Diriyah Gate Project Timeline Update

Uploaded by

Bikku Raj
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
19 views1 page

Diriyah Gate Project Timeline Update

Uploaded by

Bikku Raj
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd

Diriyah Gate Infrastructure Construction General Contractor Area B - RPV03

update as of 24-Oct-24
Activity ID Activity Name Original Duration BL1 Start BL1 Early Finish Acutal / Acutal / Forcast Total Delay (BL - 2025
Forcast Start Finish Float Current) Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct
1520 01-Aug-21 14-May-25 01-Aug-21 A 28-Sep-25 -137 -137 28-Sep-25, Diriyah Gate Infrastruc
Diriyah Gate Infrastructure Construction General Contractor Area B - RPV03
1520 01-Aug-21 14-May-25 01-Aug-21 A 28-Sep-25 -137 -137 28-Sep-25, MAIN CONSTRUCTI
MAIN CONSTRUCTION PACKAGE
Key Milestones 1520 01-Aug-21 14-May-25 01-Aug-21 A 28-Sep-25 -137 -137 28-Sep-25, Key Milestones
Key dates 1520 01-Aug-21 14-May-25 01-Aug-21 A 28-Sep-25 -137 -137 28-Sep-25, Key dates
DG004.B.S.CM.01.103 Project Overall Duration 1132 01-Aug-21 14-May-25 01-Aug-21 A 28-Sep-25 -117 -117 Project Overall Duration
DG004.B.S.CM.01.104 Project Completion date 0 14-May-25 28-Sep-25 -117 -117 Project Completion date, , 28-Sep
Control Milestone 0 14-May-25 14-May-25 28-Sep-25 28-Sep-25 -117 -117 28-Sep-25, Control Milestone
Milestone 3 - Gas Farm Delivery 0 14-May-25 14-May-25 28-Sep-25 28-Sep-25 -117 -118 28-Sep-25, Milestone 3 - Gas Farm
DG004.B.S.CM.15001 Gas farm works completion including testing and commissioning 0 14-May-25 28-Sep-25 -117 -118 Gas farm works completion includ
Milestone 5 - Overall completion 0 14-May-25 14-May-25 28-Sep-25 28-Sep-25 -117 -117 28-Sep-25, Milestone 5 - Overall c
DG004.B.S.CM.015001 Overall completion of the project 0 14-May-25 28-Sep-25 -117 -117 Overall completion of the project, ,
DGCL Coordination Milestones 0 14-May-25 14-May-25 28-Sep-25 28-Sep-25 -117 -117 28-Sep-25, DGCL Coordination M
DG004.B.S.DGCLM.260 Practical Completion 0 14-May-25 28-Sep-25 -117 -117 Practical Completion, , 28-Sep-25
DG004.B.S.DGCLM.270 Opening 0 14-May-25 28-Sep-25 -117 -117 Opening, , 28-Sep-25

Engineering 150 06-Apr-23 01-Feb-24 06-Apr-23 A 26-Oct-24 -117 -281 26-Oct-24, Engineering
Design 150 06-Apr-23 01-Feb-24 06-Apr-23 A 26-Oct-24 -117 -281 26-Oct-24, Design
Gas Farm 150 06-Apr-23 01-Feb-24 06-Apr-23 A 26-Oct-24 -117 -281 26-Oct-24, Gas Farm
3rd party Design approval 150 06-Apr-23 01-Feb-24 06-Apr-23 A 26-Oct-24 -117 -281 26-Oct-24, 3rd party Design approval
DG004.B.E-DG-0101341
Approval of Detailed Design (3rd Party/FLS) 150 06-Apr-23 01-Feb-24 06-Apr-23 A 26-Oct-24 -117 -281 Approval of Detailed Design (3rd Party/FLS)
Procurement 240 01-Feb-24 25-Nov-24 18-May-24 A 08-May-25 -117 -141 08-May-25, Procurement
Material Delivery 240 01-Feb-24 25-Nov-24 18-May-24 A 08-May-25 -117 -141 08-May-25, Material Delivery
Long Lead Items 240 01-Feb-24 25-Nov-24 18-May-24 A 08-May-25 -117 -141 08-May-25, Long Lead Items
Gas Farm Work 240 01-Feb-24 25-Nov-24 18-May-24 A 08-May-25 -117 -141 08-May-25, Gas Farm Work
DG004.B.P.BL.128500Fabrication,Delivery & Material Inspection - For Tanks 240 01-Feb-24 25-Nov-24 18-May-24 A 08-May-25 -117 -141 Fabrication,Delivery & Material Inspection - For Tanks
DG004.B.P.BL.128510Fabrication,Delivery & Material Inspection - For Tanks Accessories 240 01-Feb-24 25-Nov-24 18-May-24 A 08-May-25 -117 -141 Fabrication,Delivery & Material Inspection - For Tanks Accessories
Construction 22 25-Nov-24 23-Dec-24 10-May-25 03-Jun-25 -117 -139 03-Jun-25, Construction
Utility Plots 22 25-Nov-24 23-Dec-24 10-May-25 03-Jun-25 -117 -139 03-Jun-25, Utility Plots
Gas Farm 22 25-Nov-24 23-Dec-24 10-May-25 03-Jun-25 -117 -139 03-Jun-25, Gas Farm
Gas Farm MEP Systems 22 25-Nov-24 23-Dec-24 10-May-25 03-Jun-25 -117 -139 03-Jun-25, Gas Farm MEP Systems
Electrical Systems 12 09-Dec-24 23-Dec-24 21-May-25 03-Jun-25 -117 -139 03-Jun-25, Electrical Systems
Cathodic Protection System 12 09-Dec-24 23-Dec-24 21-May-25 03-Jun-25 -117 -139 03-Jun-25, Cathodic Protection System
DG004.B.C.GF.820
Cathodic protection system - 1st Fix 4 09-Dec-24 14-Dec-24 21-May-25 25-May-25 -117 -139 Cathodic protection system - 1st Fix
DG004.B.C.GF.830
Cathodic protection system - 2nd Fix 4 14-Dec-24 18-Dec-24 26-May-25 29-May-25 -117 -139 Cathodic protection system - 2nd Fix
DG004.B.C.GF.840
Cathodic protection system - Final Fix (inc. inspections) 4 18-Dec-24 23-Dec-24 31-May-25 03-Jun-25 -117 -139 Cathodic protection system - Final Fix (inc. inspections)
Mechanical Systems 15 25-Nov-24 16-Dec-24 10-May-25 26-May-25 -117 -138 26-May-25, Mechanical Systems
Tanks & accessories 15 25-Nov-24 16-Dec-24 10-May-25 26-May-25 -117 -138 26-May-25, Tanks & accessories
DG004.B.C.GF.420
Installation of Tank No 1 & Accessories 5 25-Nov-24 02-Dec-24 10-May-25 14-May-25 -117 -140 Installation of Tank No 1 & Accessories
DG004.B.C.GF.440
Installation of Tank No 2 & Accessories 5 02-Dec-24 09-Dec-24 15-May-25 20-May-25 -117 -139 Installation of Tank No 2 & Accessories
DG004.B.C.GF.470
Installation of Tank No 3 & Accessories 5 09-Dec-24 16-Dec-24 21-May-25 26-May-25 -117 -138 Installation of Tank No 3 & Accessories
Testing & Commissioning 24 24-Dec-24 13-Feb-25 03-Jun-25 01-Jul-25 -117 -118 01-Jul-25, Testing & Commissioning
Gas Network 24 24-Dec-24 13-Feb-25 03-Jun-25 01-Jul-25 -117 -118 01-Jul-25, Gas Network
DG004.B.H.UP.133131 Completion of Gasfarm & Network 0 24-Dec-24 03-Jun-25 -117 -138 Completion of Gasfarm & Network, , 03-Jun-25
DG004.B.H.UP.133041 T&C of the Detection System Diriyah South 2 24 25-Dec-24 21-Jan-25 04-Jun-25 01-Jul-25 -117 -138 T&C of the Detection System Diriyah South 2
DG004.B.H.UP.133061 T&C of the Detection System Diriyah Square 24 18-Jan-25 13-Feb-25 04-Jun-25 01-Jul-25 -117 -118 T&C of the Detection System Diriyah Square
Handover 89 15-Feb-25 14-May-25 02-Jul-25 28-Sep-25 -137 -137 28-Sep-25, Handover
Gas Network 64 01-Mar-25 14-May-25 16-Jul-25 28-Sep-25 -117 -118 28-Sep-25, Gas Network
DG004.B.H.01.93 Final inspections 28 01-Mar-25 01-Apr-25 16-Jul-25 17-Aug-25 -117 -118 Final inspections
DG004.B.H.01.103 Training & Closing Documents (In cluding O/Mmanuals) 28 01-Mar-25 01-Apr-25 16-Jul-25 17-Aug-25 -117 -118 Training & Closing Documents (Including O/Mmanuals)
DG004.B.H.01.000063 Final acceptance certificate 10 02-Apr-25 13-Apr-25 18-Aug-25 28-Aug-25 -117 -118 Final acceptance certificate
DG004.B.H.01.43 Final Employer Handover 26 14-Apr-25 14-May-25 30-Aug-25 28-Sep-25 -117 -118 Final Employer Handover
As Built Drawing/Handing Over Documentation 48 15-Feb-25 10-Apr-25 02-Jul-25 26-Aug-25 -117 -118 26-Aug-25,As Built Drawing/Handing Over Documen
Gas Network 48 15-Feb-25 10-Apr-25 02-Jul-25 26-Aug-25 -117 -118 26-Aug-25, Gas Network
DG004.B.H.01.63 As-built submissions for Gas Network 36 15-Feb-25 27-Mar-25 02-Jul-25 12-Aug-25 -117 -118 As-built submissions for Gas Network
DG004.B.H.01.83 As-built approvals for Gas Network 36 01-Mar-25 10-Apr-25 16-Jul-25 26-Aug-25 -117 -118 As-built approvals for Gas Network
Contractor Demobilization 14 27-Apr-25 14-May-25 09-Sep-25 28-Sep-25 -97 -97 28-Sep-25, Contractor Demobiliz
DG004.B.H.01.000001 Removal of Contractor Office 3 12-May-25 14-May-25 24-Sep-25 28-Sep-25 -97 -97 Removal of Contractor Office
DG004.B.H.01.000002 Removal of Yard 14 27-Apr-25 14-May-25 09-Sep-25 28-Sep-25 -97 -97 Removal of Yard

Actual Level of Effort Remaining Work Page 1 of 1 Critical Path Layout


Primary Baseline Critical Remaining Work Project Name: Diriyah Gate Infrastructure Construction General
Actual Work Milestone Contractor Area B
Data Date: 24-Oct-24