Volume
Tanggal Mulai Jumlah Bak
Jarak Pengecoran
Pemasangan STA Awal STA Akhir Kontrol
(m) Beton Kelas E
Bak Kontrol (bh)
(m³)
575.00 14 1.820
575.00 13 1.690
950.00 20 2.600
950.00 21 2.730
625.00 14 1.820
525.00 12 1.560
250.00 6 0.780
14 26-Sep-18 25-Oct-18 30
2.783 14 26-Sep-18 25-Oct-18 16
4.174
4.174
2.783
2.087 150
500
400
0
0
0
0
0
0
0
6
9
7
2
1
600
900
13 26-Oct-18 25-Nov-18 31
2.696 13 26-Oct-18 25-Nov-18 31
8.087
8.087
8.087
4.043 150
500
400
0
0
0
0
0
0
0
7
6
2
1
600
900
20 26-Nov-18 25-Dec-18 30
1.579 20 26-Nov-18 25-Dec-18 30
4.737
4.737
4.737
4.737 150
500
400
0
0
0
0
0
0
0
7
6
2
1
600
900
500
150 400
4.737
4.737
0
0
0
0
0
0
0
7
6
2
1
600
900
21 26-Dec-18 25-Jan-19 31
0.816 21 26-Dec-18 25-Jan-19 31
6.526
4.895
4.895
4.895 150
500
400
4.895
4.079
0
0
0
0
0
0
0
7
6
2
1
600
900
14 26-Jan-19 25-Feb-19 31
2.480 14 26-Jan-19 25-Feb-19 31
7.440
7.440
7.440
6.200
12 26-Feb-19 25-Mar-19 28
4.000 12 26-Feb-19 25-Mar-19 28
8.000
8.000
8.000
6 26-Mar-19 25-Apr-19 31
3.200 6 26-Mar-19 25-Apr-19 16
6.400
6.400
Sta. 135+600 - S
SUMMARY PERHITU
900
100 400 100
600
1200
900
50 900 50
1000
600
1200
900
50 900 50
1000
B" A"
13390
Total = 100.00
Total Komulatif = 100.00
PELAKSANAAN PE
PT. HUTAMA KARYA (Persero) JALAN TOL TRAN
DIVISI JALAN TOL
RUAS PEMATANG PANGG
Sta. 135+600 - S
SUMMARY PERHITU
KONTRAKTOR : PT. WASKITA KARYA (Persero), Tbk
KONSULTAN : PT. JAYA CM
DIVISI : 6
SUB DIVISI : DRAINASE
N0. ITEM :
ITEM : Bak Kontrol (Super Elevasi / 50 m')
BAK KONTROL
BAK KONTROL PER 10 M
PER 50 M
Total = -
Total Komulatif = -
DIPASANG
PER JARAK 50
M'
C
BAK KONTROL
BAK KONTROL PER 10 M
PER 50 M
1560
1710
BAK KONTROL
BAK KONTROL PER 10 M
PER 50 M
1560
1710
C
150
100
A" A" B"
13390
100.00 Total = -
100.00 Total Komulatif = 100.00
PELAKSANAAN PEMBANGUNAN
JALAN TOL TRANS SUMATERA
A
C
A
- Total = -
- Total Komulatif = -
200 200
AWAL AKHIR
1710
1710
138+650 138+825
141+650 142+050
100
100
50 950 50 50 950 50
1000 1000
TAMPAK C TAMPAK D
600
900
1560
1560
1710
1710
600
900
1560
1560
1710
1710
150
150
100
100
50 950 50
50 1200 50
1300 1000
900
100 400 100
600
0
0
0
0
9
2
1
50 900 50
1000
MC - 19 MC - 20 MC - 21
NOPEMBER 2018 DESEMBER 2018 JANUARI 2019
+6
PELAKSANAAN PEMBANGUNAN
PT. HUTAMA KARYA (Persero) JALAN TOL TRANS SUMATERA
DIVISI JALAN TOL
RUAS PEMATANG PANGGANG - KAYU AGUNG
PT. WASKITA KARYA
Sta. 135+600 - Sta. 157+600 (Persero), Tbk
KONTRAKTOR : PT. WASKITA KARYA (Persero), Tbk KONSULTAN MK : KSO. PT. CCM - PT. Indec Internusa - PT. CCME
KONSULTAN : PT. JAYA CM PEMILIK PROYEK : PT. HUTAMA KARYA (Persero)
DIVISI : 6 Nomor MC :
SUB DIVISI : DRAINASE Periode :
N0. ITEM :
ITEM : Bak Kontrol (Super Elevasi / 10 m')
BAK KONTROL SUPER ELEVASI PER 10 M' BAK KONTROL SUPER ELEVASI PER 10 M'
STATION STATION
NO NO
JARAK (M') VOLUME (BH) KETERANGAN JARAK (M') VOLUME (BH) KETERANGAN
AWAL AKHIR AWAL AKHIR
C
7 154+850 155+375 525.00 42.00
A
8 155+475 155+725 250.00 20.00
BAK KONTROL
900
BAK KONTROL PER 10 M
200
PER 50 M
600
900
600
50 900 50
1000
C
DETAIL 2