You are on page 1of 7

PAK PREMIER ENGINEERING

AIR CONDITINING MECHANICAL,


ELECTRICAL ENGINEERS & CONTRACTOS
Ref #: PPE/HAL/QOT/4990/1121 Date: 01/11/2021

M/S: HABIBULLAH ASSOCIATES


3rd Floor, Progressive Plaza,
Beaumont Road, Civil Lines,
Karachi, Pakistan

Attn.: Mr. Saad Sultan (Project Engineer)

Sub.: QUOTATION FOR HVAC WORKS AT DOLMEN MALL, KARACHI

Dear Sir,

Reference to the above subject works we are pleased to quote of Rs 39,007,192/- (Rupees Thirty Nine
Million Seven Thousand One Hundred Ninety Two Only) as per BOQ and specifications.

Plant Room 21,609,942


Mall 7,590,765
COB 9,806,485
GRAND TOTAL 39,007,192

Facilities to be Provided:
1- Electrical Supply for the Fabrication & Execution of the Work .
2- Area for Fabirication of Work s.
3- Store Room for Material.
4- Accomodation for Labor & Staff nearest to the Site.

Works Not Included:


1- Any k ind of False Ceiling / Decorative Work , etc.
2- Any Kind of Electrical Work s.

Note:
1- G.S.T. / P.R.A. Tax are not included in our Quoted prices. G.S.T / P.R.A will be charged separately.

Thanking and assuring you of our best services and closed cooperation all times.

For: PAK PREMIER ENGG.

Muhammad Fayyaz
(Executive)

House # L/2, Street # 6, Opp. Old House, New Airport Road, Near Bhatta Chowk Lahore - Cantt.
Phone: 042-35707785
Email: info@pakpremierengg.com.pk, pak_premier2003@hotmail.com
Web: www.pakpremierengg.com.pk
BOQ RATES AMOUNT
ITEM # DESCRIPTION QTY UNIT TOTAL AMOUNT
MATERIAL LABOR MATERIAL LABOR
A DUCT WORK (MACHINE MADE) (SECTION 23 31 13)

RATE
Sheet Metal Duct Work (Air Conditioning) (Supply Air), Machine made
1 REQUIRED SQFT 315 80 315 80 395
Ducts (IN CASE OF DUCT DAMAGED/DETERIORATED)
ONLY

THERMAL INSULATION (SECTION 23 07 13 & 23 07 19 & DS/1283-23 07


B
13 & 23 07 19)

Insulation of Supply & Fresh Air Duct with Fibre Glass Blanket in Ceiling
1 SQFT 85 30 85 30 115
Concealed Application (1-1/2" thick)
Insulation of Supply & Fresh Air Duct with Fibre Glass Board in
2 SQFT 200 45 200 45 245
Mechanical Room, in Riser or Exposed (Susceptible to Damage)
Insulation of Supply & Return Air Duct with Fibre Glass Blanket in Ceiling
3 SQFT 85 30 85 30 115
Concealed Application (1-1/2" thick)

Insulation of Chilled Water Piping Including Vapor Barrier, Jacketing &


C
Cladding (Closed Cell Foam)

26 Gauge G.I. Cladding - Insulation Make: Aeroflex (Thailand)


1 Ø 80" (Ø 2032mm) 25 RFT 28,500 1,650 712,500 41,250 753,750

2 Ø 30" (Ø 750mm) 100 RFT 11,500 680 1,150,000 68,000 1,218,000

3 Ø 25" (Ø 600mm) 30 RFT 8,095 570 242,850 17,100 259,950

4 Ø 14" (Ø 350mm) 2220 RFT 4,750 335 10,545,000 743,700 11,288,700

5 Ø 12" (Ø 300mm) 250 RFT 4,185 300 1,046,250 75,000 1,121,250

6 Ø 10" (Ø 250mm) 990 RFT 3,630 255 3,593,700 252,450 3,846,150

7 Ø 8" (Ø 200mm) 540 RFT 3,070 215 1,657,800 116,100 1,773,900

D Cladding of Valves & Specialities (Openable Boxes with Insulation)

1 Ø 14" (Ø 350mm) 32 NOS 10,300 4,200 329,600 134,400 464,000

2 Ø 12" (Ø 300mm) 6 NOS 9,150 3,600 54,900 21,600 76,500

3 Ø 10" (Ø 250mm) 18 NOS 8,000 3,000 144,000 54,000 198,000

4 Ø 8" (Ø 200mm) 8 NOS 6,850 2,400 54,800 19,200 74,000


IN CASE EXISITNG CLADDING TO BE REMOVED ALONG WITH
E
INSULATION
1 CHILLED WATER PIPES 4155 RFT - 12 - 49,860 49,860

2 DUCT SQFT - 12 - 12 12

RATE
CONDENSATION RECTIFICATION ON AHU/FCU BODY NEEDS TO
F REQUIRED NOS - - - - -
CATERED, (IF ANY)
ONLY
PAINTING & FINISHING AND MECHANICAL IDENTIFICATION (SECTION
G
23 05 50 & 23 05 53)

1 Painting & Finishing LOT 200,000 100,000 200,000 100,000 300,000

2 Stencilling of Pipes & Ducts LOT 75,000 50,000 75,000 50,000 125,000

3 Identification Tags on Valves, etc. LOT 35,000 25,000 35,000 25,000 60,000

TOTAL AMOUNT 21,609,942

(Rupees Twenty One Million Six Hundred Nine Thousand Nine Hundred Forty Two Only)
BOQ RATES AMOUNT
ITEM # DESCRIPTION QTY UNIT TOTAL AMOUNT
MATERIAL LABOR MATERIAL LABOR
A DUCT WORK (MACHINE MADE) (SECTION 23 31 13)

RATE
Sheet Metal Duct Work (Air Conditioning) (Supply Air), Machine made
1 REQUIRED SQFT 315 80 315 80 395
Ducts (IN CASE OF DUCT DAMAGED/DETERIORATED)
ONLY

THERMAL INSULATION (SECTION 23 07 13 & 23 07 19 & DS/1283-23 07


B
13 & 23 07 19)

Insulation of Supply & Fresh Air Duct with Fibre Glass Blanket in Ceiling
1 SQFT 85 30 80 25 105
Concealed Application (1-1/2" thick)
Insulation of Supply & Fresh Air Duct with Fibre Glass Board in Mechanical
2 SQFT 200 45 210 35 245
Room, in Riser or Exposed (Susceptible to Damage)
Insulation of Supply & Return Air Duct with Fibre Glass Blanket in Ceiling
3 7000 SQFT 85 30 595,000 210,000 805,000
Concealed Application (1-1/2" thick)

Insulation of Chilled Water Piping Including Vapor Barrier, Jacketing &


C
Cladding (Closed Cell Foam)

26 Gauge G.I. Cladding - Insulation Make: Aeroflex (Thailand)


1 Ø 12" (Ø 300mm) 150 RFT 4,185 300 627,750 45,000 672,750

2 Ø 10" (Ø 250mm) 500 RFT 3,630 255 1,815,000 127,500 1,942,500

3 Ø 6" (Ø 150mm) 100 RFT 2,510 175 251,000 17,500 268,500

4 Ø 5" (Ø 125mm) 200 RFT 2,230 160 446,000 32,000 478,000

5 Ø 4" (Ø 100mm) 300 RFT 1,165 120 349,500 36,000 385,500

6 Ø 3" (Ø 80mm) 400 RFT 1,040 100 416,000 40,000 456,000

7 Ø 2 ½" (Ø 65mm) 550 RFT 915 90 503,250 49,500 552,750

8 Ø 2" (Ø 50mm) 350 RFT 745 80 260,750 28,000 288,750

9 Ø 1 ½" (Ø 40mm) 150 RFT 620 70 93,000 10,500 103,500

10 Ø 1 ¼" (Ø 32mm) 360 RFT 560 65 201,600 23,400 225,000


11 Ø 1'' (Ø 25 mm) 950 RFT 505 60 479,750 57,000 536,750

D Cladding of Valves & Specialities (Openable Boxes with Insulation)

1 Ø 10" (Ø 250mm) 10 NOS 8,000 3,000 80,000 30,000 110,000

2 Ø 6" (Ø 150mm) 8 NOS 5,725 1,800 45,800 14,400 60,200

3 Ø 5" (Ø 125mm) 8 NOS 5,150 1,500 41,200 12,000 53,200

4 Ø 4" (Ø 100mm) 6 NOS 1,750 1,200 10,500 7,200 17,700

5 Ø 2 ½" (Ø 65mm) 4 NOS 1,450 900 5,800 3,600 9,400

6 Ø 2" (Ø 50mm) 2 NOS 1,200 750 2,400 1,500 3,900

7 Ø 1 ½" (Ø 40mm) 2 NOS 1,150 600 2,300 1,200 3,500


IN CASE EXISITNG CLADDING TO BE REMOVED ALONG WITH
E
INSULATION
1 CHILLED WATER PIPES 4010 RFT - 12 - 48,120 48,120

2 DUCT 7000 SQFT - 12 - 84,000 84,000

RATE
CONDENSATION RECTIFICATION ON AHU/FCU BODY NEEDS TO
F REQUIRED NOS - - - - -
CATERED, (IF ANY)
ONLY
PAINTING & FINISHING AND MECHANICAL IDENTIFICATION (SECTION 23
G
05 50 & 23 05 53)

1 Painting & Finishing LOT 200,000 100,000 200,000 100,000 300,000

2 Stencilling of Pipes & Ducts LOT 75,000 50,000 75,000 50,000 125,000

3 Identification Tags on Valves, etc. LOT 35,000 25,000 35,000 25,000 60,000

TOTAL AMOUNT 7,590,765

(Rupees Seven Million Five Hundred Ninety Thousand Seven Hundred Sixty Five Only)
BOQ RATES AMOUNT
ITEM # DESCRIPTION QTY UNIT TOTAL AMOUNT
MATERIAL LABOR MATERIAL LABOR
A DUCT WORK (MACHINE MADE) (SECTION 23 31 13)

RATE
Sheet Metal Duct Work (Air Conditioning) (Supply Air), Machine made
1 REQUIRED SQFT 315 80 315 80 395
Ducts (IN CASE OF DUCT DAMAGED/DETERIORATED)
ONLY

THERMAL INSULATION (SECTION 23 07 13 & 23 07 19 & DS/1283-23 07


B
13 & 23 07 19)

Insulation of Supply & Fresh Air Duct with Fibre Glass Blanket in Ceiling
1 SQFT 85 30 85 30 115
Concealed Application (1-1/2" thick)
Insulation of Supply & Fresh Air Duct with Fibre Glass Board in Mechanical
2 SQFT 200 45 200 45 245
Room, in Riser or Exposed (Susceptible to Damage)
Insulation of Supply & Return Air Duct with Fibre Glass Blanket in Ceiling
3 11410 SQFT 85 30 969,850 342,300 1,312,150
Concealed Application (1-1/2" thick)

Insulation of Chilled Water Piping Including Vapor Barrier, Jacketing &


C
Cladding (Closed Cell Foam)

26 Gauge G.I. Cladding - Insulation Make: Aeroflex (Thailand)


1 Ø 10" (Ø 250mm) 100 RFT 3,630 255 363,000 25,500 388,500

2 Ø 8" (Ø 200mm) 240 RFT 3,070 215 736,800 51,600 788,400

3 Ø 6" (Ø 150mm) 150 RFT 2,510 175 376,500 26,250 402,750

4 Ø 5" (Ø 125mm) 700 RFT 2,230 160 1,561,000 112,000 1,673,000

5 Ø 4" (Ø 100mm) 1180 RFT 1,165 120 1,374,700 141,600 1,516,300

6 Ø 3" (Ø 75mm) 420 RFT 1,040 100 436,800 42,000 478,800

7 Ø 2 ½" (Ø 65mm) 380 RFT 915 90 347,700 34,200 381,900

8 Ø 2" (Ø 50mm) 610 RFT 745 80 454,450 48,800 503,250

9 Ø 1 ½" (Ø 40mm) 275 RFT 620 70 170,500 19,250 189,750

10 Ø 1 ¼" (Ø 32mm) 1410 RFT 560 65 789,600 91,650 881,250


11 Ø 1'' (Ø 25 mm) 90 RFT 505 60 45,450 5,400 50,850

Cladding of Valves & Specialities (Openable Boxes with Insulation)


D
(Butterfly valve, Gate valve, PICV, Strainer included)

1 Ø 6" (Ø 150mm) 2 NOS 5,725 1,800 11,450 3,600 15,050

2 Ø 4" (Ø 100mm) 2 NOS 1,750 1,200 3,500 2,400 5,900

3 Ø 3" (Ø 75mm) 4 NOS 1,550 1,000 6,200 4,000 10,200

4 Ø 2 ½" (Ø 65mm) 2 NOS 1,450 900 2,900 1,800 4,700

5 Ø 1 ½" (Ø 40mm) 2 NOS 1,150 600 2,300 1,200 3,500

6 Ø 1 ¼" (Ø 32mm) 298 NOS 1,000 550 298,000 163,900 461,900

7 Ø 1" (Ø 25mm) 35 NOS 900 500 31,500 17,500 49,000


IN CASE EXISITNG CLADDING TO BE REMOVED ALONG WITH
E
INSULATION
1 CHILLED WATER PIPES 5555 RFT - 12 - 66,660 66,660

2 DUCT 11410 SQFT - 12 - 136,920 136,920

RATE
CONDENSATION RECTIFICATION ON AHU/FCU BODY NEEDS TO
F REQUIRED NOS - - - - -
CATERED, (IF ANY)
ONLY
PAINTING & FINISHING AND MECHANICAL IDENTIFICATION (SECTION 23
G
05 50 & 23 05 53)

1 Painting & Finishing LOT 200,000 100,000 200,000 100,000 300,000

2 Stencilling of Pipes & Ducts LOT 75,000 50,000 75,000 50,000 125,000

3 Identification Tags on Valves, etc. LOT 35,000 25,000 35,000 25,000 60,000

TOTAL AMOUNT 9,806,485

(Rupees Nine Million Eight Hundred Six Thousand Four Hundred Eighty Five Only)