Professional Documents
Culture Documents
18,0%
16,0%
14,0%
12,0%
THD ( % )
10,0%
8,0%
6,0%
4,0%
2,0%
Fig. 4 power factor of smelter
0,0%
2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 23 25 29 31 35 37 41 43 47 49
Harmonic order
Fig 2 shows harmonic currents in a low Harmonic current and power factor
capacity grid compensation system
With filter
Show generation no filter: No Min tol Nom Max
THD_U without filter 8,07%
Harmonic voltage distortion at 23 0 kV, 4500 MVA potline 1 + 2
1,85% 1,77% 1,67%
As it would not be practical to have one
1,2%
No filter Minimum Nom inal Maximum Allowed
additional generator unit producing the extra
1,0% electrical power required, due to none
0,8% compensated of the harmonic currents, and one
THD ( % )
Fig. 5 shows a typical single line of a The high voltage compensation systems are
compensation system connected to the utility power grid via the high
voltage switchgear. These compensation
systems require a more in dept system study
Compensation system design which analyses their impact to the feeding
grid, in both directions, as the system will also
Two different compensation system concepts be loaded with possible existing harmonic
are commonly used and need to be evaluated currents from the utility grid.
during the early design stage of the power They may be of a simpler design and may
conversion station. Considering the turnkey require a smaller footprint but their feeding
cost of the two concepts they both seem to switchgear needs to be rated to withstand high
work out cost neutral. voltage surges during switching operation.
Their design needs to be based on the power
Compensation at the medium voltage level contract limitation so that they can also meet
20-36kV the power factor requirements during initial
start up. Their performance is more suitable for
The medium voltage solution compensation higher grid capacities as it is very costly to
systems are connected to the regulation install multi branch filters at higher voltages.
transformer tertiary winding. Latest designs
are fitted with a MV circuit breaker to allow
step by step compensation. With this solution
each rectiformer has a compensation system
that is capable of meeting the power quality
limits, even if only four out of five units are in
operation. With this design, a high power
factor is also possible during the initial smelter
start up and harmonic currents do not reach the
high voltage level grid. One additional
advantage is that they can be designed and
installed without in-depth system studies of the Fig. 7 HV compensation system (220kV)
feeding grid. This compensation system
solution will not, or only marginally be
impacted by the power quality of the feeding
grid.
Design consideration for compensation
system at the high voltage level
Conclusion on impact of power quality for The points below show power plant interface
energy efficiency issues which are to be addressed to the power
plant and need to be made available to the
Harmonic currents create electrical losses and smelter substation.
if not compensated create costs for additional
electrical power. These additional costs for • SCC (Short Circuit Capacity) for all
electrical power pay off the investment cost of power plant operation conditions;
the compensation system in a very short time. • Max. allowed THD (Total Harmonic
Compensation systems connected to the power Distortion) by power plant or grid
grid require detailed studies and a high number • Max. power swings and rate possible in
of parameters need to be known or made MW
available by the power utility. When installed • Max. reactive – active power swing
and operated on the grid the power utility will • Max. allowed harmonic current loading
normally ask to control them as they are of cables
connected to their grid. Their drawback is that • Voltage dips to be expected and
should the feeding grid get polluted by other allowed
consumers during the years to come, they will • Power factor required
be loaded with this power quality pollution. • Grid codes to be complied with
Compensation systems connected to tertiary • Max. 2nd Harmonic current loading
windings of the regulation transformer are during transformer energizing
decoupled from the grids and are less affected • Max. power (delta u phase) unbalance
• Explain process of generator • Without synchronised switching, island
synchronising and minimal block load mode of operating may not be possible
• Explain Grid and Island operation (start • GIS or AIS breakers need to be able to
up SCC) switch with +/- 1ms accuracy between
• High speed signal available for load phases
decrease • IEEE 519 (power quality guide) can
only be met with tertiary filters on the
Smelter information to the power-plant rectiformers in island mode
• Harmonic current filters on the HV side
The points below show what the smelter may be critical and need to be studied
requirements are towards the power plant: as they get loaded with harmonic
currents which may be in the grid
• Power swings, daily anode effects • Power plant control systems need to be
create a sharp 15MW power swing able to generate and send a high speed
• Potline may trip more than 5 times in load drop signal
the first year (600MW immediate drop)
• Potline initial start up power demand
increases by 3.5MW/day Load rejection of the smelter is one of the
• Potline restart after trip, preferred most critical design issues
20MW per/min ramp up
• Power factor 0.82 during restart for The graph below shows what the smelter
short time voltage and current load curves which will be
• Voltage dip to 70% on smelter bus seen by the power plant and have to be
when rectiformers are energised considered in the overall system design.
without synchronisation of the feeder
breakers, if 5xSCC vs transformer
rating
• The higher the SCC, the lower the
efforts are required to meet power
quality demands;
• If max. allowed THD is 2%, smelter
tertiary filters are required if SCC is
<10x smelter rating
Fig. 11 load rejection after potline trip
• Synchronised switching of
transformers reduces power 200ms 1Sec 2.5Sec (tap down)
disturbances and voltage dips as well as Diode Rectiformer
Diode Rectiformer with ABB‘s Blackout Protection Control
mechanical stress on rectiformers and
harmonic current filters Fig. 12 load shedding with and without BPC
Power quality vs. grid power strength below shows the impact with and without
controlled energising. The voltage dips may
The diagram below shows the smelter result in tripping of already energised
substation power quality vs. strength of the consumers. Such voltage drops may be very
feeding grid. This is, in particular, to be critical for captive power plant smelter
considered should the grid be disconnected and projects. This is because the voltage on the
island operation will continue. Some of the MV may drop by up to 25% of the nominal
smelter power consumers such as UPS, rating, which is far beyond the normal allowed
inverters and AC drives are very susceptible to value of 10%.
high harmonic current distortions.
THD 8%
2%
Case Studies
ALBA, Kingdom of Bahrain
Dubai Aluminium (DUBAL) has a very large This single 500MW potline smelter will be fed
numbers of pot lines, some of them with less from a captive hydro power plant. A weak
that 100MW as well as a good mix of 132kV grid inter-connection is possible at the
generation. The grid can easily compensate power plant substation. The distance between
should one pot line trip. .. The large number of the power plant and the smelter is approx
potlines as well as their low rating also has an 60km. The auxiliary power for the smelter will
easier effect on the power quality level as the be taken from the same power lines feeding the
harmonic currents are compensated with the smelter rectiformers. Should the potline trip,
multi-pulse operation. Start-up power demand the power plant will need to be idled as the
and load rejection are of no concern. Icelandic grid will not be able to take the
Auxiliaries are fed from a different grid supply power.
The available short circuit capacity has to be
Nordural, Iceland considered low to very low during initial start
up and normal operation.
The Icelandic grid is becoming increasingly
stronger; however, most of generation Sohar, Sultanate of Oman
originates from low inertia geothermal steam
turbines and with non-industrial power This new smelter design is for up to three
demand fluctuating from day to night by more 550MW potlines and is fed from a captive
than half. Aluminium smelters create an ideal combined cycle power plant. A 220kV grid
load. The very large daily change of grid inter-connection is possible at the power plant
stability asks for a very flexible smelter substation. The distance between the power
substation design to allow for high speed load plant and the smelter is approx 12km. The
shedding and highest power quality auxiliary power for the smelter will be taken
performance. Due to this requirement, from the same power lines feeding the smelter
Nordural selected to use tertiary filter on the rectiformers. Should the potline trip, the power
regulations transformers as well as thyristor plant will need to be idled as the Omani grid
rectiformers for high speed load shedding. will not be able to take the power.
The available short circuit capacity has to be
Highest power quality was achieved with the considered low to very low during initial start
installation of controlled switching of the up and normal operation.
rectiformers as well as of the tertiary filters.