Report date: 12-Jan-10

DCPP 4x135 MW Unit-1 Daily Commissioning Report Status updated for: 11-Jan-10

S.No. Status of commissioning activities Remarks


1 PA FAN # 1A Lube Oil system flushing continued
2 BFP # 1A Lube Oil system flushing continued
Vibration of DE bearing is on the higher
3 SA fan # 1B motor trial taken from 10:00 hrs to 12:40 hrs side. The highest value recorded was
4.04 mm/sec
Motor started at 12:40 hrs. Tripped as the
4 ID fan # 1 A motor trial cable got punctured near ESP. Cable
replacement in progress
5
6
7
8

S.No. Planning for today Remarks


1 Trial run of ID fan # 1B motor
2 TG lube oil flushing through filters
3
4
5
6
7
8

S.No. Exceptions (Delays, if any) Remarks

Delayed as changeover from


1 DMCW line flushing up to Expansion tank Construction power to permanent power
is in progress. May take another 3days

3
4
5
6
7
8

S.No. Critical concerns Remarks


1. Feed water line flushing to be
completed before commencement of dry
1 Refractory dry out out. Agency for pre boiler system
cleaning getting delayed.
2. Compressed air of 6kg/cm2 is required.
3. CCOE clearance for filling LDO in
tanks is required