Professional Documents
Culture Documents
2underground Drainage Piping Method Statement PDF
2underground Drainage Piping Method Statement PDF
Method Statement
For
Submitted By:
INMA
(Sub-Contractor)
Date:
THE ENGINEER: New King Abdulaziz International THE CONTRACTOR:
Airport Development Project
(Phase I)
Jeddah, KSA
Contractor: Saudi Binladin Group Doc. Ref. No: 422-DCS-MST-E-00710-Rev01
Contract No.: J-10-421/422-PF-0 Date Issued: : 07 May 2012
List of Contents
5.0 MATERIALS 09
10.0 REFERENCES 10
Appendix A – Draft Final Drawing
11.0 ATTACHMENT 11
Appendix A - Sample Test Report
This Method Statement covers the installation of Sanitary, Vent and Storm
drainage piping installation. This procedure is to define the method used to
ensure that drainage and vent piping have been installed as per the
contract requirement.
d. Foremen shall be present on site at all time to give out the correct
instructions and coordination with the technician and other staff
assign to his area, while ensuring the work required are being
implemented accordingly base on the Mechanical standard and project’s
scheduled.
f. The rest of the personnel consist of labors to aid the technicians, store
keepers to ensure that the material stored is located in a safe
environment with proper conditions of storage and safety officers who
guarantee that all personnel are abiding by the safety rules and
regulations of site work.
Page 3of 10
THE ENGINEER: New King Abdulaziz International THE CONTRACTOR:
Airport Development Project
(Phase I)
Jeddah, KSA
Contractor: Saudi Binladin Group Doc. Ref. No: 422-DCS-MST-E-00710-Rev01
Contract No.: J-10-421/422-PF-0 Date Issued: : 07 May 2012
Check for setting out and mark piping location on ground using
pegs confirm the approved drawing.
The pipes shall not rest on rock at any point, including joints.
Page 4 of 11
THE ENGINEER: New King Abdulaziz International THE CONTRACTOR:
Airport Development Project
(Phase I)
Jeddah, KSA
Contractor: Saudi Binladin Group Doc. Ref. No: 422-DCS-MST-E-00710-Rev01
Contract No.: J-10-421/422-PF-0 Date Issued: : 07 May 2012
i. Clean pipes and fittings, removed oil, grease and any other loosely
adhering deposits
j. Carefully unload required lengths and sizes of pipes to the work area.
k. Install pipes on the concrete pads making sure that they are secured in
place and to the required slope.
Page 5 of 11
THE ENGINEER: New King Abdulaziz International THE CONTRACTOR:
Airport Development Project
(Phase I)
Jeddah, KSA
Contractor: Saudi Binladin Group Doc. Ref. No: 422-DCS-MST-E-00710-Rev01
Contract No.: J-10-421/422-PF-0 Date Issued: : 07 May 2012
Page 6 of 11
THE ENGINEER: New King Abdulaziz International THE CONTRACTOR:
Airport Development Project
(Phase I)
Jeddah, KSA
Contractor: Saudi Binladin Group Doc. Ref. No: 422-DCS-MST-E-00710-Rev01
Contract No.: J-10-421/422-PF-0 Date Issued: : 07 May 2012
r. Do not enclose, cover, or put piping into operation until it has been
inspected and approved by authorities having jurisdiction.
The maximum particle size in the side fill and initial backfill shall
not more than ½ inch for pipe 6” size and smaller, and ¾ inch
for 8” and larger.
After the pipe is covered with 2 feet of tamped initial backfill, the
final backfill to grade can be compacted with heavy equipment.
Page 7 of 11
THE ENGINEER: New King Abdulaziz International THE CONTRACTOR:
Airport Development Project
(Phase I)
Jeddah, KSA
Contractor: Saudi Binladin Group Doc. Ref. No: 422-DCS-MST-E-00710-Rev01
Contract No.: J-10-421/422-PF-0 Date Issued: : 07 May 2012
F F
FINAL
BACK FILL
300 mm
BEDDING
-MIN 150
Where: • F = 200 for pipe DN300 to 500 mm, • F = 300 for pipe DN600 to 900 mm
• F = 450 for pipe DN1000 to 1600 mm, • F = 600 for pipe above DN1600 mm
The Personnel on Site ensure that the work done conform to the Standard
and he required specifications.
For this task, it consist of the following project standards / specifications :
Page 8 of 11
THE ENGINEER: New King Abdulaziz International THE CONTRACTOR:
Airport Development Project
(Phase I)
Jeddah, KSA
Contractor: Saudi Binladin Group Doc. Ref. No: 422-DCS-MST-E-00710-Rev01
Contract No.: J-10-421/422-PF-0 Date Issued: : 07 May 2012
5.0 Materials
Page 9 of 11
THE ENGINEER: New King Abdulaziz International THE CONTRACTOR:
Airport Development Project
(Phase I)
Jeddah, KSA
Contractor: Saudi Binladin Group Doc. Ref. No: 422-DCS-MST-E-00710-Rev01
Contract No.: J-10-421/422-PF-0 Date Issued: : 07 May 2012
10.0 References
422-C110-SH-P-10B20601-1001,1002,2002,1004,204,3004,4004
422-C120-SH-P-10B20601-1001,1002,2002,1004,204,3004,4004
422-C130-SH-P-10B20601-1001,1002,2002,1004,204,3004,4004
Page 10 of 11
THE ENGINEER: New King Abdulaziz International THE CONTRACTOR:
Airport Development Project
(Phase I)
Jeddah, KSA
Contractor: Saudi Binladin Group Doc. Ref. No: 422-DCS-MST-E-00710-Rev01
Contract No.: J-10-421/422-PF-0 Date Issued: : 07 May 2012
12. SPECIFICATION :
Page 11 of 11