DMM22-BL2.
1-WPR-29-APR-25 Schedule layout 08-May-25 11:21
Activity ID Activity Name Original Start Finish Total Float 2025
Duration
Apr May Jun Jul Aug Sep Oct
DMM22-BL2.1-WPR-29-APR-25 189 25-Jul-24 A 31-Aug-25 0 31-Aug-25, DMM22-BL2.1-WPR-29-AP
PROJECT EXCUTION SCHEDULE 189 02-Jan-25 A 31-Aug-25 0 31-Aug-25, PROJECT EXCUTION SCH
MILESTONES 62 19-Jun-25 31-Aug-25 0 31-Aug-25, MILESTONES
MSFT MILESTONES 62 19-Jun-25 31-Aug-25 0 31-Aug-25, MSFT MILESTONES
M-AZ3-29-OV-L5CX-F
Complete L5/IST (White Tag) 0 19-Jun-25* 0 Complete L5/IST (White Tag),
M-AZ3-28-OV-EAP-F
Early Access Provided 0 30-Jun-25 0 Early Access Provided,
M-AZ3-30-OV-RFS-F
Ready for Service (RFS) 0 31-Aug-25 0 Ready for Service (RFS),
PRELIMINARY MILESTONES 3 26-Jun-25 30-Jun-25 0 30-Jun-25, PRELIMINARY MILESTONES
MIL-PRE-1090
FINAL CIVIL DEFENSE INSPECTION AND APPROVAL 0 26-Jun-25 0 FINAL CIVIL DEFENSE INSPECTION AND APPROVAL,
MIL-PRE-1030
GC SOW FINISH DATE 0 30-Jun-25 0 GC SOW FINISH DATE,
MIL-PRE-1040
BUILDING COMPLETION CERTIFICATE 0 30-Jun-25 0 BUILDING COMPLETION CERTIFICATE,
PHASE 1 (4MW) 1 26-Jun-25 26-Jun-25 0 26-Jun-25, PHASE 1 (4MW)
PHASE 1 (4MW) 1 26-Jun-25 26-Jun-25 0 26-Jun-25, PHASE 1 (4MW)
CERTIFICATIONS 1 26-Jun-25 26-Jun-25 0 26-Jun-25, CERTIFICATIONS
CIVIL DEFENSE 1 26-Jun-25 26-Jun-25 0 26-Jun-25, CIVIL DEFENSE
G-GN-G-GN.104
CIVIL DEFENSE FINAL INSPECTION AND APPROVAL 1 26-Jun-25 26-Jun-25 0 CIVIL DEFENSE FINAL INSPECTION AND APPROVAL
TESTING AND COMMISSIONING 127 02-Jan-25 A 19-Jun-25 0 19-Jun-25, TESTING AND COMMISSIONING
L4- Tagging 122 02-Jan-25 A 14-Jun-25 0 14-Jun-25, L4- Tagging
Electrical System 122 02-Jan-25 A 14-Jun-25 0 14-Jun-25, Electrical System
DC01-L4-1202
Chiller ATS - L4 7 20-Apr-25 A 11-May-25 0 Chiller ATS - L4
DC01-L4-1203
Chiller Controller - L4 3 10-May-25 12-May-25 0 Chiller Controller - L4
DC01-L4-1000
MVSWG -L4 8 13-Apr-25 A 15-May-25 0 MVSWG -L4
DC01-L4-1011
0% UNLOADED TO 100% - LOADED TRANSFERS + BUSWAY LOADING -L4 4 17-May-25 20-May-25 0 0% UNLOADED TO 100% - LOADED TRAN SFERS + BUSWAY LOADING -L4
DC01-L4-1004
MDBs -L4 11 06-Mar-25 A 22-May-25 0 MDBs -L4
DC01-L4-1010
UDPs -L4 4 24-Apr-25 A 25-May-25 0 UDPs -L4
DC01-L4-1008
UPS + Battery Banks + UPS Panels -L4 30 02-Jan-25 A 28-May-25 0 UPS + Battery Banks + UPS Panels -L4
DC01-L4-1007
Electrical System Level (Pre-IST)-L4 6 29-May-25 04-Jun-25 0 Electrical System Level (Pre-IST)-L4
DC01-L4-1015
Electrical String failure -L4 6 29-May-25 04-Jun-25 0 Electrical String failure -L4
DC01-IST-GO/NOGO
IST Go / No Go 4 10-Jun-25 14-Jun-25 0 IST Go / No Go
Mechanical System 62 18-Feb-25 A 28-May-25 0 28-May-25, Mechanical System
DC01-L4-1022
Chiller + Assosicated Plant -L4 12 18-Feb-25 A 20-May-25 0 Chiller + Assosicated Plant -L4
DC01-L4-1012
Computer Room Fan Wall -L4 7 28-Apr-25 A 24-May-25 0 Computer Room Fan Wall -L4
DC01-L5-1000
CHW System Level -L4 4 25-May-25 28-May-25 0 CHW System Level -L4
DC01-L5-1001
Data Hall System Level -L4 4 25-May-25 28-May-25 0 Data Hall System Level -L4
L5- DATA HALL SYSTEM LEVEL + IST 4 16-Jun-25 19-Jun-25 0 19-Jun-25, L5- DATA HALL SYSTEM LEVEL + IST
DC01-L5-1002
Data Hall IST -L5 4 16-Jun-25 19-Jun-25 0 Data Hall IST -L5
OUTSTANDING WORKS 5 21-Jun-25 25-Jun-25 0 25-Jun-25, OUTSTANDING WORKS
FINAL EPOXY 5 21-Jun-25 25-Jun-25 0 25-Jun-25, FINAL EPOXY
A40910 Final Epoxy works 5 21-Jun-25 25-Jun-25 0 Final Epoxy works
FACILITY MANAGEMENT OPERATIONS AND MAINTENANCE (FMO) 140 25-Jul-24 A 31-Aug-25 0 31-Aug-25, FACILITY MANAGEMENT O
FMO.0070 Witness T&C 80 25-Jul-24 A 19-Jun-25 0 Witness T&C
FMO.0170 SLAs Activated 61 21-Jun-25 30-Aug-25 0 SLAs Activated
FMO.200 Ready For Service For MSFT 1 31-Aug-25 31-Aug-25 0 Ready For Service For MSFT
Actual Level of Effort Remaining Work Milestone Page 1 of 1 TASK filter: Critical.
Actual Work Critical Remaining Work summary © Oracle Corporation