problem of the committed to make the area by next week.
the availble 11m pile
to Side Piler to drive pile 600t static area stable.
locations
locations along GL-11
PHASE 2
Constech committed to To coordinate from
Waiting for clearing To start clearing works
works at Phase 2 by of Constech by next start clearing works last Constech regarding the To monitor and follow
Constech week week but did nit clearing works and up from Constech.
materialized. when will they start.
Prepared by:
To complete clearing
Clearing works still Constech committed to Clearing works still To follow up the
ongoing at Area 3 & 4 by hand over the area ongoing at Area 3 & 4 by works on the areas by progress of clearing
Constech within 20-30days. Constech Constech on September from Constech
29, 2018.
Waiting for clearing To follow up from Waiting for clearing To start clearing works To follow up the
works at Phase 2 by Constech works at Phase 2 by of Constech by next progress of clearing
Constech Constech week from Constech
DMWAI already
Waiting for Constech Waiting for Constech received the Site
Site Instruction To follow up from Site Instruction Instruction. Excess of
regarding design of Test Constech regarding design of Test 25m Top Test Pile from
Piles for Phase 2 Piles for Phase 2 Phase 1 will be the Test
Pile for Phase 2.
Prepared by:
Clearing works still Clearing works still Constech committed to To complete clearing
ongoing at Area 3 & 4 by To follow up from
Constech ongoing at Area 3 & 4 by hand over the area works on the areas by
Constech on September
Constech Constech within 20-30days. 29, 2018.
Constech already
Revised completion Revised completion approved Option 2
schedule w/ 2 opotions To follow up from schedule w/ 2 opotions schedule during
was submitted for Constech was submitted for
approval approval coordination meeting on
August 29, 2018.
To increase the
Low productivity rate productivity rate per day follow up MSTM for
per day which result to and to add pile driving To
negative variance equipment in order to the catch up.
catch up
Prepared by: