Milestones / Activities Number of Days Year 2011 Year 2012 Year 2013 Year 2014
1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6
TIMELINES
1. Issue of Notice to Proceed ▲
2. Design 450
1. Site Survey 60
2. Basic Design 90
3. Detailed Design 390
3. Schedule of Procurement & Manufacturing Activities 630
4. Preliminary Works 330
1. Mobilization & Construction Preparation 330
2. Site Leveling 180
5. Construction of Civil Works 240
1. Main Building Foundation 90
2. GTG Foundation 90
3. HRSG Foundation 90
4. STG Foundation 90
5. DM water treatment plant foundation 30
6. HV Transformer & Switchyard Foundation 60
6. Erection Works 360
1. Main Building Erection 90
2. GTG set Erection 90
3. HRSG Erection 120
4. STG set Erection 120
5. DM equipment Erection 90
6. HV Transformer & Switchyard equipment Erection 90
7. Auxiliary Power System energized - ▲
7. Commissioning 240
1. Initial Firing for Gas Turbine - start up and commission (Open Cycle) 30 ▲
2. Initial Synchronization - trial run and testing for commercial operation (Open Cycle) 30 ▲
3. Finish Flushing Pipe 1 ▲
Page 1
Milestones / Activities Number of Days Year 2011 Year 2012 Year 2013 Year 2014
1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6
4. Start Integral Startup and Commissioning - ▲
5. Complex Test 30
8. Performance Tests 30
1. Open Cycle Generation ▲
2. Combined Cycle Generation ▲
9. Commercial Operation Date of Combined Cycle Facility ▲
Page 2