You are on page 1of 4

DOHA WEST POWER STATION

RAP WASHING SCHEDULE FOR BOILER # 7 (2018-2019) DATE


STARTING DATE 21/01/2019
COMPLETION DATE 25/01/2019
Jan-19
SL Procedure
DESCRIPTION Date 21 22 23 24 25 26 27 28 29
No. Reference
Days 0 1 2 3 4 5 6 7 8

Preparation work for RAP 1 & 2 washing and


drying

RAP - 1

1 RAP CHEMICAL WASHING

2 DRYING

RAP - 2

3 RAP CHEMICAL WASHING

4 DRYING

PLANNED
ACTUAL BOILER ENGINEER SITE ENGINEER SENIOR BOILER ENGINEER
PTW No. : 22811 NAME: SUJIT SINGH NAME: RAVI SANKAR NAME: _____________________
RECEIVED
DATE: 21/01/2019 SIGN. _____________________ SIGN. _____________________ SIGN. _____________________
EXPIRY
DATE: 25/01/2019 DATE 08-01-2019 DATE 08-01-2019 DATE 08-01-2019
DATE : 21-01-2019

Feb-19
30 31 1 2
9 10 11 12
SENIOR CHEMICAL ENGINEER
NAME: _____________________

SIGN. _____________________

DATE