You are on page 1of 6

PERT/CPM SCHEDULE

STUDENT'S PLAZA AT PHINMA - UNIVERSITY OF PANGASINAN


OCTOBER 2018 NOVEMBER 2018
22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22
1 2 3 4 5

ORDER/DELIVERY OF
MATERIALS

BUILDING PERMIT

MOBILIZ
DECEMBER 2018
23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26
5 6 7 8 9 10

APPLY FOR
TEMPORARY
POWER & WATER
CONNECTION

FOUNDATION, SHEET
EXCAVATION PILING, PEDESTALS
CLEARING

MOBILIZATION, MAN POWER,


EQUIPMENT BUILDING
LAYOUT

CONSTRUCT
TEMPORARY FACILITY
JANUARY 2018
27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29
10 11 12 13 14 15

SCAFFOLDING,
BOOM TRUCK C-PURLINS, DOWN
FOR INST. OF SPOUT
ROOF TRUSSES
MATERIALS,
BEAM,
WELDING
DATION, SHEET FABRICATION OF TRUSSES MATERIALS,
G, PEDESTALS CHB LAYING EXTERIOR
ROOFING

STRIPPING
FEBRUARY 2018
30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 1 2 3 4
15 16 17 18 19 20

BACKFILLING OF SOIL CON'T ORDER/DELIVERY


EMBANKMENT OF MATERIALS

GROUND SLAB POURING OF


COMPACTION REINFORCEMENT CONCRETE SLAB

FORMWORK OF
STAIRS & RAMP.
POURING CONCRETE
STAIRS
MARCH 2018
5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7
20 21 22 23 24

ELECTRICAL
EXCAVATION FIXTURES

FORMWORKS
INSTALLATION OF ROOF OF SINKS AND
INSULATION POURING
CONCRET
FORMWORK OF PLUMBING
STAIRS & RAMP. INSTALLATION
OF CISTERN WORKS
OURING CONCRETE TILES
STAIRS TANK
PREPARED BY:
GER RAZIL REYES
DIETHER FERRER
ARVIN UMANGAY
JULIUS PHILIP SERAPION
APRIL 2018
8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30
25 26 27

RETOUCHING WORKS
BASED ON
INSPECTION AND
CHECKLIST

LANDSCAPING

DEMOBILIZATION
PAINTING & CLEARING
CONCRETE BENCH, RAILING

TEST
ELECTRICAL &
PLUMBING

You might also like