Min Rs/sq.f Max Rs/sq.

f Unit
Residential 200 250
Industrial 350 500
Industrial with External Facility 150

Example
Considered Area in Sq. f 30,000 Sq. f.
From Above Cost/Sq.f. 350 Rs
Total Electrical Cost for Project 10,500,000 Rs

Component wise Cost Min Max


Panels 18 20 Rs
Cable 8 10 Rs
DBs 1.5 2 Rs
Light Fixtures 15 18 Rs
Point Wiring 15 20 Rs
Modular Switch Sockets 2 4 Rs
Industrial Switch Sockets 4 5 Rs
Earthing 3 5 Rs
Safety Equipments 0.8 1.5 Rs
Cable Tray/Raceway 5 7 Rs
Steel 1 1.5 Rs
Termination 1.2 1.5 Rs
Liasoning 1.5 Rs
Misc 1.5 2 Rs
Civil Work 0.5 0.8 Rs

Total 78 98.3 Rs
Scope
From Metering Panel Onwards.
From Panel Onwards.
In addition to above.

If it is FLP, it will increase by 30 to 35%