Project Timeline and Milestones 2011-2014

This document outlines a project timeline with key milestones and activities across four years from 2011 to 2014. It includes: 1) Design activities lasting 450 days from 2011 to early 2012 2) Procurement and manufacturing for 630 days from late 2011 to mid 2012 3) Preliminary works like mobilization and site leveling over 330 days in 2011-2012 4) Construction of civil works like foundations over 240 days from late 2011 to late 2012 5) Erection works like building erection and equipment installation over 360 days from 2012 to early 2013 6) Commissioning activities from early 2013 to late 2013 including initial firing, testing and complex testing 7) Performance tests in late 2013 and commercial operation
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
83 views2 pages

Project Timeline and Milestones 2011-2014

This document outlines a project timeline with key milestones and activities across four years from 2011 to 2014. It includes: 1) Design activities lasting 450 days from 2011 to early 2012 2) Procurement and manufacturing for 630 days from late 2011 to mid 2012 3) Preliminary works like mobilization and site leveling over 330 days in 2011-2012 4) Construction of civil works like foundations over 240 days from late 2011 to late 2012 5) Erection works like building erection and equipment installation over 360 days from 2012 to early 2013 6) Commissioning activities from early 2013 to late 2013 including initial firing, testing and complex testing 7) Performance tests in late 2013 and commercial operation
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd

Milestones / Activities Number of Days Year 2011 Year 2012 Year 2013 Year 2014

1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6

TIMELINES

1. Issue of Notice to Proceed ▲

2. Design 450
1. Site Survey 60
2. Basic Design 90
3. Detailed Design 390

3. Schedule of Procurement & Manufacturing Activities 630

4. Preliminary Works 330


1. Mobilization & Construction Preparation 330
2. Site Leveling 180

5. Construction of Civil Works 240


1. Main Building Foundation 90
2. GTG Foundation 90
3. HRSG Foundation 90
4. STG Foundation 90
5. DM water treatment plant foundation 30
6. HV Transformer & Switchyard Foundation 60

6. Erection Works 360


1. Main Building Erection 90
2. GTG set Erection 90
3. HRSG Erection 120
4. STG set Erection 120
5. DM equipment Erection 90
6. HV Transformer & Switchyard equipment Erection 90
7. Auxiliary Power System energized - ▲

7. Commissioning 240
1. Initial Firing for Gas Turbine - start up and commission (Open Cycle) 30 ▲
2. Initial Synchronization - trial run and testing for commercial operation (Open Cycle) 30 ▲
3. Finish Flushing Pipe 1 ▲
Page 1
Milestones / Activities Number of Days Year 2011 Year 2012 Year 2013 Year 2014

1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6

4. Start Integral Startup and Commissioning - ▲


5. Complex Test 30

8. Performance Tests 30
1. Open Cycle Generation ▲
2. Combined Cycle Generation ▲

9. Commercial Operation Date of Combined Cycle Facility ▲

Page 2