ANNEXURE FOR FINAL BILL

Rate
S.No. Description Qty Unit Amount
(INR)

PART-B LOW SIDE


1 SHEET METAL WORKS
Fabrication, Supply, Installation, Testing & Commissioning
of TDF ducting complete with supporting accessories.
1.1 22 gauge G.I sheet metal Supply Air TDF ducting 1884 Sqft 102 192,168.00
1.2 24 gauge G.I sheet metal Supply Air TDF ducting 1765 Sqft 92 162,380.00
1.3 Canvas Connection 4 Nos 2716 10,864.00
1.4 Thermal insulation of exposed ducting 959 Sq.ft 53 50,827.00

2 AIR DISTRIBUTION
2.1 Double deflection grills 60 Sq.ft 737 44,220.00
2.2 Volume control damper (VCD) 0 Sq.ft 679 0.00

3 PROVIDING INSTALLATION & ALLIED WORK OF COOLER

3.1 Assembling & Installation of Air cooler 4 NOS 7275 29,100.00

4 PROVISION FOR EXHAUST SYSTEM


Supply of HEAVY DUTY EXHAUST FANS -9400 CMH AIR
4.1
CAPACITY
6 NOS 9846 59,076.00
4.2 Installation of Exhaust fan 6 NOS 2571 15,426.00

5 MS STAND & SCAFFOLDS DUE TO DOUBLE HIEGHT


5.1 M. S. Epoxy Painted Stand for condensing unit
a AIR COOLER 624.8 KG 136 84,972.80
b DUCTING MS supports for double hieght area 123 KG 136 16,728.00
5.4 Scaffolding arrangements due to double hieght area at 1st floor 1 LOT 29100 29,100.00
(1200/Day approx 25 days)

6 Installation of casstte unit & accessories


a Copper piping with insulation 58.6 RFT 310.00 18,166.00
b Communication cable 65 RFT 53.00 3,445.00
c PVC Drain Pipe with insulation 90 RFT 44.00 3,960.00
d ODU Stand 1 NOS 1,213.00 1,213.00
e Installation & testing commissioning of casstte unit 1 NOS 3,880.00 3,880.00

NON TENDER ITEM/ EXTRA ITEMS


A Installation & commissioning of split AC unit 1 NOS 2200 2,200.00
B Outdoor Stand 1 NOS 1213 1,213.00

Total Basic Amount 728938.80