Diriyah Gate Infrastructure Construction General Contractor Area B - RPV03
update as of 24-Oct-24
Activity ID Activity Name Original Duration BL1 Start BL1 Early Finish Acutal / Acutal / Forcast Total Delay (BL - 2025
Forcast Start Finish Float Current) Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct
1520 01-Aug-21 14-May-25 01-Aug-21 A 28-Sep-25 -137 -137 28-Sep-25, Diriyah Gate Infrastruc
Diriyah Gate Infrastructure Construction General Contractor Area B - RPV03
1520 01-Aug-21 14-May-25 01-Aug-21 A 28-Sep-25 -137 -137 28-Sep-25, MAIN CONSTRUCTI
MAIN CONSTRUCTION PACKAGE
Key Milestones 1520 01-Aug-21 14-May-25 01-Aug-21 A 28-Sep-25 -137 -137 28-Sep-25, Key Milestones
Key dates 1520 01-Aug-21 14-May-25 01-Aug-21 A 28-Sep-25 -137 -137 28-Sep-25, Key dates
DG004.B.S.CM.01.103 Project Overall Duration 1132 01-Aug-21 14-May-25 01-Aug-21 A 28-Sep-25 -117 -117 Project Overall Duration
DG004.B.S.CM.01.104 Project Completion date 0 14-May-25 28-Sep-25 -117 -117 Project Completion date, , 28-Sep
Control Milestone 0 14-May-25 14-May-25 28-Sep-25 28-Sep-25 -117 -117 28-Sep-25, Control Milestone
Milestone 3 - Gas Farm Delivery 0 14-May-25 14-May-25 28-Sep-25 28-Sep-25 -117 -118 28-Sep-25, Milestone 3 - Gas Farm
DG004.B.S.CM.15001 Gas farm works completion including testing and commissioning 0 14-May-25 28-Sep-25 -117 -118 Gas farm works completion includ
Milestone 5 - Overall completion 0 14-May-25 14-May-25 28-Sep-25 28-Sep-25 -117 -117 28-Sep-25, Milestone 5 - Overall c
DG004.B.S.CM.015001 Overall completion of the project 0 14-May-25 28-Sep-25 -117 -117 Overall completion of the project, ,
DGCL Coordination Milestones 0 14-May-25 14-May-25 28-Sep-25 28-Sep-25 -117 -117 28-Sep-25, DGCL Coordination M
DG004.B.S.DGCLM.260 Practical Completion 0 14-May-25 28-Sep-25 -117 -117 Practical Completion, , 28-Sep-25
DG004.B.S.DGCLM.270 Opening 0 14-May-25 28-Sep-25 -117 -117 Opening, , 28-Sep-25
Engineering 150 06-Apr-23 01-Feb-24 06-Apr-23 A 26-Oct-24 -117 -281 26-Oct-24, Engineering
Design 150 06-Apr-23 01-Feb-24 06-Apr-23 A 26-Oct-24 -117 -281 26-Oct-24, Design
Gas Farm 150 06-Apr-23 01-Feb-24 06-Apr-23 A 26-Oct-24 -117 -281 26-Oct-24, Gas Farm
3rd party Design approval 150 06-Apr-23 01-Feb-24 06-Apr-23 A 26-Oct-24 -117 -281 26-Oct-24, 3rd party Design approval
DG004.B.E-DG-0101341
Approval of Detailed Design (3rd Party/FLS) 150 06-Apr-23 01-Feb-24 06-Apr-23 A 26-Oct-24 -117 -281 Approval of Detailed Design (3rd Party/FLS)
Procurement 240 01-Feb-24 25-Nov-24 18-May-24 A 08-May-25 -117 -141 08-May-25, Procurement
Material Delivery 240 01-Feb-24 25-Nov-24 18-May-24 A 08-May-25 -117 -141 08-May-25, Material Delivery
Long Lead Items 240 01-Feb-24 25-Nov-24 18-May-24 A 08-May-25 -117 -141 08-May-25, Long Lead Items
Gas Farm Work 240 01-Feb-24 25-Nov-24 18-May-24 A 08-May-25 -117 -141 08-May-25, Gas Farm Work
DG004.B.P.BL.128500Fabrication,Delivery & Material Inspection - For Tanks 240 01-Feb-24 25-Nov-24 18-May-24 A 08-May-25 -117 -141 Fabrication,Delivery & Material Inspection - For Tanks
DG004.B.P.BL.128510Fabrication,Delivery & Material Inspection - For Tanks Accessories 240 01-Feb-24 25-Nov-24 18-May-24 A 08-May-25 -117 -141 Fabrication,Delivery & Material Inspection - For Tanks Accessories
Construction 22 25-Nov-24 23-Dec-24 10-May-25 03-Jun-25 -117 -139 03-Jun-25, Construction
Utility Plots 22 25-Nov-24 23-Dec-24 10-May-25 03-Jun-25 -117 -139 03-Jun-25, Utility Plots
Gas Farm 22 25-Nov-24 23-Dec-24 10-May-25 03-Jun-25 -117 -139 03-Jun-25, Gas Farm
Gas Farm MEP Systems 22 25-Nov-24 23-Dec-24 10-May-25 03-Jun-25 -117 -139 03-Jun-25, Gas Farm MEP Systems
Electrical Systems 12 09-Dec-24 23-Dec-24 21-May-25 03-Jun-25 -117 -139 03-Jun-25, Electrical Systems
Cathodic Protection System 12 09-Dec-24 23-Dec-24 21-May-25 03-Jun-25 -117 -139 03-Jun-25, Cathodic Protection System
DG004.B.C.GF.820
Cathodic protection system - 1st Fix 4 09-Dec-24 14-Dec-24 21-May-25 25-May-25 -117 -139 Cathodic protection system - 1st Fix
DG004.B.C.GF.830
Cathodic protection system - 2nd Fix 4 14-Dec-24 18-Dec-24 26-May-25 29-May-25 -117 -139 Cathodic protection system - 2nd Fix
DG004.B.C.GF.840
Cathodic protection system - Final Fix (inc. inspections) 4 18-Dec-24 23-Dec-24 31-May-25 03-Jun-25 -117 -139 Cathodic protection system - Final Fix (inc. inspections)
Mechanical Systems 15 25-Nov-24 16-Dec-24 10-May-25 26-May-25 -117 -138 26-May-25, Mechanical Systems
Tanks & accessories 15 25-Nov-24 16-Dec-24 10-May-25 26-May-25 -117 -138 26-May-25, Tanks & accessories
DG004.B.C.GF.420
Installation of Tank No 1 & Accessories 5 25-Nov-24 02-Dec-24 10-May-25 14-May-25 -117 -140 Installation of Tank No 1 & Accessories
DG004.B.C.GF.440
Installation of Tank No 2 & Accessories 5 02-Dec-24 09-Dec-24 15-May-25 20-May-25 -117 -139 Installation of Tank No 2 & Accessories
DG004.B.C.GF.470
Installation of Tank No 3 & Accessories 5 09-Dec-24 16-Dec-24 21-May-25 26-May-25 -117 -138 Installation of Tank No 3 & Accessories
Testing & Commissioning 24 24-Dec-24 13-Feb-25 03-Jun-25 01-Jul-25 -117 -118 01-Jul-25, Testing & Commissioning
Gas Network 24 24-Dec-24 13-Feb-25 03-Jun-25 01-Jul-25 -117 -118 01-Jul-25, Gas Network
DG004.B.H.UP.133131 Completion of Gasfarm & Network 0 24-Dec-24 03-Jun-25 -117 -138 Completion of Gasfarm & Network, , 03-Jun-25
DG004.B.H.UP.133041 T&C of the Detection System Diriyah South 2 24 25-Dec-24 21-Jan-25 04-Jun-25 01-Jul-25 -117 -138 T&C of the Detection System Diriyah South 2
DG004.B.H.UP.133061 T&C of the Detection System Diriyah Square 24 18-Jan-25 13-Feb-25 04-Jun-25 01-Jul-25 -117 -118 T&C of the Detection System Diriyah Square
Handover 89 15-Feb-25 14-May-25 02-Jul-25 28-Sep-25 -137 -137 28-Sep-25, Handover
Gas Network 64 01-Mar-25 14-May-25 16-Jul-25 28-Sep-25 -117 -118 28-Sep-25, Gas Network
DG004.B.H.01.93 Final inspections 28 01-Mar-25 01-Apr-25 16-Jul-25 17-Aug-25 -117 -118 Final inspections
DG004.B.H.01.103 Training & Closing Documents (In cluding O/Mmanuals) 28 01-Mar-25 01-Apr-25 16-Jul-25 17-Aug-25 -117 -118 Training & Closing Documents (Including O/Mmanuals)
DG004.B.H.01.000063 Final acceptance certificate 10 02-Apr-25 13-Apr-25 18-Aug-25 28-Aug-25 -117 -118 Final acceptance certificate
DG004.B.H.01.43 Final Employer Handover 26 14-Apr-25 14-May-25 30-Aug-25 28-Sep-25 -117 -118 Final Employer Handover
As Built Drawing/Handing Over Documentation 48 15-Feb-25 10-Apr-25 02-Jul-25 26-Aug-25 -117 -118 26-Aug-25,As Built Drawing/Handing Over Documen
Gas Network 48 15-Feb-25 10-Apr-25 02-Jul-25 26-Aug-25 -117 -118 26-Aug-25, Gas Network
DG004.B.H.01.63 As-built submissions for Gas Network 36 15-Feb-25 27-Mar-25 02-Jul-25 12-Aug-25 -117 -118 As-built submissions for Gas Network
DG004.B.H.01.83 As-built approvals for Gas Network 36 01-Mar-25 10-Apr-25 16-Jul-25 26-Aug-25 -117 -118 As-built approvals for Gas Network
Contractor Demobilization 14 27-Apr-25 14-May-25 09-Sep-25 28-Sep-25 -97 -97 28-Sep-25, Contractor Demobiliz
DG004.B.H.01.000001 Removal of Contractor Office 3 12-May-25 14-May-25 24-Sep-25 28-Sep-25 -97 -97 Removal of Contractor Office
DG004.B.H.01.000002 Removal of Yard 14 27-Apr-25 14-May-25 09-Sep-25 28-Sep-25 -97 -97 Removal of Yard
Actual Level of Effort Remaining Work Page 1 of 1 Critical Path Layout
Primary Baseline Critical Remaining Work Project Name: Diriyah Gate Infrastructure Construction General
Actual Work Milestone Contractor Area B
Data Date: 24-Oct-24