Project: LANDMARK - PILE DRIVING WORKS

PREVIOUS THIS WEEK


TARGET NEXT WEEK
ISSUES & CONCERNS ACTION PLAN/S ISSUES & CONCERNS ACTION PLAN/S

PHASE 1
Already coordinated to
Clearing works still Constech & committed Clearing works still
ongoing at Area 3 & 4 by to handover the whole ongoing at Area 3 & 4 by Already coordinated to To monitor clearing
Constech area of area 4 on Sept. Constech constech progress.
27.

Delayed delivery of Delayed delivery of To follow up from


fabricated piles as per To coordinate to MSTM fabricated piles as per To coordinate to MSTM MSTM and Constech to
schedule and Constech schedule and Constech expedite the delivery of
available piles

Low productivity rate Waiting for deployment Low productivity rate To follow up the
per day which result to of additional hacker per day which result to For revision of schedule progress from MSTM
negative variance from MSTM negative variance

Still waiting for Constech


to hand over the Already coordinated to Unstable ground of
remaining area of 11m Constech & committed
to handover the area
remaining area for 11m Already coordinated to To follow up the clearing
design length (GL-20-
(GL-18-24/D-D') in order (GL - 18-24/D-D') on 23/D) & for clearing Constech works
for DMWAI to drive in Sept. 27. works of GL 24/D-D'
the area

Design length for 188 Already coordinated to Design length for 188 Still waiting for advise To follow up to Constech
positions Constech positions
Design & no. of pos. For Already coordinated to Design length for two Already coordinated to To follow up to Constech
Tower Crane Pile Tower Crane Pile
location Constech location Constech

PHASE 2
Constech committed to To coordinate from
start clearing works last Constech regarding the Still waiting for clearing Already coordinated to To monitor and follow
week but did not clearing works and works at Phase 2 constech up from Constech.
materialized. when will they start.

Prepared by:

John Kevin G. Oliquino / Froilan F. Espinosa


DMWAI - Project Engineer
Project: LANDMARK - PILE DRIVING WORKS

PREVIOUS THIS WEEK


TARGET NEXT WEEK
ISSUES & CONCERNS ACTION PLAN/S ISSUES & CONCERNS ACTION PLAN/S

PHASE 1
Already coordinated to Already coordinated to
Clearing works still Constech & committed Clearing works still Constech & committed To monitor clearing
ongoing at Area 3 & 4 by to handover the partial ongoing at Area 3 & 4 by to handover the whole progress.
Constech area of area 4 on Sept. Constech area of area 4 on Sept.
24. 27.

Still waiting for Delayed delivery of To follow up from


fabrication & delivery To coordinate to MSTM fabricated piles as per To coordinate to MSTM MSTM and Constech to
and Constech and Constech expedite the delivery of
update schedule available piles

Already issued a letter


Low productivity rate to MSTM Low productivity rate Waiting for deployment
per day which result to recommending to have
additional pile hackers per day which result to of additional hacker
To follow up the
progress from MSTM
negative variance for 320 & 600t static pile negative variance from MSTM
drivers.

Waiting for Constech to Already coordinated to Still waiting for Constech Already coordinated to
hand over the remaining Constech & committed to hand over the
remaining area of 11m Constech
& committed To follow up the clearing
area of 11m (GL-18- to handover the area to handover the area
24/D-D') in order for (GL-18-24/D-D') in order (GL - 18-24/D-D') works
DMWAI to drive in the (GL
- 18-24/D-D') on on
for DMWAI to drive in Sept. 27.
Sept. 24.
area the area

Design length for 188 Already coordinated to To follow up to Constech


positions Constech
Design & no. of pos. For Already coordinated to
Tower Crane Pile To follow up to Constech
Constech
location
PHASE 2
Constech committed to To coordinate from
start clearing works last Constech regarding the Still waiting for clearing Already coordinated to To monitor and follow
week but did not clearing works and works at Phase 2 constech up from Constech.
materialized. when will they start.

Prepared by:

John Kevin G. Oliquino / Froilan F. Espinosa


DMWAI - Project Engineer
Project: LANDMARK - PILE DRIVING WORKS

PREVIOUS THIS WEEK


TARGET NEXT WEEK
ISSUES & CONCERNS ACTION PLAN/S ISSUES & CONCERNS ACTION PLAN/S

PHASE 1

Already coordinated to Already coordinated to


Clearing works still Constech. Ongoing Clearing works still Constech & committed To monitor clearing
ongoing at Area 3 & 4 by clearing works in the ongoing at Area 3 & 4 by to handover the partial progress.
Constech Constech area of area 4 on Sept.
area 24.

Waiting for fabrication Sequence already issued Still waiting for


of MSTM as per by Constech. To follow fabrication & delivery To coordinate to MSTM To follow up from
Constech priority up fabrication schedule and Constech MSTM and Constech
sequence from MSTM update

Already issued a letter


Low productivity rate Already coordinated to Low productivity rate to MSTM
per day which result to MSTM to increase
productivity rate of the per day which result to
recommending to have To follow up the
additional pile hackers progress from MSTM
negative variance equipments. negative variance for 320 & 600t static pile
drivers.

Unstable ground at GL- Already coordinated to Unstable ground at GL-


11/A'-D' which result to Constech and 11/D-E which result to To coordinate to To monitor the progress.
mobility problem of the committed to make the mobility problem of the Constech
600t static area stable. 600t static

Waiting for Constech to Already coordinated to Waiting for Constech to Already coordinated to
hand over the remaining Constech and hand over the remaining Constech & committed
area of 11m (GL-18- committed to hand over area of 11m (GL-18- to handover the area To start driving at area
24/D-D') in order for 24/D-D') in order for by Sept. 25.
DMWAI to drive in the partial
area (GL-18/D-D') DMWAI to drive in the (GL - 18-24/D-D') on
area on September 14, 2018 area Sept. 24.

Insufficient supply of To follow up delivery To have sufficient supply


10m design length on from Constech and in order to finish the
remaining balance w/ in
site. MSTM
the area
PHASE 2

Already coordinated to
Constech committed to To coordinate from constech and committed
start clearing works last Constech regarding the Still waiting for clearing to clear the area by first To monitor and follow
week but did not clearing works and works at Phase 2 week of October in up from Constech.
materialized. when will they start. order to start the driving
of test pile

Prepared by:

John Kevin G. Oliquino / Froilan F. Espinosa


DMWAI - Project Engineer
Project: LANDMARK - PILE DRIVING WORKS

PREVIOUS THIS WEEK


TARGET NEXT WEEK
ISSUES & CONCERNS ACTION PLAN/S ISSUES & CONCERNS ACTION PLAN/S

PHASE 1

Clearing works still To complete clearing Already coordinated to


ongoing at Area 3 & 4 by works on the areas by Clearing
ongoing
works still
at Area 3 & 4 by Constech. Ongoing To monitor clearing
Constech on September clearing works in the progress.
Constech 29, 2018. Constech area

Low productivity rate Reduced pile length of Waiting for fabrication Sequence already issued To follow up the
per day of 320t static regular pile as per of MSTM as per by Constech. To follow progress of clearing
instruction of Constech
pile driver due to cutting to improve the Constech priority up fabrication schedule from MSTM and
issues productivity rate sequence from MSTM Constech

To increase the Already coordinated to To push MSTM to


Low productivity rate productivity rate per day Low productivity rate MSTM to increase complete driving of the
per day which result to and to add pile driving per day which result to
negative variance equipment in order to negative variance productivity rate of the remaining 10m piles on
catch up equipments. site.

Constech instructed
DMWAI/MSTM to
DMWAI/MSTM to Unstable ground at GL- Already coordinated to
convert 600T static pile convert the equipment 11/A'-D' which result to Constech and To finish driving in the
driver from center pile after the completion of mbility problem of the committed to make the area by next week.
the availble 11m pile
to Side Piler to drive pile 600t static area stable.
locations
locations along GL-11

Waiting for Constech to Already coordinated to


hand over the remaining Constech and
area of 11m (GL-18-
committed to hand over To
start driving in the
24/D-D') in order for area
DMWAI to drive in the partial
area (GL-18/D-D')
area on September 14, 2018

PHASE 2
Constech committed to To coordinate from
Waiting for clearing To start clearing works
works at Phase 2 by of Constech by next start clearing works last Constech regarding the To monitor and follow
Constech week week but did nit clearing works and up from Constech.
materialized. when will they start.

Prepared by:

John Kevin G. Oliquino / Froilan F. Espinosa


DMWAI - Project Engineer
Project: LANDMARK - PILE DRIVING WORKS

PREVIOUS THIS WEEK


TARGET NEXT WEEK
ISSUES & CONCERNS ACTION PLAN/S ISSUES & CONCERNS ACTION PLAN/S

To complete clearing
Clearing works still Constech committed to Clearing works still To follow up the
ongoing at Area 3 & 4 by hand over the area ongoing at Area 3 & 4 by works on the areas by progress of clearing
Constech within 20-30days. Constech Constech on September from Constech
29, 2018.

Waiting for clearing To follow up from Waiting for clearing To start clearing works To follow up the
works at Phase 2 by Constech works at Phase 2 by of Constech by next progress of clearing
Constech Constech week from Constech

DMWAI already
Waiting for Constech Waiting for Constech received the Site
Site Instruction To follow up from Site Instruction Instruction. Excess of
regarding design of Test Constech regarding design of Test 25m Top Test Pile from
Piles for Phase 2 Piles for Phase 2 Phase 1 will be the Test
Pile for Phase 2.

Revised completion Constech already Revised completion


approved Option 2 To follow the approval To received the
schedule w/ 2 opotions schedule during schedule w/ 2 options of Option 2 from approved schedule by
was submitted for coordination meeting on was submitted for Constech next week
approval approval
August 29, 2018.

MTSM 70t Crawler DMWAI already


Crane not yet mobilized one unit
operational due to Crawler Crane on August MSTM 70t crawler crane already operation last
mevhanical failure 30, 2018 and September 4, 2018
happened on August 9, operational last
2018 September 1, 2018.

Reduced pile length of


Low productivity rate MSTM suggested to Low productivity rate
per day of 320t static reduce pile length and per day of 320t static regular pile as per
of Constech To
start the fabrication
pile driver due to cutting was already approved pile driver due to cutting instruction of new design length
to improve the
issues by constech issues
productivity rate

To increase the To increase the


Low productivity rate productivity rate per day Low productivity rate productivity rate per day To follow up MSTM for
per day which result to and to add pile driving per day which result to and to add pile driving the catch up.
negative variance equipment in order to negative variance equipment in order to
catch up catch up

Waiting for the DMWAI/MSTM and


fabrication of intial To follow up from New design length Constech already MSTM to start
completed joint fabrication sequence as
150pcs - 12m + 13m Constech and MSTM issued by Constech. counting during Site per Constech Instruction
regular piles Coordiantion Meeting

Constech issued new


lay-out of pile locations DMWAI to prepare lay-
along GL-11-14/E-F, GL- out plan for the affected DMWAI to submit lay-
11/A'-D' and GL-12'/B- locations. out plan to constech.
D'.

Constech instructed DMWAI/MSTM to


DMWAI/MSTM to convert the equipment To start driving pile
convert 600T static pile after the completion of locations along GL-11
driver from center pile
to Side Piler to drive pile the availble 11m pile using Side Piler.
locations along GL-11 locations

Prepared by:

John Kevin G. Oliquino / Froilan F. Espinosa


DMWAI - Project Engineer
Project: LANDMARK - PILE DRIVING WORKS

PREVIOUS THIS WEEK


TARGET NEXT WEEK
ISSUES & CONCERNS ACTION PLAN/S ISSUES & CONCERNS ACTION PLAN/S

Clearing works still Clearing works still Constech committed to To complete clearing
ongoing at Area 3 & 4 by To follow up from
Constech ongoing at Area 3 & 4 by hand over the area works on the areas by
Constech on September
Constech Constech within 20-30days. 29, 2018.

Waiting for clearing Waiting for clearing To start clearing works


works at Phase 2 by To follow up from works at Phase 2 by To follow up from of Constech by next
Constech Constech Constech Constech week

Waiting for Constech


Site Instruction To follow up from To received the Site
regarding design of Test Constech Instruction by next
week.
Piles for Phase 2

Constech already
Revised completion Revised completion approved Option 2
schedule w/ 2 opotions To follow up from schedule w/ 2 opotions schedule during
was submitted for Constech was submitted for
approval approval coordination meeting on
August 29, 2018.

MTSM 70t Crawler MTSM 70t Crawler DMWAI already


Crane not yet Crane not yet mobilized one unit
operational due to To follow up repair of operational due to Crawler Crane on August MSTM Crawler Crane
expected to be
mevhanical failure the unit by MSTM mevhanical failure 30, 2018 and
happened on August 9, happened on August 9, operational last opeational by next week
2018 2018 September 1, 2018.

Low productivity rate Low productivity rate MSTM suggested to


per day of 320t static To follow up from MSTM per day of 320t static reduce pile length and MSTM to start the
pile driver due to cutting pile driver due to cutting was already approved fabrication.
issues issues by constech

To increase the
Low productivity rate productivity rate per day follow up MSTM for
per day which result to and to add pile driving To
negative variance equipment in order to the catch up.
catch up

Waiting for the


fabrication of intial To follow up from MSTM to start the
150pcs - 12m + 13m Constech and MSTM fabrication.
regular piles

Prepared by:

John Kevin G. Oliquino


DMWAI - Project Engineer