CMGI EVALUATION

ITEM BASIS Pile Driving Works Equivalent days


Target Actual Variance of delay
12-Aug-18 14 0 -14 -1
13-Aug-18 16 0 -16 -1
16 11 -5 -0.32
14-Aug-18

15-Aug-18 16 4 -12 -0.75

16-Aug-18 16 12 -4 -0.25

17-Aug-18 16 7 -9 -0.57

18-Aug-18 16 13 -3 -0.19

19-Aug-18 16 4 -12 -0.75

20-Aug-18 16 9 -7 -0.44

21-Aug-18 16 3 -13 -0.82

22-Aug-18 16 5 -11 -0.69

23-Aug-18 16 8 -8 -0.5

24-Aug-18 16 8 -8 -0.5

25-Aug-18 16 9 -7 -0.44

26-Aug-18 16 2 -14 -0.88

27-Aug-18 16 0 -16 -1

28-Aug-18 16 6 -10 -0.63


28-Aug-18 16 6 -10 -0.63

29-Aug-18 16 7 -9 -0.57

30-Aug-18 16 13 -3 -0.19

31-Aug-18 16 7 -9 -0.57

1-Sep-18 16 6 -10 -0.63

2-Sep-18 16 5 -11 -0.69

3-Sep-18 16 11 -5 -0.32

4-Sep-18 16 6 -10 -0.63

5-Sep-18 16 15 -1 -0.07

6-Sep-18 16 8 -8 -0.5

7-Sep-18 16 5 -11 -0.69

8-Sep-18 16 2 -14 -0.88


9-Sep-18 16 0 -16 -1

10-Sep-18 16 6 -10 -0.63


11-Sep-18 16 6 -10 -0.63

12-Sep-18 16 6 -10 -0.63

13-Sep-18 16 11 -5 -0.32

14-Sep-18 16 2 -14 -0.88

15-Sep-18 16 10 -6 -0.38

16-Sep-18 16 4 -12 -0.75

17-Sep-18 16 10 -6 -0.38

18-Sep-18 16 11 -5 -0.32

19-Sep-18 16 10 -6 -0.38

20-Sep-18 16 11 -5 -0.32

21-Sep-18 16 7 -9 -0.57

22-Sep-18 16 7 -9 -0.57

23-Sep-18 16 4 -12 -0.75


24-Sep-18 16 -16 -1

25-Sep-18 16 11 -5 -0.32
26-Sep-18 16 9 -7 -0.44
27-Sep-18 16 11 -5 -0.32

28-Sep-18 16 8 -8 -0.5

29-Sep-18 16 12 -4 -0.25
30-Sep-18 16 0 -16 -1

1-Oct-18 16 8 -8 -0.5

2-Oct-18 16 7 -9 -0.57

3-Oct-18 16 10 -6 -0.38

4-Oct-18 16 5 -11 -0.69

5-Oct-18 16 8 -8 -0.5

6-Oct-18 16 8 -8 -0.5

7-Oct-18 16 4 -12 -0.75

8-Oct-18 16 13 -3 -0.19

9-Oct-18 16 14 -2 -0.13
10-Oct-18 16 0 -16 -1
11-Oct-18 16 0 -16 -1
12-Oct-18 16 7 -9 -0.57

13-Oct-18 16 12 -4 -0.25

14-Oct-18 16 4 -12 -0.75

15-Oct-18 11 19 8 0.73

16-Oct-18 11 12 1 0.1

17-Oct-18 11 6 -5 -0.46
18-Oct-18 10 2 -8 -0.8
19-Oct-18 8 0 -8 -1

20-Oct-18 11 12 1 0.1

21-Oct-18 11 2 -9 -0.82

22-Oct-18 11 7 -4 -0.37

23-Oct-18 11 11 0 0
24-Oct-18 11 9 -2 -0.19

25-Oct-18 11 13 2 0.19

26-Oct-18 11 23 12 1.1

27-Oct-18 11 10 -1 -0.1
28-Oct-18 11 0 -11 -1

29-Oct-18 11 15 4 0.37

30-Oct-18 11 13 2 0.19

31-Oct-18 11 12 1 0.1
1-Nov-18 11 0 -11 -1
2-Nov-18 11 0 -11 -1

3-Nov-18 11 11 0 0
4-Nov-18 11 9 -2 -0.19

5-Nov-18 11 3 -8 -0.73
6-Nov-18 11 -11 -1
7-Nov-18 6 -6 -1
8-Nov-18 11 -11 -1
9-Nov-18 11 -11 -1
10-Nov-18 11 -11 -1
11-Nov-18 11 -11 -1
12-Nov-18 11 -11 -1
13-Nov-18 8 -8 -1
14-Nov-18 11 -11 -1
15-Nov-18 12 -12 -1
16-Nov-18 11 -11 -1
17-Nov-18 11 -11 -1
18-Nov-18 11 -11 -1
19-Nov-18 11 -11 -1
20-Nov-18 11 -11 -1
21-Nov-18 11 -11 -1
22-Nov-18 11 -11 -1
23-Nov-18 11 -11 -1
24-Nov-18 11 -11 -1
25-Nov-18 8 -8 -1
26-Nov-18 11 -11 -1
27-Nov-18 11 -11 -1
28-Nov-18 11 -11 -1
29-Nov-18 11 -11 -1
30-Nov-18 11 -11 -1
1-Dec-18 11 -11 -1
2-Dec-18 11 -11 -1
3-Dec-18 11 -11 -1
4-Dec-18 11 -11 -1
5-Dec-18 11 -11 -1
6-Dec-18 11 -11 -1
7-Dec-18 11 -11 -1
8-Dec-18 11 -11 -1
9-Dec-18 10 -10 -1
10-Dec-18 11 -11 -1
11-Dec-18 9 -9 -1
12-Dec-18 11 -11 -1
13-Dec-18 11 -11 -1
14-Dec-18 11 -11 -1
15-Dec-18 11 -11 -1
16-Dec-18 11 -11 -1
17-Dec-18 11 -11 -1
18-Dec-18 11 -11 -1
19-Dec-18 11 -11 -1
20-Dec-18 11 -11 -1
21-Dec-18 11 -11 -1
22-Dec-18 7 -7 -1
23-Dec-18 0 N/A N/A
24-Dec-18 0 N/A N/A
25-Dec-18 0 N/A N/A
26-Dec-18 14 -14 -1
27-Dec-18 14 -14 -1
28-Dec-18 14 -14 -1
29-Dec-18 12 -12 -1
CMGI EVALUATION DMWAI EVALUATION
Pile Driving Works Equivalent days
Cause of delay c/o
Target Actual Variance of delay
Crawler crane breakdown DMWAI 14 0 -14 -1
Force majeure (storm) CMGI 16 0 -16 -1
Low productivity. One set of -2 -0.13
DMWAI 16 11
equipment breakdown. -3 -0.19
Low productivity. One set of
equipment breakdown. DMWAI 16 4 -12 -0.75
Low productivity. One set of
equipment breakdown. DMWAI 16 12 -4 -0.25
Low productivity. One set of
equipment breakdown. DMWAI 16 7 -9 -0.57

Two sets of equipment are -1 -0.07


operational but only one feeder. DMWAI 16 13
Thus low productivity

-2 -0.13

Two sets of equipment are


operational but only one feeder.
Thus low productivity DMWAI 16 4 -12 -0.75

Two sets of equipment are


operational but only one feeder.
Thus low productivity DMWAI 16 9 -7 -0.44

Two sets of equipment are


operational but only one feeder.
Thus low productivity DMWAI 16 3 -13 -0.82

Two sets of equipment are


operational but only one feeder.
Thus low productivity DMWAI 16 5 -11 -0.69

Two sets of equipment are


operational but only one feeder.
Thus low productivity DMWAI 16 8 -8 -0.5

Two sets of equipment are


operational but only one feeder.
Thus low productivity DMWAI 16 8 -8 -0.5

Two sets of equipment are


operational but only one feeder.
Thus low productivity DMWAI 16 9 -7 -0.44

Two sets of equipment are


operational but only one feeder. DMWAI 16 2 -8 -0.5
Thus low productivity
-6 -0.375
No DMWAI on site DMWAI 16 0 -16 -1

Two sets of equipment are


operational but only one feeder. DMWAI 16 6
Thus low productivity
Two sets of equipment are
operational but only one feeder. DMWAI 16 6
Thus low productivity -10 -0.63

Two sets of equipment are


operational but only one feeder.
Thus low productivity DMWAI 16 7 -9 -0.57

Two sets of equipment are


operational but only one feeder.
Thus low productivity DMWAI 16 13 -3 -0.19
Two sets of equipment are
operational but only one feeder. DMWAI 16 7 -9 -0.57
Thus low productivity

Arrival and assembly of DMWAI's


crawler crane. MSTM's crane used to
assemble DMWAI's crane. Thus, low
productivity DMWAI 16 6 -10 -0.63

Two sets of equipment are


operational but only one feeder.
Thus low productivity DMWAI 16 5 -11 -0.69

Two sets of equipment are


operational but only one feeder.
Thus low productivity DMWAI 16 11 -5 -0.32

Two sets of equipment are


operational. 70t crane fixed at 10:am
but still low productivity DMWAI 16 6 -10 -0.63
Two sets of equipment are
operational but low productivity DMWAI 16 15 -1 -0.07
Two sets of equipment are
operational but low productivity DMWAI 16 -16 -1

Low productivity due to Site


Instruction to DMWAI to prioritize
driving side piles at GL - 11/A-F.
Convertion of 600t static to side piler
starts 3pm CMGI 16 -16 -1

Only one set of equipment is


operational. 600t static still
converting to side piller DMWAI 16 -16 -1
No pile driving DMWAI 16 -16 -1

Two sets of equipment are


operational but low productivity DMWAI 16 -16 -1
Low productivity due to unstable
ground at GL- 11/A-F. MCPI making
stable platform CMGI 16 -16 -1

Low productivity due to Protruding


dowels from MDC building and area
of 320t static with obstruction
beneath ground CMGI 16 -16 -1
Two sets of equipment but low
productivity DMWAI 16 -16 -1

Two sets of equipment are


operational but low productivity DMWAI 16 -16 -1

Two sets of equipment are


operational but low productivity DMWAI 16 -16 -1

Two sets of equipment are


operational but 320t cannot drive at
GL 18/D due to unstable platform CMGI 16 -16 -1

Two sets of equipment are


operational but low productivity DMWAI 16 -16 -1

Two sets of equipment are


operational but low productivity DMWAI 16 -16 -1

Two sets of equipment are


operational but low productivity DMWAI 16 -16 -1

Two sets of equipment are


operational but low productivity DMWAI 16 -16 -1
Low productivity due to
unavailability of materials MSTM 16 -16 -1

Low productivity due to


unavailability of materials. Transfer
of 600t from GL - 11/A'-D' to GL -
16/A (w/ available pile) MSTM 16 -16 -1

Two sets of equipment are


operational but low productivity DMWAI 16 -16 -1
Relocation of Temfacil. MSTM 16 -16 -1

Two sets of equipment are


operational but low productivity DMWAI 16 -16 -1
Force majeure (Heavy Rain) CMGI 16 -16 -1
Two sets of equipment are CMGI
operational but 320t cannot drive at
GL 18/D-D' due to unstable platform 16 -16 -1

Two sets of equipment are


operational but low productivity DMWAI 16 -16 -1

Two sets of equipment are


operational but low productivity DMWAI 16 -16 -1
No pile driving DMWAI 16 -16 -1

Two sets of equipment are CMGI


operational but 320t cannot drive at
GL 18/D-D' due to unstable platform 16 -16 -1

Two sets of equipment are CMGI


operational but 320t cannot drive at
GL 18/D-D' due to unstable platform 16 -16 -1

Two sets of equipment are


operational but low productivity DMWAI 16 -16 -1

Two sets of equipment are CMGI


operational but 320t cannot drive at
GL 18/D-D' due to unstable platform 16 -16 -1

Two sets of equivalent are


operational but 600t cannnot drive CMGI
properly at GL - 12/A due unstable
ground platform 16 -16 -1

Two sets of equipment are


opearational but 600t cannot drive CMGI
properly due to platfom of MDC at
GL - 11/A'-D' 16 -16 -1

Two sets of equipment are CMGI


operational but 600t cannot drive
properly due to unstable ground at
GL - 11/A'-D' 16 -16 -1

Two sets of equipment are


operational but low productivity DMWAI 16 -16 -1

Two sets of equipment are


opearational but 600t cannot drive CMGI
properly due to platfom of MDC at
GL - 11/A'-D' 16 -16 -1
2 static breakdown DMWAI 16 -16 -1
2 static breakdown DMWAI 16 -16 -1
600t static breakdown DMWAI 16 -16 -1

Two sets ofequipment are


operational but 600t cannot drive CMGI
properly due to unstable ground at
GL - 11/E 16 -16 -1

Two sets of equipment are


operational but low productivity DMWAI 16 -16 -1

Exceed daily target accomplishment DMWAI 11 -11 -1

Exceed daily target accomplishment DMWAI 11 -11 -1

Two sets of equipment are


operational but 600t cannot drive at
GL 11/A due to no coordinates yet DMWAI 11 -11 -1
320t static on breakdown DMWAI 10 -10 -1
2 crawler crane breakdoown DMWAI 8 -8 -1

Exceed daily target accomplishment DMWAI 11 -11 -1


Two static are operational but 70t
crane brekadown DMWAI 11 -11 -1
Two static are operational but 70t
crane brekadown DMWAI 11 -11 -1

Attain daily target accomplishment DMWAI 11 -11 -1


70t and 30t crane breakdown DMWAI 11 -11 -1

Exceed daily target accomplishment DMWAI 11 -11 -1

Exceed daily target accomplishment DMWAI 11 -11 -1

Two sets of equipment are


operational but low productivity DMWAI 11 -11 -1
No DMWAI on site DMWAI 11 -11 -1

Exceed daily target accomplishment DMWAI 11 -11 -1

Exceed daily target accomplishment DMWAI 11 -11 -1

Exceed daily target accomplishment DMWAI 11 -11 -1


No DMWAI on site DMWAI 11 -11 -1
No DMWAI on site DMWAI 11 -11 -1

Attain daily target accomplishment DMWAI 11 -11 -1


Two sets of equipment are
operational but 320t cannot drive at
GL - 12-14/E-F due to unstable
platform CMGI 11 -11 -1

Two sets of equipment are


operational but 320t cannot drive at
GL - 12-14/E-F due to unstable
platform CMGI 11 -11 -1
11 -11 -1
6 -6 -1
11 -11 -1
11 -11 -1
11 -11 -1
11 -11 -1
11 -11 -1
8 -8 -1
11 -11 -1
12 -12 -1
11 -11 -1
11 -11 -1
11 -11 -1
11 -11 -1
11 -11 -1
11 -11 -1
11 -11 -1
11 -11 -1
11 -11 -1
8 -8 -1
11 -11 -1
11 -11 -1
11 -11 -1
11 -11 -1
11 -11 -1
11 -11 -1
11 -11 -1
11 -11 -1
11 -11 -1
11 -11 -1
11 -11 -1
11 -11 -1
11 -11 -1
10 -10 -1
11 -11 -1
9 -9 -1
11 -11 -1
11 -11 -1
11 -11 -1
11 -11 -1
11 -11 -1
11 -11 -1
11 -11 -1
11 -11 -1
11 -11 -1
11 -11 -1
7 -7 -1
0 0 #DIV/0!
0 0 #DIV/0!
0 0 #DIV/0!
14 -14 -1
14 -14 -1
14 -14 -1
12 -12 -1
DMWAI EVALUATION
Cause of delay c/o Remarks

Heavy rain (whole day) CMGI


Heavy rain (7am - 12pm (5hrs)) CMGI
1. Heavy rain from 7am - 11pm (4hrs), 2. CMGI
still one feeder for two static DMWAI driving starts at 9:33am
1. Only one feeder for two static (low
productivity) DMWAI
1. Only one feeder for two static (low
productivity) DMWAI
1. Only one feeder for two static (low
productivity) DMWAI

1. only 7pcs. 10m PSC Pile was delivered


on site and all driven as of 10:09pm using
600t static. Therefore from 10:09pm
onwards the said equiment is idle. CMGI
DMWAI

1. only 1 set of equipment is driving (600t


static & 30t feeder) DMWAI

1. only 1 set of equipment is driving (600t


static & 30t feeder) DMWAI

1. only 1 set of equipment is driving (600t


static & 30t feeder) DMWAI

1. only 1 set of equipment is driving (600t


static & 30t feeder) DMWAI

1. only 1 set of equipment is driving (600t


static & 30t feeder) DMWAI

1. only 1 set of equipment is driving (600t


static & 30t feeder) DMWAI

1. only 1 set of equipment is driving (600t


static & 30t feeder) DMWAI

1. only 1 set of equipment is driving (600t


static & 30t feeder), DMWAI
2. Cannot drive pile location at GL-20/C
due to obstructions. CMGI
No pile driving works DMWAI
1. Only one feeder for two static (low
productivity)
2. Cannot drive pile location at GL-20/C
due to obstructions. CMGI

3. 30t Crawler crane breakdown (trackpad)


due to intruction of constech to travel and CMGI
lift scaffolding of VSL which result to stop
operations.

1. 30t feeder become operational at


3:30pm, 2. Still can't drive at GL - 20/C due CMGI
to obstruction

1. Only one feeder for two static (low


productivity) DMWAI

Heavy rain (12pm - 8pm) CMGI

1. Only one feeder (DMWAI crane) for two


static (low productivity) DMWAI

1. only 1 set of equipment is driving (600t


static & 55t feeder DMWAI's crane) DMWAI

1. only 1 feeder for 600t & 320t static DMWAI

1.2 sets of equipment is driving but still


low productivity DMWAI
1.2 sets of equipment is driving but still
low productivity DMWAI
1.2 sets of equipment is driving but still
low productivity