You are on page 1of 20

PHYSICAL PLANNING & HOUSING DEPARTMENT

CONSTRUCTION OF TUCK SHOP


ABSTRACT OF COST TUCK SHOP'S
S.NO DESCRIPTION ESTIMATED COST Covered Per Sft
(MILLION RS.) Area (Sft) Amount

1 CANTEEN GROUND FLOOR C.W 1953208.78 720.3 2711.69

2 ELECTRIC WORK 284751.85

3 PLUMBING WORK 252,580.23

4 SEPTIC TANK 535,024.27

Total 3,025,565.1
(MILLION RS.) 3.026

Executive Engineer (Building)


Physical Planning & Housing Department
District Sherani.
CONSTRUCTION OF TUCK SHOP
BILL OF QUANTITY
S/No. Rate Amount
Description NO L W D/H Quantity Unit
(Rs.) (Rs.)
CANTEEN G.FLOOR (C.W)
1 Excavation in foundation of buildings,
bridges, and other structures, including
dagbelling, dressing, refilling around
structures with excavated earth, watering
and ramming lead upto 30 m, lift upto 1.5 m.
(Hard soil )
S.I # 3-21/b-iv
(Foundation Details)
Long wall # 012.00 32.500 2.50 2.50 406.25 Cft
Short Wall # 011.00 26.00 2.50 2.50 162.50 Cft
Long wall # 021.00 10.000 2.50 2.50 62.50 Cft
Short Wall # 021.00 26.50 2.50 2.50 165.63 Cft
Partion Wall
1.00 23.00 2.50 2.50 143.75 Cft
Total 940.63
COL Type#01 (12"x9") 4.00 4.00 3.50 1.50 84.00 Cft
COL Type#02 (9"x9") 8.00 4.00 3.50 1.50 168.00 Cft

Total 252.00
G.Total Quantity 1192.63
Total Rs 1192.63 Cft 10.25 12,224.41

2 Filling, watering and compacting earth under


floors in layers not exceeding 8 inchs in
thickness. With new earth excavated from
outside, lead upto 100 ft. (30m) and lift upto
5 ft. (1.5m) including royality of Clay

S.I # 3-16/b+3-16/a
CANTEEN KITCHEN/STORE 21'-3"X10'-0" 1.00 21.25 10.00 2.00 425.00 Cft
STATIONARY AREA 11'-0"X12'-0" 1.00 10.00 10.00 2.00 200.00 Cft
PRINTING AREA 10'-0" X 7'-0" 1.00 10.00 7.00 2.00 140.00 Cft
SHOP 10'-0" X 8'-0" 1.00 10.00 8.00 2.00 160.00 Cft
HOT KITCHEN 21'-3" X 12'-6" 1.00 21.25 12.50 2.00 531.25 Cft
VARANDAH 8' WIDE 1.00 32.15 8.00 2.00 514.40 Cft

SUB TOTAL 1970.65 Cft


30% Excavition Quantity Use in Re-fill 591.20 Cft
TOTAL Total 1379.46 Cft 10.50 14,484.28

3 Spraying approved anti-termite chemical


mixed with water in the ratio of 1:40
S.I # 30-69
2.000
Long wall # 01 32.50 7.50 487.50 Sft
1.000
Short Wall # 01 26.00 7.50 195.00 Sft
1.000
Long wall # 02 10.00 7.50 75.00 Sft
1.000
Short Wall # 02 26.50 7.50 198.75 Sft
1.000
Partion Wall 23.00 7.50 172.50 Sft
Total 1128.75
D/D COLUMNS#01 4.00 7.00 7.00 196.00 Sft
D/D COLUMNS#02 8.00 7.00 7.00 392.00 Sft

Total 588.00 Sft


G.Total Quantity 1716.75
Total Rs 1716.75 Sft 9.75 16,738.31

3 Providing and laying plain machine mixed


cement concrete using coarse sand and
crushed aggregate having maximum size
upto 1- 1/2" (38mm) & down gauge in
foundation including levelling, compacting
and curing. (1:4:8)
S.I # 5-5/c
Long wall # 01 2.00 32.50 2.50 0.25 40.63 Cft
Short Wall # 01 1.00 26.00 2.50 0.25 16.25 Cft

2
BILL OF QUANTITY
S/No. Rate Amount
Description NO L W D/H Quantity Unit
(Rs.) (Rs.)
CANTEEN G.FLOOR (C.W)
Long wall # 02 1.00 10.00 2.50 0.25 6.25 Cft
Short Wall # 02 1.00 26.50 2.50 0.25 16.56 Cft
Partion Wall 1.00 23.00 2.50 0.25 14.38 Cft

Total 94.06
COL Type#01 (12"x9") 4.00 4.00 3.50 0.25 14.00 Cft
COL Type#02 (9"x9") 8.00 4.00 3.50 0.25 28.00 Cft
0 0.00 0.00 0.00 0.25 0.00 Cft
Total 42.00
G.Total Quantity 136.06
Total Rs 136.06 Cft 185.35 25,219.18

4 Providing and laying 1:2:4 cement concrete


using crushed stone 19 mm. (3/4") and
down gauge in foundation including leveling
compacting and curing. Extra for crushed
stone
S.I # 5-5/a
Long wall # 01 2.00 32.50 2.50 0.75 121.88 Cft
Short Wall # 01 1.00 26.00 2.50 0.75 48.75 Cft
Long wall # 02 1.00 10.00 2.50 0.75 18.75 Cft
Short Wall # 02 1.00 26.50 2.50 0.75 49.69 Cft
Partion Wall 1.00 23.00 2.50 0.75 43.13 Cft

Total Quantity 282.19 Cft


Total Rs 282.19 Cft 232.50 65,608.59

5 Providing and laying in situ cement concrete


using approved coarse sand and crushed
aggregate 3/4" (19mm) and down gauge in
pillars and columns of any shape in super
structure including compacting, curing, cost
of form-work & its removal in basement and
ground floor.
S.I # 5-15/b
COL Type#01 (12"x9") 4.00 4.00 3.50 0.75 42.00
COL Type#02 (9"x9") 8.00 4.00 3.50 0.75 84.00
126.00 Cft 359.50 45,297.00

6 Providing, fabricating and laying deformed


Grade 40 steel reinforcement (deformed
bar) for all kinds of R.C.C work in
foundation, plinth and ground floor including
the cost of straightening, removal of rust,
cutting, bending, binding, wastage and
providing such over-laps as are not shown
on the drawings. The cost of bindin gwire
and cement concrete spacer blocks or
chairs for binding and holding the
reinforcement in position is inclusive upto 15
ft. (5m) height
S.I # 5-44/a
Footing (Qty*12/2204) 408.19 12-lbs/cft 2.22 2.22
2.22 Tonne 123903.05 275,366.66

7 Providing and laying first class solid burnt


brick masonry (Brick Strength:1800psi-
2000psi) including scaffolding, raking out
joints and curing in foundation and
substructure/Basement i/c cost of testing
S.I # 11-3/b-iii
(Brick Details) Ist Step
Long wall # 01 2.00 32.50 1.50 1.00 97.50 Cft
Short Wall # 01 1.00 26.00 1.50 1.00 39.00 Cft
Long wall # 02 1.00 10.00 1.50 1.00 15.00 Cft

3
BILL OF QUANTITY
S/No. Rate Amount
Description NO L W D/H Quantity Unit
(Rs.) (Rs.)
CANTEEN G.FLOOR (C.W)
Short Wall # 02 1.00 26.50 1.50 1.00 39.75 Cft
Partion Wall 1.00 23.00 1.50 1.00 34.50 Cft
Total Rs 225.75 Cft
(Brick Details) 2nd Step
Long wall # 01 2.00 32.50 1.125 1.00 73.13 Cft
Short Wall # 01 1.00 26.00 1.125 1.00 29.25 Cft
Long wall # 02 1.00 10.00 1.125 1.00 11.25 Cft
Short Wall # 02 1.00 26.50 1.125 1.00 29.81 Cft
Partion Wall 1.00 23.00 1.125 1.00 25.88 Cft
Total Rs 169.31 Cft

Step # 01 Total 225.75 Cft


Step # 02 Total 169.31 Cft
395.06 Cft
D/D Col Qty 12.00 1.50 1.50 1.00 27.00 Cft
D/D Col Qty 12.00 1.13 1.13 1.00 15.19 Cft
total 42.19
Total (A+B) Rs 42.19 Cft 269.50 11,369.53
8 Providing and laying plain hand mixed
cement concrete using sand approved
source and crushed aggregate having
maximum size upto 1-1/2" (38mm) & down
gauge in foundation and plinth including
leveling, compacting & curing.

S.I # 5-4/a
Plinth Protection 1.00 96.00 1.00 0.50 48.00
48.00 Cft 177.65 8,527.20

9 Providing and laying in situ cement concrete


using approved coarse sand and crushed
aggregate 3/4" (19mm) and down gauge in
pillars and columns of any shape in super
structure including compacting, curing, cost
of form-work & its removal in basement and
ground floor. (1:1.5:2)
S.I # 5-15/b
COLUMNS # 01,02 & 03 up to Plinth Beam 12.00 1.50 1.50 1.00 27.00
COLUMNS # 01,02 & 03 up to Plinth Beam 12.00 1.13 1.13 1.00 15.19

42.19 Cft 359.50 15,166.41


10 Providing and laying 1:2:4 cement concrete
using approved coarse sand and crushed
aggregate 3/4" (19mm.) and down gauge in
plinth band, door band and roof band of
required shape or section including
formwork and its removal, compacting and
curing in basement and ground floor but
excluding the cost of reinforcement.
S.I # 5-49/a
PLINTH BEAM
Long wall # 01 2.00 32.50 0.75 0.75 36.56 Cft
Short Wall # 01 1.00 26.00 0.75 0.75 14.63 Cft
Long wall # 02 2.00 10.00 0.75 0.75 11.25 Cft
Short Wall # 02 2.00 26.50 0.75 0.75 29.81 Cft
Partion Wall 1.00 23.00 0.75 0.75 12.94 Cft
Total Rs 105.19 Cft 296.20 31,156.54

11 Providing and laying in situ cement concrete


using approved coarse sand and crushed
aggregate 3/4" (19mm) and down gauge in
pillars and columns of any shape in super
structure including compacting, curing, cost
of form-work & its removal in basement and
ground floor.
S.I # 5-15/b

4
BILL OF QUANTITY
S/No. Rate Amount
Description NO L W D/H Quantity Unit
(Rs.) (Rs.)
CANTEEN G.FLOOR (C.W)
COL Type#01 (12"x9") 4.00 1.00 0.75 13.00 39.00
COL Type#02 (9"x9") 8.00 0.75 0.75 13.00 58.50

97.50 Cft 359.50 35,051.25

12 Providing, fabricating and laying deformed


Grade 40 steel reinforcement (deformed
bar) for all kinds of R.C.C work in
foundation, plinth and ground floor including
the cost of straightening, removal of rust,
cutting, bending, binding, wastage and
providing such over-laps as are not shown
on the drawings. The cost of bindin gwire
and cement concrete spacer blocks or
chairs for binding and holding the
reinforcement in position is inclusive upto 15
ft. (5m) height
S.I # 5-44/a
Beam (Qty*10/2204) (P/Beam + Roof Beam) 245.4 10-lbs/cft 1.11 1.11
Door Band (Qty*8/2204) 70.1 10-lbs/cft 0.25 0.25
COLUMNS s (Qty*10/2204) 97.5 10-lbs/cft 0.44 0.44
Slab (Qty*5/2204) 354.0 5-lbs/cft 0.80 0.80
2.61 Tonne 123903.05 323,840.26
13 Providing and laying first class solid burnt
brick masonry (Brick Strength:1800psi-
2000psi) including scaffolding, raking out
joints and curing in ground floor
superstructure S.I
and# i/c cost of testing
11-12/b-iii
(Brick)
Long wall # 01 2.00 32.50 0.75 7.00 341.25
Short Wall # 01 1.00 26.00 0.75 7.00 136.50
Long wall # 02 1.00 10.00 0.75 7.00 52.50
Short Wall # 02 1.00 26.50 0.75 7.00 139.13
Partion Wall 1.00 23.00 0.00 0.00 0.00

Total Quantity 669.38


Above (Door Band) Brick work
Long wall # 01 2.00 32.50 0.75 1.50 73.13
Short Wall # 01 1.00 26.00 0.75 1.50 29.25
Long wall # 02 1.00 10.00 0.75 1.50 11.25
Short Wall # 02 1.00 26.50 0.75 1.50 29.81
Parapet wall 1.00 96.00 0.75 1.50 0.00
Total Quantity 143.44
Sub Total Quantity 812.81
D/D of Door 4.00 8.00 0.75 9.00 216.00
D/D of Win & v 3.00 6.00 0.75 4.00 54.00
D/D of Col Qty 12.00 0.75 0.75 8.50 57.38
Total 327.38
G.Total Quantity 485.44
Total Rs 485.44 Cft 261.75 127,063.27

14 Providing and laying 1:2:4 cement concrete


using approved coarse sand and crushed
aggregate 3/4" (19mm.) and down gauge in
plinth band, door band and roof band of
required shape or section including
formwork and its removal, compacting and
curing in basement and ground floor but
excluding the cost of reinforcement.
S.I # 5-49/b
(Door Band)
Long wall # 01 2.00 32.50 0.75 0.50 24.38
Short Wall # 01 1.00 26.00 0.75 0.50 9.75
Long wall # 02 2.00 10.00 0.75 0.50 7.50
Short Wall # 02 2.00 26.50 0.75 0.50 19.88
Partion Wall 1.00 23.00 0.75 0.50 8.63

5
BILL OF QUANTITY
S/No. Rate Amount
Description NO L W D/H Quantity Unit
(Rs.) (Rs.)
CANTEEN G.FLOOR (C.W)
Total Rs 70.13 Cft 302.80 21,233.85

15 Providing and laying 1:2:4 cement concrete


using approved coarse sand and crushed
aggregate 3/4" (19mm.) and down gauge in
plinth band, door band and roof band of
required shape or section including
formwork and its removal, compacting and
curing in basement and ground floor but
excluding the cost of reinforcement.

S.I # 5-49/c
(Roof Beam)
Long wall # 01 2.00 32.50 0.75 1.00 48.75
Short Wall # 01 1.00 26.00 0.75 1.00 19.50
Long wall # 02 2.00 10.00 0.75 1.00 15.00
Short Wall # 02 2.00 26.50 0.75 1.00 39.75
Partion Wall 1.00 23.00 0.75 1.00 17.25
Total Rs 140.25 Cft 299.25 41,969.81

16 Providing and laying 1:2:4 cement concrete


using approved coarse sand and crushed
aggregate 3/4" (19mm) and down gauge in
slabs including formwork and its removal,
compacting and curing
S.I. # 5-17/a-i
Ground Floor Slab 1.000 684.29 Area 0.50 342.15 Cft
342.15 Cft 327.30 111,984.27

17 Providing and laying 1:2:4 cement concrete


using approved coarse sand and crushed
aggregate 3/4" (19mm) and down gauge in
balustrade of stairs or balcony, sun
breakers, sun shades, parapets and eave
boards upto 3" (75 mm) of required shape or
section including formwork & its removal,
compacting and curing in basement and
ground floor.
S.I. # 5-20/a
Shed on Win 4.00 6.00 1.50 0.33 11.88 Cft
Total 11.88 Cft 374.70 4,451.44

18 Providing and laying hand mixed cement


concrete bed under floors using graded
shingle/bajri 50 mm and down gauge
complete with leveling, ramming, watering
and curing. 1:4:8 (1 cement:4 sand and 8
shingle/bajri).
S.I.# 14-1/b
CANTEEN KITCHEN/STORE 21'-3"X10'-0" 1.00 21.25 10.00 0.33 70.13
STATIONARY AREA 11'-0"X12'-0" 1.00 10.00 10.00 0.33 33.00
PRINTING AREA 10'-0" X 7'-0" 1.00 10.00 7.00 0.33 23.10
SHOP 10'-0" X 8'-0" 1.00 10.00 8.00 0.33 26.40
HOT KITCHEN 21'-3" X 12'-6" 1.00 21.25 12.50 0.33 87.66
VARANDAH 8' WIDE 1.00 32.15 8.00 0.33 84.88
0 0.00 0.00 0.00 0.33 0.00
0 0.00 0.00 0.00 0.33 0.00
Total 325.16 Cft 145.65 47,359.15

6
BILL OF QUANTITY
S/No. Rate Amount
Description NO L W D/H Quantity Unit
(Rs.) (Rs.)
CANTEEN G.FLOOR (C.W)
19 Providing and laying super white 12"x12"
marble tiles floor fine dressed on surface
without winding in ground floor and laid over
1" (25mm) thick cement sand mortar 1:2
setting tiles with portland cement slurry over
cement mortar, jointing and washing the tiles
with white cement slurry including curing,
rubbing and polishing including the cost of
cement mortar. 3/4" (19 mm) thick marble
tiles floor S.I.# 14-9/b
CANTEEN KITCHEN/STORE 21'-3"X10'-0" 1.00 21.25 10.00 212.50
STATIONARY AREA 11'-0"X12'-0" 1.00 10.00 10.00 100.00
PRINTING AREA 10'-0" X 7'-0" 1.00 10.00 7.00 70.00
SHOP 10'-0" X 8'-0" 1.00 10.00 8.00 80.00
Total 462.50 Sft 325.25 150,428.13

20 Providing and laying 1/4" to 3/8" (6mm to


9mm) thick Glazed/ Matt tiles of any colour
and size in ground floor laid over 1" (25mm)
thick cement sand mortar base including
jointing and washing the tiles with white
cement slurry of matching color by using
color pigment and curing
S.I.# 14-25
HOT KITCHEN 21'-3" X 12'-6" 1.00 21.25 12.50 265.63 Sft
VARANDAH 8' WIDE 1.00 32.15 8.00 257.20 Sft
Total 522.83 Sft 182.25 95,284.86
21 Providing and fixing 6.4 mm (1/4²) nominal
thickness glazed tiles of any colour and size
in dado/skirting in ground floor over 13 mm
(½²) thick base of cement mortar 1:3, setting
of grey cement over mortar base including
Engineer-in-Charge in dado/skirting in
ground floor over 1/2" (13mm) thick base of
cement mortar 1:3, setting of tiles in slurry of
grey cement over mortar base including
filling the joints and washing the tiles with
white cement slurry of matching color,
cleaning & curing.
S.I.# 14-64/a
HOT KITCHEN 21'-3" X 12'-6" 2 21.25 1.00 42.50 Sft
HOT KITCHEN 21'-3" X 12'-6" 2 12.50 1.00 25.00 Sft
VARANDAH 8' WIDE 2 32.15 1.00 64.30 Sft
Total 131.80 Sft 144.05 18,985.79
20 Cement plaster using Coarse Sand on
soffits of ceiling, cantilever slabs, sides and
soffits of beams, in basement and ground
floor including making edges, corners and
curing.
S.I. # 15-1/ii+15-6-1
As Per Ground Floor Slab Area 1.0 684.29 Area 0.00 684.29 Sft
Projection# 01 4.00 6.00 1.50 0.00 36.00 Sft
Total 720.29 Sft 28.40 20,456.27

22 1/2 inch (13mm) thick cement plaster using


Coarse Sand on walls and columns in
basement, plinth and ground floor including
making edges, corners and curing.

S.I.# 15-3/ii
Plaster (Inner wall)
Long wall # 01 4.00 32.50 10.00 1300.00

7
BILL OF QUANTITY
S/No. Rate Amount
Description NO L W D/H Quantity Unit
(Rs.) (Rs.)
CANTEEN G.FLOOR (C.W)
Short Wall # 01 2.00 26.00 10.00 520.00
Long wall # 02 2.00 10.00 10.00 200.00
Short Wall # 02 2.00 26.50 10.00 530.00

Total 2550.00
D/D Door Win Qty 288.00
2262.00 Sft 25.05 56,663.10
23 3/4 inch (19mm) thick cement plaster using
Coarse Sand on walls and columns in
basement, plinth and ground floor including
making edges, corners and curing.

S.I.# 15-4-ii

Plaster (Outer Wall)


Outer wall 1.00 96.00 11.50 1104.00
Total 3312.00 Sft 30.55 101,181.60

24 Providing and fixing First class deodar wood


shutters fully glazed with glass of approved
quality and approved brass hinges, tower
bolts, deodar wood beading and putty
packing to glasses as required. 2" (50 mm)
thick fully glazed shutters with 1/4" (6 mm)
thick plain imported glass.
S.I.# 16-9-ii
Ventilator 2.00 4.00 2.00 16.00
Total 16.00 Sft 842.15 13,474.40

25 Providing and fixing moulded steel door


frame of approved 150 mm (6") profile,
manufactured from zinc-coated mild steel
sheets of 1.41 mm thickness (18 gauge),
strike plate, one sliding bolt eye, and three
rubber buffers including cutting holes with
lean cement mortar 1:4 as directed by the
Engineer Incharge.
S.I. # 28-40/a)
Door,s Frames
canteen 2.0 22.00 44.00 Rft
Ventilator 2.0 12.00 24.00 Rft
68.00 Rft 264.05 17,955.40
26 Providing and fixing steel gate of flat iron
sections of approved design with or without
M.S. sheet covering including hold fast with
or without roller and track arrangement
including providing wicket shutter of required
size with all accessories and locking
arrangement as per direction of the Engineer
Incharge
S.I. # 28-18
Door,s Wood
SHOP MAIN GATE 4.0 8.00 9.00 288.00 Sft
288.00 Sft
Total 864.00 KG 83.84 72,437.76

8
BILL OF QUANTITY
S/No. Rate Amount
Description NO L W D/H Quantity Unit
(Rs.) (Rs.)
CANTEEN G.FLOOR (C.W)
28 Providing and fixing fully glazed (with 3 mm
glass sheet) partly fixed and partly hung
aluminum windows, ventilators approved
color of Prime, Chawal, Alcop, Pakistan
Cable or any approved section as approved
by Engineer Incharge including aluminium
fittings, local tinted glass, lugs, cutting holes
and making good the damages to walls
S.I.No ( 28-26/a )
Win Type# 1 1.00 6.00 5.00 30.00 Sft
Win Type# 2 1.00 5.00 4.00 20.00 Sft
Win Type# 3 1.00 4.00 6.00 24.00 Sft
Ventilator 2.00 4.00 2.00 16.00 Sft
Total 90.00 Sft 847.20 76,248.00

29 Distempering with Berger/ ICI or equivalent


synthetic vinyl emulsion paint of approved
shade on old surface of walls and ceiling
including dusting, sand papering and
cleaning in basement and ground floor.
S.I.# 17-60/b
As Per Ground Floor Slab Area 1.0 684.3 Area 684.29
Projection# 01 4.00 6.00 1.50 36.00
Add Plaster (Qty) Total 720.29 Sft 10.00 7,202.91

30 Painting with paint mixed at site using


ingredients and pigment to produce required
texture and shade in two or more coats on
plastered, rendered and/or concrete surface
over and including the cost of priming coat,
surface preparation, dusting, rubbing down
smooth, filling cracks, holes removing
blisters & other blisters & other
imperfections in ground floor or basement.

S.I.# 17-4/1
Long wall # 01 4.00 32.50 8.50 1105.00
Short Wall # 01 2.00 26.00 8.50 442.00
Long wall # 02 2.00 10.00 8.50 170.00
Short Wall # 02 2.00 26.50 8.50 450.50

Total 2167.50 Sft 31.20 67,626.00

30 Painting in ground floor or basement with


Robbialac or equivalent super gloss
synthetic enamel paint in two or more coats
as per manufacturer’s instruction on steel
and iron work over and including the cost of
priming coat, surface preparation removing
rust, scales and dust with wire brush

S.I.# 17-7-1
Ventilator 4.00 4.00 2.00 0.00 32.00 Sft
60% Quantity Total 19.20 Sft 27.30 524.16

31 Painting in ground floor or basement with


Robbialac or equivalent super gloss
synthetic enamel paint in two or more coats
as per manufacturer’s insruction on wood
work over and including the cost of priming
coat, surface preparation, rubbing down
smooth, knotted, filling cracks, holes and
joints
S.I.#17-6
SHOP MAIN GATE 8.000 8.00 9.000 576.00 Sft

9
BILL OF QUANTITY
S/No. Rate Amount
Description NO L W D/H Quantity Unit
(Rs.) (Rs.)
CANTEEN G.FLOOR (C.W)
Total 576.00 Sft 28.85 16,617.60

TOTAL Rs 1,953,208.78
Total Cost in (Million Rs.) 1.953

Sub Engineer Sub Divisional Officer


Physical Planning & Housing Department Physical Planning & Housing Department
District Sherani District Sherani

10
CONSTRUCTION OF TUCK SHOP
BILL OF QUANTITIES

S/No. Description Quantity Unit Rate Amount


(Pak Rs) (Pak Rs)
CANTEEN ELECTRIC WORKS
1 Light circuit concealed wiring with length upto
75 ft. (25m) from distribution board to
point/switch with 3x2.5 Sq.mm PVC insulated
single core copper conductor Pakistan Cables,
Pioneer, Newage or approved equivalent
cables for offices/multi storeyed buildings.
S.I # 30-1/a 9.0 Point 4,433.25 39899.25

2 Light circuit concealed/open wiring with length


upto 65 ft. (20m) from distribution board to
point/switch with 3x2.5 Sq.mm PVC insulated
single core copper conductor Pakistan Cables,
Pioneer, Newage or approved equivalent
cables for offices/multi storeyed buildings.
S.I # 31-2/a) 11.00 Point 3546.60 39012.60

3 Concealed/open wiring for 5 Amp. Socket


outlets from nearest available circuit with a
length upto 20 ft. (6m) with 3x1.5 Sq.mm PVC
insulated single core copper conductor
Pakistan Cables, Pioneer, Newage or approved
equivalent cables

S.I # 30-8/a 18.0 Point 1469.55 26451.90

4 Wiring of 5 Amps. socket outlet with 4 sq.mm


PVC insulated single core copper conductor
cable including 3/4" (20mm) dia. PVC conduit,
8.7sq.mm (10SWG) copper wire as earth
continuity conductor and wiring accessories
such as bends, elbows, junction boxes etc.

S.I # 30-9 120.0 Rft 101.95 12234.00

5 Supply and install 5 Amp, 250 Volt moulded,


one-way, single pole, flush mounting piano type
light control switch on appropriate size
plastic box to be fixed recessed in wall
alongwith switch box and plate suitable for
single switch on a common board.
S.I # 30-16 11.0 Nos 431.40 4745.40

6 Supply and install 5 Amp, 250 Volt moulded,


one-way, single pole, flush mounting piano type
light control switch alongwith fan dimmers on
appropriate size plastic box to be fixed
recessed in wall alongwith switch box and plate
suitable for upto 3 switches on a common
board.
BILL OF QUANTITIES

S/No. Description Quantity Unit Rate Amount


(Pak Rs) (Pak Rs)
CANTEEN ELECTRIC WORKS
S.I # 30-17 33.0 Nos 720.50 23776.50

7 Supply and install combined 2/3 pin 5 Amps,


250 Volt switch socket unit including plastic box
to be fixed recessed in wall.
S.I # 30-19 6.0 Nos 938.75 5632.50

8 Supply and install combined 3 pin 15 Amps.


switch socket unit.250 Volt switch socket unit
including plastic box to be fixed recessed in
wall.
S.I # 30-20 6.0 Nos 1045.00 6270.00

9
Supply and install 2.5 sq.mm PVC insultated
single core 6000V.cable with copper conductor
in already concealed PVC conduit.
S.I # 30-36 225.0 Rft 19.30 4342.50

10 Supply and installation of 14 SWG (3.2 sq.mm)


solid bare hard drawn electrolytic copper wire
as earth continuity conductor in already
installed/laid conduit or underground pipe.

S.I # 30-46 315.0 Rft 16.40 5166.00

11 Supply and install 15 Amp, triple pole, 30 volts


metal clad load breaker switch on surface of
walls.
S.I # 30-57 3.0 No 2785.20 8355.60

12 Supply and install 15 Amp, triple pole, 60 volts


metal clad load breaker switch on surface of
walls.
S.I # 30-58 9.0 No 4694.10 42246.90

13 Supply and install 10" (250 mm) sweep exhaust


fan including plastic louvers.
S.I # 30-113 5.0 Each 2,760.00 13800.00

14 Supply and install surface mounted flourescent


light fixture with a No. 40W lamps, Philips GKD-
140 type or approved equivalent complete with
ballast, power factor improvement capacitor,
starter etc. and including all installation
materials.
S.I # 31-61 3.0 Nos 4,402.00 13206.00
BILL OF QUANTITIES

S/No. Description Quantity Unit Rate Amount


(Pak Rs) (Pak Rs)
CANTEEN ELECTRIC WORKS
16 Supply and install Energy Saver electric bulbs
25W to 100W
S.I # 30-117/C 6.0 Each 315.00 1890.00

17 Supply and install 40W electric tube light rod


including patty
S.I # 30-120 3.0 Each 1665.60 4996.80

18 Light Fixture Philips Type LED 13W,complete


in all respect with allied accessories or
approved equivalent. The fitting shall be
approved by
the Engineer. S.I # 30-120 2.0 Each 16362.95 32725.90

Total 284751.85

Sub Engineer Sub Divisional Officer


Physical Planning & Housing Department Physical Planning & Housing Department
District Sherani District Sherani
CONSTRUCTION OF TUCK SHOP
BILL OF QUANTITIES
S/No. Description Quantity Unit Rate Amount
(Pak Rs) (Pak Rs)
CANTEEN Plumbing Works
1 Providing and fixing European type glazed
earthenware water closet ICL Ifo/Forte or approved
equivalent make including cost of inlet pipe, lid
cistern kit, stop cock deluxe and other accessories,
fitting material such as brackets, PVC down pipe
where required, rubber rings/washers, making
requisite number of holes in walls, plinth and floor
for pipe connection and making good with
approved material. 1.00 Each 13527.00 13527.00
S.I # 23-3/b

2 Providing and fixing export quality glazed earthen


ware wash basin manufactured by ICL Boch/Karam
Cera or equivalent approved make with single hole
chromium plated mixer tap 1/2" (15mm), pillar tap
delux, stop cocks, C.I. or W.I. brackets 6" (150mm)
built into walls 1.5" (40mm) C.P. brass waste with
malleable iron or C.P. brass trap with malleable
iron or brass union and making requisite number of
holes in walls, plinth and floor for pipe connections
and making good with approved material.
4.00 Each 11775.60 47102.40
b) washing basin 600 mm(24") white.
S.I.# 23-5/b-i

d) Extra over above for providing and fixing white


glazed earthenware pedestal manufactured by ICL
(Bosh/KaramCera) or approved equivalent make. 1.00 Each 417.75 417.75
S.I.# 23-5/d-i

3 Providing and fitting superior quality C.P. or brass


oxidised 1/2" (12mm) swan neck pillar cock (tap) of
approved make.

S.I # 23-40/b 1.00 Each 2467.50 2467.50

4 Providing, laying, cutting, jointing, testing and disinfecting


PPRC pipes confirming to ISO 4427, PN-20, complete in
all respects with specials and valves etc. including all
fittings, connnections and jointing material

S.I # 27-47/a-iii & iv


Water Supply
a) 25mm 180.00 Rft 49.86 8974.80
b) 32mm 153.00 Rft 55.96 8561.88
5 Providing manhole type 'A' size 24" x 18" (inside
dimensions) as per approved design and
specifications complete for 4" to 12" dia pipes upto
4 ft. (1.2 m) depth with 16" dia.Concrete Cover
fixed in 4" thick RCC 1:2:4 slab (with 5 lbs per
Cu.ft. or 80 kg/Cu.m of steel), burnt brick masonry
walls 9" (225 mm) thick set in 1:3 cement sand
mortar, 6" thick 1:3:6 cement concrete in
foundation, 4" av. thickness 1:2:4 cement concrete
in benching and 1/2" (13mm) thick cement sand
plaster in 1:3 to all inside wall surfaces, channels
and benching including making requisite number of
main and branch channels but excluding the cost
of excavation, back filling and disposal of
excavated stuff.
S.I # 25-4/a
3.00 Each 12811.70 38435.10

7 Supplying uPVC blind pipe IIL, Dadex or equivalent


make registered with PSQCA. Class B
4" Dia 105.00 Rft 204.00 21420.00
S.I # 27-48/a-ii+27-49/a-ii

8 Providing and fixing looking mirror of Belgium/


Malaysian/ Indonesian glass with chromium plated
screws.

S.I # 23-15-1 36.00 Sft 137.10 4935.60


9 Providing and fixing approved quality chromium
plated towel rail with bracket and screws.
4.00 Each 2391.00 9564.00
S.I # 23-17/b

10 Providing and laying R.C.C pipe with bell and


spigot or tongued & grooved joint conforming to
ASTM C-76 class II wall B orBS 3911 Part I class
M including cost of reinforcement.
i) 225 mm (9") i/d 36.00 Rft 297.10 10695.60
S.I # 25-1/b-i
11 Earthwork excavation in open cutting upto 5ft.
(1.5m) depth for storm water channels, drains in
open area, roads, streets lanes and shoring to
protect existing works, shuttering and timbering the
trenches dressed to designed level and dimension,
trimming from trenches, backfilling and disposal of
surplus excavated material upto 50ft (15m)
including dressing, excluding removal of surface
water from drains. 216.00 Cft 9.40 2030.40
S.I # 25-1/b-i
17 Providing and fixing LDPE overhead tank
manufactured by Dura or equivalent on top of any
floor
S.I # 27-44/c
1000 gallons capacity 1.00 No.s 62688.00 62688.00
18 Providing and fixing stainless steel sink Pakistan
made with C.I. or W.I brackets 6" built in wall, 1.5"
(40 mm) rubber plug,C.P. brass chain, C.P. brass
waste, pillar tap 2 way delux, 1.5" dia malleable
iron or C.P. brass trap and unions and making
requisite number of holes in walls, plinth and
floor for pipe connections and making good with
approved material. Stainless steel sink 40" x 20"
(1000 mm x 500 mm)
S.I # 23-8/a 2.00 Each 8610.00 17220.00

20 Providing and fixing gulley trap with 6" (150mm)


outlet, complete with 4" (100mm) thick 1:2:4
cement concrete using 3/4" (19mm) crushed
aggregate for bed and kerb, 1/2" (13mm) thick
cement plaster 1:3, 12"x12"x18" deep inside
dimension chamber with C.I.grating 6"x6" cover
and frame 12"x12".
Cement concrete gulley trap 6" x 6" x 4" (150 x 150
x 100 mm) with C.I. cover and frame weighing not
less than 10 kg.
(S.I No. 25-3(b)) 1.00 Each 4540.20 4540.20

G.Total (Rs.) 252580.23

Sub Engineer Sub Divisional Officer


Physical Planning & Housing Department Physical Planning & Housing Department
District Sherani District Sherani
SEPTIC TANK BILL OF QUANTITIES
HT/DEPT
S/No Description NO LENGTH WIDTH Quantity Unit Rate Amount
H
(Pak Rs) (Pak Rs)
Septic tank
1 Excavation in foundation of buildings,
bridges, and other structures, including
dagbelling, dressing, refilling around
structures with excavated earth,
watering and ramming lead Up to 30 m,
lift Up to 1.5 m. (Gravel and Shingle
formation)
S.I.# 3-21/a-iv
1 9.50 7.50 8.00 570.00 Cft 9.20 5244.00
2 Providing and laying plain machine
mixed cement concrete using coarse
sand and crushed aggregate having
maximum size upto 1- 1/2" (38mm) &
down gauge in foundation including
levelling, compacting and curing.
S.I.# 5-5/c
1 : 4 : 8 Septic Tank 1 9.50 7.50 0.25 17.81 Cft 185.35 3301.55

Providing and laying cement concrete


using 3/4" (19mm) and down gauge
crushed aggregate in base (foundation)
of flat or semi circular surface drain of
required thickness cast in panels not
exceeding 24 sq.in (60 sq.cm) including
curing, but excluding the cost of
reinforcement and expansion joints.
S.I.# 5-5/a
1 : 2 : 4 Septic Tank 1 9.50 7.50 0.50 35.63 Cft 232.50 8282.81

4 Providing & laying in situ cement


concrete in wall and piers etc, upto
12" (300 mm) in thickness using
approved coarse sand & crushed
aggregate 3/4" (19mm) & down gauge
including compacting, curing,
cost of formwork and its removal in
basement and ground floor
S.I.# 5-13-c
Long Walls 2 8.00 0.75 9.00 108.00
Short Walls 2 8.00 0.75 9.00 108.00
Fillet / Wall Corner Pond 4 1.33 1.33 9.00 64.04
Total 280.04 Cft 292.15 81815.09

5 3/4 inch (19mm) thick cement plaster


using Coarse Sand on walls and
columns in basement, plinth and
ground floor including making edges,
corners and curing.
S.I.# 15-4
4 9.50 8.00 304.00 Sft 30.55 9287.20
SEPTIC TANK BILL OF QUANTITIES
HT/DEPT
S/No Description NO LENGTH WIDTH Quantity Unit Rate Amount
H
(Pak Rs) (Pak Rs)
Septic tank
6 Providing and laying 1:2:4 cement
concrete using approved coarse sand
and crushed aggregate 3/4" (19mm)
and down gauge in
underground tank, septic tank and
underground drain including formwork
and its removal, compacting and
curing. (Top slab upto 6" (150 mm)
thick)
S.I. # 5-22/c
Top slab 1 9.00 9.00 0.50 40.50 Cft 327.30 13255.65

7 Supplying and fitting C.I. manhole cover


with frame weighing not less than 10.25
lbs/sq.ft (50 kg per sq.m.).

S.I.# 23-47/f
60 cm (24") square
8 - - 8.00 Each 2407.50 19260.00

8 Providing, fabricating and laying


deformed Grade 40 steel reinforcement
(deformed bar) for all kinds of R.C.C
work in foundation, plinth and ground
floor including the cost of straightening,
removal of rust, cutting, bending,
binding, wastage and providing
such over-laps as are not shown on the
drawings. The cost of bindin gwire and
cement concrete spacer blocks or
chairs for binding and holding the
reinforcement in position is inclusive
upto 15 ft. (5m)
height

S.I # 5-44/a+f

Bed 1 35.63 9-lbs/cft 0.145 0.15 Kg


Wall 1 280.04 9-lbs/cft 1.144 1.14 Kg
Slab 1 40.50 9-lbs/cft 0.165 0.17 Kg
Total 1.45 Tonne 126036.75 183,309.60

9 Providing and fixing 150mm (6") dia c.i.


went bend up pipe in U shape of
approved shape and design .
on each panel of septic tank (N.S.R) 4 4.00 P.No 1426.80 5707.20

SOAK PIT
10
Excavation in foundation of buildings,
bridges and other structures including
dagbelling, dressing sidesand refilling
around the structures with excavated
earth, watering and ramming, lead upto
30 m., lift upto1.5 m. (Hard soil)
S.I.# 3-21/a-iv
1 Area 235.62 15.00 3534.29 Cft 9.20 32515.48
SEPTIC TANK BILL OF QUANTITIES
HT/DEPT
S/No Description NO LENGTH WIDTH Quantity Unit Rate Amount
H
(Pak Rs) (Pak Rs)
Septic tank
11 Providing and laying pitrun gravel in
sub base or base course of any
thickness to required grade and
camber including watering and
compacting with road roller with all lead
and lift. (compacted
thickness to be measured)
S.I.# 3-15/b
1 Area 134.01 12.00 1608.15 Cft 28.35 45591.12

12 Providing and laying plain machine


mixed cement concrete using coarse
sand and crushed aggregate having
maximum size upto 1- 1/2" (38mm) &
down gauge in foundation including
levelling, compacting and curing.
S.I.# 5-5/a
Columns footings (1 :2 :4)
2 Area 65.97 1.00 131.95
G.Total 131.95 Cft 232.50 30677.45
13 Providing, fabricating and laying
deformed Grade 40 steel reinforcement
(deformed bar) for all kinds of R.C.C
work in foundation, plinth and ground
floor including the cost of straightening,
removal of rust, cutting, bending,
binding, wastage and providing
such over-laps as are not shown on the
drawings. The cost of bindin gwire and
cement concrete spacer blocks or
chairs for binding and holding the
reinforcement in position is inclusive
upto 15 ft. (5m)
height

S.I # 5-44/a+f
Steel 1 0.37 0.37
Top Slab Total 0.37 Tonne 126036.75 46,003.41

14 Providing and laying first class brick


masonry (Brick Strength:1800psi-
2000psi) in steining of walls including
scaffolding and curing upto 10 ft (3 m)
depth and i/c cost of testing.
S.I # 11-29/b-iii
2 1.33 1.33 6.50 23.00
2 0.67 0.67 6.50 5.84
Total 28.83 Cft 285.55 8232.81

15 3/4 inch (19mm) thick cement plaster


using Coarse Sand on walls and
columns in basement, plinth and
ground floor including making edges,
corners and curing.
S.I.# 15-4
1 47.50 15.50 736.23 Sft 30.55 22491.96
SEPTIC TANK BILL OF QUANTITIES
HT/DEPT
S/No Description NO LENGTH WIDTH Quantity Unit Rate Amount
H
(Pak Rs) (Pak Rs)
Septic tank
16 Providing and laying 1:2:4 cement
concrete using approved coarse sand
and crushed aggregate 3/4" (19mm)
and down gauge in
underground tank, septic tank and
underground drain including formwork
and its removal, compacting and
curing. (Top slab upto 6" (150 mm)
thick)
S.I. # 5-22/c
1 Area 57.00 0.49 28.04 Cft
Top slab 1 Area 58.64 0.49 28.85 Cft
56.90 Cft 327.30 18622.15
17 Providing and fixing 150mm (6") dia c.i.
went bend up pipe in U shape of
approved shape and design .
on each panel of septic tank (N.S.R) 1 1.00 P.No 1426.80 1426.80

Sub Total 535,024


G.Total 535,024

Sub Division Officer Executive Engineer (Building)


Physical Planning & Housing Department Physical Planning & Housing Department
District Sherani District Sherani