Water Resources Division Katni

Abstract for Construction of Earthen Dam in Ghugri Village(Belk

Tahsil-Dheemarkheda

S.No Item Quantaty


Excavation in all kind of soft/loose/hard/dense soils,

moorum & moorum mixed with boulders and mud

including dressing, placing the excavated soil neatly

2 in specified dump area or disposing off the same as 101030.23

directed, including cost of site clearance, all

materials,machinery, labour and dressing etc.

Complete.
Watering earthwork for compaction at
3 optimum moisture content. 13190.4

Providing and constructing dump riprap as per IS-


8237 over 400mm thick graded filter media backing
consisting of sand, clean, hard, and
graded(Metal/shingle) aggregates laid in layers of
4 200 mm thick each including cost of all materials for 1067.97
riprap filter media, machinery, labour, laying to
required slopes as per approved drawings, packing
and wedging with stone chips etc. Complete. 750
mm thick
Providing filter blanket on inclined surface steeper
than 1 in 5 and chimney filter , Including
laying,spreading, packing etc. Complete in layers of
required thickness but excluding excavation of 213.6
foundation. On inclined surfaces steeper than 1 in 5
5 (a)
Aggregate 40 mm nominal size.

(b) Sand passing through 4.75 mm screen. 213.6


Excavation in all kind of soft/loose/hard/dense soils,
moorum & moorum mixed with boulders and mud
including dressing, placing the excavated soil neatly
6 in specified dump area or disposing off the same as 221.55
directed, including cost of site clearance, all
materials,machinery, labour and dressing etc.
Complete.

Providing and constructing Dry rubble wall (toe wall)


with stone of minimum size 0.021 cum at the base
7 221.55
of stone pitching or rip-rap excluding excavation
etc.complete.

Dewatering and pumping the working area including


all connecting operation required etc. complete. For
8 960
cleanliness of working area by 5hp to 10
hp diesel pump

Add GST @ 12%

Grand Total

Say as Rs. 61.37 lakh


es Division Katni
in Ghugri Village(Belkund River Diversion)

District-Katni

taty Rate Unit Amount UCSR no(Ref)

30.23 38 Cum 3839149 2.01 3839149

90.4 8 Cum 105523 2.1

7.97 783 Sqm 836221 3.46.2

3.6 880 Cum 187968 3.36.1.3

3.6 1035 Cum 221076 3.36.1.10


.55 38 Cum 8419 2.01

.55 614 Cum 136032 3.45

0 151 Hour 144960 3.55.2

Total 5479347.05

657521.65

6136868.7

Say as Rs. 61.37 lakhs


0.6255876
0.6136869
Water Resources Division Katni

Details for Construction of Earthen Dam in Ghugri Village(Belkund River Di


Tahsil-Dheemarkheda
S.No Item Length Width Depth/Height
Excavation in all kind of soft/loose/hard/dense soils,

moorum & moorum mixed with boulders and mud

including dressing, placing the excavated soil neatly in


1 As per Sheet Enclosed -1
specified dump area or disposing off the same as directed,

including cost of site clearance, all materials,machinery,

labour and dressing etc. Complete.


Watering earthwork for compaction at
2 optimum moisture content. As per Sheet Enclosed -2

Providing and constructing dump riprap as per IS-8237 over

400mm thick graded filter media backing consisting of sand,

clean, hard, and graded(Metal/shingle) aggregates laid in

3 layers of 200 mm thick each including cost of all materials

for riprap filter media, machinery, labour, laying to required

slopes as per approved drawings, packing and wedging with

stone chips etc. Complete. 750 mm thick


Providing filter blanket on inclined surface steeper than 1 in
5 and chimney filter , Including laying,spreading, packing
etc. Complete in layers of required thickness but excluding
excavation of
foundation. On inclined surfaces steeper than 1 in 5
4 (a) Aggregate 40 mm
nominal size.

(b) Sand passing through 4.75 mm screen.


Excavation in all kind of soft/loose/hard/dense soils,
moorum & moorum mixed with boulders and mud
including dressing, placing the excavated soil neatly in
5
specified dump area or disposing off the same as directed,
including cost of site clearance, all materials,machinery,
labour and dressing etc. Complete.

Providing and constructing Dry rubble wall (toe wall) with


6 stone of minimum size 0.021 cum at the base of stone
pitching or rip-rap excluding excavation etc.complete.

Dewatering and pumping the working area including all


connecting operation required etc. complete. For
7
cleanliness of working area by 5hp to 10 hp
diesel pump
atni

ge(Belkund River Diversion)

Quantaty Unit UCSR no(Ref)

101030.230 Cum 2.01

13190.4 Cum 2.1

1067.97 Sqm 3.46.2

213.6 Cum 3.36.1.3

213.6 Cum 3.36.1.10


221.55 Cum 2.01

221.55 Cum 3.45

960 Hour 3.55.2