HVAC BOQ - R0 - HS Infra Projects LLP 03.02.

2023

Sr. No. Description Qty. Unit Rate (Rs.) Amount (Rs.)

PART - 'A' HIGH SIDE ( EQUIPMENT SIDE )

Supply of Daikin Make Fix Speed type Hi-wall Split Unit of R32
1
Refrigerant type of following capacity
1.1 2.2 TR 3 No. 64,400 1,93,200

Supply of Daikin Make Fix Speed type Hi-wall Split Unit of R32
2
Refrigerant type of following capacity
2.1 1.9 TR 4 No. 58,200 2,32,800

BASIC TOTAL 4,26,000


GST @ 28% 1,19,280
TOTAL WITH GST 5,45,280

PART - 'B' LOW SIDE ( INSTALLATION SIDE )

Installation, Testing & Commissioning of Fix Speed type Hi-wall


1
Split Unit of R32 Refrigerant type of following capacity
1.1 2.2 TR 3 No. 3,100 9,300
1.2 1.9 TR 4 No. 3,100 12,400

Supply, Installation, Testing & Commissioning of soft copper


2
piping with Nitrile Rubber Insulation for the following units
2.1 2.2 TR 60 Rmt. 1,285 77,100
2.2 1.9 TR 75 Rmt. 1,285 96,375

3 Electrical Cabling Work


Supply & installation of electrical control cabling of 4 Core x 2.5
3.3 Sq.mm. between condenser and evaporator unit. (Rate and Qty. 150 Rmt. 136 20,400
are considered as per no. of circuit)
Supply, installation, testing & commissioning of electrical
Power cabling between Outdoor unit to MCB. (MCB to be
3.4 20 Rmt. 345 6,900
provided by Client/Electrical Vendor near ODU within 5
Rmt.)

Supply and installation of MS frame/Stand for placing outdoor


4
units.
4.1 2.2 TR 3 Nos 2,800 8,400
4.2 1.9 TR 4 Nos 2,800 11,200

5 DRAIN PIPING
Supply, Installation, Testing & Commissioning of Hard PVC
5.1 85 Rmt. 177 15,045
Pipes of 25mm/32mm sizes with Heatlon Insulation.

6 Supply of additional Refrigerant Gas for Split Units. 20 Kg 743 14,860

7 Lifting, Shifting and rigging charges 1 Lot 11,655 11,655

BASIC TOTAL 2,83,635


GST @ 18% 51,054
TOTAL WITH GST 3,34,689

Note : 1) Final Billing Shall be as per actual measurement.


2) 50% Advance along with order & 30% on material
delivery and remaining 20% on installation and
commissioning.
3) Civil Work, Carpentry and other Gypsem work is not in our Scope.
4) Power supply need to supply by client at each
Outdoor/Indoor unit.