Item Description Unit Quantity Rates Amount

1 Site Clearing
Allow for necessary site clearing including
removal of all shrubs, vegetation, weeds,
bushes, undergrowth, hedges, trees &
stumps of any girth including grubbing up
roots, filling voids and disposal of debris
and load and cart away excess excavated m² 3,249.00 2,230.00 7,245,270.00
materials away from site as it accumulates
from time to time and at completion. And
including Removal of a 150mm thick top
soil layer up to a distance of 3.0 m from
the building area
2 Excavation
Excavate in any material including
levelling and compacting the bottom of
excavation(-10.6m) as specified in design
guide issued by the Engineer and in stages
as necessary
2.1 Bulk excavation using Excavator 120 Hp m³ 28,237.23 1,330.00 37,555,521.22