DMM22-Critical Path

The document outlines a project execution schedule with various activities and milestones planned from January 2025 to August 2025. Key milestones include the completion of civil defense inspections, early access provision, and readiness for service. The schedule also details specific tasks related to testing, commissioning, and facility management operations.

Uploaded by

Salahu Salu
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
26 views1 page

DMM22-Critical Path

The document outlines a project execution schedule with various activities and milestones planned from January 2025 to August 2025. Key milestones include the completion of civil defense inspections, early access provision, and readiness for service. The schedule also details specific tasks related to testing, commissioning, and facility management operations.

Uploaded by

Salahu Salu
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd

DMM22-BL2.

1-WPR-29-APR-25 Schedule layout 08-May-25 11:21


Activity ID Activity Name Original Start Finish Total Float 2025
Duration
Apr May Jun Jul Aug Sep Oct
DMM22-BL2.1-WPR-29-APR-25 189 25-Jul-24 A 31-Aug-25 0 31-Aug-25, DMM22-BL2.1-WPR-29-AP

PROJECT EXCUTION SCHEDULE 189 02-Jan-25 A 31-Aug-25 0 31-Aug-25, PROJECT EXCUTION SCH

MILESTONES 62 19-Jun-25 31-Aug-25 0 31-Aug-25, MILESTONES


MSFT MILESTONES 62 19-Jun-25 31-Aug-25 0 31-Aug-25, MSFT MILESTONES
M-AZ3-29-OV-L5CX-F
Complete L5/IST (White Tag) 0 19-Jun-25* 0 Complete L5/IST (White Tag),
M-AZ3-28-OV-EAP-F
Early Access Provided 0 30-Jun-25 0 Early Access Provided,
M-AZ3-30-OV-RFS-F
Ready for Service (RFS) 0 31-Aug-25 0 Ready for Service (RFS),
PRELIMINARY MILESTONES 3 26-Jun-25 30-Jun-25 0 30-Jun-25, PRELIMINARY MILESTONES
MIL-PRE-1090
FINAL CIVIL DEFENSE INSPECTION AND APPROVAL 0 26-Jun-25 0 FINAL CIVIL DEFENSE INSPECTION AND APPROVAL,
MIL-PRE-1030
GC SOW FINISH DATE 0 30-Jun-25 0 GC SOW FINISH DATE,
MIL-PRE-1040
BUILDING COMPLETION CERTIFICATE 0 30-Jun-25 0 BUILDING COMPLETION CERTIFICATE,
PHASE 1 (4MW) 1 26-Jun-25 26-Jun-25 0 26-Jun-25, PHASE 1 (4MW)
PHASE 1 (4MW) 1 26-Jun-25 26-Jun-25 0 26-Jun-25, PHASE 1 (4MW)
CERTIFICATIONS 1 26-Jun-25 26-Jun-25 0 26-Jun-25, CERTIFICATIONS
CIVIL DEFENSE 1 26-Jun-25 26-Jun-25 0 26-Jun-25, CIVIL DEFENSE
G-GN-G-GN.104
CIVIL DEFENSE FINAL INSPECTION AND APPROVAL 1 26-Jun-25 26-Jun-25 0 CIVIL DEFENSE FINAL INSPECTION AND APPROVAL
TESTING AND COMMISSIONING 127 02-Jan-25 A 19-Jun-25 0 19-Jun-25, TESTING AND COMMISSIONING
L4- Tagging 122 02-Jan-25 A 14-Jun-25 0 14-Jun-25, L4- Tagging
Electrical System 122 02-Jan-25 A 14-Jun-25 0 14-Jun-25, Electrical System
DC01-L4-1202
Chiller ATS - L4 7 20-Apr-25 A 11-May-25 0 Chiller ATS - L4
DC01-L4-1203
Chiller Controller - L4 3 10-May-25 12-May-25 0 Chiller Controller - L4
DC01-L4-1000
MVSWG -L4 8 13-Apr-25 A 15-May-25 0 MVSWG -L4
DC01-L4-1011
0% UNLOADED TO 100% - LOADED TRANSFERS + BUSWAY LOADING -L4 4 17-May-25 20-May-25 0 0% UNLOADED TO 100% - LOADED TRAN SFERS + BUSWAY LOADING -L4
DC01-L4-1004
MDBs -L4 11 06-Mar-25 A 22-May-25 0 MDBs -L4
DC01-L4-1010
UDPs -L4 4 24-Apr-25 A 25-May-25 0 UDPs -L4
DC01-L4-1008
UPS + Battery Banks + UPS Panels -L4 30 02-Jan-25 A 28-May-25 0 UPS + Battery Banks + UPS Panels -L4
DC01-L4-1007
Electrical System Level (Pre-IST)-L4 6 29-May-25 04-Jun-25 0 Electrical System Level (Pre-IST)-L4
DC01-L4-1015
Electrical String failure -L4 6 29-May-25 04-Jun-25 0 Electrical String failure -L4
DC01-IST-GO/NOGO
IST Go / No Go 4 10-Jun-25 14-Jun-25 0 IST Go / No Go
Mechanical System 62 18-Feb-25 A 28-May-25 0 28-May-25, Mechanical System
DC01-L4-1022
Chiller + Assosicated Plant -L4 12 18-Feb-25 A 20-May-25 0 Chiller + Assosicated Plant -L4
DC01-L4-1012
Computer Room Fan Wall -L4 7 28-Apr-25 A 24-May-25 0 Computer Room Fan Wall -L4
DC01-L5-1000
CHW System Level -L4 4 25-May-25 28-May-25 0 CHW System Level -L4
DC01-L5-1001
Data Hall System Level -L4 4 25-May-25 28-May-25 0 Data Hall System Level -L4
L5- DATA HALL SYSTEM LEVEL + IST 4 16-Jun-25 19-Jun-25 0 19-Jun-25, L5- DATA HALL SYSTEM LEVEL + IST
DC01-L5-1002
Data Hall IST -L5 4 16-Jun-25 19-Jun-25 0 Data Hall IST -L5
OUTSTANDING WORKS 5 21-Jun-25 25-Jun-25 0 25-Jun-25, OUTSTANDING WORKS
FINAL EPOXY 5 21-Jun-25 25-Jun-25 0 25-Jun-25, FINAL EPOXY
A40910 Final Epoxy works 5 21-Jun-25 25-Jun-25 0 Final Epoxy works
FACILITY MANAGEMENT OPERATIONS AND MAINTENANCE (FMO) 140 25-Jul-24 A 31-Aug-25 0 31-Aug-25, FACILITY MANAGEMENT O
FMO.0070 Witness T&C 80 25-Jul-24 A 19-Jun-25 0 Witness T&C
FMO.0170 SLAs Activated 61 21-Jun-25 30-Aug-25 0 SLAs Activated
FMO.200 Ready For Service For MSFT 1 31-Aug-25 31-Aug-25 0 Ready For Service For MSFT

Actual Level of Effort Remaining Work Milestone Page 1 of 1 TASK filter: Critical.
Actual Work Critical Remaining Work summary © Oracle Corporation